PAK: Sindh Provincial Road Improvement Project (SPRIP)

Similar documents
PAK: Sindh Provincial Road Improvement Project (SPRIP)

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project

IND: Uttarakhand Emergency Assistance Project

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II

MON: Urban Development Sector Project Bulgan Subproject

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report

MLD - Kulhudhuffushi Harbor Expansion Project

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report

Land Acquisition and Resettlement Due Diligence Report

Due Diligence Report on Social Safeguards

IND: Uttarakhand Emergency Assistance Project

Semi-annual Social Safeguards Monitoring Report (January to June 2012)

PAK: Loan 2299: Lower Bari Doab Canal Improvement Project

Involuntary Resettlement Due Diligence Report

Resettlement Plan. IND: Bihar State Highways II Project. March Siwan-Siswan Subproject (SH-89)

Land Acquisition and Resettlement Framework. PAK: Khyber Pakhtunkhwa Provincial Roads Improvement Project

PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project

TIM G-0180: Road Network Development Sector Project Contract Packages R1 Liquica - Maubara Road Contract Packages R2 Karimbala Atabae Road

India: Delhi Meerut Regional Rapid Transit System Project

PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project Reach 3: Aman Chowk to Hayatabad

PAK: Additional Financing for Khyber Pakhtunkhwa Provincial Roads Improvement Project

PAK: MFF II Power Transmission Enhancement Program (PTEIP II)

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the

IND: Chhattisgarh State Road Sector Project

IND: Mumbai Metro Rail Systems Project

IND: Chhattisgarh State Road Sector Project

TAJ: CAREC Corridors 3 and 5 Enhancement Project. Rehabilitation of 88 km Vose - Khovaling subnetwork

India: Jammu & Kashmir Urban Sector Development Project

Technical Assistance Consultant s Report. TA 7566-REG: Strengthening and Use of Country Safeguard Systems

ASIAN DEVELOPMENT BANK

IND: Railway Sector Investment Program

IND: Bihar State Highways II Project Additional Financing

India: Uttarakhand State Road Investment Program

AFG: MFF Water Resources Development Investment Program- Tranche 1, Nangarhar Valley Development Authority Grant No: 0167 AFG

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT

Revised Resettlement Plan Tibar-Gleno Road

Resettlement Plan. February Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank.

Final Monitoring Report to the Board of Directors. on the. Implementation of Remedial Actions. for the

Resettlement Plan. October Prepared by the Government of Jammu and Kashmir, Economic Reconstruction Agency for the Asian Development Bank.

Resettlement Plan. October Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank.

Earthquake Emergency Assistance Project

Resettlement Plan Dili-Tibar-Liquica Road

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B.

Indonesia: Enhanced Water Security Investment Project

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing

PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project Reach 1: Chamkani Mor to Firdous Cinema

BAN: Railway Sector Investment Program

BAN: Railway Sector Investment Program

JBIC ODA Loan Project Mid-Term Review

BAN: South Asia Subregional Economic Cooperation Dhaka-Northwest Corridor Road Project, Phase 2

PROJECT RATIONALE. The new road and tunnel will open up the area to tourists coming south from Russia and north from Tblisi.

SRI: Additional Financing for National Highway Sector Project

Involuntary Resettlement Due Diligence Report

MYA: Maubin-Phyapon Road Rehabilitation Project

Resettlement and Indigenous Peoples Plan. IND: North Eastern State Roads Investment Program

IND: Infrastructure Development Investment Program for Tourism - Tranche 3

Bangladesh: Urban Public and Environmental Health Sector Development Program

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

Updated Land Acquisition and Compensation Plan. LAO: Additional Financing of Water Supply and Sanitation Sector Project (Xamneau Subproject)

SRI: Local Government Enhancement Project

Garma-Nele-Bogal Subproject, Solukhumbu Chainage: (O )

Annex 2: Does the Xayaburi resettlement comply with Lao law?

India: Madhya Pradesh Urban Services Improvement Project (MPUSIP)

Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Mannar Subprojects

Social Safeguards Monitoring Report. TIM L-2857/2858: Road Network Upgrading Project Contract Packages R4 Tibar - Gleno Road

Indigenous Peoples Planning Framework. India: Assam Power Sector Investment Program

Ethnic Minorities Development Framework. PRC: Guangxi Regional Cooperation and Integration Promotion Investment Program

IND: Railway Sector Investment Program Tranche 3

IND: Second Jharkhand State Road Project

ASIAN DEVELOPMENT BANK JFPR: AFG 36553

Donated for a Cause: Land Transfers in DRILP

IND: Uttarakhand State Roads Investment Program (Project 3)

Public Disclosure Authorized SFG3015 V1. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

MATARBARI PORT ACCESS ROAD DEVELOPMENT PROJECT

SRI: Southern Road Connectivity Project

TRIBAL DEVELOPMENT PLAN

2862/63/64-BAN (SF): Greater Dhaka Sustainable Urban Transport Project

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005

SUMMARY POVERTY REDUCTION AND SOCIAL STRATEGY

BANK MANAGEMENT RESPONSE TO REQUEST FOR INSPECTION PANEL REVIEW OF THE INDIA MUMBAI URBAN TRANSPORT PROJECT (IBRD LOAN

BASIC SOCIAL ASSESSMENT REPORT FOR THE N11, SECTION 13, MOKOPANE

PNG: Bridge Replacement for Improved Rural Access Sector Project

IND: Infrastructure Development Investment Program for Tourism - Tranche 3

Resettlement Framework. BHU: Urban Infrastructure Project. October Prepared by the Royal Government of Bhutan for the Asian Development Bank.

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION

Ex-Post Evaluation of Japanese ODA Loan Project Pak Kret Bridge and Connecting Road Construction Project

IND: Second Jharkhand State Road Project

BAN: City Region Development Project for Shakhari Bazaar Urban Renewal Subproject

Summary of the Indigenous Peoples' Consultation with the Asian Development Bank, November 27 th 2007

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang)

People s Republic of China: Jilin Yanji Low-Carbon Climate-Resilient Urban Development Project

SRI: Local Government Enhancement Project

EBRD Performance Requirement 5

SRI: Integrated Road Investment Program

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE

Transcription:

SOCIAL SAFEGUARD DUE DILIGENCE REPORT Social Safeguard Due Diligence Report for proposed Additional Road Sections (Sindh Provincial Road Improvement Project SPRIP) (September 2018) PAK: Sindh Provincial Road Improvement Project (SPRIP) Prepared by Project Management Unit (PMU), Works and Services Department (WSD), Government of Sindh (GOS) for the Asian Development Bank.

(i) (ii) NOTES The fiscal year (FY) of the Government of the Islamic Republic of Pakistan and its agencies ends on 30 June. In this report, "$" refers to US dollars. This Social Safeguard Due Diligence Report for 3 proposed additional road sections is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Clients: Asian Development Bank Works & Services Department Government of Sindh SOCIAL SAFEGUARD DUE DILIGENCE REPORT FOR THE CONSTRUCTION OF A NEW BRIDGE AT CHAINAGE 44+224 UNDER ICB-04 SEPTEMBER 2018 SINDH PROVINCIALROAD IMPROVEMENT PROJECT (SPRIP) Loan No. 3305 PAK/Contract No. SPRIP CS1 This consultant s report does not necessarily reflect the view of ADB or the Government concerned and ADB and the Government cannot be held liable for its contents.

SOCIAL SAFEGUARDS DUE DILIGENCE REPORT FOR THE CONSTRUCTION OF A NEW BRIDGE AT ICB-04 CHAINAGE 44+224 SEPTEMBER 2018 MEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 2 of 11

TABLE OF CONTENTS SR NO DESCRIPTION 1 INTRODUCTION 5 Background 5 2 METHODOLOGY 7 3 FINDINGS 7 4 TRAFFIC DIVERSION PLAN 7 5 IMPACT ON INDIGENOUS PEOPLE 8 6 STAKEHOLDER CONSULTATIONS 8 Type of Participants (Stakeholders) 9 Future Consultation and Participation 10 7 GRIEVANCE REDRESS PROCESS 10 PAGE NO 8 CONCLUSIONS AND RECOMMENDATIONS 11

LIST OF ABBREVIATIONS ADB SPRIP FGD WSD GOS IR LAR GRC APs IP MPR NGO PIU ROW RD SPS ToR UTM RP VOC SC DP L/S Asian Development Bank Sindh Provincial Road Improvement Project focus group discussion Works and Services Department Government of Sindh involuntary resettlement land acquisition and resettlement plan grievances redress committee affected persons indigenous people monthly progress report non-governmental organization project implementation unit right of way reduced distance Safeguard Policy Statement terms of reference universal transverse mercator resettlement plan vehicle operating cost supervision consultants displaced persons left side Page 4 of 11 SMEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 4 of 11

1. INTRODUCTION Background 1. The Government of Sindh (GOS), with assistance from the Asian Development Bank (ADB) is rehabilitating six major provincial roads in Sindh covering 328 km of the provincial highway network. These six roads include: (i) Thull to Kandhkot, (ii)sheranpur to Ratodero, (iii) Khyber to Sanghar, (iv)sanghar to Mirpurkhas, (v) Tando Muhammad Khan to Badin, and (vi) Digri to Naukot. 2. The Project Rehabilitation works were limited to the existing right of way (ROW), which is 110 feet wide. Adjustments in the design were made to avoid impacting encroaching structures in the ROW as provided in the approved Social Safeguards Due Diligence Report prepared in May 2017 and are monitored by the Resettlement Specialist hired under the Project Management Consultants (PMC) for the project. Implementation of civil works in these 6 road packages is ongoing and is expected to be completed before January 2019. 3. Asian Development Bank (ADB) has approved variation order No. 2 for construction of a new bridge at Subproject-4 Sanghar-Mirpurkhas subproject. The new bridge would have width of 9.5 meters with approach slabs of 3 meters each on both sides and 60 meters length. Drawing of new bridge attached as figure-1. Figure 1 Drawing of New Bridge ICB-04 4. A social safeguard due diligence report has been prepared to assess if the construction of a new bridge will have involuntary resettlement (IR) risks that need to be addressed either through design adjustments, or compensated if cannot be avoided, Page 5 of 11 SMEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 5 of 11

following the ADB Safeguards Policy Statement (2009) and the loan covenants of the Project. Page 6 of 11 SMEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 6 of 11

2. METHODOLOGY 5. A survey was conducted in September 2018 by PMC Resettlement Specialist following professionals conducted field visit. i. Mr. Saeed uz Zafar Resettlement Specialist, PMC ii. Mr. Bhura Lal Resident Engineer ICB # 04 iii. Mr. Israr Ali iv. Mr. Shahnawaz Magsi Surveyor, PMC Surveyor, PMC 6. During the field survey, the team visited the bridge site and the diversion road to identify any social and resettlement impacts which may be caused by the construction of new bridge and selected diversion road. Consultation meetings were held with local people and notables for providing them information regarding construction of new bridge and selected diversion road. Local community was also consulted regarding social and likely resettlement impacts of the diversion road in compliance of ADB Safeguard Policy 2009. 3. FINDINGS Involuntary Resettlement Impact Assessment No Land acquisition is required for construction of the new bridge as itis to be constructed on existing alignment. No residential, commercial and religious importance structure was located at bridge site within ROW. 4. TRAFFIC DIVERSION PLAN 7. For uninterrupted flow various types of long route and local commuter traffic a diversion plan has been formulated by utilization of existing 14.5 Km length starting from Chainage42+00 and meets the project road at chainage53+240. Available width of diversion road is found 5.5 meters 2 lane road which is sufficient for movement of heavy trucks and passenger buses traffic without causing any traffic congestion. Diversion plan has been prepared by conducting preliminary involuntarily resettlement impact assessment survey along the populated areas located along the road and conducting consultation meetings and interviews with local communities. A detailed description of Diversion plan is described hereunder: Diversion road passes through following4 villages and there was one hotel was located atchange14+00. Team found no resettlement impacts on the whole stretch of the diversion road as shown in Table-1. Diversion road Sindhri Dilber Khan Meharis owned by Works Services department Govt. of Sindh which has been selected for diverting traffic for a limited period of time i.e, about 04 months. Page 7 of 11 SMEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 7 of 11

Table-1: Preliminary Involuntary Resettlement Impact Assessment Sr. # Chainage 1 2+500 Name of village Besham Brohi 2 6+000 Nako Stop 3 7+00 4 10+00 5 14+00 Dilber khan Mehar Kerio Shakh Hakeem Hotel Remarks 4 katcha shops were located on both sides of diversion road (figure-2). Shops were found located at sufficient distance from the road Shops were found located at sufficient distance from the road Shops were found located at sufficient distance from the road (figure-3). Hotel is located at sufficient distance from the road Figure 2 Shops located at the edge of diversion road at Besham Brohi Bazar Chainage 2+500 Figure 3 Shops located at sufficient distance from the diversion road at Nako Stop chainage10+000 5. IMPACT ON INDIGENOUS PEOPLE 8. The main castes located in the project area are Junejo, Syed, Soomro. Team observed that almost 90% are Kacha houses and remaining 10% are semi pacca houses scarcely located. The predominant language is Sindhi. None of these people may be considered as IP as defined in ADB SPS (2009). 6. STAKEHOLDERCONSULTATIONS 9. Consultations were made with the stakeholders and general public by the survey team. Consultative meeting was held to learn about the views and concerns of the public on the proposed construction of new bridge. In order to enhance the Project acceptability for the general public on social considerations. The main objectives of the consultation were to: Introduce the project Page 8 of 11 SMEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 8 of 11

Sharing full information with the stakeholders about the expected impact on the socioeconomic environment of the project corridor. Information was shared with them regarding formulation of diversion plan to safeguard social and resettlement issues in compliance of ADB Safeguard policy 2009. Ensure transparency in all activities related to social mitigation and resettlement matters. Receive feedback from stakeholders on their concerns regarding the project s input and mitigation measures suggested by them. Gather information regarding stakeholders' views about the project; TYPE OF PARTICIPANTS (STAKEHOLDERS) 10. Stakeholders who were consulted include shopkeepers, and notables of the area s such as shopkeepers, gov t employees and road users such as truck and bus drivers. 11. Consultation sessions were made with local community in September 2018. A list of consultations and participants is given in Table-2 In addition to these, official consultations were held with WSD officials and PMC to make the plan better and organized. Table-2: Consultations with Local People & Notables Serial NO. Date Location/ Venue Name of Main Participants Results of Consultations Besham Brohi Nasurallah S/O 1 11-Sept. 2018 Ghulam Ali Besham Brohi Muhammad Sadiq S/O 11-Sept. 2018 2 Muhammad Yousaf 3 11-Sept. 2018 Besham Brohi GulMunir S/O Ghulab 4 11-Sept. 2018 5 11-Sept. 2018 6 11-Sept. 2018 7 11-Sept. 2018 Besham Brohi Muqadar Ali S/O Fizal Ahmed Besham Brohi Yousaf S/O Ismial Keerio Shakh MuhramKeerio S/O Ghulam Haider Keerio Shakh PirBux S/O NabiBux Keerio Shakh Allah Warayo S/O 8 11-Sept. 2018 Bashir Warayo 9 11-Sept. 2018 Keerio Shakh Samano S/O Haji Jagan 10 11-Sept. 2018 Keerio Shakh Ghulam Haider S/O Ghulam Qadir The business of the shopkeeper would not be affected due to movement of diverted traffic. Safe and free mobility of locals especially women and children as well as safety measures to be taken during construction activities. Proper arrangements should be made for smooth and un interrupted flow of traffic passing through the road during the construction of the project works. Page 9 of 11 SMEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 9 of 11

Serial NO. Date Location/ Venue Name of Main Participants Results of Consultations 11 11-Sept. 2018 12 11-Sept. 2018 Hakim Lashari Stop Hakim Lashari Stop Rattan Kumar S/O GordanLal Naroo S/O Rana Due to long route and local commuter, Tea star and food hotel business will be increased. 13 11-Sept. 2018 14 11-Sept. 2018 15 11-Sept. 2018 Hakim Lashari Stop Hakim LashariStop Hakim Lashari Stop Jodhu S/O Dhano Lakhana S/O Alan Muhammad Anwar S/O Haji WaheedBux Speed breakers should be constructed in the built up area. Traffic signals must be installed at various points Figure 4 Consultation meeting with local shopkeepers at Besham Brohi at Chainage 20+500 Figure 5 Interview with shopkeepers at Keerio Shakh at Chainage 10+000 Future Consultation and Participation 12. Resettlement Specialist accompanied by PMU & Supervision Consultant staff will hold meetings with the local communities during construction and implementation stages so as to reduce potential damage to the properties of the of community reduce traffic accident possibilities. 7. GRIEVANCE REDRESS PROCESS 13. A grievance redress mechanism is already working under Deputy Director (Safeguards Quality Control), PMU for social monitoring of existing 6 roads for this purpose a Resettlement specialist has been hired through PMC. Page 10 of 11 SMEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 10 of 11

8. CONCLUSIONS AND RECOMMENDATIONS 14. This Due Diligence Report evaluates IR impacts due to construction of Bridge at ICB-04 Chainage 44+224. Due to construction activities no impact has been found because a good diversion motorable 2-lane road is already available which is owned by Works & Services Department and sufficient ROW of irrigation Channel and Highways Department is also available. Hence, it is assessed that safe mobility of the local communities, particularly women and children and their livestock will not be hindered by the diverted traffic during construction of new bridge. To ensure this, the following are recommended. Proper safety measures like traffic signs to be erected at interval of 100m. Warning signs like reduced speed will be erected. These cautioning signs must be placed commencing at least 1 km before the start of populated area. Proper care should be undertaken by the contractor to avoid accidental damage to the shop, residential houses and religious or community structures due to movement of heavy traffic. To avoid inconvenience to the locals due to noise, smoke and fugitive dust caused by movement of diverted traffic, the contractor should frequently sprinkle water on diversion road. In case of accidentally damaged/affected private structures (houses), compensation should be assessed and compensated promptly. ------------------ Page 11 of 11 SMEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 11 of 11