IceCube Project Monthly Report April An IceCube collaboration meeting was held in Madison from April 29 th through May 3 rd.

Similar documents
FULL SCALE DOM PRODUCTION DETERMINE FULL DEPLOYMENT RATE DEPLOY INITIAL STRINGS & TANKS COMPLETE EHWD INTEGRATION & TEST

IceCube Project Monthly Report March DOM production is in progress at the three production sites world-wide and proceeding according to plan.

Cost and Schedule Performance The project is 81.7% complete versus the plan of 82.2% complete, as measured using earned value techniques.

IceCube Project Monthly Report November 2007

IceCube Project Monthly Report December 2005

Increased drilling efficiency saved approximately 26,000 gallons of fuel.

IceCube Project Monthly Report - December 2008

IceCube Project Monthly Report November 2006

IceCube Project Monthly Report November 2005

IceCube Project Baseline

IceCube Project Monthly Report - October 2010

Nearly all of the cargo needed for this season arrived by December 4 th.

IceCube Project Monthly Report April 2009

IceCube Project Monthly Report - December 2009

IceCube Project Monthly Report June 2005

IceCube Project Monthly Report - September 2010

The IceCube Upgrade Marek Kowalski DESY & Humboldt-University Zeuthen-Meeting in Mainz September 2018

DM-Ice A Direct Dark Matter Search at the South Pole

Dark Matter Searches with AMANDA and IceCube

Historical unit prices - Super - Australian Shares

IC Chapter 15. Ballot Card and Electronic Voting Systems; Additional Standards and Procedures for Approving System Changes

EPO 2013/ CR-34 Obed Mountain Mine Monthly Status Report - December 2016

Search for Dark Matter Captured in the Sun with the IceCube Neutrino Observatory

Hon Hai Precision Industry Co., Ltd. Articles of Incorporation Chapter I General Provisions

-CITE- 41 USC TITLE 41 - PUBLIC CONTRACTS 01/07/2011 -EXPCITE- TITLE 41 - PUBLIC CONTRACTS -HEAD- TITLE 41 - PUBLIC CONTRACTS

Volume I Appendix A. Table of Contents

DM-Ice A Direct Dark Matter Search at the South Pole

(Translation) Articles of Incorporation. United Microelectronics Corporation

Sewage Disposal ARTICLE II SEWAGE RETAINING TANKS

Statement on Security & Auditability

SF Summary of HIPER and Defective PTFs. I B M i P R E V E N T I V E S E R V I C E P L A N N I N G I N F O R M A T I O N

ORDINANCE NO. 7,592 N.S. ADDING CHAPTER 2.99 TO THE BERKELEY MUNICIPAL CODE, ACQUISITION AND USE OF SURVEILLANCE TECHNOLOGY

Arizona 2. DRAFT Verified Voting Foundation March 12, 2007 Page 1 of 9

Key Considerations for Implementing Bodies and Oversight Actors

S-1. Supplementary Provisions. (Date of Enforcement) Article 1 These Articles of Agreement shall come into force as of July 1, 1999.

REGULATION ON THE APPROVAL AND IMPORTATION OF TELECOMMUNICATIONS EQUIPMENT CONNECTED TO PUBLIC TELECOMMUNICATIONS NETWORKS. Article 1 Definitions

Search for Dark. Dark Matter in LHC Era Kolkata 2011

STORAGE RATES & RULES

IDS Terms and Conditions Guide Effective: 10/21/2005 Page 1 of 7

RULES OF TENNESSEE PUBLIC UTILITY COMMISSION CHAPTER REGULATIONS FOR TELEPHONE COMPANIES TABLE OF CONTENTS

Welcome the Logistics Officer Association Professional Development Module 3, Show Me the Money. This module was developed by the Robins Air Force

for the IceCube Collaboration

The Government of the United States of America and the Government of the United Arab Emirates,

Board Agenda Wednesday, Dec. 13, 2017 LCRA Board Room Austin

Training Calendar ALPHA PARTNERS

TECHNICAL ADVISORY GROUP ON MACHINE READABLE TRAVEL DOCUMENTS (TAG-MRTD)

Surface Transportation Authorization extended to March 4 th

DOE s Office of Science and the FY2016 Budget Request

The Angola National ID Card

CHAPTER 1 RECORDS RETENTION AND DISPOSITION

10126 Federal Register / Vol. 81, No. 39 / Monday, February 29, 2016 / Rules and Regulations

Amended Technical Indicator Descriptions

1995 Settlement Agreement

, 1994, by and between the CITY OF CALAIS, County of

a GAO GAO HOMELAND SECURITY Performance of Information System to Monitor Foreign Students and Exchange Visitors Has Improved, but Issues Remain

Tariff 9900: OHD Percentage Based Fuel Cost Adjustment Historical Schedule ( )

Options for New Jersey s Voter-Verified Paper Record Requirement

Electricity Regulations 1947

RECORD OF PROCEEDINGS. XENIA TOWNSHIP TRUSTEES: August 20, :00 PM

Act means the Municipal Elections Act, 1996, c. 32 as amended;

STATE OF NEW MEXICO COUNTY OF OTERO ALAMOGORDO MUNICIPAL SCHOOL DISTRICT NO. 1

EXECUTIVE OFFICE OF THE PRESIDENT OFFICE OF MANAGEMENT AND BUDGET WASHINGTON, D.C

Using Technology to Improve Jury Service 39

ARCHITECT OF THE CAPITOL

Belton I.S.D. Records Management Policy and Procedural Manual. Compiled by: Record Management Committee

Global Conditions (applies to all components):

SPECIFICATIONS. Autoclave/Sterilizer FOR. Lake Land College District Number 517 Mattoon, Illinois PROJECT NO Bid Date; May 22, 2018

CASE STUDY 2 Portuguese Immigration & Border Service

The Therma Gauge Type H - FDEP EQ 730

Training Calendar ALPHA PARTNERS

Cell Site Simulator Privacy Model Bill

David Mikolajczyk 1, Lee Welhouse 1, Matthew Lazzara 1,2, Carol Costanza 1,George Weidner 1, Linda Keller 1, & Mark Seefeldt 3

Robert E. Foelber Foreign Affairs and National Defense Division

SECURITY, ACCURACY, AND RELIABILITY OF TARRANT COUNTY S VOTING SYSTEM

Reference services are provided through in-person visits, by telephone, via , through chat and by regular mail correspondence.

EXFO Care - Simulators

FY Foreclosure Initiative. Data Collection Plan

Telecommunications (Interception Capability and Security) Bill

P.O. BOX CHOLLITA ROAD JOSHUA TREE CALIFORNIA TELEPHONE (760) FAX (760)

UNHCR WASH MANUAL MONITORING AND REPORTING 361

GAO. Statement before the Task Force on Florida-13, Committee on House Administration, House of Representatives

TOWN BOARD MEETING July 9, The Town Board of the Town of Spafford assembled at the Spafford Town Hall, 1984 Route 174, Skaneateles, New York.

IDS Terms and Conditions Guide Effective: 11/18/2009 Page 1 of 8 CUSTOMER CONTRACT REQUIREMENTS B-52 CONECT LRIP CUSTOMER CONTRACT FA D-1000

Florida Supreme Court Standards for Electronic Access to the Courts

Tackling Electrical System Efficiency, Safety and Reliability for pharmaceutical plants

HILLSIDE PUBLIC LIBRARY BOARD OF TRUSTEES MEETING MINUTES July19, 2017

The documents listed below were utilized in the development of this Test Report:

CHAPTER Committee Substitute for Committee Substitute for House Bill No. 687

Choosing the Right Monitor for Your Application

M E M O R A N D U M. The Promontory project debt service will be funded with special assessment paid by the Promontory developer.

Benefits of a Modern Court Case Management System by Richard Slowes, Former Commissioner of Minnesota Supreme Court WHITE PAPER

MINUTES OF THE REGULAR MEETING OF THE MOUNT LAUREL TOWNSHIP MUNICIPAL UTILITIES AUTHORITY

Cosentino Brands Monthly Social Media Report. December/End of the Year 2014

Estonian National Electoral Committee. E-Voting System. General Overview

State Oil and Gas Board on the Petition of Pachuta Corporation

RESOLUTION NO

Lakeland Regional Sewer District lakelandrsd.com

IDS Terms and Conditions Guide Effective: 10/21/2005 Page 1 of 8 CUSTOMER CONTRACT REQUIREMENTS F-15E CUSTOMER CONTRACT F C-0013

D. Statement on Internal Control Structure E. Management Summary G. Detailed Audit Findings II. MANAGEMENT'S RESPONSE...

REQUEST FOR QUOTATION (RFQ) REFERENCE: RFQ/KRT/12/127 DATE: 10/14/2012

Transcription:

IceCube Project Monthly Report April 2008 Accomplishments An IceCube collaboration meeting was held in Madison from April 29 th through May 3 rd. Commenced inspection and testing the drill cables that were used last season and shipped back from the South Pole. Continuing DOM integration and test at each of the three production sites worldwide. Planning a data challenge for the IC-40 array. Detector up-time for the month was 97.6 percent. IceCube was a featured exhibit at the annual Science Expeditions Fair on the UW-Madison campus. 300 250 IceCube Project Baseline (M$) Initial In-Ice Strings & IceTop Tanks Installed Initial Operational Capability Jan-2005 2007 Project Completion & Closeout Sep-2011 Total Project Cost $275.4 Value of Foreign Contributions $33.3 NSF Funding $242.1 Remaining Contingency $10.5 Contingency as % of Remaining Work 23.6% Strings installed 50% Performance and Cost through: 31-08 235.3 260.6 273.5 275.1 275.4 264.9 231.6 DOLLARS IN MILLIONS 200 150 100 50 15.0 39.5 85.7 140.1 199.4 DEPLOY INITIAL STRINGS & TANKS COMPLETE EHWD INTEGRATION & TEST INITIAL OPERATIONS & DATA ANALYSIS CAPABILITY FULL SCALE DOM PRODUCTION DETERMINE FULL DEPLOYMENT RATE FULL OPERATIONS & DATA ANALYSIS CAPABILITY Total Funds (US & NonUS) Original Budget (BCWS) (excluding contingency) Current Budget (BCWS) 83.4 % Earned Value (BCWP) 83.2 % Actual Cost (ACWP) 82.4 % 0 FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FISCAL YEAR

Cost and Schedule Performance The project is 83.2% complete versus the plan of 83.4% complete, as measured using earned value techniques. The contingency % of the remaining work is 23.6%. The earned value measurement includes all tasks completed to date including design, development, procured materials, and the construction of the infrastructure that supports the seasonal installation plan, e.g., the hot water drill, cargo shipments, etc. IceCube Neutrino Observatory Cost Schedule Status Report Reporting Period Ending: 3/31/2008 Cumulative To Date (AY K$) Budgeted Cost Actual Cost Variance Contingency Latest 2 Work Work of Work Budgeted Revised OBS Structure L2 Scheduled Performed Performed Schedule Cost Assigned % ETC AY $s Estimate Variance Sched Perf Project Support 22,874.1 22,874.1 22,522.3 0.0 351.8 186.5 5.0% 27,184.4 26,288.4 896.0 84.1% 84.1% 82.9% Implementation 33,648.7 33,648.7 33,954.4 0.0-305.7 3,007.5 20.7% 46,587.9 48,501.6-1,913.6 72.2% 72.2% 72.9% Instrumentation 66,704.5 66,130.7 64,848.0-573.8 1,282.7 439.2 6.0% 72,173.4 72,173.4 0.0 92.4% 91.6% 89.9% Data Acquisition 33,324.1 33,288.7 33,153.8-35.5 134.8 89.9 11.2% 33,954.2 33,954.2 0.0 98.1% 98.0% 97.6% Data Systems 22,965.5 22,761.8 22,842.8-203.7-81.0 100.3 2.5% 26,789.4 26,789.4 0.0 85.7% 85.0% 85.3% Note 1 At Completion (AY K$) Note 5 Complete (%) Actl Cost Detector Comm. & Verification 18,241.4 18,241.4 18,385.5 0.0-144.1 240.4 10.8% 20,610.5 20,610.5 0.0 88.5% 88.5% 89.2% Pre Operations 533.8 533.8 492.0 0.0 41.8 0.0 0.0% 966.0 966.0 0.0 55.3% 55.3% 50.9% Subtotal 198,292.3 197,479.2 196,198.9-813.0 1,280.4 4,063.9 12.3% 228,265.8 229,283.5-1,017.7 86.9% 86.5% 86.0% RPSC SUPPORT 21,844.8 22,049.7 21,221.4 204.9 828.3 1,526.0 10.9% 35,339.9 35,220.4 119.5 61.8% 62.4% 60.0% NSF 826.4 826.4 826.4 0.0 0.0 26.2 6.0% 1,263.0 1,263.0 0.0 65.4% 65.4% 65.4% Total 220,963.4 220,355.3 218,246.6-608.1 2,108.6 5,616.1 11.8% 264,868.7 265,766.9-898.2 83.4% 83.2% 82.4% CONTINGENCY Notes 3,4 10,513.3 9,615.1 898.2 IceCube Total Note 2 220,963.4 220,355.3 218,246.6-608.1 2,108.6 5,616.1 11.8% 275,382.0 275,382.0 0.0 83.4% 83.2% 82.4% Notes: 1 Incorporates approved baseline changes. 2 Total Budget at Completion includes non-us contributions 3,611 K over the amount in the post Hartill III baseline of: $29,698 K 3 Budgeted contingency is: 23.6% of the Budgeted cost of work remaining. 4 Budgeted contingency is: 23.2% of the Estimated Cost to Complete (ETC) 5 All latest revised estimates detailed planning for PY6-10 6 Contingency is assigned to each L-2 element based on the ETC, a bottom-up risk assessment model, management judgement, and cost constraints. 03/31/08 Change Log - IceCube Total Project Budget Baseline ($K) No. NA CR119 CR120 NA Description Status as of February 2008 CR 0119 PY7 Baseline Replan (US) CR 0119 PY7 Baseline Replan NonUS CR 0120 Ship all remaining IceTop tanks Status as of March 2008 Date Approved Total Baseline Allocated Budget Allocated Budget Change Contingency Budget Estimate To Complete (ETC) Budgeted Cost of Work Remaining Contingency % of Remaining Work 276,628 263,872 0 12,755 45,765 45,180 28.2% 04/09/08 276,628 266,058 2,186 10,570 04/09/08 275,382 264,812-1,245 10,570 04/23/08 275,382 264,869 56 10,513 275,382 264,869 0 10,513 45,412 44,513 23.6% 2

Risk Assessment & Potential Contingency Adjustments 1 Item Estimated contingency that might be required to address the cost impact of technical, cost and schedule risks identified with the defined scope of work. Risk factors were assessed at WBS-Level 4. Restore 80-string configuration. This is the current estimate of the cost to restore the array to the 80-string configuration described in the original IceCube proposal. RPSC FY07-FY10 Rebaseline (rev 7.0): This pending baseline change includes the support for 4 additional strings (76-80), addresses the cargo and fuel cost increases under ANG, and returns FY07 under-spent budget to contingency. Current RPSC estimate of base cost to support the 2010/11 drilling season. Pre-Operations activities may be extended beyond the two years currently budgeted to conduct engineering runs concurrent with operations and to debug software and ensure reliability of the installed equipment. The costs of returning IceCube equipment and materials from the South Pole, e.g., the Enhanced Hot Water Drill, was not included in the baseline budget. The retro work will be planned for FY2012. Potential Contingency Use $3,845K $1,500K $412K $2,260K $150K $825K Assign contingency against major fuel price increases beyond normal inflation. $500K Upgrade Data Center and Data Warehouse capacity to handle data rates that are higher than originally planned. $1,000K 40% IceCube Contingency: % of Remaining Work 30% 20% 10% 0% 04 Jun- 04 Sep- 04 Dec- 04 05 Contingency Usage Implementation 61% Instrumentation 27% DAQ 11% RPSC 8% Project support -10% Others 4% Jun- 05 Sep- 05 Dec- 05 Annual Baseline Re-Plan 2005, 06, 07, 08 Additional IceTop Stations + Installation Season Instrumentation for >75 strings 06 Jun- 06 Sep- 06 Dec- 06 07 Jun- 07 Sep- 07 Dec- 07 23.6% 08 1 IceCube is sensitive to increasing energy costs. The pump price paid for fuel to be used during the FY09 season is $2.85 per gallon (FY09 fuel was already shipped). An increase of one dollar per gallon of fuel used in FY10 would result in a total cost increase of approximately $710K. This includes fuel for drilling, cargo transport, personnel at Pole, and heavy equipment use. We included $180K for potential fuel cost increases in the WBS-Level 4 baseline risk assessment plus an additional $500K for the extraordinary current pricing. 3

Drill Operation and Installation The highest priority activity during the off-season is to address the drill cable communications problem. The drill team is developing plans to build new replacement cables based on the testing and analysis effort that has started this month. All three EHWD Drill Support Cables were shipped back from the South Pole and received at PSL in April, referred to as cables 1, 2, and 3. Cable 2 has been electrically tested with a TDR and showed multiple wire breaks at about 800m from the end, making the entire cable unusable. Cable 3 has damage only to the outer jacket. The original manufacturer, Cortland Cable Co., is in the process of electrical testing and visual inspection of this cable. Once they complete their inspections, Cortland Cable Co. will quote a price for the refurbishment of Cable 3. Cable 1 is at PSL on the Drill Cable Winch. Electrical testing shows that the cable is electrically continuous after one damaged end of the cable was removed. Once placed on another spool, Cable 1 will also be sent to Cortland Cable Co. for inspection and most likely refurbishment. One entirely new Drill Support Cable will also be procured. All these activities are being closely tracked to ensure one cable will be ready to ship Sept. 1 st for a ROS of Nov. 20 th, 2008. One spare cable will be ready to ship on Oct. 15 th for a ROS of Dec. 1 st, 2008. The second spare cable should also arrive in Antarctica by Jan. 2009, but will most likely be kept in McMurdo for winter storage. A site plan for the upcoming season has been developed and includes hole locations, drilling sequence, IceTop locations, special devices, cable trench paths and roads. The plan has been circulated to the collaboration and Raytheon Polar Services Company for review. Digital Optical Module and Cable Production Status and Plans - DOM production is in progress at all 3 sites and is progressing smoothly. Surface to DOM cable production is normal. Procurement plans have been developed for instrumentation (primarily DOM hardware and cables) to restore IceCube to the originally planned 80 string configuration. This will include 15 surface cables and 6 surface-to-dom cables, and associated breakouts and connectors. 800 IceCube DOM Integration PY7 (April, 2008 to October, 2008) - Plan vs. Actual Plan to IC75+ with existing materials on hand DOMs ready for DFL @ PSL - cumulative plan 700 600 DOMs ready for DFL @ DESY - cumulative plan DOMs ready for DFL @ Swed - cumulative plan DOMs ready for DFL - cumulative plan all sites DOMs ready for DFL - cumulative actual all sites 500 400 300 200 100 0 4/5/2008 4/12/2008 4/19/2008 4/26/2008 5/3/2008 5/10/2008 5/17/2008 5/24/2008 5/31/2008 6/7/2008 6/14/2008 6/21/2008 6/28/2008 7/5/2008 7/12/2008 7/19/2008 7/26/2008 8/2/2008 8/9/2008 8/16/2008 8/23/2008 8/30/2008 9/6/2008 9/13/2008 9/20/2008 9/27/2008 10/4/2008 10/11/2008 Quantity of DOMs ready for DFL Week ending 4

Detector Commissioning and Verification - Verification has run continuously since the start of IC-40 data taking. Initial studies of high-level quantities from IC-40 running were performed. Thus far no significant problems were found. A data challenge will be done to determine how sensitive the various verification tests are to problems by taking some already-acquired IC-40 data, introducing a fault, writing out the faulty data to a new file, and giving that resulting file to the verification group to study. Long-term studies of IC-22 data from 2007 have found a handful of DOMs with minor problems in their timing and charge distributions. These problems are also under investigation. Data from the entire IC-22 dataset, from May 23, 2007 to April 5, 2008, has been evaluated for run quality. Using a set of simple criteria such as minimal run length, 94% of the acquired InIce data is labeled good. For AMANDA, this number is 55%. Similar work is underway for IceTop data. Data analyzers will be able access this information conveniently and directly from within their analysis code by the end of May, which they can already do for individual DOMs. In the next few months, information gathered by the verification tests will be used to determine whether or not a DOM is good in a particular run. Initially this will be done manually. Verification criteria can also be used to determine whether a run is good or not (again, manually), although the high stability of the detector thus far suggests this may not be necessary. The IC-22 data has also been analyzed for detector stability. An internal note will be written on detector stability. The first version of a new webpage to display the verification information and make it easier for verification experts, data analyzers and shift takers to see problems has been implemented. It is being tested and used by the verification group. Data Acquisition Software - We have begun refurbishing 8 Rev3 hubs in preparation for a shipment of 15 hubs to South Pole towards the end of August this year. Some minor mechanical modifications must be made. The single-fused power entry modules are being replaced with double-fused assemblies suitable for the 208 VAC power used at Pole. Additionally, the ground fault circuit has been upgraded last year on the 33 UW manufactured hubs and must be retrofitted into the existing Rev3 hubs. DAQ software has been running stably with 40 strings since April 5 th. We are still running the Aqua release however the "Bay Wolf" version was released on May 5 th that addresses some minor bugs. Deployment to Pole is expected during the week of May 12 th. 5

IceCube Detector Operations Detector Up Time 97.6% IceCube Clean Run Up-Time not including AMANDA Array 96.7% Unscheduled Downtime 1.0% Events from DAQ 3.16 billion IceCube Detector Operation for April 2008 100% Percentage of Day 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 Day Unscheduled Downtime Maintainance C&V Special Tests / commiss. of new strigs DOM Calibration Monthly Benchmark/Calibrations Partial IceCube + AMANDA Partial IceCube AMANDA Only IceCube Only IceCube+AMANDA Data taking during April 2008 achieved an overall 97.6% uptime. The in-ice clean run uptime achieved 96.7%. On April 5 th we formally stopped the IC-22 running season and smoothly transitioned to IC-40 operation. During the first period of IC-40 operation, until April 17 th (run 110847), there was no physics filtering but the combined Joint-Event Builder (JEB) events were written to tape and will be filtered once the data arrives North at the end of the season. The inice DAQ configurations for IC-40 converged on April 9 th. The IceTop configurations underwent major changes, including the re-inclusion of the solar physics capability, change of the gain of the low-gain DOMs and the tuning of the discriminators and local coincidence cable delays converging by April 11 th. Also the AMANDA/TWR configuration was changed to add string trigger capability and to reduce the sampling in the electrical channels. In all, it was a very successful and smooth transition to IC-40 running due to the planning and multiple test runs done in preparation for the switch. However, there is room for improvement in future years by having all necessary configurations and filtering code in place before making the actual transition. Data Systems Data Handling - South Pole Systems in the IceCube Laboratory (ICL) began IC-40 physics operation in April. The figure below shows the daily satellite data transfer rates. The remaining backlog of IC-22 data was cleared during April as the transition from IC-22 to IC-40 took place. The transition from IC-22 to IC-40 physics running in April went smoothly from the Data Handling standpoint. A detailed requirements document and execution plan for upgrades of disk to the data warehouse to accommodate higher data rates was finalized and reviewed. There was 6

significant planning for requirements in the ICL for the coming deployment season to accommodate the new strings. Filtering and Software - Filtering of IC-40 data began on April 14, 2008, representing the full transition from running IC-22 to IC-40. The Joint-Event Builder and Processing and Filter server (JEB/PnF) merging of IceCube-40 and Amanda TWR data streams continues at the South Pole, sending filtered data sets of about 38 GB/day over the satellite. The figure below represents a snapshot of the filter rate monitoring page near the start of IC-40 physics running. The IC-40 trigger rate is approximately 1300 Hz with the filter selecting about 80 Hz of events for satellite transmission. Offline processing for IC-22 data through Level 2 was completed. This is the last offline processing step done in common for all physics topics. Higher level processing is now ongoing 7

by individual analysis groups using the common Level 2 data sets. Preparations have begun for offline processing on the IC-40 data as it flows north over the satellite. Testing on L0 and L1 processing has gone well, and we expect to start routine processing of L0/L1 next month, with finalizing of the Level 2 processing planned before June. This schedule is nearly six months ahead of last year s IC-22 offline processing, which was the first year it was implemented. Simulation - Mass simulation production continues with IceSim Version 2 to produce large background and signal Monte Carlo datasets for the physics working groups to prepare for IC-22 physics analysis. The distributed production system along with better tracking and monitoring of CPU time supplied at each institution continues to monitor the production sites. There was also a new release in April for production Monte Carlo runs to be used for the IC-40 run next year. Quality Assurance and Safety SafeStart training, by NANA systems, is planned for all IceCube personnel deploying during the upcoming season. Education and Outreach On Saturday, April 5 th, over 1000 people saw the IceCube exhibit at Science Expeditions, an annual event showcasing science research on the University of Wisconsin Madison campus. Graduate students from the IceCube project showed the extreme cold weather (ECW) gear used at the South Pole and explained the basic concepts of IceCube to people of all ages using a DOM, video, and images of the South Pole. IceCube staff from UW- Madison also visited six schools and colleges with the ECW gear in April. Mark Krasberg spoke to the Madison Astronomical Society. High School teacher Steve Stevenoski made a presentation about IceCube at the National Science Teachers Association Meeting on April 2, 2008. The April 19, 2008 issue of New Scientist featured an article about IceCube by Anil Ananthaswamy, who was a recipient of a grant from the National Science Foundations Antarctic Artists and Writers Program. The monthly reports are posted at IceCube Monthly Reports. Meetings and Events Neutrino 2008 @ Christchurch, NZ May 26-31, 2008 NSF Annual Review of IceCube @ UW-Madison June 11-12, 2008 8