IceCube Project Monthly Report November 2005

Similar documents
IceCube Project Monthly Report December 2005

IceCube Project Monthly Report June 2005

IceCube Project Baseline

IceCube Project Monthly Report November 2006

IceCube Project Monthly Report April An IceCube collaboration meeting was held in Madison from April 29 th through May 3 rd.

IceCube Project Monthly Report November 2007

IceCube Project Monthly Report - December 2008

FULL SCALE DOM PRODUCTION DETERMINE FULL DEPLOYMENT RATE DEPLOY INITIAL STRINGS & TANKS COMPLETE EHWD INTEGRATION & TEST

IceCube Project Monthly Report March DOM production is in progress at the three production sites world-wide and proceeding according to plan.

Increased drilling efficiency saved approximately 26,000 gallons of fuel.

Cost and Schedule Performance The project is 81.7% complete versus the plan of 82.2% complete, as measured using earned value techniques.

Nearly all of the cargo needed for this season arrived by December 4 th.

IceCube Project Monthly Report - December 2009

IceCube Project Monthly Report - September 2010

IceCube Project Monthly Report - October 2010

IceCube Project Monthly Report April 2009

The IceCube Upgrade Marek Kowalski DESY & Humboldt-University Zeuthen-Meeting in Mainz September 2018

Dark Matter Searches with AMANDA and IceCube

DM-Ice A Direct Dark Matter Search at the South Pole

THE TEXT OF THE SAFEGUARDS AGREEMENT RELATING TO THE BILATERAL AGREEMENT BETWEEN INDIA AND THE UNITED STATES OF AMERICA

Case: 1:15-cv SO Doc #: Filed: 08/11/17 1 of 23. PageID #: 3143 EXHIBIT A

The Government of the United States of America and the Government of the United Arab Emirates,

Trust Fund Grant Agreement. (Second Palestinian NGO Project) between

The Saskatchewan Fire Code Regulations

1995 Settlement Agreement

RULES AND REGULATIONS BEAUMONT BASIN WATERMASTER

NORTH TEXAS MUNICIPAL WATER DISTRICT

IDS Terms and Conditions Guide Effective: 10/21/2005 Page 1 of 7

Amended Technical Indicator Descriptions

CHAPTER 7 TRADE IN SERVICES. Article 1: Definitions

REQUEST FOR FINAL ACTION AUDIT AUDIT OF TVA'S DIRECT LOAD CONTROL PROGRAM

DOE s Office of Science and the FY2016 Budget Request

The Angola National ID Card

DM-Ice A Direct Dark Matter Search at the South Pole

Fire safety basics for hot work operatives. CFPA-E Guideline No 12:2012 F

-CITE- 41 USC TITLE 41 - PUBLIC CONTRACTS 01/07/2011 -EXPCITE- TITLE 41 - PUBLIC CONTRACTS -HEAD- TITLE 41 - PUBLIC CONTRACTS

ENFORCEMENT DECREE OF THE SOIL ENVIRONMENT CONSERVATION ACT

LINKAGE TO STRATEGIC PLAN, POLICY, STATUTE OR GUIDING PRINCIPLE:

Section III. Contract for Supply and Delivery of Goods

GUNNISON COUNTY COLORADO NORTH FORK VALLEY COAL RESOURCE SPECIAL AREA REGULATIONS

RULES OF TENNESSEE PUBLIC UTILITY COMMISSION CHAPTER REGULATIONS FOR TELEPHONE COMPANIES TABLE OF CONTENTS

IC Chapter 15. Ballot Card and Electronic Voting Systems; Additional Standards and Procedures for Approving System Changes

TPI ASSIGNMENT, NOVATION AND FIRST AMENDMENT AGREEMENT

ICC CONSENSUS PROCEDURES

IACUC POLICIES, PROCEDURES, and GUIDELINES

ORDINANCE NO. 7,592 N.S. ADDING CHAPTER 2.99 TO THE BERKELEY MUNICIPAL CODE, ACQUISITION AND USE OF SURVEILLANCE TECHNOLOGY

South Florida Seaports Internal Conspiracy Project

Purchase Agreement (Goods)

Public Services and Procurement Canada Departmental Oversight Branch

Index of the Minutes Airports Commission June 3, 1997 SECTION ITEM TITLE NUMBER PAGE A. CALL TO ORDER: 3 B. ROLL CALL: 3 C. ADOPTION OF MINUTES: 3

LEGISLATIVE COUNSELʹS DIGEST

FIRST READING: SECOND READING: PUBLISHED: PASSED: TREATMENT AND DISPOSAL OF WASTEWATER BY LAND APPLICATION

Training Calendar ALPHA PARTNERS

Hon Hai Precision Industry Co., Ltd. Articles of Incorporation Chapter I General Provisions

BY LAWS OF THE NTID FACULTY CONGRESS. Each group elects or appoints one representative and one alternate.

RECORD OF PROCEEDINGS. XENIA TOWNSHIP TRUSTEES: August 20, :00 PM

FINANCIAL RECOVERY AGREEMENT

TOWN MANAGER S WEEKLY REPORT

IDS Terms and Conditions Guide Effective: 10/21/2005 Page 1 of 8 CUSTOMER CONTRACT REQUIREMENTS F-15E CUSTOMER CONTRACT F C-0013

Key Considerations for Implementing Bodies and Oversight Actors

IEEE POWER & ENERGY SOCIETY TECHNICAL COUNCIL ORGANIZATION AND PROCEDURES MANUAL. Approved: September 2008

5222 E. Baseline Road, Suite 101 Gilbert, AZ 85234

Common Terms and Conditions Guide Section 5 Government Contract Requirements Clause Number: 5061 Effective: 11/20/2002 Page: 1 of 6

BEFORE THE STATE OIL AND GAS BOARD OP MISSISSIPPI

PRO Hot Work

NFRC Manufacturer License Agreement

INDIANA UNIVERSITY Policy and Procedures on Research Misconduct DRAFT Updated March 9, 2017

8.130, 8.201, 8.235, 8.310, and 8.315, relating to General Applicability and Standards; Definitions;

Agreement between the Government of India and the International Atomic Energy Agency for the Application of Safeguards to Civilian Nuclear Facilities

Rocky Mountain Chapter BMW CCA Chapter Bylaws

Section moves to amend H.F. No as follows: 1.2 Delete everything after the enacting clause and insert:

2016 Statistical Yearbook. Republic of Palau Bureau of Budget and Planning Ministry of Finance

Welcome the Logistics Officer Association Professional Development Module 3, Show Me the Money. This module was developed by the Robins Air Force

IDS Terms and Conditions Guide Effective: 11/18/2009 Page 1 of 8 CUSTOMER CONTRACT REQUIREMENTS B-52 CONECT LRIP CUSTOMER CONTRACT FA D-1000

Desiring to cooperate in the development, use and control of peaceful uses of nuclear energy; and

Hot Work Program. Program Origination: October, 2017

TREATY BETWEEN THE GOVERNMENT OF CANADA AND THE GOVERNMENT OF THE UNITED STATES OF AMERICA ON PACIFIC COAST ALBACORE TUNA VESSELS AND PORT PRIVILEGES

The Dairy Producers Regulations, 1995

DM-Ice: A Search for Dark Matter in the Antarctic Ice

SUBCHAPTER 34C - CREMATORIES SECTION.0100 GENERAL PROVISIONS

BY-LAWS OF AMA DISTRICT 13 MOTORCYCLIST ASSOCIATION, INC.

THE ORISSA DISTRIBUTION AND RETAIL SUPPLY LICENCE, 1999 (WESCO)

Facilities Operations Policy and Procedures Statements System

MEMORANDUM OF AGREEMENT BETWEEN U.S. ARMY CORPS OF ENGINEERS AND U.S. GEOLOGICAL SURVEY

CUSTOMER CONTRACT REQUIREMENTS RAYTHEON LETTER SUBCONTRACT

Key Considerations for Oversight Actors

Safe Work Permit Practice

New Mexico Sentencing Commission

CHAPTER 1 RECORDS RETENTION AND DISPOSITION

SNOMED CT Grant of License of the Swedish National Release

Search for Dark Matter Captured in the Sun with the IceCube Neutrino Observatory

Zab Zab Application Privacy Policy Terms and Conditions

ARLINGTON COUNTY CODE. Chapter 55 UNDERGROUND UTILITY PROTECTION

Client Order Routing Agreement Standard Terms and Conditions

Environmental Protection Act

CHAPTER 25B. Change of Owner, Operator, or Guarantor for Certain Oil and Gas Facilities

ATOMIC ENERGY. Peaceful Uses of Nuclear Energy TREATIES AND OTHER INTERNATIONAL ACTS SERIES 12950

DEPARTMENT OF ENVIRONMENTAL QUALITY ENVIRONMENTAL RESPONSE DIVISION ENVIRONMENTAL CONTAMINATION RESPONSE ACTIVITY

Sewage Disposal ARTICLE II SEWAGE RETAINING TANKS

Training Calendar ALPHA PARTNERS

Transcription:

IceCube Project Monthly Report November 200 Accomplishments The annual IceCube construction season at the South Pole is underway. The project will conduct work at the South Pole from mid November through the first week in February 2006. The Enhanced Hot Water Drill seasonal equipment site is in place and operational. The start of deep ice drilling is currently forecast for December 18, 200. The second drill tower and operations structure was constructed and will be used this season so that deployment of IceCube strings can take place concurrently with drilling activities. An additional twenty-four IceTop tanks are located in twelve trenches with Digital Optical Modules installed. The tanks will be filled with water beginning on December 1, 200. The South Pole System for data handling for the 2006 is now operational in the Temporary Counting House. The system is available to the data acquisition team. DOM testing at the South Pole in support of this season s installation goals is well advanced with failure rates of roughly 2%. External modifications to the permanent counting house (IceCube Laboratory) are underway and material is being staged at the Laboratory for the internal work planned for this winter. 100 ICECUBE - TOTAL Cost / Schedule Performance Percent Complete 90 80 70 60 0 0 30 20 IceCube Project Baseline (M$) Initial In-Ice Strings & IceTop Tanks Installed Jan-200 Initial Operational Capability Mar-2007 Project Completion & Closeout Sep-2010 Total Project Cost $273.1 Value of Foreign Contributions $31.0 NSF Funding $22.1 Contingency as % of Remaining Costs 28.3% # Strings/Tanks 70/10 9.1 8.0 6.1 8.0% Complete 10 0 3& 1&2 3& FY03 FY0 FY02 FY0 A-0 M-0 J-0 J-0 A-0 S-0 O-0 N-0 D-0 J-06 F-06 M-06 FY07 FY06 FY08 FY09 FY10 FY11 Scheduled % 2.3 10.0 23. 3.6 36.2 38.9 0.7 3.0.9 7. 9.1 0.7 3.7.6 8.0 9. 70.6 82.9 92.0 97.0 99. 100.0 Performed % 2.3 8.9 22.3 32.9 36.0 36.8 39.2 1.3 3.6 6. 8.0 Cost % 2.3 8.8 23.0 31.9 3.0 3.6 38.0 39.9 3.6.7 6.1 Fiscal Months, Quarters & Years

Cost and Schedule Performance The project is roughly 8% complete versus the planned performance of 9.1% complete as measured using earned value techniques. The earned value measurement includes all tasks completed to date including design, development, procured materials, and the construction of the infrastructure that supports the current seasonal installation plan, e.g., the hot water drill, cargo shipments, etc. The total contingency percentage (contingency/cost-to-complete) as a function of time is shown at the end of this report. Reporting Period Ending: 10/31/200 Cumulative To Date (AY K$) At Completion (AY K$) Complete (%) Budgeted Cost 2 Actual Cost Variance Latest Work Work of Work Budgeted Revised OBS Structure L2 Scheduled Performed Performed Schedule Cost AY $s Estimate Variance Scheduled Performed Actual PROJECT SUPPORT 1662.3 1666.3 192.0.0-27.7 3018.9 303.6-27.7 1.9% 1.9% 2.8% IMPLEMENTATION 1936. 19299.2 1888. -7.3 13.6 322.6 32011.9 13.6 9.7% 9.% 8.2% INSTRUMENTATION 3087.7 30128.3 29821.7-76. 306.6 68.0 611. 306.6 7.2% 6.0%.6% DATA ACQUISITION 2029. 20226.0 2078. -303.3-32. 3286.6 33217.0-32. 62.% 61.% 62.6% DATA SYSTEMS 1027.2 9863.2 9817.3-66.0.9 2017.6 2971.7.9 2.1% 39.% 39.2% DETECTOR COMM. & VERIFICATION IceCube Neutrino Observatory Cost Schedule Status Report 1 760.0 738.0 6911.2-22.0 26.8 1882.0 18298.2 26.8 39.6% 39.% 36.7% RPSC SUPPORT 12077. 11260.0 72.2-817. 3817.8 320. 28236.7 3817.8 37.7% 3.1% 23.2% NSF 02.1 02.1 02.1 0.0 0.0 1263.0 1263.0 0.0 39.8% 39.8% 39.8% Sub Total 116989.6 11383.1 109882. -2606. 00.7 23808.2 23383. 00.7 9.1% 8.0% 6.2% Management Reserve Total Contingency 3,969.1 39,69.8,00.7 Items Outside of Approved Baseline IceCube Neutrino 116,989.6 11,383.1 109,882. -2,606.,00.7 273,03.3 273,03.3 0.0 9.1% 8.0% 6.2% Observatory 2 Notes: 1 Incorporates approved and currently pending baseline changes. 2 Total Budget at Completion includes non-us contributions $1,283K over the amount in the post Hartill III baseline. 3 The budgeted contingency 28.3% is: of the Budgeted cost of work remaining. Drill Construction and Operation The hot water drill set up and commissioning for the 200/2006 season is progressing satisfactorily. The forecast date for the start of drilling is Sunday, December 18 th, one week later than the original plan. The IceCube Rod Well is operational and the commissioning of the main heating plants is underway. The second tower was constructed and will be used this year to allow the string deployment and drilling to take place concurrently. New hose is now being spooled onto the large hose reel. It is clear that the steps taken to increase the size of the drilling crews and to ensure technical depth in key areas is paying off along with the benefits of retaining almost the entire crew from last year. A series of drilling readiness review activities were completed the weekend of December 10 th including: Preliminary Readiness Assessment w/ IceCube Leadership December 10 th Project Director s Readiness Discussion w/ Drill Crew December 11 th IceCube Open House and Tours December 11 th Readiness Review Meeting w/ IceCube, RPSC, and NSF December 11 th 2

In addition special tours for South Pole Station emergency response personnel were conducted over that weekend. IceCube will conduct an emergency drill prior to the start of drilling. A final decision to proceed with drilling will be made once all technical work is complete and an assessment of the readiness of the drill crew is made. During the construction and commissioning of the drill there were two incidents that warranted detailed study and documentation given the potential safety and environmental implications. The first incident was the overheating of a Rod Well System (RWS) burner. The burner was turned on when water flow was not present causing the burner to overheat. There was no permanent damage to the burner and the staff commissioning the burners responded promptly by shutting down fuel to the RWS. A detailed incident investigation was conducted and an incident report prepared that identifies root causes, findings, and recommended corrective actions. The second incident involved overfilling of the day tank used to distribute fuel. The system runs automatically but the high level trip failed to engage resulting in fuel spilling into the secondary basin that is designed to ensure that fuel does not spill onto the ground. Like the burner incident there were no direct adverse impacts but the critical nature of the system warranted and incident investigation and report. In both cases Raytheon and NSF were notified of the incidents. Digital Optical Module and Cable Production Status and Plans - The status of DOM production for 200 is provided in the chart below along with the DOM, cable, and tank production plan for 200 2008. There are no major issues with instrumentation production. The plans provide for instrumentation well in advance of the installation need dates and allows the project to exploit inexpensive shipping methods. 1000 IceCube DOM Production PY(CY200) - Summary Revision 7/12: Change shipping dates and quantities to more accurately reflect DOM production progress to date. DESY to keep all CAEN HV units. 900 DOMs ready for DFL @ PSL - cumulative plan DOMs ready for DFL @ DESY - cumulative plan 800 DOMs ready for DFL @ Swed - cumulative plan DOMs ready for DFL - cumulative plan all sites DOMs ready for DFL - cumulative actual all sites Quantity of DOMs ready for DFL 700 600 00 00 300 200 100 0 3//200 3/12/200 Summary: 1. PSL integrates 610 DOMs from /2 to 9/3, ships 8 DOMs (includes 16 from CY200). 2. DESY integrates 160 DOMs from /23 to 8/6, ships 108 ( includes 12 from CY200, hold back 6 CAEN HV units). 3. Sweden integrates 160 DOMs from /30 to 8/27, ships 1 ( includes 2 from CY200 ) 3/19/200 3/26/200 /2/200 /9/200 /16/200 /23/200 /30/200 /7/200 /1/200 /21/200 /28/200 6//200 6/11/200 6/18/200 6/2/200 Week ending 7/2/200 7/9/200 7/16/200 7/23/200 7/30/200 8/6/200 8/13/200 8/20/200 8/27/200 9/3/200 9/10/200 9/17/200 9/2/200 10/1/200 10/8/200 3

IceCube DOM, Cable and Tank Production CY200 - CY2008 for 80 strings installed 90 80 Cable Systems 70 60 Equivalent InIce strings 0 0 30 IceTop Tanks DOMs Strings installed in ice at Pole 20 10 0 7/2/200 9/2/200 11/2/200 1/2/200 3/2/200 /2/200 7/2/200 9/2/200 11/2/200 1/2/2006 3/2/2006 /2/2006 7/2/2006 9/2/2006 11/2/2006 1/2/2007 3/2/2007 /2/2007 7/2/2007 9/2/2007 11/2/2007 1/2/2008 3/2/2008 /2/2008 7/2/2008 9/2/2008 11/2/2008 1/2/2009 3/2/2009 /2/2009 7/2/2009 9/2/2009 11/2/2009 1/2/2010 Week ending The production goals for this calendar year were to produce 16 surface-dom cables, 16 surface cables, and 930 DOMs. These goals will be met. Cargo Shipments to the South Pole Cable shipments this season to McMurdo via ChristChurch include twelve surface cables and eight surface-to-dom cables. An additional five surface cables and six surface-to-dom cables will be sent directly to McMurdo on the annual supply vessel and stored at McMurdo. There was about a week interruption in deliveries to the South Pole during early December. There are immediate impacts on the schedule for trenching due to the lack of surface cables. This has slowed progress on IceTop as the surface cables are needed to begin filling the surface tanks with water. There are also a few items that are critical for progress on the drill. The IceCube Logistics Manager, Terry Hannaford, is working with his counterparts in RPSC and NSF to ensure that IceCube priorities are adhered to the impacts of cargo delays are minimized. Final Acceptance Testing of DOMs The first pass yield of DOMs passing final acceptance tests in the dark freezer laboratories is routinely approaching 90% on average, a long-term goal for the project. The second pass yield is 9%. A final FAT cycle that was used to test second pass DOMs is complete and the freezer is now at room temperature. The results of this FAT cycle will be available in about one week. The delay in the analysis of the test results is due to the fact that key personnel are on travel. Hagar Landsmann recently arrived at the South Pole to test DOMs and Claire Petterson is now on traveling back after a few weeks of DOM testing at the South Pole.

String and IceTop Commissioning All 76 IceCube DOMs at the South Pole are operating and reading data (60 DOMs on the string and 16 DOMs in eight surface tanks). Overall, the quality of the data from the first string and the eight IceTop tanks is very good. The IceCube scientific collaboration is evaluating data from AMANDA and the initial IceCube instrumentation. Plans are in place for verification and commissioning the strings and surface tanks that will be installed during the 200/2006 season. The basic strategy for string commissioning is to conduct detailing performance testing on only a few strings and a minimal set of tests on the rest of the strings. Data from the existing IceCube string is currently extracted using a test version of the data acquisition software. Recently there has been very good progress preparing the final data acquisition software. Modules of the software is now being uploaded onto the first string and surface computing hardware and the full software chain will be run on the South Pole System (SPS) in late December or early January. A technical review of the DAQ system is planned for early March 2006. The review will respond to the results from this coming season. System Testing The South Pole Test System, a mirror image of the SPS, continues to provide a critical test bed for the data acquisition and data handling software. Data Systems The data handling systems required for the 200/2006 were installed in the temporary counting house (future optical module laboratory) and are now fully operational. The IceCube Laboratory or permanent counting house will be available on December 1, 2006. Quality Assurance & Safety There are no significant quality assurance issues to report. Hank Leweling, Safety Manager, is now at the South Pole and is conducting weekly formal inspections of the drill camp and towers. In addition there are weekly safety meetings and there is also a plan being developed for an emergency drill prior to the start of drilling. An incident report was prepared for the Rod Well System heater incident and another is being prepared for minor spill associated with the day fuel tank. The monthly reports are posted at IceCube Monthly Reports. The IceCube 200-2006 Weekly Construction Reports are posted at IceCube 200-2006 Weekly Construction Reports. Meetings and Events Drill Advisory Panel Meeting March 27-28, 2006 Panel Advisory Panel Meeting March 29-30, 2006 Science Advisory Committee Meeting March 30-31, 2006 IOFG April 3-7, 2006 Collaboration Meeting-Baton Rouge, LA April 10-1, 2006 NSF Annual Review May 30-June 1, 2006

Contingency % of ETC 30.0% 28.3% Annual Baseline Replanning 20.0% 10.0% 0.0% 0 toc g-0 Au n-0 Ju r-0 Ap b-0 Fe c-0 De t-0 Oc g-0 Au n-0 Ju r-0 Ap b-0 Fe IceTop DOM installation by Tom Gaisser and Len Shulman, Bartol Research Institute. 6

Farshid Feyzi, UW Physical Sciences Laboratory, inside the IceCube drill tower during the IceCube Open house at the South Pole. Hagar Landsmann, UW Physics, inside the IceCube DOM testing building during the IceCube Open house at the South Pole. 7