BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON DR 10, UE 88, UM 989

Similar documents
BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON DR 10, UE 88, UM 989

IN THE COURT OF APPEALS OF THE STATE OF OREGON

Oregon Theodore R. Kulongoski, Governor

ENTERED 02/13/08 BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON. DR 10, UE 88, and UM 989 ) ) ) ) ) ) ) ) ) ) ) ) ) )

TEL (503) FAX (503) Suite S.W. Taylor Portland, OR November 8, 2007

Case 3:17-cv PK Document 9 Filed 02/08/17 Page 1 of 11

If!~ PACIFIC POWER A DIVISION OF PACIFICORP

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON

TEL (503) FAX (503) Suite SW Taylor Portland, OR April 24, 2008

March 3, An extra copy of this cover letter is enclosed. Please date stamp the extra copy and return it to me in the envelope provided.

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM I. INTRODUCTION The Oregon Citizens Utility Board and the Alliance of Western Energy Consumers

IN THE CIRCUIT COURT OF THE STATE OF OREGON FOR THE COUNTY OF MULTNOMAH

DOCKET UM 1182: In the Matter of an Investigation Regarding Competitive Bidding

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UE and OAR , and by this Petition asks the Public Utility Commission of

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON

May 13, In the Matter of PACIFICORP 2009 Renewable Energy Adjustment Clause Docket No. UE 200

1\V\cb,UA L.1(tLLtJ~/,I~ Andrea L. Kelly ~ Vice President, Regulation. UE Renewable Adjustment Clause Motion for General Protective Order

UM 1802 PacifiCorp s Second Motion to Amend the Procedural Schedule and Withdrawal of June 28, 2017 Motion

CABLE HUSTON. July 20, 2012 VIA ELECTRONIC FILING & FIRST CLASS MAIL

2017, by Dayton Solar I LLC, Starvation Solar I LLC, Tygh Valley Solar I LLC, Wasco

August 13,2009 UM INVESTIGATION INTO INTERCONNECTION OF PURPA QF LARGER THAN 10MW

July 13, In the Matter of PACIFIC POWER & LIGHT Request for a General Rate Increase in the Company's Oregon Annual Revenues Docket No.

DEPARTM.ENT OF JUSTICE GENERAL COUNSEL DIVISION. March 2, 2015

Re: UM Idaho Power Company's Application for Deferred Accounting of Revenue Requirement Variances Associated with the Langley Gulch Power Plant

McDo~rell Rackner & Gibson PC

UM 1824 Oregon Investigation into PacifiCorp s Oregon-Specific Cost Allocation Issues

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM 1658 ) ) ) ) ) ) ) ) Pursuant to ORS and OAR (2), the Industrial

September 15,2009 MOTION TO ADMIT TESTIMONY (WITH AFFIDAVITS)

Case 1:04-cv EGS Document 9 Filed 01/21/2005 Page 1 of 14

ADMINISTRATIVE RULES FOR CONTESTED CASE HEARINGS MUNICIPAL EMPLOYEES RETIREMENT SYSTEM OF MICHIGAN. Effective June 1, 2016 Amended June 19, 2017

Diane Henkels, Attorney at Law

Y Richard George Assistant General Counsel )1,~~ REQUEST FOR CHANGE TO SERVICE LIST. Via Electronic Filing and U.S. Mail RE:UM1610.

ORAL ARGUMENT NOT YET SCHEDULED IN NO ORAL ARGUMENT HELD SEPTEMBER 27, 2016 IN NO

PUBLIC UTILITY COMMISSION OF OREGON STAFF REPORT PUBLIC MEETING DATE: October 11, 2016

l/yf3~ September 6, Rc: UE Attention Filing Center: Enclosed for filing in the captioned docket are an original and five copies of:

An extra copy of this cover letter is enclosed. Please date stamp the extra copy and return it to

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM 1877-UM 1882, UM 1884-UM 1886, UM 1888-UM 1890

IN THE CIRCUIT COURT FOR THE STATE OF OREGON FOR THE COUNTY OF MULTNOMAH

IN THE CIRCUIT COURT OF THE STATE OF OREGON FOR THE COUNTY OF MULTNOMAH. Oral Argument Requested

BEFORE THE PUBLIC UTILITY COMMISSION OF THE STATE OF OREGON UM 1087

October 4, 2005 RE: APPLICATION /INVESTIGATION

EMPLOYMENT RELATIONS BOARD OF THE STATE OF OREGON ) ) ) ) ) ) ) ) ) ) ) ) Complainant, Respondent

Agreement for Net Metering and Interconnection Services (Level 1, 2 and 3 Interconnection)

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Via Electronic Filing

ORS Pruiies to this Review and their Counsel are: 22

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM 1208 ) ) ) ) ) ) ) Pursuant to ORS and OAR , the Industrial Customers

March 8, 2013 UM PHASE II - INVESTIGATION REGARDING COMPETITIVE BIDDING

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF GEORGIA ROME DIVISION

IN THE COURT OF APPEALS OF THE STATE OF OREGON. To: Thomas M. Christ, John A. Bennett, Margaret S. Olney and Gregory A.

IN THE SUPREME COURT OF THE STATE OF OREGON

FAX TRANSMISSION COVER SHEET

Case M:06-cv VRW Document 424 Filed 02/04/2008 Page 1 of 5

December 13, 2004 VIA ELECTRONIC FILING

IN THE CIRCUIT COURT FOR THE STATE OF OREGON FOR THE COUNTY OF MULTNOMAH UTCR CONFERRAL STATEMENT

is before the Commission and is being issued

7/19/2018 6:06 PM 18CV30704 IN THE CIRCUIT COURT OF THE STATE OF OREGON FOR THE COUNTY OF MULTNOMAH. Plaintiff WOF SW GGP 1 LLC alleges as follows:

UNITED STATES DISTRICT COURT ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) WHEREAS, Portland General Electric Company ( PGE ) is an Oregon corporation;

UM 1810 PacifiCorp s Notice of Settlement, Unopposed Motion to Suspend Procedural Schedule and Request for Expedited Consideration

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM 1610 ) ) ) ) ) ) ) ) ) ) I. INTRODUCTION

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON AR 499. The League of Oregon Cities offers these comments in the matter of the adoption of

IN THE INDIANA COURT OF APPEALS } } } } } EMERGENCY MOTION FOR STAY PENDING APPEAL

UNITED STATES BANKRUPTCY COURT DISTRICT OF OREGON COMPLAINT

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON

Case 2:17-cv RAJ Document 36 Filed 07/21/17 Page 1 of 5

BEFORE THE OREGON PUBLIC UTILITY COMMISSION COMMENTS OF TRACFONE WIRELESS INC.

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UE 219 ) ) ) ) ) ) Pursuant to ORS and OAR , the Industrial Customers

Case 3:10-cv BR Document 77 Filed 12/10/12 Page 1 of 6 Page ID#: 998

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA105 FERC 63, 016 FEDERAL ENERGY REGULATORY COMMISSION

ALABAMA SURFACE MINING COMMISSION ADMINISTRATIVE CODE

REPLY OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) TO PROTEST OF DIVISION OF RATEPAYER ADVOCATES

IN THE CIRCUIT COURT FOR THE STATE OF OREGON FOR THE COUNTY OF MULTNOMAH COUNSEL

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION. Docket No. DG Liberty Utilities (EnergyNorth Natural Gas Corp.) d/b/a Liberty Utilities

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

2/13/ :36 PM 19CV07131 IN THE CIRCUIT COURT FOR THE STATE OF OREGON FOR MULTNOMAH COUNTY. Case No. COMPLAINT. Negligence FACTUAL ALLEGATIONS

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA SOUTHERN CALIFORNIA EDISON COMPANY S (U338-E) JOINT PREHEARING CONFERENCE STATEMENT

IN THE CIRCUIT COURT OF THE STATE OF OREGON FOR THE COUNTY OF MULTNOMAH. Petitioner, Respondent.

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA SOUTHERN CALIFORNIA EDISON COMPANY S (U 338-E) MOTION FOR PARTY STATUS

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA RESPONSE OF SOUTHERN CALIFORNIA EDISON COMPANY (U 338-E) TO PROTESTS

April 15,2011. Peoples Natural Gas Purchased Gas Cost Section 1307(f) Filing

IN THE SUPREME COURT OF THE STATE OF OREGON CA A

F I L E D :45 PM


If you have questions about this filing, please contact me at (503)

Case 1:16-cv KBJ Document 15 Filed 04/06/17 Page 1 of 9 UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

ORAL ARGUMENT HELD DECEMBER 10, 2013 DECIDED APRIL 15, 2014 IN THE UNITED STATES COURT OF APPEALS FOR THE DISTRICT OF COLUMBIA CIRCUIT

McDowell & Rackner PC

Administrative Rules for the Office of Professional Regulation Effective date: February 1, Table of Contents

Standing Practice Order Pursuant to 20.1 of Act Establishing Rules Governing Practice and Procedure in Medical Assistance Provider Appeals

FACTUAL BACKGROUND AND PROCEDURAL POSTURE

Case 3:10-cv BR Document 262 Filed 07/23/15 Page 1 of 7

IN THE UNITED STATES DISTRICT COURT FOR THE MIDDLE DISTRICT OF NORTH CAROLINA. Case No. CLASS ACTION COMPLAINT PRELIMINARY STATEMENT

Case 6:18-cv MC Document 1 Filed 01/04/18 Page 1 of 12

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF OREGON

December 28, Via Electronic Filing

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) )

mg Doc Filed 09/13/16 Entered 09/13/16 12:39:53 Main Document Pg 1 of 14

Case 3:14-cv BR Document 1 Filed 06/24/14 Page 1 of 7 Page ID#: 1

UNITED STATES DISTRICT COURT DISTRICT OF OREGON

Transcription:

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON DR 10, UE 88, UM 989 In the Matters of The Application of Portland General Electric Company for an Investigation into Least Cost Plan Plant Retirement, (DR 10) Revised Tariffs Schedules for Electric Service in Oregon Filed by Portland General Electric Company, (UE 88) PORTLAND GENERAL ELECTRIC COMPANY'S MOTION TO CONSOLIDATE PHASES AND RE-OPEN RECORD Portland General Electric Company's Application for an Accounting Order and for Order Approving Tariff Sheets Implementing Rate Reduction. (UM 989) I. INTRODUCTION Pursuant to ORS 756.558 and OAR 860-13-0031, Portland General Electric Company ("PGE") requests the entry of an order or ruling (1) amending the procedural schedule to consolidate the phases of this proceeding and (2) re-opening the record to permit the parties to submit additional testimony. Consolidation will expedite this proceeding and give parties the opportunity to submit testimony and briefs on issues raised by the recent Oregon Supreme Court decision in Dreyer v. Portland General Electric Co., 341 Or 262, 142 P3d 1010 (2006). In addition, consolidation will lead to a single comprehensive order that identifies any harm or injury to customers for the entire relevant time period and offers complete and final relief to former and current PGE customers. Such a single final order will lead to an orderly and efficient review by the courts for all customer claims from UE 88 to present. In section V, PGE proposes a schedule that would result in a final comprehensive order no later than July 30, 2007. Page 1 - PORTLAND GENERAL ELECTRIC COMPANY'S MOTION TO CONSOLIDATE PHASES AND RE-OPEN RECORD

II. BACKGROUND The Commission re-opened dockets DR 10, UE 88 and UM 989 to comply with the remand orders of the Marion County Circuit Court. The remand orders implemented the Court of Appeals' decision that concluded that the Commission wrongly interpreted ORS 757.140 and ORS 757.355 in dockets DR 10 and UE 88, and the Circuit Court's ruling in connection with the Commission's final order in UM 989. The Commission re-opened these dockets to address all the reviewing courts' rulings. Order No. 05-091 at 1 (Feb. 11, 2005). On May 5, 2004, the Administrative Law Judge issued a Ruling that divided the proceeding into phases. ALJ Ruling at 8. The Commission ultimately determined that its task in Phase I was: Order No. 05-091 at 5. [T]o undertake a retrospective examination of what rates would have been approved in UE 88 if the Commission had interpreted the authority delegated to it by the legislature in ORS 757.355 to not allow a return on investment in retired plant, as the Court of Appeals did in Citizens' Utility Board. In a later phase (or phases), the parties would address (1) the Commission's legal authority to order refunds, (2) rates set in UM 989, and (3) administrative issues relating to the implementation of any refund. Ruling at 8-9. In particular, the ALJ concluded that the legal question concerning the Commission's legal authority to order refunds was "premature" in light of the pending court proceedings. Id. The parties submitted written testimony on Phase I issues, and a hearing was conducted on August 29 and 30, 2005. On September 19, 2005, ALJ Kirkpatrick issued a ruling closing the record. Briefing was completed on December 14, 2005. On August 31, 2006, the Oregon Supreme Court issued its decision in Dreyer v. PGE, a case directly related to these remand proceedings (the "Class Action Case"). In that case, certain former and current customers, some of whom intervened in Page 2 - PORTLAND GENERAL ELECTRIC COMPANY'S MOTION TO CONSOLIDATE PHASES AND RE-OPEN RECORD

these remand proceedings and all of whom are represented by the same counsel in both venues, filed complaints against PGE in Marion County Circuit Court, seeking refunds of all "unlawful" amounts collected as a result of the Commission's decisions allowing PGE to include the unamortized Trojan balance in rate base from April 1, 1995 forward. Dreyer, 341 Or at 273. In the Class Action Case, PGE argued that ORS 757.225 barred plaintiffs' claims because that statute legally obligated PGE to charge the Commission-approved rates and no others. The Dreyer Court disagreed, concluding that ORS 757.225 and the common law filed-rate doctrine imposed no bar to plaintiffs' claim or the issuance of refunds to compensate customers for amounts collected under Commission-approved tariffs that a court later finds unlawful. Dreyer, 341 Or at 278-79. Nevertheless, the Oregon Supreme Court abated the Class Action Case. The Court noted that this Commission remand proceeding "involves (essentially) the same controversy, the same ratepayers, and the same effort at determining a remedy for PGE's collection of unlawful rates, as do the [Class Action Cases]." Dreyer, 341 Or at 283. Because of the overlapping issues and the Commission's "special expertise" in this area, the Court concluded that the doctrine of primary jurisdiction required abatement of the Class Action Case until a final decision had been reached in this Commission proceeding: [T]he PUC proceeding that is underway thus has the potential for disposing of the central issue in these cases, viz., the issue whether plaintiffs have been injured (and if they have been, the extent of the injury) * * * Depending on how the PUC responds to that remand, some or all plaintiffs claimed injuries may cease to exist. Moreover, the PUC's specialized expertise in the field of ratemaking gives it primary, if not sole, jurisdiction over one of the remedies contemplated in the remand: revision of rates to provide for recovery of unlawful collected amounts. * * * If [the PUC] can and does provide a full or partial remedy, then plaintiffs either are not injured at all or, if they remain injured, their remedy is to seek judicial review of the PUC's order. In the former case, the circuit court can dismiss the actions. In the latter case, the scope of the court's work will be usefully curtailed. Page 3 - PORTLAND GENERAL ELECTRIC COMPANY'S MOTION TO CONSOLIDATE PHASES AND RE-OPEN RECORD

Dreyer, 341 Or at 285. A court decision ordering an appropriate remedy, if any, before the Commission acted would "interfere with that agency's performance of its regulatory functions." Id. at 286. The class action was, therefore, deferred to permit the Commission "the opportunity to do its work." Id. III. CONSOLIDATE ALL PHASES OF THIS PROCEEDING The reasons for separating the issues into phases no longer apply. The Commission delayed consideration of its legal authority because it was "reluctant to prematurely address this legal issue." Ruling at 8. The Dreyer Court reached the exact opposite conclusion. It is for the Commission not the courts to serve as the primary authority to determine whether former and current customers have been injured, the extent of any injury, and the appropriate remedy, if any. In fact, the issue of the Commission's legal authority is premature for the courts until the Commission determines whether a refund is required under these circumstances and whether it has the legal authority to provide such relief: Dreyer, 341 Or at 286 n.19. "whether the PUC has authority to order refunds or other retroactive relief will not be ripe for decision by an appellate court until the PUC acts" Moreover, the desire to expedite this proceeding, which initially led to a phased approach, now indicates consolidation. The Dreyer decision offers substantial guidance on the legal issue of the Commission's legal authority. In light of the Dreyer Court's indication that ORS 757.225 is no bar to refunds, PGE believes the Commission has the legal authority under these circumstances to order refunds and customer rate credits to the extent necessary to provide full, complete and final relief to former and current PGE customers. Before the Dreyer decision, this issue may have appeared to require a protracted proceeding to resolve. PGE's acknowledgment of this principle should streamline resolution of the Commission's legal authority. Page 4 - PORTLAND GENERAL ELECTRIC COMPANY'S MOTION TO CONSOLIDATE PHASES AND RE-OPEN RECORD

Finally, consolidation will promote an efficient and orderly process. The Commission should issue a single final order addressing its legal authority to order refunds, any injury to customers that resulted from rates that the Court of Appeals later ruled violated ORS 757.355 or rates approved in UM 989, and relief to current and former customers to remedy any such harm or injury. 1 Such an order would cover the entire time period from the effective date of the UE 88 final order to present, and offer current and former customers complete and final relief. Parties could then appeal a single comprehensive order to the courts, avoiding the type of piece-meal, disjointed court review that has plagued these Trojan-related proceedings. IV. RE-OPEN THE RECORD There are two reasons to re-open the record. First, the Dreyer decision addressed a number of significant topics that are directly relevant to this remand proceeding. For example, the Dreyer decision underscored the importance of identifying any injury to former and current customers, the Commission's expertise in fashioning complete and final relief, and the relationship between the Class Action Case and this Commission proceeding. The parties should have an opportunity to present factual evidence and submit briefs on these issues and any other relevant issue in this docket in light of the Dreyer decision. Such an approach will provide the factual record that is necessary for a comprehensive final order. Second, consolidation of this proceeding will require re-opening the record. As noted above, Phase I was limited to rates during the 5.5-year period from the effective date of the UE 88 final order until the Commission's initial approval of the UM 989 settlement (Sept. 30, 2000). No party introduced evidence regarding the UM 989 settlement 1 Administrative details relating to a customer remedy can be addressed expeditiously after the Commission issues a final consolidated order. Page 5 - PORTLAND GENERAL ELECTRIC COMPANY'S MOTION TO CONSOLIDATE PHASES AND RE-OPEN RECORD

and the time period after September 30, 2000. The parties should now have the opportunity to present evidence regarding the rates established in UM 989. V. PROPOSED SCHEDULE To implement consolidation of the phases and re-opening the record, PGE proposes adoption of the following procedural schedule: January 12, 2007 March 2, 2007 April 6, 2007 April 13, 2007 May 4, 2007 May 18, 2007 June 1, 2007 July 30, 2007 PGE files opening testimony Other parties file rebuttal testimony PGE files reply testimony Hearing Simultaneous opening briefs (all parties) Simultaneous rebuttal briefs (all parties) PGE files reply brief Commission order VI. CONCLUSION For the reasons stated above, PGE respectfully requests that the ALJ or Commission enter a ruling or order (1) consolidating the phases in this proceeding, (2) re-opening the record, and (3) adopting a procedural schedule as outlined in this Motion. DATED this 15th day of November, 2006. PORTLAND GENERAL ELECTRIC COMPANY TONKON TORP LLP J. Jeffrey Dudley, OSB No. 89042 121 SW Salmon Street, 1WTC1300 Portland, OR 97204 Telephone: 503-464-8860 Fax: 503-464-2200 E-Mail jay.dudley@pgn.com 001991\00226\723353 V001 Jeanne M. Chamberlain, OSB No. 85169 Direct Dial 503-802-2031 Direct Fax 503-972-3731 E-Mail jeanne@tonkon.com David F. White, OSB No. 01138 Direct Dial 503-802-2168 Direct Fax 503-972-3868 E-Mail davidw@tonkon.com 888 S.W. Fifth Avenue, Suite 1600 Portland, OR 97204-2099 Of Attorneys for Portland General Electric Company Page 6 - PORTLAND GENERAL ELECTRIC COMPANY'S MOTION TO CONSOLIDATE PHASES AND RE-OPEN RECORD

CERTIFICATE OF SERVICE I hereby certify that on this day I caused to be served the foregoing PORTLAND GENERAL ELECTRIC COMPANY'S MOTION TO CONSOLIDATE PHASES AND RE-OPEN RECORD by mailing a copy thereof in a sealed, first-class postage prepaid envelope, addressed to each party listed below and depositing in the U.S. mail at Portland, Oregon. Paul A. Graham Department of Justice Regulated Utility & Business Section 1162 Court Street, N.E. Salem, OR 97301-4096 paul.graham@state.or.us Stephanie S. Andrus Assistant Attorney General Oregon Department of Justice Regulated Utility & Business Section 1162 Court Street NE Salem, OR 97301-4096 stephanie.andrus@state.or.us Daniel W. Meek Daniel W. Meek, Attorney At Law 10949 S.W. Fourth Avenue Portland, OR 97219 dan@meek.net Linda K. Williams Kafoury & McDougal 10266 S.W. Lancaster Road Portland, OR 97219-6305 linda@lindawilliams.net J. Jeffrey Dudley Portland General Electric Company 121 SW Salmon, 1WTC1300 Portland, OR 97204 Email: jay.dudley@pgn.com Patrick G. Hager, III Manager, Regulatory Affairs Portland General Electric Company 121 SW Salmon, 1WTC0702 Portland, OR 97204 patrick.hager@pgn.com Rates & Regulatory Affairs Portland General Electric Company 121 SW Salmon Street, 1WTC0702 Portland, OR 97204 pge.opuc.filings@pgn.com DATED this 15th day of November, 2006. 001991\00226\723353 V001 By J. JEFFREY DUDLEY, OSB No. 89042 Attorneys for Portland General Electric Company Page 1 - CERTIFICATE OF SERVICE