IceCube Project Monthly Report November 2006

Similar documents
IceCube Project Monthly Report December 2005

IceCube Project Monthly Report November 2007

IceCube Project Monthly Report November 2005

IceCube Project Monthly Report April An IceCube collaboration meeting was held in Madison from April 29 th through May 3 rd.

IceCube Project Baseline

Cost and Schedule Performance The project is 81.7% complete versus the plan of 82.2% complete, as measured using earned value techniques.

IceCube Project Monthly Report March DOM production is in progress at the three production sites world-wide and proceeding according to plan.

FULL SCALE DOM PRODUCTION DETERMINE FULL DEPLOYMENT RATE DEPLOY INITIAL STRINGS & TANKS COMPLETE EHWD INTEGRATION & TEST

IceCube Project Monthly Report - December 2008

IceCube Project Monthly Report June 2005

Increased drilling efficiency saved approximately 26,000 gallons of fuel.

Nearly all of the cargo needed for this season arrived by December 4 th.

IceCube Project Monthly Report - December 2009

IceCube Project Monthly Report - October 2010

IceCube Project Monthly Report - September 2010

IceCube Project Monthly Report April 2009

The IceCube Upgrade Marek Kowalski DESY & Humboldt-University Zeuthen-Meeting in Mainz September 2018

DM-Ice A Direct Dark Matter Search at the South Pole

Dark Matter Searches with AMANDA and IceCube

IDS Terms and Conditions Guide Effective: 10/21/2005 Page 1 of 7

Training Calendar ALPHA PARTNERS

CUSTOMER CONTRACT REQUIREMENTS Communications Integration Kit CUSTOMER CONTRACT W904TE-14-M-0724

Historical unit prices - Super - Australian Shares

CUSTOMER CONTRACT REQUIREMENTS CH-47 Actuator CUSTOMER CONTRACT W58RGZ-13-D-0031

IDS Terms and Conditions Guide Effective: 1/24/2007 Page 1of 7 CUSTOMER CONTRACT REQUIREMENTS PPS Services CUSTOMER CONTRACT W58RGZ-06-C-0234

The Angola National ID Card

Key Considerations for Implementing Bodies and Oversight Actors

DM-Ice: A Search for Dark Matter in the Antarctic Ice

DM-Ice A Direct Dark Matter Search at the South Pole

Innovative installation techniques for fiber drop terminals. White paper

SF Summary of HIPER and Defective PTFs. I B M i P R E V E N T I V E S E R V I C E P L A N N I N G I N F O R M A T I O N

Common Terms and Conditions Guide Section 5 Government Contract Requirements Clause Number: 5061 Effective: 11/20/2002 Page: 1 of 6

BDS Terms and Conditions Guide Effective: 11/14/2012 Page 1 of 8

Training Calendar ALPHA PARTNERS

EXFO Care - Simulators

Grand Junction Regional Airport Authority Board Board Meeting *CORRECTED* Meeting Minutes October 17, 2017

Amended Technical Indicator Descriptions

REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL

IDS Terms and Conditions Guide Effective: 07/13/2009 Page 1 of 7 CUSTOMER CONTRACT REQUIREMENTS N C-0001 CUSTOMER CONTRACT N C-0001

VOLUNTARY VOTING SYSTEM GUIDELINES DOCUMENT COMPARE SECTION 1

CUSTOMER CONTRACT REQUIREMENTS (EA-18G System Development and Demonstration (SDD) Program) CUSTOMER CONTRACT N C-0005

CUSTOMER CONTRACT REQUIREMENTS PAC-3: Recertification Planning/Replenishment Spares CUSTOMER CONTRACT

Key Considerations for Oversight Actors

CUSTOMER CONTRACT REQUIREMENTS (GPS-IIF) CUSTOMER CONTRACT F C-0025

CUSTOMER CONTRACT REQUIREMENTS RAYTHEON LETTER SUBCONTRACT

1995 Settlement Agreement

SPECTRUM SHARING AGREEMENT

IDS Terms and Conditions Guide Effective: 10/21/2005 Page 1 of 8 CUSTOMER CONTRACT REQUIREMENTS F-15E CUSTOMER CONTRACT F C-0013

Public Services and Procurement Canada Departmental Oversight Branch

Members of the City Council of the City of Gulfport, Mississippi, held on the day ORDINANCE NO.

Tununuk Point (BAR-C) Remediation, NT

Secretary of State Summary of Recommendations - House Historical Funding Levels (Millions)

BDS Terms and Conditions Guide Effective: 08/24/2011 Page 1 of 7

Tariff 9900: OHD Percentage Based Fuel Cost Adjustment Historical Schedule ( )

Library Archives Commission Summary of Recommendations - Senate

Statement on Security & Auditability

Position No. Job Title Supervisor s Position Court Librarian Director, Court Services ( )

Internal audit in the Office of the United Nations High Commissioner for Refugees for the period from 1 July 2016 to 30 June 2017

"FAR" means the Federal Acquisition Regulation, issued as Chapter 1 of Title 48, Code of Federal Regulations.

h. Proposals shall include sufficient technical data to describe all changes from existing contract requirements.

CUSTOMER CONTRACT REQUIREMENTS T-38 Production CUSTOMER CONTRACT FA D-0001

This Addendum Number 1 to the above referenced IFB responds to a clarification question asked with the MST response.

Estonian National Electoral Committee. E-Voting System. General Overview

SUMMARY OF CHANGES IN ISO 9001:2008 (DRAFT INTERNATIONAL STANDARD)

IDS Terms and Conditions Guide Effective: 10/21/2005 Page 1 of 9

IDS Terms and Conditions Guide Effective: 11/18/2009 Page 1 of 8 CUSTOMER CONTRACT REQUIREMENTS B-52 CONECT LRIP CUSTOMER CONTRACT FA D-1000

Introduction to National Inventory System of energy sector

REPORT 2016/024 INTERNAL AUDIT DIVISION

IDS Terms and Conditions Guide Revised: 5/23/2006 Page 1 of 6

CASE STUDY 2 Portuguese Immigration & Border Service

IDS Terms and Conditions Guide Effective: 8/17/2006 Page 1 of 8

Butte County Board of Supervisors Agenda Transmittal

DHS Biometrics Strategic Framework

IDS Terms and Conditions Guide Effective: 05/11/2004 Page 1 of 8 CUSTOMER CONTRACT REQUIREMENTS ESGN CUSTOMER CONTRACT N C-0026

BRICKWORK APARTMENTS BODY CORPORATE

Digital research data in the Sigma2 prospective

Electricity Act, 1998 Loi de 1998 sur l électricité

Business Practice Group Report for the 2014 General Election

Telecommunications (Interception Capability and Security) Bill

Southern California Edison Original Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

CUSTOMER CONTRACT REQUIREMENTS P-8A (MMA) PROGRAM CUSTOMER CONTRACT N00019-C

8.130, 8.201, 8.235, 8.310, and 8.315, relating to General Applicability and Standards; Definitions;

-CITE- 41 USC TITLE 41 - PUBLIC CONTRACTS 01/07/2011 -EXPCITE- TITLE 41 - PUBLIC CONTRACTS -HEAD- TITLE 41 - PUBLIC CONTRACTS

CUSTOMER CONTRACT REQUIREMENTS PAC-3 LRIP-3 LOCKHEED MARTIN SUBCONTRACT UNDER GOVERNMENT CONTRACT DAAH01-02-C-0050

The Government of the United States of America and the Government of the United Arab Emirates,

RE: Quarterly Fish Passage Center Report for January March 2008

Office for Democratic Institutions and Human Rights OSCE/ODIHR DISCUSSION PAPER IN PREPARATION OF GUIDELINES FOR THE OBSERVATION OF ELECTRONIC VOTING

IC Chapter 15. Ballot Card and Electronic Voting Systems; Additional Standards and Procedures for Approving System Changes

American Border Patrol 2160 E. Fry Blvd. Sierra Vista, AZ 85635

NIGERIAN ELECTRICITY REGULATORY COMMISSION REGULATIONS FOR EMBEDDED GENERATION 2012

ROI CASE STUDY MARKLOGIC CQ ROLL CALL

IDS Terms and Conditions Guide Effective: 10/13/2006 Page 1 of 6

Volume I Appendix A. Table of Contents

Common Terms and Conditions Guide Section 5 Government Contract Requirements Clause Number: 5023 Effective: 10/15/2002 Page: 1 of 7

a GAO GAO HOMELAND SECURITY Performance of Information System to Monitor Foreign Students and Exchange Visitors Has Improved, but Issues Remain

VUSUMUZI MKHIZE 16 January 2017

4th International Industrial Supercomputing Workshop Supercomputing for industry and SMEs in the Netherlands

Service Level Agreement

Chapter 2.2: Building the System for E-voting or E- counting

SIGAR SEPTEMBER. Special Inspector General for Afghanistan Reconstruction. SIGAR Audit SIGAR Audit 13-17/Health Services in Afghanistan

Transcription:

IceCube Project Monthly Report November 2006 Accomplishments The first hole of the season, hole #58, commenced with firn drilling on December 11 th (the South Pole is 19 hours ahead of UW) and was completed on December 14 th. Installation of the first string was completed on Friday, December 15 th. NSF granted conditional occupancy of the IceCube Laboratory on December 8 th. IceCube personnel, with support from Raytheon, started moving equipment into the laboratory on December 9 th. IceTop installation is on schedule with six of the ten stations planned for this season now in place. The final stations will be in place by the middle of December. 100% 90% 80% 70% Scheduled, 63.4% IceCube Earned Value Performance Scheduled, 65.0% Performed, 65.0% Cost, 64.5% Percent Complete 60% 50% 40% 30% 20% 10% IceCube Project Baseline (M$) Initial In-Ice Strings & IceTop Tanks Installed Jan-2005 Initial Operational Capability Mar-2007 Project Completion & Closeout Sep-2011 Total Project Cost $274.7 Value of Foreign Contributions $32.6 NSF Funding $242.1 Contingency as % of Remaining Costs 26.4% # Strings/Tanks 70/160 0% A-06 M -06 J-06 J-06 A-06 S-06 O-06 N-06 D-06 J-07 F-07 M -07 Scheduled 54.5% 56.1% 57.9% 59.5% 60.9% 63.4% 65.0% 67.1% 69.1% 71.0% 73.7% 75.8% Performed 53.1% 54.8% 57.3% 58.7% 60.5% 62.6% 65.0% Cost 51.8% 54.8% 57.4% 59.0% 60.7% 62.6% 64.5% April 2006 - March 2007 Cost and Schedule Performance The project is 65.0% complete versus the plan of 65.0% complete, as measured using earned value techniques. The earned value measurement includes all tasks completed to date including design, development, procured materials, and the construction of the infrastructure that supports the seasonal installation plan, e.g., the hot water drill, cargo shipments, etc.

IceCube Neutrino Observatory Cost Schedule Status Report Reporting Period Ending: 10/31/2006 Cumulative To Date (AY K$) Budgeted Cost 2 Actual Cost Variance Contingency Latest Work Work of Work Budgeted Revised OBS Structure L2 Scheduled Performed Performed Schedule Cost Assigned % ETC AY $s Estimate Variance Sched Perf Project Support 19,481.1 19,366.7 19,103.3-114.4 263.4 793.8 7.7% 30,260.8 29,452.6 808.2 64.4% 64.0% 63.1% Implementation 25,283.9 25,370.9 25,446.6 87.0-75.7 7,212.1 39.3% 39,320.0 43,775.9-4,456.0 64.3% 64.5% 64.7% Instrumentation 45,490.4 45,692.0 45,153.4 201.6 538.7 3,330.7 14.7% 68,426.6 67,850.2 576.4 66.5% 66.8% 66.0% Data Acquisition 26,001.8 25,893.9 25,891.8-107.9 2.1 755.5 9.3% 33,998.9 33,998.9 0.0 76.5% 76.2% 76.2% Data Systems 16,523.8 15,964.5 17,393.3-559.2-1,428.8 1,776.5 22.3% 25,368.9 25,368.9 0.0 65.1% 62.9% 68.6% Note 1 At Completion (AY K$) Note 5 Complete (%) Actl Cost Detector Comm. & Verification 12,657.5 12,654.0 12,623.0-3.5 31.0 1,026.7 14.0% 19,962.4 19,962.4 0.0 63.4% 63.4% 63.2% Subtotal 145,438.5 144,942.1 145,611.4-496.4-669.3 14,895.3 19.9% 217,337.6 220,409.0-3,071.3 66.9% 66.7% 67.0% RPSC SUPPORT 17,484.2 17,772.7 15,921.4 288.5 1,851.3 8,004.7 36.1% 32,856.2 38,104.0-5,247.8 53.2% 54.1% 48.5% NSF 633.8 633.8 633.8 0.0 0.0 160.0 25.4% 1,263.0 1,263.0 0.0 50.2% 50.2% 50.2% Total 163,556.6 163,348.7 162,166.7-207.9 1,182.0 23,060.1 23.6% 251,456.9 259,775.9-8,319.1 65.0% 65.0% 64.5% CONTINGENCY Notes 3,4 23,228.7 14,909.6 8,319.1 IceCube Total Note 2 163,556.6 163,348.7 162,166.7-207.9 1,182.0 23,060.1 23.6% 274,685.5 274,685.5 0.0 65.0% 65.0% 64.5% Notes: 1 Incorporates approved baseline changes. 2 Total Budget at Completion includes non-us contributions 2,915 K over the amount in the post Hartill III baseline o$29,698 K 3 Budgeted contingency is: 26.4% of the Budgeted cost of work remaining. 4 Budgeted contingency is: 23.6% of the Estimated Cost to Complete (ETC) 5 The latest revised estimate equals either the budgeted cost of work remaining divided by the historical cost performance index, or a currently proposed baseline revision. 40% IceCube Contingency (% of Work Remaining) 30% 26.4% 20% 10% Original Baseline Annual Baseline RePlan Annual Baseline RePlan Additional Installation Seasons 10 n IceTop Stations 0% Jan-04 Apr-04 Jul-04 Oct-04 Jan-05 Apr-05 Jul-05 Oct-05 Jan-06 Apr-06 Jul-06 Oct-06 2

Change Log IceCube Total Project Budget Baseline ($K) No. Description Date Approved Total Baseline Allocated Budget Allocated Budget Change Contingency Budget Estimate To Complete (ETC) Budgeted Cost of Work Remaining Contingency % of Remaining Work NA CR74 Status as of Sep 2006 CR 0075 Implementation PY5 rebaseline correction 274,686 251,613 23,072 102,651 94,088 24.5% 11/15/06 274,686 251,457-156 23,229 97,609 88,108 26.4% High Level Risk Assessment & Potential Contingency Adjustments Item Spares, increased number of drillers (6 to 18 seasonal drillers), increased retro and maintenance costs may drive-up Implementation out-year budgets. Scope and higher unit pricing will increase the RPSC outyear budget baseline Restore 80-string configuration Potential draw on contingency due to a slow ramp up in operations support Potential Contingency Adjustments $4,500K $5,200K $5,600K $4,000K Notes This potential change will be addressed as part of the revised plan for construction completion. The completion plan is expected to be approved by April 1, 2007, following the third installation season at the South Pole This potential change will be addressed as part of the revised plan for construction completion. The completion plan is expected to be approved by April 1, 2007, following the third installation season at the South Pole Cost of instrumentation to restore the original 80 string configuration. Assigned against Commissioning. Currently working to reduce the funding requirements for operations. Drill Operation and String Installation IceCube personnel arrived at the South Pole about one week later than planned due to delays in the opening of the South Pole Station. The Station opening was delayed by weather conditions that were colder than normal. Repairs and modifications to the Enhance Hot Water Drill commenced during this time. All planned modifications and repairs were completed, with the exception of a minor RWS reconfiguration that was deemed unnecessary. Surveying and site preparation of the Seasonal Equipment Site (SES) was completed ahead of schedule. All of the Modular Drilling Structures were relocated to the SES as planned. Cables and hoses were laid out between the modules. Testing and troubleshooting was completed. There is a general problem with air getting drawn into the fuel lines for the burners. This will be addressed by the installation of return lines taking place in parallel with ongoing drilling operations. Following the completion of a series of readiness reviews organized by the IceCube On-Ice Lead, drilling of the first hole for the season commenced with firn drilling on December 11 th at 6:30 a.m. Firn drilling was completed to a depth of 50 meters in five hours. Main hole drilling commenced at approximately 9:00 p.m. December 11 th and was completed on December 14 th. The first string was successfully installed by Friday morning, December 15 th. 3

IceTop installation continues on schedule. Six trenches are complete with two tanks each and the DOMs installed. Four more IceTop locations (total of ten locations for this season) will be completed by the middle of December on schedule. The next phase includes the placement of the Surface Junction Boxes (SJB) into the trenches. This work is underway with SJBs installed in six trenches. DOM connections will be completed next week. Logistics Major shipments to the South Pole were completed after a slow start due to weather delays early in the season. There are no major cargo delivery issues at this time. Digital Optical Module and Cable Production Status and Plans - There are no major issues with instrumentation production. The plans provide instrumentation well in advance of the installation dates and support the use of the least expensive shipping methods. The actual status of DOM integration is provided in the following chart. IceCube DOM Integration PY5 (April, 2006 to March, 2007) - Plan vs. Actual 2000 1800 1600 1400 DOMs ready for DFL @ PSL - cumulative plan DOMs ready for DFL @ DESY - cumulative plan DOMs ready for DFL @ Swed - cumulative plan DOMs ready for DFL - cumulative plan all sites DOMs ready for DFL - cumulative actual all sites Quantity of DOMs ready for DFL 1200 1000 800 600 400 200 0 4/8/2006 4/22/2006 5/6/2006 5/20/2006 6/3/2006 6/17/2006 7/1/2006 7/15/2006 7/29/2006 8/12/2006 8/26/2006 9/9/2006 9/23/2006 10/7/2006 10/21/2006 11/4/2006 11/18/2006 12/2/2006 12/16/2006 12/30/2006 1/13/2007 1/27/2007 2/10/2007 2/24/2007 3/10/2007 3/24/2007 Week ending DOM Testing A total of 21 Final Acceptance Testing (FAT) cycles have been completed at the University of Wisconsin, DESY, and Uppsala. A total of 1,113 DOMs have been tested in the 21 FAT cycles. Detector Commissioning and Verification There is good progress on efforts to automate many of the high-level commissioning tests. The automated tests should be ready for testing before the end of the deployment season. A meeting at University of Maryland is scheduled for early December to install and test software to run many verification monitoring tasks on the unfiltered data at the South Pole. The AMANDA laser system was successfully set up and calibrated early in the South Pole season. The system is to provide in situ light for a study of the hole ice of IceCube string 48, 4

which is intentionally being deployed relatively close to AMANDA string 4. The laser system will provide light to fibers that terminate in diffuser balls at various depths along AMANDA String 4. The upgrade of the AMANDA TWR hardware at Pole will be completed at the end of the season. The AMANDA TWR system will connect with IceCube to form a joint detector. The old AMANDA muondaq system will be decommissioned. Data Acquisition System Hardware The primary deliverables for the DAQ hardware group are DOM Main Board Assemblies, a GPS/Master Clock Distribution system and DOM Hub Industrial Computers. DOM Main Board production continues to progress smoothly. The DOM Main Board assembly and test vendor has started loading and testing Main Boards and is on schedule to deliver fully tested units in early December. Delivery of Main Boards to LBNL for final test and QA was delayed by 2 weeks due to component procurement and loading issues, but the issues were resolved quickly and Main Board shipments to Integration sites will start up in December. Delivery of all components of the final version of the GPS/Master Clock Distribution system, which is used to distribute time codes and system clocks to all of the DOM/Hubs in the IceCube array, to support 80 In-Ice detector strings and the IceTop detector is complete. All of the DOM Hub computers for deployment this year have been shipped to UW. Final documentation checking is in process, and the handoff of DOM Hub production to UW should be complete by March 2007. Data Acquisition System Software Following the plan to re-implement large portions of the DAQ the development team began to move the existing DAQ code to a new source code repository and to factor out dependencies on the JBoss distributed framework. The opportunity to move to a new code repository was taken due to short-term and long-term support issues with the current repository which resides at LBNL. In the short term the LBNL repository computing hardware will need a significant amount of maintenance to keep it running. In addition, it now only hosts the DAQ software repository, the other IceCube software projects having migrated some time ago to the IceCube SVN repository; therefore, a long-term goal which pre-dated the new DAQ effort was to move the code to SVN. The JBoss distributed framework code is being factored out of the DAQ components to be replaced by a custom thin control system layered on top of XML-RPC. While JBoss offers a very rich feature set, the DAQ was only using a minimal subset the functionality of which is provided by the new control system. There is already a working version of this system in test. It also has the advantage that it is not Java-centric: Java objects are now being controlled by a central authority which is written in Python. The DAQ components, including the new StringHub component, are being outfitted with the proper software objects to operate as remotely-controllable network object in this scheme. On the timescale of 1-2 weeks we anticipate having a full set of DAQ components which will connect and flow data from DOMs to events on disk. 5

The complex configuration system has also seen a major overhaul. The Postgres database utilized in the older DAQ was discarded in favor of a simpler system which relies on XML files to contain the DAQ component and hardware configuration information. Again, the additional complexity of the RDBMS approach was not justified by the particular utilization and the simpler system provides equivalent functionality. The DOM configuration code, which represents by far the major portion of the configuration, is complete. The mechanism by which the configuration information is communicated to the downstream systems from the viewpoint of the DAQ requires no additional coding beyond handing an identification tag to PnF. The information that this tag represents is conveyed by a simple convention negotiated between the DAQ and online processing groups: the configuration files that bear this identifying tag are distributed to the online group in advance of their use in the DAQ. This obviates the existing problem of real-time delivery of a large set of constants from DAQ to PnF. Data Systems - Overall progress on Data Systems remains good with no major delays or cost variances. Equipment (~18 racks and associated computer equipment) for the South Pole System (SPS) that will be installed in the new IceCube Laboratory arrived at the South Pole. Equipment for the 64- bit computing South Pole Test System (SPTS-64) at the UW is online and being used for deployment testing of the South Pole software systems. Installation and upgrades of computing equipment for the Northern Hemisphere Tier 1 Data Center and upgraded storage capacity for the Tier 0 Data Warehouse at UW continues on schedule. Online filtering of data at the South Pole of select events for transmission continued with high efficiency and reliability since June 1 with no major problems through the season. Official filtering for last season ended in late November. Continued enhancements to the online and offline database tools for IceTray were delivered in preparation for deployment to the South Pole this year. Continued development on the Joint-Event-Builder (JEB), which will join the Icecube and Amanda TWR data streams into the PnF IceTray framework for online filtering of the joined events from the two arrays. This major milestone in the integration of the AMANDA detector into IceCube will allow us to turn off several legacy systems on AMANDA to save power at the South Pole and to make optimal use of the available satellite bandwidth. Interfaces and system integration planning for online filter/jeb to work with the new DAQ are being deployed this season. Simulation production with version 1.9.4 began this month. Progress is being made with the distributed production of simulation events. Several new institutions were added including non- US groups for the first time. Work continues on using GRID computing for simulation production through the GLOW cluster at UW. Planning for increased use of GRID computing is proceeding. Progress in experiment control continues with improvements in configuration infrastructure and detector monitoring web pages. New requirements and system design planning for compatibility with new the DAQ system is being developed. 6

Quality Assurance and Safety There was an accident at the South Pole on November 21 st when an IceCube seasonal driller injured his finger while operating the SIMCO drill used for exploratory holes. The injured driller was treated at the South Pole and flown to New Zealand for additional medical care. He has returned to work at the IceCube drill camp and will complete the remainder of the drilling season. An accident report was prepared and modifications to the drilling equipment, procedures, and training were implemented to reduce the chances of additional injuries. The accident response and decision to resume drilling with the SIMCO drill was coordinated with NSF and RPSC management. The monthly reports are posted at IceCube Monthly Reports. Construction Reports are posted at IceCube 2006-2007 Weekly Construction Reports. Meetings and Events Forecast for End of Drilling for the 2006/2007 Season January 30, 2007 Project Advisory Panel/Science Advisory Committee Meeting March 1-2, 2007 IceCube Collaboration Meeting, Lake Geneva, Wisconsin April 24-28, 2007 NSF Annual Review of the IceCube Project (tentative) May 2007 Cable Tower and Cable Bridge to the IceCube Laboratory 7

Alan Elcheikh, IceCube Drilling Manager, at the Completion of Firn Drilling on the First IceCube Hole of the 2006/2007 Season. 8