FULL SCALE DOM PRODUCTION DETERMINE FULL DEPLOYMENT RATE DEPLOY INITIAL STRINGS & TANKS COMPLETE EHWD INTEGRATION & TEST

Similar documents
IceCube Project Monthly Report April An IceCube collaboration meeting was held in Madison from April 29 th through May 3 rd.

IceCube Project Monthly Report March DOM production is in progress at the three production sites world-wide and proceeding according to plan.

Cost and Schedule Performance The project is 81.7% complete versus the plan of 82.2% complete, as measured using earned value techniques.

IceCube Project Monthly Report November 2007

IceCube Project Monthly Report - December 2008

Increased drilling efficiency saved approximately 26,000 gallons of fuel.

IceCube Project Monthly Report November 2006

Nearly all of the cargo needed for this season arrived by December 4 th.

IceCube Project Monthly Report December 2005

IceCube Project Baseline

IceCube Project Monthly Report April 2009

IceCube Project Monthly Report - October 2010

IceCube Project Monthly Report November 2005

IceCube Project Monthly Report - September 2010

IceCube Project Monthly Report - December 2009

IceCube Project Monthly Report June 2005

The IceCube Upgrade Marek Kowalski DESY & Humboldt-University Zeuthen-Meeting in Mainz September 2018

DM-Ice A Direct Dark Matter Search at the South Pole

Amended Technical Indicator Descriptions

Dark Matter Searches with AMANDA and IceCube

Training Calendar ALPHA PARTNERS

Search for Dark Matter Captured in the Sun with the IceCube Neutrino Observatory

DOE s Office of Science and the FY2016 Budget Request

Sewage Disposal ARTICLE II SEWAGE RETAINING TANKS

Volume I Appendix A. Table of Contents

a GAO GAO HOMELAND SECURITY Performance of Information System to Monitor Foreign Students and Exchange Visitors Has Improved, but Issues Remain

Elections. Mission Statement. Mandates. Expenditure Budget: $1,583,167. General Government Expenditure Budget: $69,278,846

Key Considerations for Implementing Bodies and Oversight Actors

IC Chapter 15. Ballot Card and Electronic Voting Systems; Additional Standards and Procedures for Approving System Changes

Secretary of State Summary of Recommendations - House Historical Funding Levels (Millions)

DM-Ice A Direct Dark Matter Search at the South Pole

CONEJO VALLEY UNIFIED SCHOOL DISTRICT

-CITE- 41 USC TITLE 41 - PUBLIC CONTRACTS 01/07/2011 -EXPCITE- TITLE 41 - PUBLIC CONTRACTS -HEAD- TITLE 41 - PUBLIC CONTRACTS

ORDINANCE NO. 7,592 N.S. ADDING CHAPTER 2.99 TO THE BERKELEY MUNICIPAL CODE, ACQUISITION AND USE OF SURVEILLANCE TECHNOLOGY

OPERATING PROCEDURES of the Design Automation Conference Revised and Approved, August 29, 2016

Training Calendar ALPHA PARTNERS

OPERATING PROCEDURES of the Design Automation Conference Revised and Approved, October 9, 2017

Key Considerations for Oversight Actors

Welcome the Logistics Officer Association Professional Development Module 3, Show Me the Money. This module was developed by the Robins Air Force

Hon Hai Precision Industry Co., Ltd. Articles of Incorporation Chapter I General Provisions

GUILFORD COUNTY CONTRACT NO /95-211, AMENDMENT NO. 8 CITY OF GREENSBORO

COOS COUNTY AIRPORT DISTRICT REGULAR BOARD MEETING Thursday July 21, 2016

S-1. Supplementary Provisions. (Date of Enforcement) Article 1 These Articles of Agreement shall come into force as of July 1, 1999.

Special Report - House FY 2013 Department of Homeland Security Appropriations and California Implications - June 2012

APTA PRIMER ON TRANSIT FUNDING The Moving Ahead for Progress in the 21st Century Act and Other Related Laws, FY 2013 Through FY 2015.

Search for Dark. Dark Matter in LHC Era Kolkata 2011

EM s FY 2014 Appropriations Outlook

VII. Approval of Claims in an Amount Not-to-Exceed $9,511.76

Williamstown, MA September 28, :00 PM. Agenda

Options for New Jersey s Voter-Verified Paper Record Requirement

9-152 THE BUDGET FOR FISCAL YEAR 1990

Department of Homeland Security Appropriations: A Summary of Congressional Action for FY2013

MINUTES OF THE REGULAR MEETING OF THE MOUNT LAUREL TOWNSHIP MUNICIPAL UTILITIES AUTHORITY

The Health Center Funding Cliff: What YOU Can Do to Ensure Congress Acts to Fix the Cliff

REPORT 2016/024 INTERNAL AUDIT DIVISION

Town of Madawaska, ME. CSO Success Overcoming Funding & Design Challenges

ARCHITECT OF THE CAPITOL

Board of Directors Regular Meeting

STATE COURTS SYSTEM FY LEGISLATIVE BUDGET REQUEST Revised 2/17/14

Rider Comparison Packet General Appropriations Bill

IDS Terms and Conditions Guide Effective: 10/21/2005 Page 1 of 7

New Mexico Sentencing Commission

ST. CLAIR COUNTY COMMISSION MEETING SEPTEMBER 27, 2016

S P P U R C H A S I N G S P WI- 03 P U R C H A S E O R D E R G T C DATE OF ISSUE: 15/11/2015 REVISION: 01

This Addendum Number 1 to the above referenced IFB responds to a clarification question asked with the MST response.

Statement on Security & Auditability

Department and Branch Recommendations

DM-Ice: A Search for Dark Matter in the Antarctic Ice

TESTIMONY OF SENATOR CURT BRAMBLE PRESIDENT PRO-TEMPORE UTAH STATE LEGISLATURE President-elect, National Conference of State Legislatures

TYEE PTSA Job Descriptions

UNIVERSITY OF RHODE ISLAND FACULTY SENATE

WFP Mali SPECIAL OPERATION SO

AFRICA AS ONE P A N - A F R I C A N P R O G R A M M E

Office of the Commissioner of Lobbying of Canada

EVESHAM MUNICIPAL UTILITIES AUTHORITY. Meeting Minutes from December 7, 2016

M E M O R A N D U M. The Promontory project debt service will be funded with special assessment paid by the Promontory developer.

SOUTHWEST MOSQUITO ABATEMENT & CONTROL DISTRICT MEETING MINUTES March 12, 2009

RESEARCH COORDINATOR

1995 Settlement Agreement

COUDERSPORT BOROUGH AUTHORITY REGULAR MONTHLY MEETING NOVEMBER 19, :53 PM

AMENDED AND RESTATED VERDUGO FIRE COMMUNICATIONS SERVICE AGREEMENT BETWEEN THE CITIES OF BURBANK, GLENDALE, AND PASADENA AND THE CITY OF SIERRA MADRE

Board of Light, Gas and Water Commissioners220 S. Main Street

The Angola National ID Card

IT COMMITTEE Agenda Administration Conference Room Thursday, March 21, :00 p.m.

PYC BOARD RESPONSIBILITIES AND JOB DESCRIPTIONS 3/22/2018

UNHCR WASH MANUAL MONITORING AND REPORTING 361

for the IceCube Collaboration

WFP Somalia SPECIAL OPERATION SO

Reference services are provided through in-person visits, by telephone, via , through chat and by regular mail correspondence.

Forest Service Appropriations: Five-Year Trends and FY2016 Budget Request

SIAM Graduate Student Chapter. Rules of Procedure PURPOSE

municipalities shall have governmental corporate and proprietary powers to enable

SPECIAL INSPECTOR GENERAL FOR AFGHANISTAN RECONSTRUCTION CHIEF FOIA OFFICER REPORT FISCAL YEAR 2010

DEER ISLAND COMMUNITY DEVELOPMENT DISTRICT. Agenda Package. Board of Supervisors Meeting. Date & Time: Tuesday October 27, :00 a.m.

REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL

ELECTORAL COMMISSION. Annual Performance Plan 2014 Technical Indicator Descriptions

MINUTES OF REGULAR MEETING OF THE NORTH TAHOE PUBLIC UTILITY DISTRICT BOARD OF DIRECTORS

Science & Congress: a scientist's perspective from inside the House of Representatives

Proviso Township High School District 209 Financial Oversight Panel Meeting Regular Session March 24, 2017

MINUTES - TILLAMOOK COUNTY BOARD OF COMMISSIONERS' MEETING Monday, June 30, 2008 Page 1

Transcription:

IceCube Project Monthly Report - July 2008 Accomplishments The Integrated Master Schedule is currently being revised based upon RPSC support, flight changes and station opening constraints. Currently, Drilling begins on December 5 th, 2008, and provides for the installation of 19 strings and 19 IceTop stations. Procurements for spare parts have been made and are ready for shipment to the South Pole. Personnel have been identified and deployment dates have been coordinated. Data taking during July 2008 was excellent and we achieved an all-time peak of 98.6% clean runs suitable for physics analysis, with a steady flow of data from the South Pole to the IceCube Data Warehouse. Hardware has been purchased for upgrades to the South Pole computing system for the coming season and work is underway integrating and testing in preparations for shipping to the Pole in September. Automatic emails are now being sent whenever a DOM goes out of the normal range of its expected behavior. Eventually this system will be incorporated into IceCube Live. SafeStart training has started and is planned for all IceCubers deploying during the upcoming season. This training is about the importance of staying focused and teaches concepts on how to recognize your own mindset in order to avoid behaviors that place you in harm s way at the Pole. Cost and Schedule Performance The project is 85.8% complete versus the plan of 85.5% complete, as measured using earned value techniques. The Remaining Contingency is $9.9M which is 26.3% of the remaining work. 300 250 IceCube Project Baseline (M$) Initial In-Ice Strings & IceTop Tanks Installed Jan-2005 Initial Operational Capability 2007 Project Completion & Closeout Sep-2011 Total Project Cost $275.3 Value of Foreign Contributions $33.2 NSF Funding $242.1 Remaining Contingency $9.9 Contingency as % of Remaining Work 26.3% Strings installed 40 Performance and Cost through: 30-08 235.3 260.5 273.4 275.0 275.3 265.4 231.6 DOLLARS IN MILLIONS 200 150 100 85.7 140.1 199.4 INITIAL OPERATIONS & DATA ANALYSIS CAPABILITY FULL SCALE DOM PRODUCTION DETERMINE FULL DEPLOYMENT RATE FULL OPERATIONS & DATA ANALYSIS CAPABILITY 50 15.0 39.5 DEPLOY INITIAL STRINGS & TANKS COMPLETE EHWD INTEGRATION & TEST Total Funds (US & NonUS) Original Budget (BCWS) Current Budget (BCWS) 85.5 % Earned Value (BCWP) 85.8 % Actual Cost (ACWP) 85.5 % 0 FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FISCAL YEAR

Budgeted Cost 2 Actual Cost Variance Risk Contingency Note5 Work Work of Work Budgeted Actl OBS Structure L2 Scheduled Performed Performed Schedule Cost Assigned % ETC AY $s Sched Perf Cost Project Support 23,018.2 23,018.2 22,968.7 0.0 49.5 129.8 3.4% 26,832.6 85.8% 85.8% 85.6% Implementation 35,089.9 35,089.9 34,828.5 0.0 261.4 1,679.5 13.9% 46,939.7 74.8% 74.8% 74.2% Instrumentation 66,691.0 67,651.2 67,492.3 960.1 158.9 298.1 7.4% 71,498.0 93.3% 94.6% 94.4% Data Acquisition 33,278.6 33,278.6 33,245.8 0.0 32.7 77.7 14.1% 33,798.3 98.5% 98.5% 98.4% Data Systems 23,276.9 23,276.9 23,356.2 0.0-79.4 80.7 2.4% 26,666.6 87.3% 87.3% 87.6% Detector Comm. & Verification IceCube Neutrino Observatory Cost Schedule Status Report Reporting Period Ending: 6/30/2008 Cumulative (AY K$) Note 1 At Completion 18,746.6 18,746.6 18,785.8 0.0-39.2 178.9 9.1% 20,754.5 90.3% 90.3% 90.5% Pre Operations 613.5 613.5 545.1 0.0 68.4 0.0 0.0% 966.2 63.5% 63.5% 56.4% Subtotal 200,714.6 201,674.8 201,222.4 960.1 452.4 2,444.7 9.3% 227,456.0 88.2% 88.7% 88.5% RPSC SUPPORT 25,255.5 25,249.8 24,747.8-5.7 502.0 680.8 5.7% 36,672.2 68.9% 68.9% 67.5% NSF 861.6 861.6 861.6 0.0 0.0 24.1 6.0% 1,263.0 68.2% 68.2% 68.2% Total 226,831.7 227,786.2 226,831.8 954.5 954.4 3,149.5 8.2% 265,391.2 85.5% 85.8% 85.5% CONTINGENCY Notes 3 9,902.3 Note 2 IceCube Total 226,831.7 227,786.2 226,831.8 954.5 954.4 3,149.5 8.2% 275,293.5 85.5% 85.8% 85.5% Notes: 1 Incorporates approved baseline changes. 2 Total Budget at Completion includes non-us contributions 3,522 K over the amount in the post Hartill III baseline. 3 Budgeted contingency is: 26.3% of the Budgeted cost of work remaining. 4 The BAC (Budget At Completion), reflects PY7-10 detailed planning Baseline Re-Plan. 5 Contingency is assigned based on the ETC, a bottom-up risk assessment, management judgement, and cost constraints. Note 4 Complete (%) IceCube s Schedule Variance at the end of June 2008 is $955K. This favorable variance is driven entirely by Instrumentation Production. IceCube s Cost Variance at the end of June 2008 is $954K. RPSC s favorable $502K variance is mostly due to lower than planned FY08 labor and On-Ice support charges. The $261K favorable variance in Implementation is due to lagging invoices for Capital Equipment and M&S purchases and ramping down of Senior Engineers ahead of schedule. Contingency Status and plans 40% IceCube Contingency : % of Remaining Work 30% 26.3% 20% 10% 0% 04 04 Contingency Usage Implementation 61% Instrumentation 25% RPSC 11% DAQ 10% Project Support -10% Others 4% Sep- 04 Dec- 04 05 05 Sep- 05 Dec- 05 Annual Baseline Re-Plan 2005, 06, 07, 08 Additional IceTop Stations + Installation Season Instrumentation for >75 strings Launch RPSC FY2011 Season 06 06 Sep- 06 Dec- 06 07 07 Sep- 07 Dec- 07 08 08 During June 2008, the contingency percentage of remaining work has been decreased from 28.3% to 26.3% as a result of a baseline change request for Launching RPSC FY2011 Season.

6/30/08 Change Log - IceCube Total Project Budget Baseline ($K) No. Description Date Approved Total Baseline Allocated Budget Allocated Budget Change Contingency Budget Budgeted Cost of Work Remaining Contingency % of Remaining Work NA Status as of May 2008 275,293 264,423 0 10,871 38,403 28.3% CR126 Launch RPSC FY2011 06/11/08 275,293 265,349 926 9,944 Season CR125 Additional UW SC effort for DOM MB Software 07/16/08 275,293 265,391 42 9,902 NA Status as of June 2008 275,293 265,391 0 9,902 37,605 26.3% Item Risk Assessment & Potential Contingency Adjustments 1. Assign contingency to mitigate technical, cost and schedule risks associated with the defined scope of work. Risk applied at WBS-Level 4 to assess appropriate contingency as a percent of the cost of work remaining. 2. Pre-Operations Exposure for Upgrading Data Storage - 1st phase: upgrade the Data Storage and South Pole Systems to meet the collaboration's needs. 3. Pre-Operations Exposure for Upgrading Data Storage - 2nd phase: upgrade the Data Storage to meet the collaboration's needs. 4. Instrumentation critical path materials for up to 86 strings (Purchase 5 Surface to DOM cables, build ~100 DOMs) 5. Current RPSC estimate of base cost to support the installation of 6 strings during the 2010/11 drilling season. 6. The cost to retro IceCube equipment/materials from the South Pole at the end of the project in FY12, was not included in the baseline budget. 7. Potential cost exposure to additional fuel price increases beyond normal inflation and to transferring the installation of 4 strings from FY09 to FY11. 8. Potential cost exposure should a full FY11 drilling season be required resulting in the need to send UW personnel to the South Pole in FY12 to dismantle the drill equipment/materials and prepare the equipment for retro out of South Pole. 9. Potential cost to implement a retention plan to secure the continued services of the experienced and highly trained U.S drillers in the final two drilling seasons, FY10 and FY11. Estimate ($K) $3,150K $870K $700K $1,350K $1,340K $825K $600K $450K $250K 10. Potential cost of restoring Basler flights and original drilling start date of December 1, 2008. $300K Total $9,885K Available Contingency as of Jun 30, 2008 $9,902K Fuel Cost Increase Impact Analysis - IceCube actual costs are sensitive to increasing energy prices. The Antarctic Program s pump price paid for fuel that will be used during the FY2009 season was $2.85 per gallon. The price is expected to substantially increase for FY2010 and beyond. The project is evaluating the potential impact of higher fuel costs in the last two drilling seasons (FY2010 and FY2011) and for subsequent retro cargo transport (FY2012). This includes fuel for drilling, cargo transport, personnel at Pole, and heavy equipment use.

The project includes $150K for potential fuel cost increases in the WBS-Level 4 baseline risk assessment. We also includes an additional $600K potential contingency adjustment, for the extraordinary current pricing. The graphs below show the total cost exposure as a result of potential fuel cost increase. The right graph shows the impact of a 20 40% increase each year and the left graph shows a one time increase in FY2010 of up 20 40% and additional 2.5% inflation in FY2011 and FY2012. IceCube Fuel Cost Increase Impact Analysis $600 K FY10 20%, 2.5%, 2.5% 510 $500 K FY10 30%, 2.5%, 2.5% $400 K $300 K $200 K $100 K $0 K 382 255 192 147 102 FY10 40%, 2.5%, 2.5% FY10 FY11 FY12 70 39 54 FY09 Baseline fuel rates : 2.85 $/gal at the pump, 11.73 $/gal at the pole IceCube Fuel Cost Increase Impact Analysis $600 K 20% each year 510 $500 K 30% each year 382 424 40% each year $400 K $300 K 305 255 259 195 $200 K 178 $100 K 108 $0 K FY10 FY11 FY12 FY09 Baseline fuel rates : 2.85 $/gal at the pump, 11.73 $/gal at the pole Drill Operation and Installation The Integrated Master Schedule is currently being revised based upon RPSC support, flight changes and station opening constraints. Shipping activities are scheduled to begin this month. Off-ice activities for drilling including repairs, procurements, upgrades and spares are approximately 60% complete. All off-ice Installation activities have been completed and this area is prepared for the season. Procedure and Hazard Analysis reviews and revisions are complete. Procurements for spare parts have been made and are ready for shipment to the South Pole. Personnel have been identified and deployment dates have been coordinated with the current schedule. Digital Optical Module and Cable Production Status and Plans - DOM production is in progress at all 3 sites and is progressing smoothly. Surface to DOM cable production is on track. Procurement plans have been developed for instrumentation (primarily DOM hardware and cables) to restore IceCube to the originally planned 80 string configuration. This will include 15 surface cables and 6 surface-to-dom cables, and associated breakouts and connectors.

IceCube DOM Integration PY7 (April, 2008 to October, 2008) - Plan vs. Actual Plan to IC75+ with existing materials on hand with exceptions 4/18/08 (see Jonathan's email) 800 DOMs ready for DFL @ PSL - cumulative plan 700 600 DOMs ready for DFL @ DESY - cumulative plan DOMs ready for DFL @ Swed - cumulative plan DOMs ready for DFL - cumulative plan all sites DOMs ready for DFL - cumulative actual all sites 500 400 300 200 100 0 4/5/2008 4/12/2008 4/19/2008 4/26/2008 5/3/2008 5/10/2008 5/17/2008 5/24/2008 5/31/2008 6/7/2008 6/14/2008 6/21/2008 6/28/2008 7/5/2008 7/12/2008 7/19/2008 7/26/2008 8/2/2008 8/9/2008 8/16/2008 8/23/2008 8/30/2008 9/6/2008 9/13/2008 9/20/2008 Quantity of DOMs ready for DFL 9/27/2008 10/4/2008 10/11/2008 Week ending Detector Commissioning and Verification Verification continues to run since the start of IC40 data collection. The verification web page is now up and running and automatic emails are being sent to a small group of people whenever a DOM goes out of the normal range of its expected behavior. As before, minor problems have been found, although now the discovery time is shorter due to the webpage and emails. Eventually this system will be incorporated into IceCube Live, the detector control and monitoring system currently under development. The Bad DOM list, a compilation of DOMs deemed problematic or non-functioning by the DAQ team or by the Run Coordinator, will be used in official IC40 offline processing. Likewise, a Bad Run List has also been compiled and is being used as the starting point for selecting good runs for analysis purposes. (Working Groups are then expected to refine the basic criteria according to the specific needs of their analyses.) Calibration and Monitoring - A regular phone call has been established to focus on calibration issues, primarily on ice properties and the differences observed between simulation and data. Some effort has also been dedicated to understanding DOM-specific calibrations. Data Acquisition Software In July the DAQ S/W group cleared the path for a new release of DAQ software called BayWolf. This release will include a fix for the subthreshold bug #2 (loss of 0.1% of triggers due to sorting problem in the trigger system) and includes a feature enhancement for IceTop that will allow tank calibration information to be extracted from the physics data stream instead of requiring special calibration runs every month. Finally, the DAQ control infrastructure was instrumented with the ability to be controlled from either the existing experimental control infrastructure, anvil, or the new IceCube Live Web-2.0 framework currently under active development and slated for release spring 2009. The performance of the Aqua release was quite good during July. The monthly-averaged livetime reached an all-time peak of 98.6% clean runs suitable for physics analysis.

The day-by-day breakdown is shown in the following figure: DAQ S/W has received 3 new computing hosts to be installed in the ICL during the 2008/2009 season. These new machines will replace the 5 existing server-class computing hosts currently used by the DAQ and is made possible by improvements in computing hardware and the continual performance tweaks in the DAQ software. In addition a few of the DAQ developers were invited to present an IceCube talk at the 2008 Open Source Software Conference in Portland, OR (OSCON-08). This talk is posted at http://gallery.icecube.wisc.edu/internal/v/graphics/neutrinos_and_open_source.mov.html

IceCube Maintenance and Operations Detector Up Time 98.6% IceCube Clean Run Up-Time not including AMANDA Array 98.1% Unscheduled Downtime 0.2% Events from DAQ 3.35 billion IceCube Detector Operation for July 2008 Percentage of Day 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% Unscheduled Downtime Maintainance C&V Special Tests / commiss. of new strigs DOM Calibration Monthly Benchmark/Calibrations Partial IceCube + AMANDA Partial IceCube AMANDA Only IceCube Only IceCube+AMANDA 0% 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 Day Data collection during July 2008 was very smooth and hit an overall 98.6% uptime. The in-ice clean run uptime was 98.1%. Data Handling Routine data operations have continued since IC40 operations began in April. Operations have continued smoothly with a very high up time of the detector and steady flow of data from the South Pole to the IceCube Data Warehouse. The figure shows the data transferred over the TDRS SPTR system from July 1 to present.

Hardware has been purchased for upgrades at South Pole for the coming season and work is underway integrating and testing on the South Pole Test System in preparations for shipping to the South Pole in September. The Data Warehouse storage upgrade is close to finalized with the final components to be ordered before the end of August, with expected time to installation and move to operations by late October. Filtering, Software & Database - Filtering of IC40 data began on April 14, 2008 representing the full transition from IC-22 to IC-40. The Joint-Event Builder and Processing and Filter server (JEB/PnF) merging of IceCube-40 and Amanda TWR data streams continues at South Pole sending filtered data sets of about 35 GB/day over the satellite. Work continued on upgrading the PnF server with higher data throughput, which will accommodate the full 80 plus string detector when completed. Simulation - Mass simulation production with IceSim Version 2.2 to produce large background and signal Monte Carlo datasets for the physics working groups to prepare for IC-40 physics analysis continued in July. Education and Outreach Professor Jim Madsen and high school teacher Steve Stevenoski made the keynote address at the annual meeting of the Knowles Science Teaching Foundation (KSTF) on July 25 in Philadelphia. The Knowles Science Teaching Foundation supports individuals and programs designed to encourage and sustain young scientists and mathematicians as they dedicate their lives to teaching other young people and to becoming leaders in the field of education. KSTF Teaching Fellows are young men and women who have received a bachelor's or advanced degree in science, engineering or mathematics and are committed to teaching high school science and/or mathematics in U.S. schools. The fellowship supports them professionally and financially for up to five years through a teacher preparation program to eligibility for tenure. Following the presentation by Madsen and Stevenoski, the KSTF has agreed to support the preparation of one or two of their Teaching Fellows to go to the South Pole with IceCube during the 2009-2010 season (or 2010-2011) as well as to involve all of their 120 teaching fellows with IceCube in some way. Quality Assurance and Safety The Non-Conforming Material (NCM) process has been expanded to include the EHWD and the Winter Over equipment at the South Pole in addition to the analysis of failures or issues with DOM verification, test equipment, DOM components and production articles. All EHWD Hazard Analyses (HAs), have been finalized this summer and presented for Driller/Deployer training, in an effort to incorporate the seasons lessons learned. SafeStart training, being taught by NANA Systems, is planned for all IceCubers, deploying during the upcoming season. The training is about the importance of staying focused and teaches concepts on how to recognize your own mindset in order to avoid behaviors that place you in harm s way at the Pole. We now have 10 certified IceCube SafeStart Trainers that will train everyone at the Pole. In addition, the vast majority of the drillers received training and are certified to all five modules of the SafeStart Program. In addition to the regular CPR/AED & First Aid, and the OSHA based

training, the drillers were taught job specific procedures, basic electricity, basic plumbing/fittings, and rigging training.. The monthly reports are posted at IceCube Monthly Reports. Meetings and Events International Oversight & Financial Group Meeting TBD, September 2008 Fall Collaboration Meeting @ Utrecht, Netherlands September 15-19, 2008