IceCube Project Monthly Report December 2005

Similar documents
IceCube Project Monthly Report November 2005

IceCube Project Baseline

IceCube Project Monthly Report June 2005

IceCube Project Monthly Report November 2006

IceCube Project Monthly Report November 2007

IceCube Project Monthly Report April An IceCube collaboration meeting was held in Madison from April 29 th through May 3 rd.

IceCube Project Monthly Report March DOM production is in progress at the three production sites world-wide and proceeding according to plan.

Increased drilling efficiency saved approximately 26,000 gallons of fuel.

IceCube Project Monthly Report - December 2008

FULL SCALE DOM PRODUCTION DETERMINE FULL DEPLOYMENT RATE DEPLOY INITIAL STRINGS & TANKS COMPLETE EHWD INTEGRATION & TEST

Cost and Schedule Performance The project is 81.7% complete versus the plan of 82.2% complete, as measured using earned value techniques.

Nearly all of the cargo needed for this season arrived by December 4 th.

IceCube Project Monthly Report - December 2009

IceCube Project Monthly Report - October 2010

IceCube Project Monthly Report - September 2010

IceCube Project Monthly Report April 2009

The IceCube Upgrade Marek Kowalski DESY & Humboldt-University Zeuthen-Meeting in Mainz September 2018

Historical unit prices - Super - Australian Shares

Tariff 9900: OHD Percentage Based Fuel Cost Adjustment Historical Schedule ( )

Cairns Airport financial year passenger totals.

DM-Ice A Direct Dark Matter Search at the South Pole

TOWN MANAGER S WEEKLY REPORT

SF Summary of HIPER and Defective PTFs. I B M i P R E V E N T I V E S E R V I C E P L A N N I N G I N F O R M A T I O N

IDS Terms and Conditions Guide Effective: 10/21/2005 Page 1 of 7

IDS Terms and Conditions Guide Effective: 1/24/2007 Page 1of 7 CUSTOMER CONTRACT REQUIREMENTS PPS Services CUSTOMER CONTRACT W58RGZ-06-C-0234

EPO 2013/ CR-34 Obed Mountain Mine Monthly Status Report - December 2016

Jail Population Trend Report April - June 2016

7 May Questions 1-16 released separately

IDS Terms and Conditions Guide Effective: 07/13/2009 Page 1 of 7 CUSTOMER CONTRACT REQUIREMENTS N C-0001 CUSTOMER CONTRACT N C-0001

1. Do you approve or disapprove of the job Barack Obama is doing as president? Republicans 28% Democrats 84% 10 6

Monthly Trading Report Trading Date: Feb Monthly Trading Report February 2018

1Business Bulletin. 2Bfor the Free State of Saxony. June/Julyi 2010

Common Terms and Conditions Guide Section 5 Government Contract Requirements Clause Number: 5061 Effective: 11/20/2002 Page: 1 of 6

IDS Terms and Conditions Guide Effective: 10/21/2005 Page 1 of 8 CUSTOMER CONTRACT REQUIREMENTS F-15E CUSTOMER CONTRACT F C-0013

CUSTOMER CONTRACT REQUIREMENTS Communications Integration Kit CUSTOMER CONTRACT W904TE-14-M-0724

FOR RELEASE: TUESDAY, FEBRUARY 17 AT 12:30 PM

IDS Terms and Conditions Guide Effective: 10/21/2005 Page 1 of 6

The William C. Davis Collection. Records, (Predominantly, ) 6.5 linear feet

Dark Matter Searches with AMANDA and IceCube

Schoolbelles 4747 West 160 th Street Cleveland, OH December 1, Dear Applicant:

FOR RELEASE: WEDNESDAY, SEPTEMBER 2 AT 2 PM

Report on the Implementation of the Public Information Interim Policy (November 2017 to September 2018)

PUBLIC MEETINGS. Please see the City of Geneva Public Meeting Guide for more information regarding City Council and Committee of the Whole meetings.

Digital Marketing. Opportunities to reach Corporate Event Planners & Booking Agents

CUSTOMER CONTRACT REQUIREMENTS PAC-3 LRIP-3 LOCKHEED MARTIN SUBCONTRACT UNDER GOVERNMENT CONTRACT DAAH01-02-C-0050

CUSTOMER CONTRACT REQUIREMENTS (EA-18G System Development and Demonstration (SDD) Program) CUSTOMER CONTRACT N C-0005

TREND: Do you approve or disapprove of the way Donald Trump is handling his job as president?

CUSTOMER CONTRACT REQUIREMENTS RAYTHEON LETTER SUBCONTRACT

ASYLUM STATISTICS 2016

BADAN PUSAT STATISTIK KEPALA BADAN PUSAT STATISTIK 1

Reference services are provided through in-person visits, by telephone, via , through chat and by regular mail correspondence.

QUALITY. MANAGEMENT SYSTEMS 2015/2016 SABS Training Academy

2015 COURT CALENDAR CUMBERLAND COUNTY, PENNSYLVANIA DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

Rep Dem Party Party DK/NA

DM-Ice A Direct Dark Matter Search at the South Pole

IDS Terms and Conditions Guide Effective: 05/11/2004 Page 1 of 8 CUSTOMER CONTRACT REQUIREMENTS ESGN CUSTOMER CONTRACT N C-0026

Short-Term Transitional Leave Program in Oregon

Political Environment and Congressional Breakdown Charts. August 23, 2017

IDS Terms and Conditions Guide Effective: 8/17/2006 Page 1 of 8

IDS Terms and Conditions Guide Effective: 11/18/2009 Page 1 of 8 CUSTOMER CONTRACT REQUIREMENTS B-52 CONECT LRIP CUSTOMER CONTRACT FA D-1000

(Translation) Articles of Incorporation. United Microelectronics Corporation

IDS Terms and Conditions Guide Effective: 10/21/2005 Page 1 of 9

13 May Questions 1-14 released separately

IDS Terms and Conditions Guide Effective: 10/13/2006 Page 1 of 6

(READ AND RANDOMIZE LIST)

Common Terms and Conditions Guide Section 5 Government Contract Requirements Clause Number: 5023 Effective: 10/15/2002 Page: 1 of 7

EUROPE REFUGEES & MIGRANTS EMERGENCY RESPONSE NATIONALITY OF ARRIVALS TO GREECE, ITALY AND SPAIN

OFFICE OF THE ASSOCIATE CIRCUIT JUDGES Thirteenth Judicial Circuit Court Boone County Courthouse 705 E. Walnut St. Columbia, MO 65201

OFFICE OF THE ASSOCIATE CIRCUIT JUDGES Thirteenth Judicial Circuit Court Boone County Courthouse 705 E. Walnut St. Columbia, MO 65201

2. Do you approve or disapprove of the job Congress is doing? Sep 08 17% 73 9 Democrats 28% Sep 08 23% 68 8 Republicans 10% 87 3

thewholething learning and development success Public Course Calendar UK Beyond Business Growth Consulting and Training

Chart A Initial Release Decisions for Criminal Justice Reform Eligible Defendants January 1 December 31, 2017

6. 9. How frustrated and upset are you with [ITEM] these days? (RANDOMIZE)

Characteristics of the Ethnographic Sample of First- and Second-Generation Latin American Immigrants in the New York to Philadelphia Urban Corridor

BDS Terms and Conditions Guide Effective: 04/20/2012 Page 1 of 7 CUSTOMER CONTRACT REQUIREMENTS SIRIUS CUSTOMER CONTRACT FA C-7234

RECOMMENDED CITATION: Pew Research Center, May, 2015, Negative Views of New Congress Cross Party Lines

CUSTOMER CONTRACT REQUIREMENTS PAC-3: Recertification Planning/Replenishment Spares CUSTOMER CONTRACT

Restrictions on Subcontractor Sales to the Government (Sep 2006). This clause applies only if this contract exceeds $100,000..

FOR RELEASE: TUESDAY FEBRUARY 17 at 6:00 a.m. ET

Political Environment and Congressional Breakdown Charts. November 7, 2017

REFUGEE AND IMMIGRATION LAW SERVICES: SERVICE SUSPENSION CONSULTATION

BDS Terms and Conditions Guide Effective: 11/14/2012 Page 1 of 8

1 PEW RESEARCH CENTER

CUSTOMER CONTRACT REQUIREMENTS NSW IDIQ II - N D-0016

Introduction to National Inventory System of energy sector

CUSTOMER CONTRACT REQUIREMENTS BLOCK III FY05 NONRECURRING ENGINEERING CUSTOMER CONTRACT W58RGZ-05-C-0001

CUSTOMER CONTRACT REQUIREMENTS CH-47 Actuator CUSTOMER CONTRACT W58RGZ-13-D-0031

TERMS OF REFERENCE FOR THE CORPORATE GOVERNANCE COMMITTEE

FOR RELEASE MAY 10, 2018

CHAIN ANNUAL BULLETIN GREATER LONDON 2016/17

Implementing an ABC System: The Experience of the Czech Republic

Atchison County Commisssion Meeting. Atchison County Courthouse 423 North 5th St Atchison, Kansas May 15, 2018 REGULAR MEETING AGENDA

Congressional Official Mail Costs

Twin Cities Events Calendar

CURRENT AND NON-RECENT SEXUAL OFFENCES

REPORT OF RECEIPTS AND DISBURSEMENTS

IDS Terms and Conditions Guide Effective: 5/17/2007 Page 1of 10 CUSTOMER CONTRACT REQUIREMENTS Japan RSIP CUSTOMER CONTRACT F D-0016 DO 0050

Hired Labor Use in the Texas Fresh Fruit and Vegetable Industry

TREND: Do you approve or disapprove of the way Charles Schumer is handling his job as United States Senator? (* High also 69%)

CUSTOMER CONTRACT REQUIREMENTS (GPS-IIF) CUSTOMER CONTRACT F C-0025

Transcription:

IceCube Project Monthly Report December 2005 Accomplishments The IceCube drill crew completed four holes as of January 13 th. The locations of the four holes are 29, 39, 38, and 30. The drilling start dates for each hole were December 19 th, January 1 st, January 5 th, and January 10 th respectively (South Pole dates). The installation of the string at location #29, the first string of the season, was successfully completed on the morning of December 26 th after a twelve-hour deployment period. String 39 and 38 were both deployed in roughly an equivalent amount of time. Deployment of string #30 is currently underway. After a delay of a few weeks in the arrival on station of the final surface cables, all twelve surface cables planned for this year are now in place in subsurface trenches and connected to junction boxes on the surface. The twenty-four IceTop tanks, two tanks at each of the twelve locations, are positioned with all forty-eight DOMs installed. The tanks are filled with water and a controlled freeze is underway. On-ice Digital Optical Module (DOM) testing is complete. The initial pass rate was greater than ninety-seven percent. Some failed DOMs will likely pass after additional testing and analysis. Lower level commissioning tests of strings 29, 39, and 38 are underway and preliminary results are positive. Communication has been established with each string. 100% ICECUBE - TOTAL Cost / Schedule Performance 90% 80% Scheduled %, 51.8% 70% Performed %, 50.6% Percent Complete 60% 50% 40% Cost %, 48.8% IceCube Project Baseline (M$) Initial In-Ice Strings & IceTop Tanks Installed Initial Operational Capability Jan-2005 Mar-2007 30% Project Completion & Closeout Sep-2010 Total Project Cost $273.1 20% Value of Foreign Contributions $31.0 NSF Funding $242.1 Contingency as % of Remaining Costs 30.1% 10% # Strings/Tanks 70/140 0% J-05 A-05 FY05 O-05 N-05 D-05 J-06 F-06 M-06 A-06 M-06 J-06 Scheduled % 43.1% 44.9% 47.4% 49.1% 51.8% 53.8% 55.7% 58.0% 59.3% 60.4% 62.7% 64.2% Performed % 41.4% 43.7% 46.6% 48.0% 50.6% Cost % 40.0% 43.7% 45.8% 46.2% 48.8% Calendar Months, 2005-2006

Cost and Schedule Performance The project is roughly 50.6% complete versus the planned performance of 51.8% complete as measured using earned value techniques. The earned value measurement includes all tasks completed to date including design, development, procured materials, and the construction of the infrastructure that supports the current seasonal installation plan, e.g., the hot water drill, cargo shipments, etc. The cost and schedule status report and total contingency percentage (contingency/cost-to-complete) as a function of time, currently roughly 30%, is shown in the following tables. 11/30/2005 Budgeted Cost 2 Actual Cost Variance Latest Work Work of Work Budgeted Revised OBS Structure L2 Scheduled Performed Performed Schedule Cost AY $s Estimate Variance Scheduled Performed Actual PROJECT SUPPORT 15919.5 15919.9 16345.3 0.4-425.5 29904.8 30330.3-425.5 53.2% 53.2% 54.7% IMPLEMENTATION 19915.0 19739.1 19599.5-175.9 139.6 32388.6 32249.0 139.6 61.5% 60.9% 60.5% INSTRUMENTATION 34142.3 33592.4 32404.6-549.9 1187.8 65432.7 64245.0 1187.8 52.2% 51.3% 49.5% DATA ACQUISITION 20956.8 20560.3 21139.6-396.5-579.3 32864.6 33443.9-579.3 63.8% 62.6% 64.3% DATA SYSTEMS 11024.3 10431.5 10515.5-592.8-83.9 25017.6 25101.5-83.9 44.1% 41.7% 42.0% DETECTOR COMM. & VERIFICATION Reporting Period Ending: Cumulative To Date (AY K$) IceCube Neutrino Observatory Cost Schedule Status Report 1 At Completion (AY K$) Complete (%) 7979.4 7855.7 7598.4-123.8 257.3 18825.0 18567.7 257.3 42.4% 41.7% 40.4% RPSC SUPPORT 12616.6 11587.5 7821.2-1029.1 3766.3 31997.8 28231.6 3766.3 39.4% 36.2% 24.4% NSF 512.9 512.9 512.9 0.0 0.0 1263.0 1263.0 0.0 40.6% 40.6% 40.6% Sub Total 123067.0 120199.3 115937.1-2867.7 4262.2 237694.2 233432.0 4262.2 51.8% 50.6% 48.8% Management Reserve Total Contingency 35,359.1 39,621.4 4,262.2 Items Outside of Approved Baseline IceCube Neutrino Observatory 2 123,067.0 120,199.3 115,937.1-2,867.7 4,262.2 273,053.3 273,053.3 0.0 51.8% 50.6% 48.8% Notes: 1 Incorporates approved and currently pending baseline changes. 2 Total Budget at Completion includes non-us contributions $1,283K over the amount in the post Hartill III baseline. 3 The budgeted contingency is: 30.1% of the Budgeted cost of work remaining. IceCube Neutrino Observatory Contingency % of ETC 30.0% 30.1% 20.0% Annual Baseline Replanning 10.0% 0.0% Mar-05 Feb-05 Jan-05 Dec-04 Nov-04 Oct-04 Sep-04 Aug-04 Jul-04 Jun-04 May-04 Apr-04 Mar-04 Feb-04 May-05 Apr-05 Nov-05 Oct-05 Sep-05 Aug-05 Jul-05 Jun-05 2

Drill Construction and Operation Following completion of final preparation and readiness review activities the start of firn drilling for the first hole of 2005/2006 commenced on Monday, December 19, 2005, nine days later than the original plan. Firn drilling proceeded as expected. Ice drilling started a few days after firn drilling once several issues were resolved related to incorrect readouts from load cells and programming of the motor control drives in the tower operations structure (TOS-1). The second hole commenced on January 1, 2006, after longer than expected start-up and commissioning times for the second tower operations structure (TOS-2). The two towers are now commissioned and drilling will proceed in a leap frog manner for the duration of the season. The firn holes are now drilled with a new firn drill head (one for each TOS) that reduces the time to drill through firn (~ 40 meters) to less than five hours. This is less than one half of the time it took to drill through the firn last season. The IceCube drill crew completed four holes as of January 13 th. The locations of the four holes are 29, 39, 38, and 30. The drilling start dates for each hole were December 19 th, January 1 st, January 5 th, and January 10 th respectively (South Pole dates). The drill crew is directed to take a day off after the completion of each hole in order to ensure proper rest prior to the start of the subsequent hole. Data on hole 39, the second hole of the season, is provided at the end of the report. The start of drilling on the fifth hole of the season is planned for January 15 th. Deployment Deployment of the first string, #29, went extremely well. The string was installed to the target depth of 2450m in less than 10 hours. Deployment for string 29 breaks down as follows: 1 hour for startup; ~7 hours for the installation of 60 DOMs; ~1.5 hours for the final drop. A logging run was performed on the second hole to determine the exact diameter of the hole after reaming. The pressure sensors on the cable delivered good data. The data was read out and displayed by the integrated drill/deployment readout system. On January 4 th the second string for the season was successfully deployed. Deployment for string 39 took approximately 14 hours from start to finish. Deployment for string 39 went as follows: January 3 at 2337 hours: start of string deployment January 3 at 2340 hours: first DOM installed January 4 at 1010 hours: last DOM installed January 4 at 1230 hours: depth of 2450m reached January 4 at 1302 hours: string is secured Digital Optical Module and Cable Production Status and Plans - The status of DOM production for 2005 is provided in the chart below along with the plan for DOM, cable, and tank production plan for 2004 2008. There are no major issues with instrumentation production. The plans provide instrumentation well in advance of the installation need dates and support the use of the least expensive shipping methods. 3

A large number of cables will be stored at McMurdo station this winter and will be available for shipment to the South Pole at the beginning of next season. The project is looking at plans to off load surface cables at the beginning of next season, so called drift or combat off loading at the South Pole when temperatures do not permit aircraft to come to a complete stop. The production goals for 2005 were met resulting in 16 surface-dom cables, 16 surface cables, and 930 DOMs. 1000 IceCube DOM Production PY4(CY2005) - Summary Revision 7/12: Change shipping dates and quantities to more accurately reflect DOM production progress to date. DESY to keep all CAEN HV units. 900 DOMs ready for DFL @ PSL - cumulative plan DOMs ready for DFL @ DESY - cumulative plan 800 DOMs ready for DFL @ Swed - cumulative plan DOMs ready for DFL - cumulative plan all sites DOMs ready for DFL - cumulative actual all sites Quantity of DOMs ready for DFL 700 600 500 400 300 200 100 0 3/5/2005 3/12/2005 90 80 Summary: 1. PSL integrates 610 DOMs from 4/2 to 9/3, ships 548 DOMs (includes 16 from CY2004). 2. DESY integrates 160 DOMs from 4/23 to 8/6, ships 108 ( includes 12 from CY2004, hold back 64 CAEN HV units). 3. Sweden integrates 160 DOMs from 4/30 to 8/27, ships 144 ( includes 24 from CY2004 ) 3/19/2005 3/26/2005 4/2/2005 4/9/2005 4/16/2005 4/23/2005 4/30/2005 5/7/2005 5/14/2005 5/21/2005 5/28/2005 6/4/2005 6/11/2005 6/18/2005 6/25/2005 Week ending 7/2/2005 7/9/2005 7/16/2005 7/23/2005 7/30/2005 8/6/2005 8/13/2005 8/20/2005 8/27/2005 9/3/2005 9/10/2005 9/17/2005 9/24/2005 10/1/2005 IceCube DOM, Cable and Tank Production CY2004 - CY2008 for 80 strings installed Cable Systems 10/8/2005 70 60 Equivalent InIce strings 50 40 30 IceTop Tanks DOMs Strings installed in ice at Pole 20 10 0 7/24/2004 9/24/2004 11/24/2004 1/24/2005 3/24/2005 5/24/2005 7/24/2005 9/24/2005 11/24/2005 1/24/2006 3/24/2006 5/24/2006 7/24/2006 9/24/2006 11/24/2006 1/24/2007 3/24/2007 5/24/2007 7/24/2007 9/24/2007 11/24/2007 1/24/2008 3/24/2008 5/24/2008 7/24/2008 9/24/2008 11/24/2008 1/24/2009 3/24/2009 5/24/2009 7/24/2009 9/24/2009 11/24/2009 1/24/2010 Week ending 4

Cargo Shipments to the South Pole After a delay in getting the surface cables from Christ Church to McMurdo station, all the surface cables required this year arrived at the South Pole. Final Acceptance Testing of DOMs The DOM testing group passed 777 DOMs. There were 25 DOMs that failed initial testing due to high or unstable noise rates, low or high gain, flasher failures, and two with significant gel crazing. Many of the failed DOMs will ultimately pass final acceptance after further review and analysis. String and IceTop Commissioning All 76 IceCube DOMs installed at the South Pole last season are operating and reading data (60 DOMs on the string and 16 DOMs in eight surface tanks). Overall, the quality of the data from the first string and the eight IceTop tanks is very good. The basic strategy for string commissioning this season is to conduct detailed performance testing on only a few strings and a minimal set of tests on the rest of the strings. Communication tests on the first three strings deployed this season were successful. Data Acquisition System - There is very good progress preparing the final data acquisition software. Modules of the software are now being uploaded onto the first string and surface computing hardware and the full software chain is being run on the South Pole System (SPS). A technical review of the DAQ system is planned for the spring 2006. The review will evaluate the results of the current season. System Testing The South Pole Test System, a mirror image of the South Pole System located at the UW-Madison Physics Department, continues to provide a critical test bed for the data acquisition and data handling software. Data Systems The temporary counting house is fully operational. The IceCube Laboratory or permanent counting house is expected to be available on December 15, 2006. Quality Assurance & Safety There are no significant quality assurance issues to report. Hank Leweling, IceCube Safety Manager on On-Ice Safety Officer during November and December left the pole on December 26th. Michael Zernick will be assume the On-Ice Safety Officer role beginning in mid-january and will remain at the South Pole for the rest of the season. The monthly reports are posted at IceCube Monthly Reports. The IceCube 2005-2006 Weekly Construction Reports are posted at IceCube 2005-2006 Weekly Construction Reports. Meetings and Events NSF Site Visit Madison February 23, 2006 Season Review Meeting w/ UW/RPSC/NSF March 16-17, 2006 Drill Advisory Panel Meeting Madision March 27-28, 2006 Panel Advisory Panel Meeting Madison March 29-30, 2006 Science Advisory Committee Meeting Madison March 30-31, 2006 International Oversight & Finance Group NSF April 7, 2006 Collaboration Meeting - Baton Rouge, LA April 10-14, 2006 NSF Annual Review - Madison May 23-25, 2006 5

String 39 January 4, 2006 String 39 Deployment Chart

String 39 Caliper Width vs. Depth Chart String 39 Depth vs. Time Chart 7