IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE September 14, 2007 Session

Similar documents
IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE June 27, 2007 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON May 19, 2009 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE May 23, 2014 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE Assigned on Briefs October 8, 2008

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE March 3, 2005 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE November 8, 2007 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE August 8, 2007 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE November 14, 2008 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON January 21, 2009 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE April 5, 2006 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE March 6, 2012 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE Assigned on Briefs May 7, 2009

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON August 16, 2007 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE Assigned on Briefs, September 6, PEGGY J. COLEMAN v. DAYSTAR ENERGY, INC.

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON July 16, 2013 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE February 13, 2008 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE Assigned on Briefs April 3, 2017

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE May 27, 2010 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON October 25, 2011 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE JULY 9, 2003 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE March 11, 2009 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE AUGUST 7, 2003 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON OCTOBER 14, 2010 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE Assigned on Briefs March 9, 2010

IN THE SUPREME COURT OF TENNESSEE SPECIAL WORKERS COMPENSATION APPEALS PANEL AT NASHVILLE June 29, 2009 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON January 17, 2007 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE Submitted on Briefs January 8, MOUNTAIN WOOD PRODUCTS, LLC v. AUTUMN CREEK FIREWOOD, LLC

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE September 13, 2007 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE March 17, 2003 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE October 17, 2008 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE October 11, 2011 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE February 14, 2005 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE February 11, 2002 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE May 12, 2005 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE February 12, 2008 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE November 7, 2011 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE March 17, 2003 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE February 13, 2003 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON August 4, 2004 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON ASSIGNED ON BRIEFS NOVEMBER 29, 2006

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON August 24, 2005 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE March 19, 2008 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON February 13, 2019 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON April 22, 2014 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON OCTOBER 14, 2003 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE November 6, 2009 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE July 18, 2006 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE May 10, 2011 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE June 29, 2006 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON October 11, 2005 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON Assigned on Briefs January 31, 2011

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE September 22, 2010 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE October 13, 2011 Session. THE FARMERS BANK v. CLINT B. HOLLAND, ET AL.

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE May 11, 2007 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE December 16, 2015 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE August 18, 2006 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE May 22, 2015 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE Assigned on Briefs May 8, 2007

IN THE COURT OF APPEALS OF TENNESSEE WESTERN SECTION AT JACKSON. Petitioner/Appellant, ) Shelby Chancery No R.D. )

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE MARCH 20, 2003 Session

IN THE SUPREME COURT OF TENNESSEE SPECIAL WORKERS COMPENSATION APPEALS PANEL AT NASHVILLE September 21, 2009 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE Assigned on Briefs, February 26, 2004

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON October 10, 2005 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE June 19, 2008 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON October 25, 2011 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE August 23, 2012 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON March 17, 2005 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE Assigned on Briefs January 9, 2008

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE Assigned on Briefs June 25, 2001 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE June 10, 2013 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE January 28, 2015 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON January 23, 2004 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE May 8, 2008 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE May 19, 2010 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE ASSIGNED TO WESTERN SECTION ON BRIEFS MARCH 30, 2007

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE June 29, 2012 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE February 15, 2001Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE April 12, 2016 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON October 13, 2010 Session

STATE OF MICHIGAN COURT OF APPEALS

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE Assigned on Briefs September 3, 2008

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE Assigned on Briefs November 29, 2007

NOT DESIGNATED FOR PUBLICATION. No. 118,990 IN THE COURT OF APPEALS OF THE STATE OF KANSAS. JENNIFER VANDONSEL-SANTOYO, Appellee,

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE January 18, 2018 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE September 23, 2015 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON August 22, 2005 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE JULY 17, 2008 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE April 18, 2012 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE Assigned On Briefs May 29, 2007

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE April 24, 2008 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE. CRAFTBILT MANUFACTURING CO., ) ) E COA-R3-CV Plaintiff/Appellee )

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON April 22, 2009 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE June 12, 2007 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON September 21, 2005 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE December 13, 2001 Session

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON May 2000 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE August 5, 2002 Session

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE December 7, 2010 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE September 16, 2005 Session

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE November 6, 2008 Session

Transcription:

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE September 14, 2007 Session ROBERT G. O NEAL, d/b/a R & R CONSTRUCTION CO. v. PAUL E. HENSON, ET AL. Direct Appeal from the Chancery Court for Sequatchie County No. 1875 Jeffrey F. Stewart, Chancellor No. M2006-02118-COA-R3-CV - Filed November 15, 2007 This is a construction contract dispute. The trial court entered judgment in favor of Defendants Buyers/Counter-Plaintiffs in the amount of $72,418, less an offset in the amount of $48,713.15 for payments due to Plaintiff Builder; attorney s fees; and costs. Plaintiff Builder appeals. We affirm. Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed; and Remanded DAVID R. FARMER, J., delivered the opinion of the court, in which HOLLY M. KIRBY, J. and STEVE R. DOZIER, SP. J., joined. Edward L. Boring and Keith Harding Grant, Pikeville, Tennessee, for the appellant, Robert G. O Neal. Keith S. Smartt, McMinnville, Tennessee, for the appellees, Paul E. Henson and Patricia Nell Henson. MEMORANDUM OPINION 1 This case arises from a February 2000 contract executed by Builder Robert G. O Neal d/b/a R & R Construction Co. (Mr. O Neal) and Paul E. Henson and Patricia N. Henson ( the Hensons ) to construct a log home to buyers specifications. The contract provided a completion date of June 30, 2000, and included a provision for attorney s fees upon default or breach. The contract price was 1 Rule 10 of the Rules of the Court of Appeals of Tennessee provides: This Court, with the concurrence of all judges participating in the case, may affirm, reverse or modify the actions of the trial court by memorandum opinion when a formal opinion would have no precedential value. When a case is decided by memorandum opinion it shall be designated MEMORANDUM OPINION, shall not be published, and shall not be cited or relied on for any reason in any unrelated case.

actual cost plus ten percent. Difficulties arose between the parties during the course of construction, and in September 2000 Mr. O Neal left the job site unfinished. In February 2001, Mr. O Neal filed a complaint in the Chancery Court of Sequatchie County alleging he had performed all obligations under the contract in a timely and workman-like fashion, and that the Hensons had breached the contract by failing to pay amounts due. He prayed for a judgment in the amount of $48,713.15, plus prejudgment interest, costs, and attorney s fees. The Hensons answered and counter-complained in April 2001, alleging construction defects and failure to complete the contract according to schedule. They prayed for actual and punitive damages, attorney s fees, and treble damages under the Tennessee Consumer Protection Act. The matter was heard in the trial court in May and July, 2005 and the trial court made oral findings of fact in April 2006. Final judgment was entered in September 2006. The trial court found Mr. O Neal had committed no fraudulent or deceptive practices that would justify an award of treble damages under the Tennessee Consumer Protection Act. Based on the testimony of experts for both the Hensons and Mr. O Neal, the trial court found that the work performed by Mr. O Neal was defective and substandard. It determined the Hensons has sustained damages in the amount of $72,418, including $30,000 arising from substandard and defective workmanship; $20,000 for completion of work not completed by Mr. O Neal; and $22,418 for replacement of a defective roof. The trial court ordered [s]uch judgment shall be allowed as an offset against the amount claimed and allowed to Plaintiff of $48,713.15, resulting in a net judgment to the Hensons in the amount of $23,704.85. It further awarded attorney s fees and costs to the Hensons as the prevailing parties. Mr. Henson filed a timely notice of appeal to this Court. We affirm. Issues Presented The following issues, as presented by Mr. O Neal, are raised for our review: (1) The trial court erred in awarding damages to the Appellees despite the fact that the Appellees initially breached the contract. (2) The trial court erred by charging finishing costs to the Appellant when the Appellee[s] initially breached the contract by refusing to pay the amount due under the contract (3) The trial court erred by failing to grant attorney[ s] fees for the Appellant[s ] attorney[] pursuant to the contract and the partially favorable ruling, or, in the alternative, Appellees should not have been granted attorney[ s] fees. Standard of Review Our standard of review of a trial court sitting without a jury is de novo upon the record. Wright v. City of Knoxville, 898 S.W.2d 177, 181 (Tenn. 1995). We review the trial court s findings -2-

of fact with a presumption of correctness unless the evidence preponderates otherwise. Tenn. R. App. P. 13(d). Thus, we may not reverse the trial court s factual findings unless they are contrary to the preponderance of the evidence. We review the trial court s conclusions on matters of law de novo, with no presumption of correctness. Tenn. R. App. P. 13(d); Bowden v. Ward, 27 S.W.3d 913, 916 (Tenn. 2000). Analysis The issues raised on appeal essentially require a determination of which party was initially and primarily responsible for the failure of this contractual relationship. Mr. O Neal does not dispute the trial court s factual finding of defective or substandard workmanship. Rather, he asserts that the Hensons initially breached the contract by failing to pay invoices due, and that he therefore had no choice but to discontinue work on the home. He asserts that because the Hensons initially breached the contract, they could not thereafter assert damages against Mr. O Neal where Mr. O Neal was given no opportunity to cure and no written documentation of alleged defects prior to the filing of his complaint. He further asserts the Hensons may not recover costs to finish where the contract was a cost-plus contract and where Mr. O Neal was forced off the job site by the Hensons refusal to pay. Mr. O Neal finally submits that the trial court erred in awarding the Hensons attorney s fees under the contract where the Hensons initially breached and, in the alternative, where they only partially prevailed on their counterclaim. The Hensons, on the other hand, assert Mr. O Neal initially breached by failing to complete the job by June 30, 2000, as specified in the contract. They further assert they brought quality problems to Mr. O Neal during construction, and that Mr. O Neal failed to correct the problems. They contend that they ceased making payments to Mr. O Neal after he failed to complete the job on time; failed to carry out his assurances to correct the defects ; and after they became aware of substantial defects in the home. As the trial court observed, the dispute over which party breached first is essentially a he said/she said determination. Ultimately, however, the trial court found the Hensons had brought construction defects to Mr. O Neal s attention during the course of construction, that Mr. O Neal s work had been, in fact, substandard and/or defective, and that the Hensons were the prevailing party. The question of which party initially breached is, in this case, a matter of credibility. We review a trial court s determinations on matters of witness credibility with great deference and will not re-evaluate a trial judge s credibility determinations unless they are contradicted by clear and convincing evidence. Wells v. Tenn. Bd. of Regents, 9 S.W.3d 779, 783 (Tenn. 1999). Finding no clear and convincing evidence to contradict the trial court s determination on this matter, we affirm the award of damages to the Hensons arising from Mr. O Neal s breach. We next turn to Mr. O Neal s assertion that the trial court erred in awarding the Hensons the costs of finishing construction on the home where the contract was a cost-plus contract and where the Hensons essentially forced him off the job site by refusing to pay installments due. Mr. O Neal s rather brief argument to this Court on this issue essentially reiterates his position that, because the -3-

Hensons were the initial breaching party, the award of damages was in error. As noted above, we find no evidence to disturb the trial court s determinations on this matter. Finally, Mr. O Neal asserts the award of attorney s fees to the Hensons was in error where the Hensons only partly prevailed on their claims and where the court also awarded Mr. O Neal the damages asserted in his complaint. The contract provision providing for attorney s fees states: Upon the default of either party or breach of the terms of this contract, the nondefaulting party shall be entitled to recover any and all expenses incurred by the nondefaulting party in conjunction with the enforcement of this contract, or the rights hereunder, including reasonable attorney s fees and other associated expenses of litigation. The trial court awarded attorney s fees to the Hensons as the prevailing parties. However, although we agree with Mr. O Neal that he prevailed on his claim, the determination of who is entitled to attorney s fees under the plain language of the contract again requires a determination of which party defaulted and which party was the non-defaulting party. The interpretation of a contract is a matter of law which we review de novo, with no presumption of correctness for the determination of the trial court. Barnes v. Barnes, 193 S.W.3d 495, 498 (Tenn. 2006). The cardinal rule of contract construction is to ascertain the intent of the parties and to effectuate that intent consistent with applicable legal principles. Frizzell Constr. Co. v. Gatlinburg, L.L.C., 9 S.W.3d 79, 85 (Tenn. 1999). When the language of the contract is plain and unambiguous, courts determine the intentions of the parties from the four corners of the contract, interpreting and enforcing it as written. Int l Flight Ctr. v. City of Murfreesboro, 45 S.W.3d 565, 570 (Tenn. Ct. App.2000). A contract is not rendered ambiguous simply because the parties disagree as to the interpretation of one or more of its provisions. Id. at n. 5. The court must seek to ascertain the parties intent in light of the context of the entire agreement. Burns v. Temperature Control Co., 371 S.W.2d 804, 806 (Tenn. Ct. App.1963) (citations omitted). Additionally, we must construe any ambiguity in a written contract against the drafter. E.g., Spiegel v. Thomas, Mann & Smith, P.C., 811 S.W.2d 528, 531 (Tenn. 1991). Although the Hensons claim for damages was offset by amounts which the trial court determined were owed to Mr. O Neal for work done, the performance of substandard and defective work by Mr. O Neal preceded the Hensons refusal to pay him. Mr. O Neal clearly defaulted under the terms of the contract. We affirm the award of attorney s fees. Holding The judgment of the trial court is affirmed. Costs of this appeal are taxed to the Appellant, -4-

Robert G. O Neal d/b/a R & R Construction Co., and his surety, for which execution may issue if necessary. DAVID R. FARMER, JUDGE -5-