IceCube Project Monthly Report - October 2010

Similar documents
Increased drilling efficiency saved approximately 26,000 gallons of fuel.

IceCube Project Monthly Report - September 2010

IceCube Project Monthly Report April An IceCube collaboration meeting was held in Madison from April 29 th through May 3 rd.

FULL SCALE DOM PRODUCTION DETERMINE FULL DEPLOYMENT RATE DEPLOY INITIAL STRINGS & TANKS COMPLETE EHWD INTEGRATION & TEST

IceCube Project Monthly Report November 2007

IceCube Project Monthly Report - December 2009

Cost and Schedule Performance The project is 81.7% complete versus the plan of 82.2% complete, as measured using earned value techniques.

IceCube Project Monthly Report March DOM production is in progress at the three production sites world-wide and proceeding according to plan.

IceCube Project Monthly Report - December 2008

IceCube Project Monthly Report November 2006

IceCube Project Monthly Report December 2005

IceCube Project Baseline

Nearly all of the cargo needed for this season arrived by December 4 th.

IceCube Project Monthly Report April 2009

IceCube Project Monthly Report November 2005

IceCube Project Monthly Report June 2005

The IceCube Upgrade Marek Kowalski DESY & Humboldt-University Zeuthen-Meeting in Mainz September 2018

DM-Ice A Direct Dark Matter Search at the South Pole

Search for Dark Matter Captured in the Sun with the IceCube Neutrino Observatory

DM-Ice A Direct Dark Matter Search at the South Pole

Dark Matter Searches with AMANDA and IceCube

DOE s Office of Science and the FY2016 Budget Request

for the IceCube Collaboration

REPORT 2016/024 INTERNAL AUDIT DIVISION

Search for Dark. Dark Matter in LHC Era Kolkata 2011

DM-Ice: A Search for Dark Matter in the Antarctic Ice

Volume I Appendix A. Table of Contents

BIOMETRICS IN A HUMANITARIAN CONTEXT

Statement on Security & Auditability

REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL

Stanford Linear Accelerator Center

Choosing the Right Monitor for Your Application

DM-Ice. A direct detection experiment for dark matter at the South Pole

Approved Minutes Thursday, October 18, :00 P.M. Regular Meeting of the Hartford Parking Authority Board 155 Morgan Street, Hartford, CT 06103

IC Chapter 15. Ballot Card and Electronic Voting Systems; Additional Standards and Procedures for Approving System Changes

ORDINANCE NO. 7,592 N.S. ADDING CHAPTER 2.99 TO THE BERKELEY MUNICIPAL CODE, ACQUISITION AND USE OF SURVEILLANCE TECHNOLOGY

CONEJO VALLEY UNIFIED SCHOOL DISTRICT

Minutes of Regular Board Meeting December 19, 2018

STATE OF NEW MEXICO COUNTIES OF DOÑA ANA AND OTERO GADSDEN INDEPENDENT SCHOOL DISTRICT NO. 16

Cook County Emergency Telephone System Board

The ESO Observing Process

Maryland State Board of Elections Comprehensive Audit Guidelines Revised: February 2018

GEORGE MASON UNIVERSITY AGENDA FOR THE FACULTY SENATE MEETING FEBRUARY 7, 2018 Robinson Hall B113, 3:00 4:15 p.m.

NASA Budget and the Political Process

Training Calendar ALPHA PARTNERS

Key Considerations for Implementing Bodies and Oversight Actors

Special Report - House FY 2012 Department of Homeland Security Appropriations and California Implications - June 2011

REQUEST FOR QUALIFICATIONS RFQ No. CS PROGRAM MANAGEMENT SERVICES ADDENDUM #4

Global Conditions (applies to all components):

SEMIANNUAL REPORT TO THE CONGRESS

Members action as necessary on closed session items. 12 Future agenda items Members 13 Next meeting date Members 14 Adjourn Members

Last month, the federal Bureau of Labor Statistics (BLS), reporting on national

Ocean Observatories Initiative Julie Morris Division of Ocean Sciences National Science Foundation

Tackling Electrical System Efficiency, Safety and Reliability for pharmaceutical plants

The State of. Working Wisconsin. Update September Center on Wisconsin Strategy

-CITE- 41 USC TITLE 41 - PUBLIC CONTRACTS 01/07/2011 -EXPCITE- TITLE 41 - PUBLIC CONTRACTS -HEAD- TITLE 41 - PUBLIC CONTRACTS

The National Earthquake Hazards Reduction Program (NEHRP): Issues in Brief

Estonian National Electoral Committee. E-Voting System. General Overview

The Digital Appellate Court Introduction to the edca Electronic Portal

Tununuk Point (BAR-C) Remediation, NT

1 HB By Representative Chesteen. 4 RFD: Ways and Means Education. 5 First Read: 02-FEB-16 6 PFD: 01/29/2016.

Allegheny Chapter. VotePA-Allegheny Report on Irregularities in the May 16 th Primary Election. Revision 1.1 of June 5 th, 2006

April 1, RE: Florida Courts Technology Commission Yearly Report. Dear Chief Justice Labarga:

AVIATION AUTHORITY REGULAR BOARD MEETING. Thursday, December 3, :00 A.M. Boardroom Level 3 at Tampa International Airport DRAFT AGENDA

VOLUNTARY VOTING SYSTEM GUIDELINES DOCUMENT COMPARE SECTION 1

Amended Technical Indicator Descriptions

Position Paper IDENT Implementation for U.S. VISIT

Special Report - House FY 2013 Department of Homeland Security Appropriations and California Implications - June 2012

The National Earthquake Hazards Reduction Program (NEHRP): Issues in Brief

XMM-Newton Instrument Operations & Data Generation. J.R. Muñoz and the IOT members, SRE-OOX UGM#15, ESAC Apr 2014

State of the Judiciary

New Mexico Sentencing Commission

SLR 105 Form SLR105C must accompany this form 1 STATE OF TEXAS. Page 4 of 104. Records Retention Schedule

SECURITY, ACCURACY, AND RELIABILITY OF TARRANT COUNTY S VOTING SYSTEM

CHAPTER Committee Substitute for Committee Substitute for House Bill No. 687

NASS Resolution Reaffirming Support for the National Electronic Notarization Standards

The Angola National ID Card

Inventory Project: Identifying and Preserving Minnesota s Digital Legislative Record

CHAPTER 500. (Senate Bill 277) Vehicle Laws Speed Monitoring Systems Statewide Authorization and Use in Highway Work Zones

DEPARTMENT OF STATE ADMINISTRATION OF FOREIGN AFFAIRS

StuyPulse Team Charter

Key Considerations for Oversight Actors

LIVINGSTON COUNTY BOARD PROPERTY COMMITTEE MINUTES OF AUGUST 3, 2015

RESOLUTION NO

SWAN Administrators Quarterly Meeting

Dora Public Library 2014 Oregon Public Library Statistical Report

Public Services and Procurement Canada Departmental Oversight Branch

Government Gets High Marks for Response to Fires CALIFORNIA WILDFIRES DRAW LARGE AUDIENCE

Millennium Pipeline Company, L.L.C. 6 th Annual Customer Meeting October 14, Joe Shields President

SOLIND TRANSIT CAPITAL COMMITTEE MEETING Summary Minutes March 11,2010. (P) Julia Patterson, King County Councilmember

The documents listed below were utilized in the development of this Test Report:

ELECTIONS AND CAMPAIGN PROCEDURES

. ADVISORY COMMITTEE ON CAPITOL AREA SECURITY

BY-LAWS OF THE Queen Anne s County High School Band Boosters, Inc.

Budget and Finance Committee Minutes - June

DELAWARE PHOTOGRAPHIC SOCIETY, INCORPORATED BYLAWS. Article I Finance

Board of Directors Meeting Monday November 20, :30 p.m.

Fiscal Year 2020 Budget Proposals Public Defender (BU 0204)

Board of Directors Regular Meeting

Turning Missed Opportunities Into Realized Ones The 2014 Hollywood Writers Report

Transcription:

DOLLARS IN MILLIONS Accomplishments IceCube Project Monthly Report - October 2010 The first IceCube drillers departed for South Pole in late October to prepare the Seasonal Equipment Site for the upcoming drilling season. A readiness review was conducted in October for special devices that will be installed with the final Digital Optical Modules (DOMs) cables, e.g. the Swedish bubble camera. Data movement goals for the month of October were met. The project continues to conduct a series of reviews of the MREFC deliverables including the Data Acquisition, IceTop, Processing and Filtering, etc. The objective of these reviews is to ensure that the entire IceCube MREFC scope is complete. The final IceTop stations and IceCube strings will be installed in December 2010. 300 250 IceCube Project Baseline (M$) Initial In-Ice Strings & IceTop Tanks Installed Jan-2005 Initial Operational Capability Mar-2007 Project Completion & Closeout Sep-2011 Total Project Cost $279.5 Value of Foreign Contributions $37.4 NSF Funding $242.1 Remaining Contingency $4.0 Strings installed 79 Performance and Cost through: 30-Sep-10 235.3 260.8 273.6 279.2 279.5 275.5 231.6 199.4 200 FULL OPERATIONS & DATA ANALYSIS CAPABILITY 150 140.1 INITIAL OPERATIONS & DATA ANALYSIS CAPABILITY FULL SCALE DOM PRODUCTION 100 85.7 DETERMINE FULL DEPLOYMENT RATE Total Funds (US & NonUS) 50 39.5 Original Budget (BCWS) DEPLOY INITIAL STRINGS & TANKS Current Budget (BCWS) 97.3 % 15.0 Earned Value (BCWP) 97.3 % COMPLETE EHWD INTEGRATION & TEST Actual Cost (ACWP) 96.5 % 0 FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FISCAL YEAR Cost and Schedule Performance The project is 97.3% complete. Remaining contingency is $3.997 million. The NSF IceCube MREFC funding of $242.1 million remains unchanged since the project baseline was established in early 2004. 1

Actual Cost Performed Scheduled IceCube Neutrino Observatory Cost Schedule Status Report Reporting Period Ending: 9/30/2010 Note 1 Cumulative (AY K$) At Complete Note 4 Complete (%) OBS Structure L2 Budgeted Cost 2 Work Scheduled Work Performed Actual Cost of Work Performed Cost Variance Risk Contingency Note5 Assigned % Remain Work Budgeted AY $s Project Support 26,528 26,528 26,440 88.0 125 13.3% 27,471 96.6% 96.6% 96.2% Implementation 43,998 43,998 43,665 333.0 560 20.2% 46,767 94.1% 94.1% 93.4% Instrumentation 76,753 76,753 76,583 169.7 30 21.2% 76,895 99.8% 99.8% 99.6% Data Acquisition 33,855 33,855 33,855 0.6 0 0.0% 33,855 100.0% 100.0% 100.0% Data Systems 26,495 26,495 26,518-23.4 50 10.1% 26,989 98.2% 98.2% 98.3% Commissioning & Verification 20,562 20,562 20,544 18.2 25 28.9% 20,649 99.6% 99.6% 99.5% Pre Operations 4,772 4,772 4,637 134.5 50 10.2% 5,263 90.7% 90.7% 88.1% Subtotal 232,963 232,963 232,242 720.6 840 17.1% 237,889 97.9% 97.9% 97.6% RPSC SUPPORT 33,809 33,809 32,434 1,375.4 300 11.9% 36,323 93.1% 93.1% 89.3% NSF 1,188 1,188 1,188 0.0 15 20.0% 1,263 94.1% 94.1% 94.1% Total 267,960 267,960 265,864 2,096.0 1,155 15.4% 275,475 97.3% 97.3% 96.5% CONTINGENCY Note 3 3,997 IceCube Total Note 2 267,960 267,960 265,864 2,096.0 1,155 279,472 97.3% 97.3% 96.5% Notes: 1 Incorporates approved baseline changes. 2 Total Budget at Completion includes $37.4 M 3 Remaining Contingency is $4.0 M 4 The BAC (Budget At Completion), reflects PY9-10 detailed Baseline Review. 5 Contingency is assigned based on the remaining Technical, Cost & Schedule risks associated with the approved scope of work. The cost variance at the end of September 2010 was a favorable $2,096M, primarily due to Raytheon and NY Air National Guard FY10 on-ice fuel and labor cost savings. Contingency Status and Plans One change request on the amount of $596k was implemented this month to support Pre-Operations effort during the 2 nd half of Project Year 9 and slightly increases Project Support effort. 9/30/2010 Change Log - IceCube Total Project Budget Baseline ($K) No. Description Approval Date Total Baseline Allocated Budget Allocated Budget Change Contingency Budget CR166 Pre-Operations Budget Plan through Sep.2010-07/12/10 279,472 274,880 367 4,593 2nd phase NA Status as of July 2010 279,472 274,880 0 4,593 NA Status as of August 2010 279,472 274,880 0 4,593 CR167 Pre-Operations Plan through March 2011 and 10/07/10 279,472 275,475 596 3,997 Project Support Budget Replan NA Status as of September 2010 279,472 275,475 0 3,997 Reviews of MREFC subsystems continue and any additional resources necessary to ensure success are considered in the risk assessment process and can be addressed within available contingency. Remaining contingency will be adequate to complete the approved scope. A nocost extension was submitted to NSF requesting an extension of the project end date from March 31, 2011 to March 31, 2012 to accommodate activities associated with the final disposition of the IceCube Enhanced Hot Water Drill (EHWD); the orderly termination of construction activities; and the preparation of a comprehensive completion report on construction. 2

Risk Assessment & Potential Contingency Adjustments Item Estimate ($K) 1. Potential cost exposure for the approved scope of work based on Level 3 technical, cost and schedule risk assessment. $1,155K 2. Computing infrastructure and software development. $1,260K 3. Estimated cost to retro IceCube equipment/materials from the South Pole at the end of the project. 4. Potential labor cost to retain experienced personnel in the final year of construction to ensure that the final season will be a success. Total $1,050K $150K $3,615K Available Contingency as of Sep 30, 2010 $3,997K Drill Operation and Installation All readiness reviews were completed and equipment was shipped South. The South Pole Station opened in mid-october. In early November the first IceCube staff reached the South Pole. The Seasonal Equipment Site excavation plans were reviewed in October and the plan is for actual excavation to begin in early November. The Drill Control Center and Tower Operations housing essential do-not-freeze equipment remain powered and heated. The Northern Hemisphere Support Group (located in UW-Madison) was re-started to provide technical/logistical support to the on-ice team. The group provides dedicated contact points available 24/7 to respond to all support requests from the ice. The following off-ice activities were completed in October: A Special Devices Readiness Review was conducted for approved equipment. Drillers completed final preparations, procurements, and shipments, including repaired equipment and the Enhanced Hot Water Trencher. Hazard Analysis reviews were completed in October and Operating Procedure revisions finalized. EHWD Capital Equipment disposition was coordinated with NSF and Raytheon Polar Services Company (RPSC) for turnover of custodianship at end of construction. Plans for drill-hole water samples/testing was coordinated through RPSC and a New Zealand laboratory. This month the EHWD Test Bed/Training Facility at the Physical Sciences Laboratory was winterized and closed. 3

Detector Operations and Maintenance Detector Performance - Austral summer work began at the South Pole is underway. Two brief power outages at the ICL were observed since the South Pole station opened. The detector recovered well following both instances. A high detector up-time of 98.44% was achieved in October. The clean run up-time was 96.12%. Unscheduled downtime in October was caused by a routine DOM hub failure and an unusual DAQ issue that required the DOMs to be rebooted. Detector Up-Time: 98.44% Clean run Up-Time: 96.12% Unscheduled Downtime: 0.72% Definition of terms: Detector Up-Time is the percentage of time that data are acquired and delivered at an event rate of at least 500Hz. The up-time measurement includes periods in which the detector was taking data in a partial detector configuration or with light contamination from calibration sources. Clean run Up-Time is the percentage of time determined to have pristine data in the standard hardware and software configuration, with the full nominal detector enabled, no contamination from light sources, and for which no serious alerts were generated by the monitoring, verification or other systems. The criteria applied are not algorithmic but represent the Run Coordinator s overall impression of the data quality, including run uniformity. Fire suppression testing, a new power drop in the ICL, an extensive server upgrade, and numerous special test runs will impact detector up-time and clean up-time throughout the summer. Preventive planning to limit the impacts is in place and frequent communication among staff in the North and the South Pole is already underway to help mitigate issues as they arise. The IceCube Live (https://live.icecube.wisc.edu, access information available upon request) monitoring page was upgraded to allow for a more comprehensive annotation of the detector history for operators and physicists. The Crab flare analysis recently highlighted the integration of additional run quality information into IceCube Live, which looked at a transient event in IC79. Collaborators analyzing transient events now have a quick way to assess a run before the formal good run list is compiled. 4

A problem with a four-month-old flasher run was resolved, enabling the collection of verification data to reliably resume. Data acquisition will realize a significant change by the end of the year when the roughly three minutes of down-time between runs will be eliminated. The continual running of the detector will increase detector up-time by nearly 0.6%. The online filtering system is running smoothly with daily satellite transmission of filtered data to the northern data warehouse at the University of Wisconsin. We have made significant progress on the feasibility of writing a short data summary record (called a DST) for every event triggered by the DAQ in addition to the raw data for the selected filter events. This will aid in some analysis using down-going events (i.e., galactic center and moon shadow) as well as provide a possible source of data for eventual public availability. Data movement goals for the month of October were met, despite minor technical problems in the middle of the month. In two instances, the bandwidth provided by the satellite link fell to practically zero. IceCube was provided with additional bandwidth to resolve the backlog. A total of 2.34 TB of data were sent over the satellite, averaging 77.3 GB/day. A total of 21 TB of data were written to LTO tapes in October, averaging 696.3 GB/day. The figure below shows the daily satellite data transfer rates in MB/day for October. The steady IC79 filtered physics data, in blue, dominates the total bandwidth. Offline Filtering - Work continues on L3 data offline processing at the data warehouse. IC59 is the first run with a planned L3, which will reduce dataset sizes and split the sets out for the different working groups. The muon group successfully ran the data through L3 and other groups are in the process of getting it implemented. Work continues in preparing the L2 offline processing for IC79 run including investigating the possibility of a new Super DST. 5

Simulation - The IC59 simulation data are produced and processed with the latest software release. Production of the background physics datasets using CORSIKA resumed in mid-august after an increase in available storage capacity for the data. A dramatic increase in the production of neutrino signal simulation data and special simulation data compensated for the reduced background data production. Production sites: EGEE - German Grid; SWEGRID Swedish Grid; LONI Louisiana Optical Network Infrastructure; GLOW Grid Laboratory of Wisconsin; UMD University of Maryland; NPX3 UW IceCube; and, CHTC UW Campus. Figure 1: Left: Cumulative production of IceCube-59 background events with CORSIKA generator (continuous line) compared with 2010 plan (dashed line). Right: Relative contribution of production sites to the background production. Between June and August, the target of neutrino signal event generation, for all the types, exceeded the plan by more than a factor of two (see Figure 2) with a total of 18 CPU-years used. Figure 2: Left: Cumulative production of IceCube-59 neutrino events (continuous line) compared with 2010 plan (dashed line). The graph includes the generator of electron neutrinos, muon neutrinos and tau neutrinos. Right: Relative contribution of production sites to the neutrino signal production. 6

The summer pause was very active in the production of several benchmark datasets essentially aimed at systematic checks as noted below. The IC79 detector configuration for simulation purposes is finalized and the corresponding data production will start shortly. 1. Production of IC86 benchmark datasets for background and neutrino signal (all types) has exceeded the plan. These data serve multiple purposes, from testing a newly developed reconstruction algorithm for the newly deployed Deep Core detector, to the intensive study of offline processing of IC79. We will also use these data to study online data filtering strategies for 2011 science runs. 2. Benchmark datasets were produced with the newly developed direct photon propagation as an alternative to the current use of the bulky lookup photon tables. The simulation of Cherenkov light detected by IceCube requires the knowledge of ice optical properties. A new ice properties profile is under study and the generation of benchmark simulation datasets with direct photon propagation is necessary to perform high statistical comparisons with experimental data. 3. Dedicated physics datasets for IC40 were generated in DESY and in the Swedish Grid to address specific data analyses. Education and Outreach Seven IceCube scientists participated in a lab-wide open house at Lawrence Berkeley National Lab on October 2. Approximately 3,000 visitors attended the event. IceCube researchers interacted with visitors and provided hands-on displays for them. Engineer and driller Matt Newcomb educated groups of third grade and fifth grade classes in Cross Plains, WI. He talked about life in Antarctica, ice drilling with hot water, and some of the physics behind the project. Grad student Laura Gladstone and researcher Reina Maruyama presented to the Madison Area Women's Philanthropy Group about women in science. Francis Halzen, IceCube Principal Investigator, was profiled in an October 25 th video by Science Nation, a series commissioned by the NSF Office of Legislative and Public Affairs. The story received great feedback and continues to be picked up by a number of media outlets. The video is available at the following site: http://www.nsf.gov/news/special_reports/science_nation/icecube.jsp Albrecht Karle gave the plenary address at the Wisconsin Association of Physics Teachers annual meeting on October 29 th. This meeting was held in conjunction with the Minnesota Association of Physics Teachers and the Wisconsin Society of Physics Students. Prof. Karle brought the audience up-to-date on the IceCube construction project and recent analysis results. On November 1 st, collaborator Kirill Filimonov gave a talk at Sonoma State University in California as part of the public lecture series/undergraduate colloquium What Physicists Do. His talk, titled Extreme astronomy: Eyeing the cosmos through a cubic kilometer of ice was attended by over 100 people. 2011 Detector Completion Planning The next IceCube collaboration meeting will be held in Madison from April 26 May 2. An event commemorating the completion of the detector is planned for the afternoon of Thursday, April 28 th. 7

Upcoming IceCube Meetings and Events DAQ Subsystems and Test DAQ Review November 17-18, 2010 Monitoring & Verification Review November 30 December 2, 2010 On-line Processing & Filtering Review December 6-7, 2010 IceCube Collaboration Meeting, Madison April 25 May 2, 2011 IceCube Detector Completion Event April 28, 2011 Acronym List DAQ EHWD ICL MREFC RPSC Data Acquisition Enhanced Hot Water Drill IceCube Laboratory Major Research Equipment and Facilities Construction Raytheon Polar Services Company 8