Evolution of dispute resolution under the FIDIC Red Book. Bill Smith, Partner 10 May 2018

Similar documents
FIDIC SUITE OF CONTRACTS 2017 NEW DISPUTE RESOLUTION REGIMES 21 March 2018

COMPARISON TABLE OF DISPUTE BOARD RULES

AN OUNCE OF PREVENTION IS WORTH A POUND OF CURE - Benjamin Franklin. Gordon L. Jaynes 24 May 2018

FIDIC contracts Claims and disputes under international construction contracts. Claims and dispute resolution procedures under FIDIC contracts

Chapter 10. A Note on Dispute Boards. Chapter 10

DAAB and Dispute Resolution Under the 2017 FIDIC Forms of Contract

FIDIC Conditions of Contract for Construction

THE NEW ENGINEERING CONTRACT FOURTH EDITION (NEC4)

The Gap in Sub-Clause 20.7 of The 1999 FIDIC Contracts for Major Works

Arbitral tribunals; Decisions; Dispute adjudication boards; Enforcement; FIDIC forms of contract; Jurisdiction; Singapore

THE ICC S NEW DISPUTE BOARD RULES. CARROLL S DORGAN Jones Day Paris

Cross-border recognition of resolution decisions. Stuart McNeill Pinsent Masons LLP

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory

Procurement Challenges. Tactics and Lessons Learnt from Recent Developments 6 December 2016 Jennifer Robinson

The legal justification for the enforcement of a binding DAB decision under the FIDIC 1999 Red Book

LIMITATIONS AND CONSTRAINTS IMPOSED BY ROMANIAN LAW ON FIDIC CONDITIONS OF CONTRACT A CONTRACTOR S DILEMMA WHILE PERFORMING PUBLIC WORKS IN ROMANIA

Model letters for use by the Contractor

Getting ready for Ontario s new Construction Act. Understanding the key changes and how to prepare for them. Howard Krupat

Making an Effective and Persuasive Case to a Dispute Board

The Pinsent Masons Planning Toolkit Series

Protocol Relating to Legal Representation at Public Expense

IMPROVING PAYMENT PRACTICES IN THE CONSTRUCTION INDUSTRY

FIDIC Dispute Adjudication Boards

UK immigration briefing:

Arbitration Act 1996

The SIAC Arbitration Rules 2016: A detailed look at the new rules 1 August 2016

PART 8 ARBITRATION REGULATIONS CONTENTS

ASTON UNIVERSITY Free Movement in the UK & Brexit. Shuabe Shabudin 13 October 2017

Elements of a Civil Claim

Security of payment under FIDIC contracts: more secure, for now

1.2. This book covers the three Agreements published by JBCC (see 2.1 below) and the MBSA 2014 Domestic Subcontract Agreement.

IN THE HIGH COURT OF JUSTICE. Between MOOTILAL RAMHIT & SONS CONTRACTING LIMITED. And EDUCATIONAL FACILITIES COMPANY LIMITED

Disciplinary & Dispute Resolution Procedures

Dispute Board Rules. in force as from 1 September Standard ICC Dispute Board Clauses. Model Dispute Board Member Agreement

Inside this issue. Issue 21 - April

An Engineer s / Dispute Adjudication Board s Decision Is Enforceable By An Arbitral Award

TERMS OF REFERENCE INSURANCE & FINANCIAL SERVICES OMBUDSMAN SCHEME INCORPORATED

New Expert Rules launched by the ICC

Mott MacDonald Ltd v London & Regional Properties Ltd [2007] Adj.L.R. 05/23

9/13/2013 gerard o sullivan Mulcahy McDonagh & Partners 1

Consolidated text PROJET DE LOI ENTITLED. The Arbitration (Guernsey) Law, 2016 * [CONSOLIDATED TEXT] NOTE

Enforceability of Multi-Tiered Dispute Resolution Clauses

ADR in FIDIC Contracts and the Cyprus perspective

The Construction Act of Ontario

Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland

A DAB Decision between the Notice of Dissatisfaction and the Enforcement in ICC Arbitration

Construction & Engineering News

Statute of limitation in FIDIC contracts concluded in the public procurement procedures

English jurisdiction clauses should commercial parties change their approach?

Hong Kong International Arbitration Centre ADJUDICATION RULES

Regulatory enforcement proceedings

Code of Practice on the discharge of the obligations of public authorities under the Environmental Information Regulations 2004 (SI 2004 No.

CONDITIONS OF APPOINTMENT

GAR KNOW HOW CONSTRUCTION ARBITRATION. Saudi Arabia. Joseph Chedrawe, Emily Beirne and Amr Omran Vinson & Elkins LLP AUGUST 2018.

Trusts Bill. Explanatory note. Government Bill

In the Blue Corner Construction Law: in the Red Corner Insolvency Law working through the clash RICHARD WILLIAMS

ARBITRATION & CONCILIATION ACT AND MEDIATION

Japan Arbitration Update: New JCAA Rules Comparison of Key Asian Arbitral Institutions

Singapore Court Should Not Have Set Aside ICC Award Enforcing Dispute Adjudication Board Decision

Financiers' Certifier Direct Deed

Financiers' Certifier Direct Deed

JCLI Scottish Landscape Maintenance Works Agreement April 2017 (JCLI SLMWA )

Statutory Instrument 1998 No The Scheme for Construction Contracts (England and Wales) Regulations 1998

/...1 PRIVATE ARBITRATION KIT

SUBMISSION OF THE SCOTTISH LAW COMMISSION ON THE CONTRACT (THIRD PARTY RIGHTS) (SCOTLAND) BILL

Construction Industry Security of Payment Legislation. Development Bureau

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013)

STATEMENT OF INSOLVENCY PRACTICE 3A (SCOTLAND) 2009 TRUST DEEDS

SOCIAL CARE WALES (INVESTIGATION) RULES 2017 INTERNAL VERSION

1) ICC ADR proceedings are flexible and party-controlled to the greatest extent possible.

Dr. Nael Bunni, Chairman, Dispute Resolution Panel, Engineers Ireland, 22 Clyde Road, Ballsbridge, Dublin 4. December 2000.

Dispute Resolution Process between Commissioners and Providers for the 2014/15 Contracting Process

Strata Renewal Reforms

Catholic Multi Academy Model Mainstream 16-19

Unit 5 : ADJUDICATION

CONSTITUTION OF THE ASSOCIATION RULES & PRINCIPLES

Shaikh Sk Sameer 1, Dr Rajendra B. Magar 2, Fauwaz Parkar 3 1 M. E. Construction Engg. & Management, Kalsekar Technical Campus, New Mumbai, India

Complaints Policy. Policy: Complaints Policy Effective Date: December 2014 Revision Number : 3.0 Revised: January 2018

CIArb/IMPRESS ARBITRATION SCHEME RULES ( the Rules ) FOR USE IN ENGLAND & WALES

GUIDE. Administration Guidance Notes

For personal use only

Annual Review of English Construction Law Developments. An international perspective

ICC Rules of Conciliation and Arbitration 1975

1 DEFINITIONS AND INTERPRETATION

Law Commission consultation on the Sentencing Code Law Society response

New Zealand Institute of Chartered Accountants RULES OF THE NEW ZEALAND INSTITUTE OF CHARTERED ACCOUNTANTS EFFECTIVE 26 JUNE 2017 CONTENTS

SCHEME OF DELEGATION. made between. The Good Shepherd Trust. and. The LGB of St Mary s Church of England Primary School, Chiddingfold

Electricity Retail Licence. NewRet Pty Ltd

Resolution Institute. Policy on the Accreditation and Register of Adjudicators

LABOUR RELATIONS AMENDMENT BILL, [Words in bold type indicate omissions from existing enactments]

Personal Information has been redacted from this document under Section 40 of the Freedom of Information (FOI) Act.

AAA Dispute Resolution Board Guide Specifications Effective December 1, 2000

PETERBOROUGH REGIONAL COLLEGE FURTHER EDUCATION CORPORATION STANDING ORDERS

Multi-Tier Dispute Resolution Clauses Definition and Examples

CONCODE. Guide to the agreement for the appointment of architects, surveyors and engineers for commissions in the NHS (1995edition) STATUS IN WALES

Code of Complaints & Disciplinary Procedures

THE LONDON BAR ARBITRATION SCHEME. Administered by The London Common Law and Commercial Bar Association

Brexit Essentials: Dispute resolution clauses

DRAFTING AND INTERPRETING GOVERNING LAW AND JURISDICTION CLAUSES A PRACTICAL GUIDE

City Planning & Environmental Services. 2 September 2010

Transcription:

Evolution of dispute resolution under the FIDIC Red Book Bill Smith, Partner 10 May 2018

Outline Disputes why a dispute resolution procedure is needed How the dispute resolution provisions in the FIDIC Red Book have evolved from 1987 2017 Role of the Engineer in resolving claims and disputes How has the process changed? What potential pitfalls have caused these changes? Conclusions

What disputes? Construction and engineering projects commonly run into problems why? Every project is different site conditions supply chain regulatory landscape changes Asset owners demand continuous improvement faster cheaper better

Projects are inherently risky Quality suffers Cost Time Quality Costly Perfection everybody s expectation! Slow

Which issues most commonly lead to construction / engineering disputes? Variations to scope Interpretation of contract terms Delayed completion Site conditions Late, incomplete or substandard design Obtaining approvals Site access Poor performance and defects Pricing errors

Resolving disputes Claims and disputes are almost inevitable Parties say that they want their disputes resolved: - quickly cheaply correctly (i.e. their position prevails) minimal disruption to the project maintaining commercial relationships Query whether this is the case once they are involved in a dispute How has FIDIC addressed this over the past 30 years?

Evolution of dispute resolution under FIDIC Red Book 1987-2017

1987

The Engineer The Engineer is not a Party - will likely be involved before there is a contract in place with the Contractor The Engineer has a central role to play in the avoidance, resolution and crystallisation of disputes : Receiving Contractor s notices and claim Assessment of payment claims Assessment of time claims Assessment of Variation claims Giving instructions, determinations and approvals Power to audit and make inspections Historically a quasi-arbitral function The Engineer s role in dispute resolution has also evolved

Evolution of the Engineer s role Pre-1999: multiple roles: designer, project manager, contract administrator, certifier, and adjudicator all disputes must go to the Engineer for a decision prior to arbitration the Engineer s role was twofold: Issues: acting as the Employer s agent in executing certain duties, and acting impartially when deciding disputes between the Employer and Contractor. impartiality of the Engineer questioned (paid/employed by the Employer) potential for conflict of interest where Engineer also the designer Post-1999: Engineer replaced by the Dispute Adjudication Board (DAB) for resolution of disputes.

1987 Red Book Dispute Resolution Process No challenge Engineer Decision is final and binding. If Party fails to comply with the decision (67.4) Engineer Decision 70 days Challenge Serving Notice of intention to commence arbitration (67.1) 56 days Attempts to settle in amicably (67.2) Arbitration (67.3) (ICC Rules) Reference of dispute to Engineer 84 days No Engineer Decision Dispute arises

1987 Red Book Extension of time claim example Contractor notifies EoT entitlement and makes initial claim Clause 44.2 Engineer determines EOT Claim Clause 44.1 Contractor dissatisfied and refers EoT claim to the Engineer Clause 67.1 Engineer determines the EOT claim (again) Clause 67.1 Notice of dissatisfaction (otherwise Engineer s determination is final and binding) Clause 67.1 Amicable settlement 56 days (mandatory prior to commencing arbitration) Clause 67.2 Arbitration Clause 67.3

1987 Red Book Issues: Complex drafting difficult to understand Duplication of process in most cases the reference to the Engineer will be in respect of a claim s/he has assessed potentially futile? Engineer is quasi-arbitrator Impartiality? Duty to consult? Decision final and binding by default Lengthy procedure 84 + 70 + 56 days Jurisdictional issues - Engineer s reference is a condition precedent to commencing arbitration

1999

1999 Red Book Revisions to the procedure for assessment of claims by the Engineer Introduction of the Dispute Adjudication Board where the Engineer s determination is disputed Amicable settlement and Arbitration are retained Four distinct phases Claim notification Engineer s determination/ Party agreement Dispute Adjudication Board Arbitration

1999 Red Book Notification of Claims Event giving rise to entitlement to extension of time for completion or additional payment ( Claim ) 28 Days No notice Employer discharged of all liability in connection with Claim (Clause 20.1) 28 Days Notice to Engineer describing the event / circumstance (clause 20.1). Contractor to keep contemporary records to substantiate the claim and for potential inspection (clause 20.1). 42 Days Fully detailed claim to Engineer including full supporting particulars of the basis of the claim and the extension of time/additional payment claimed (clause 20.1).

1999 Red Book Engineer s determination of a claim The fully detailed claim is considered interim (clause 20.1(a)). Contractor sends further interim claims at monthly intervals stating accumulated delay (and such other particulars as Engineer reasonably requires) (clause 20.1(b)). End of effects resulting from event/circumstance 28 days Contractor sends Engineer its final claim (clause 20.1(c)). Cycle of further particulars 42 days Yes Fully detailed claim to Engineer including full supporting particulars of the basis of the claim and the extension of time/additional payment claimed (clause 20.1). Does the event/circumstance have continuing effect? No 42 days Engineer gives approval or disapproval, and detailed comments (and may request further particulars) (clause 20.1). Engineer consults with parties to determine the claim (clause 3.5). Is agreement reached? Yes Engineer gives notice to both parties of agreement / determination with supporting particulars. The parties give effect to the agreement / determination (clause 3.5). No Engineer makes a fair determination taking due regard of all relevant circumstances (clause 3.5).

1999 Red Book Appointment of the DAB Where a dispute arises and there is no DAB in place due to expiry or otherwise, the dispute may be referred directly to arbitration. ARBITRATION Referral of dispute by either party to the DAB for its decision, (with copies to the other Party and the Engineer.) by date stated in ATT Parties jointly appoint a DAB in the number stated in the ATT. If no number is stated, the default shall be 3. 1 member DAB Parties agree 1 member DAB If the Parties fail to agree the DAB for any of the reasons contained in clause 20.2, the appointing entity or official named in the ATT shall, upon the request of and after consultation with both Parties, appoint the member. DAB appointed 3 member DAB If a 3 party DAB, each party shall nominate one member for the approval of the other Party. Party nominated DAB member agreed/appointed. Parties shall consult both members and agree upon the third member, who shall be appointed chairman * ATT = Appendix to Tender

1999 Red Book DAB to arbitration DAB APPOINTMENT 84 days DAB DECISION 28 days No notice of dissatisfaction. DAB decision becomes final and binding If a Party fails to comply with the decision, the other Party may refer the failure itself to arbitration. 28 days Notice of dissatisfaction. Amicable settlement 56 Days Amicable settlement ARBITRATION NO DAB IN PLACE

1999 Red Book What has evolved? Claim determination procedure is more detailed, but: Scope of clause 20.1 any EoT and/or any additional payment, under these Conditions or otherwise in connection with the Contract. Does it apply to claims where no time or money is claimed (e.g.. Defect/no defect disputes?) Is payment for Variations additional? Unclear drafting distinction between the Engineer s determination of claim and response with approval / disapproval and response on principles of the claim Unclear relationship with clause 3.5 and clause 14.6 Payment Certificate shall include such amounts as have been reasonably substantiated as due underutilised in practice. How does this relate to the determination/approval process? Requirement for a fully detailed claim with full supporting particulars in practice this has been abused Further particulars cycle in practice this has also been abused. Potentially perpetual (when can the Contractor escalate the dispute if the Engineer doesn t determine it) Patently asymmetric favours the Employer (c.f. clause 2.5 for Employer claims)

1999 Red Book What else has evolved? Introduction of the DAB Standing / ad hoc DAB unclear but either is possible; standing appears to be preferred (procedural rules require site visits every 4 months) One / three members Parties to choose Adjudicative role only not advisory. Inquisitorial approach. May require hearings. Appointment process if not appointed at the outset, this may be abused. Party appointed members must be approved and contract is silent as to what happens if not approved. No time limit within which appointment authority must appoint the DAB member or chairman, if not agreed. Time while 84 day process appears expedited, this is after the initial claim process has been exhausted, and the DAB is appointed. Realistically not a quick process Cost can be expensive (mini-arbitration). Costs may not be recoverable Enforcement New York Convention / local laws do not apply. Arbitration for breach of contract (clause 20.7) Optional or Mandatory clause 20.8 no DAB in place

2017

2017 Red Book What has evolved? Engineer s determination process for claims is clearer Claims process now clearly separated from dispute resolution process (different clauses) Claims process is revamped asymmetry largely removed Time bar for notification has been softened (but uncertainty is introduced) DAB has transformed into a DAAB ( A for Advisory) DAAB is to be a standing board Many of the drafting problems have been fixed to give greater certainty of interpretation

2017 Red Book Claims Claims / Disputes now split between two clauses Clause 20 Employer s and Contractor s Claims Clause 21 Disputes and Arbitration Clause 20 corrects and improves upon 1999 Red Book: Claim is defined Contractor and Employer claims are addressed in the same way Not limited to EoT and additional payment claims Time bar application is modified Applies to Contractor and Employer claims (28 days) Engineer must give initial response on time bar within 14 days Notice deemed valid if Engineer fails to give initial response, but deemed position can be challenged by other party Claiming party can challenge application of the time bar (factual or why late submissions is justified )

2017 Red Book Claims Fully detailed claim now defined (but not exhaustively) Time for submission now 84 days from becoming aware of circumstances of claim Additional time bar (Notice lapses) if legal basis of claim not provided within 84 days: Engineer to give initial response within 14 days If Engineer fails to do this, Notice becomes valid again Additional particulars curtailed (one iteration only) Engineer s response on principles of claim clarified to be contractual or legal basis of the Claims to be provided within the time limit for agreement in clause 3.7 Claim agreement / determination procedure in clause 3.7 clarified

2017 Red Book Agreement/Determination under Clause 3.7 Scenario : The Parties early advice that agreement cannot be reached and so Engineer s determination is necessary, no error in Engineer s determination. Engineer starts performing duties Sub-Clause 3.7 Parties advise the Engineer: no agreement Sub-Clause 3.7.1(b) Engineer s Notice of determination Sub-Clause 3.7.2 Notice of Dissatisfaction Sub-Clause 3.7.5 No Notice of error Consultations Period for making Engineer s determination 42d 42d 14d Sub-Clause 3.7.3 (a), (b) or (c) 28d Source: 2017 FIDIC Red Book

2017 Red Book

2017 Red Book Disputes Disputes is now a defined term (adds clarity) Disputes must be settled by DAAB (if in place) at least, initially Final dispute resolution is by arbitration

2017 Red Book: Disputes DAB role enhanced as DAAB Clear intention for DAAB to be standing board Drafting of DAAB appointment improved for clarity Clear mandate to DAAB to advise on the avoidance of disputes is asked jointly, or of its own accord (but by invitation) Advisory role Request for advice can be made at any time except when the Engineer is consulting / making a determination on the issue under clause 3.7 The process envisages the DAAB undertaking site visits and convening meetings. This will give rise to considerable additional cost The Parties are not bound to act on the DAAB's advice The DAAB shall not be bound in any future dispute resolution process by any advice or views given during the dispute avoidance process

2017 Red Book Disputes Dispute resolution role If a Notice of Dissatisfaction with an Engineer's Determination has been served, the Dispute must be referred within 42 days of the Notice. Otherwise, the Notice will be deemed to lapse (in which case the Engineer's Determination will become final and binding) Referral of a Dispute to the DAAB shall be deemed to interrupt the running of any applicable statute of limitation or prescription period, unless prohibited by law (dealt with later) Procedural rules for DAAB are enhanced

2017 Red Book Disputes DAAB Decisions It is possible to dispute only parts of the DAAB's decision Parties must promptly comply with the DAAB decision, whether or not a Party also serves a Notice of Dissatisfaction If a Party fails to comply with a DAAB decision (whether or not it has become final and binding), the other Party may refer the failure itself directly to arbitration This has clarified that DAAB decisions which have not yet become final and binding can be enforced directly by arbitration The application of clause 21 requires careful consideration in the GCC States as adjudication is not recognised (unlike arbitration), and in some States there is a statutory prohibition on curtailment of prescription periods.

2017 Red Book DAAB to arbitration DAAB DECISION 28 days No notice of dissatisfaction. DAAB decision becomes final and binding If a Party fails to comply with the decision, the other Party may refer the failure itself to arbitration. 28 days Notice of dissatisfaction. Amicable settlement 28 Days Amicable settlement ARBITRATION No DAAB in place

FIDIC 2017 Arbitration Arbitration is a last resort There are 5 routes to arbitration: Notice of Dissatisfaction with DAAB's decision followed by an attempt to amicably settle the Dispute Notice of Dissatisfaction with DAAB's decision followed by a 28 day period A failure to comply with an agreement / final and binding Engineer's Determination A failure to comply with a DAAB decision There is no DAAB in place or being constituted.

2017 Red Book Summary of Clause 21 Dispute resolution Contractor receives the Letter of Acceptance 21.1 Parties appoint the DAAB 21.4.1 A Party refers the Dispute to the DAAB 21.4.4 A Party may issue a Notice of Dissatisfaction 21.6 A Party may initiate arbitration Parties present submissions to the DAAB 21.5 Amicable settlement 28d* 84d 28d >28d * If not stated otherwise in the Contract Data (Sub-Clause 21.1) DAAB gives its decision Arbitrator/s appointed Source: 2017 FIDIC Red Book

Conclusions Has the evolution been progressive? Time Cost Quality What are the biggest improvements in 2017? What are the potential issues?

Speaker contact details Bill Smith Partner bill.smith@pinsentmasons.com +971 4373 9626 Pinsent Masons LLP is a limited liability partnership, registered in England and Wales (registered number: OC333653) authorised and regulated by the Solicitors Regulation Authority and the appropriate jurisdictions in which it operates. The word 'partner', used in relation to the LLP, refers to a member or an employee or consultant of the LLP, or any firm of equivalent standing. A list of the members of the LLP, and of those non-members who are designated as partners, is available for inspection at our registered office: 30 Crown Place, London, EC2A 4ES, United Kingdom. Pinsent Masons 2018. For a full list of the jurisdictions where we operate, see www.pinsentmasons.com