CONSTRUCTION COMMITTEE

Similar documents
MEETING MINUTES LIVINGSTON COUNTY FINANCE COMMITTEE

AD HOC JAIL PLANNING AND SPECIFICATIONS DEVELOPMENT COMMITTEE MEETING AGENDA

PERSONNEL COMMITTEE AGENDA

The City of Andover, Kansas. Public Building Commission Minutes

MEETING MINUTES LIVINGSTON COUNTY GENERAL GOVERNMENT & HEALTH AND HUMAN SERVICES COMMITTEE

FILED: NEW YORK COUNTY CLERK 01/17/ :26 PM INDEX NO /2015 NYSCEF DOC. NO. 55 RECEIVED NYSCEF: 01/17/2016

PUBLIC FACILITIES January 26, 2012

REGULAR MEETING AGENDA. 4. Scott Freeman HVAC Installment for Farmington Civic Theater

CITY OF GROSSE POINTE WOODS Mack Plaza Conference Room Special City Council Meeting Agenda Monday, April 30, :00 p.m.

NOTICE OF SPECIAL MEETING OF THE BARTLESVILLE EDUCATION AUTHORITY

CORPORATION OF THE MUNICIPALITY OF CHATHAM-KENT. By-law

MOKENA COMMUNITY PARK DISTRICT REGULAR MEETING THE OAKS RECREATION & FITNESS CENTER LaPORTE ROAD, MOKENA, IL APRIL 25, 2017

THE VERANDAHS COMMUNITY DEVELOPMENT DISTRICT BOARD OF SUPERVISORS MEETING DECEMBER 2, 2014

LICENSE APPEAL COMMISSION CITY OF CHICAGO

Evaluation of Courthouse Needs for Southampton County Southampton County, Virginia

Debt Management Committee IMMEDIATELY FOLLOWING FINANCE

Public Hearing to Adopt Local Law #1 of 2014 To Override the 2% Tax 6:00 PM REGULAR BOARD MEETING to Town Hall June 17, 2014

BOARD OF COMMISSIONERS 9/8/ E. Grand River Ave., Howell, MI 7:30 PM

PUBLIC SAFETY and INFRASTRUCTURE & DEVELOPMENT

CITY OF GAINESVILLE APPLICATION CHECKLIST CERTIFICATE OF APPROPRIATENESS

Law Offices of JULIANNE M. HOLT

Rochester Joint Schools Construction Board Minutes February 4, :30 PM

Avrohom Ackerman July 7, 2016 Comments on the Proposed DOB Rule Regarding Construction Codes and Zoning Resolution Determinations and Appeals Fees

Citation: Queens Co. Const. v Currie Date: PROVINCE OF PRINCE EDWARD ISLAND IN THE SUPREME COURT - TRIAL DIVISION

Present: Ms. Butts, Mr. Corrigan, Ms. Rodriguez, Mr. Hairston, Mr. Parker. Absent: Mr. Seifullah, Ms. Washington

Table of Contents SE-310, Invitation for Construction Services... 1

LEAVENWORTH WATER DEPARTMENT

TUESDAY, NOVEMBER 13, 2018 OFFICE OF THE BOARD OF COMMISSIONERS PICKAWAY COUNTY, OHIO

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

WASHINGTON COUNTY PUBLIC SCHOOLS - NORTH HAGERSTOWN HIGH SCHOOL HEALTH SUITE EXPANSION

TITLE 12 BUILDING, UTILITY, ETC. CODES 1

TOWN OF SEABROOK ISLAND Planning Commission Meeting January 10, :30 PM

MEMORANDUM OF AGREEMENT BETWEEN TEXAS FACILITIES COMMISSION TEXAS HISTORICAL COMMISSION

BOARD OF APPEALS CITY & COUNTY OF SAN FRANCISCO MEETING MINUTES - WEDNESDAY, NOVEMBER 13, 2013

THE CORPORATION OF THE TOWN OF OAKVILLE BY-LAW NUMBER

CDBG SIDEWALK IMPROVEMENTS Burks Road, North Avenue, Stillwood Cove CITY OF FOREST PARK, GEORGIA

INFORMATION SYSTEMS COMMITTEE

MINIMUM HOUSING STANDARDS ORDINANCE

State of West Virginia Request For Quotation. Document Description : Addendum No. 01 Holly River SP Group 1 Cabin Rehabilitation

NOTICE THE COMMISSIONERS OF THE CITY OF REHOBOTH BEACH ON JANUARY 18, 2013, ADOPTED ORDINANCE NO WHICH READS AS FOLLOWS:

7:00 P.M. BOARD MEETING. CONSENT AGENDA A. October 25th Agenda Approval B. October 11th Approval of Meeting Minutes

COUNTY OF LOUISA, VIRGINIA

General Contractor shall provide their own dumpster. Dumpster shall be located in parking lot behind Gymnasium. Coordinate location with Owner.

CONSTRUCTION COMMITTEE MEETING AGENDA

Fort Collins Amendments to the 2009 International Mechanical Code

FLOOR PLAN OF THE TECHNICAL EXHIBITION AREA.

INVITATION FOR BIDS: Maintenance Repairs FY Bristol Warren Regional School District

MINUTES OF THE REGULAR BOARD MEETING BOARD OF DIRECTORS OF THE ASSOCIATION OF APARTMENT OWNERS OF KUHIO SHORES AT POIPU

CITY OF VANCOUVER BRITISH COLUMBIA

LIVINGSTON COUNTY BOARD PROPERTY COMMITTEE MINUTES OF AUGUST 3, 2015

MINUTES WALNUT CREEK MUTUAL NO. TWENTY-EIGHT FORTY-FOURTH ANNUAL MEETING OF MEMBERS WEDNESDAY, MARCH 4, 2015 AT 9:30 A.M. DONNER ROOM EVENT CENTER

Tiny Home Construction and Sale Agreement

OLD BUSINESS: Northern Agreement Negotiations Item was not discussed.

GENERAL GOVERNMENT & HEALTH AND HUMAN SERVICES COMMITTEE

City of Del Mar Design Review Board Agenda Del Mar Communications Center 240 Tenth Street, Del Mar, California

An excavation permit is required for any excavation work within the public right-ofway.

DISTRICT OF LILLOOET AGENDA

Present: Thomas Gifford, John VanDenHurk, Margaret Starbuck, J.P. Coleman, Carl Blowers, Fagan, Tim O Hearn, Peggy Tomassi, Mark Gorgos

BUILDING PERMIT ORDINANCE TOWN OF WOODSTOCK

MEETING MINUTES LIVINGSTON COUNTY GENERAL GOVERNMENT & HEALTH AND HUMAN SERVICES COMMITTEE

BILL ORDINANCE 10003

ICC-ES APPLICATION FOR BUILDING PRODUCT LISTING REPORT FORM A

1. CALL TO ORDER The regular meeting of the Howell City Council was called to order by Mayor Nick Proctor at 7:00 p.m.

He is now recommending that the Board proceed in obtaining bids as follows:

Legal Services for Representation to Indigent Parents RFP Laramie County

AGENDA. NOMINATING COMMITTEE MEETING June 29, :15 P.M S. Washington Ave. REO Town Depot

AGENDA PLAN COMMISSION MEETING Thursday December 28, :00 pm Jackson Village Hall N168W20733 Main St Jackson, WI 53037

FREDERICKSBURG CITY PUBLIC SCHOOLS Fredericksburg, Virginia

Bed Bug Plan Multi Family - 90 Day

One Technology Court, Montgomery, AL Telephone:

Town of Charlton Saratoga County Town Board Meeting. March 14, 2016

BOARD OF APPEALS APPLICATION (VARIANCE FROM SUBDIVISION OR ZONING ORDINANCE) Sec or Sec (c)

S U B S T I T U T E O R D I N A N C E AS AMENDED BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CHICAGO:

LIVINGSTON COUNTY BOARD PROPERTY COMMITTEE MINUTES OF SEPTEMBER 4, 2018

odt1d M. Medina, Jus~~-

Coastal Carolina University Ingle Residence Hall Renovations

Central Michigan Intra-Area 32 Area Assembly February 6, 2011 Corunna, MI

EXHIBIT A. LARIMER COUNTY CODE Chapter 10 Article VIII. Building Contractor Licensing Program

Finance Committee. 11/17/ E. Grand River Ave., Howell, MI 7:30 AM AGENDA

ORDINANCE NO AN ORDINANCE TO BE KNOWN AS THE HERNANDO COUNTY,MECHANICAL CODE: PROVIDING FOR THE ADOPTION OF THE I-

THE CORPORATION OF THE TOWNSHIP OF OTONABEE-SOUTH MONAGHAN BY-LAW NUMBER

Charleston County Historic Courthouse

RULE CAPTION. RULEMAKING ACTION List each rule number separately,

MINUTES. Vice Chairman Stark entertained a motion to approve the Minutes of the April 13, 2017 meeting as written.

FORM A: BID (See B8) 1. Contract Title FERRY ROAD RIVERBEND COMBINED SEWER RELIEF CONTRACT NO. 2

CLINTON COUNTY BOARD OF COMMISSIONERS

Business and Tourist Visas

ARTICLE 905 Street Excavations. EDITOR S NOTE: Resolution , passed February 3, 2009, established street excavation fees.

Town of Manchester, Maine

FLCC Projects Committee

PLAINTIFF INFORMATION STARTING YOUR ACTION

CONTRACT FOR THE DEMOLITION OF A RESIDENTIAL BUILDING

October 8, Ms. Mary Jo Kunkle Executive Secretary Michigan Public Service Commission 6545 Mercantile Way P.O. Box Lansing, MI 48909

LIVINGSTON COUNTY COMMUNITY MENTAL HEALTH AUTHORITY (LCCMHA) FOIA Policies, Procedures and Guidelines

THE CORPORATION OF THE CITY OF BRAMPTON OFFICE CONSOLIDATION BY-LAW (amended by By-laws and )

March 23, Subject: Proposed Ordinance to Amend Chapter 16 (Building Code)

Ten-year survey by licensed architect/engineer Annual inspection by Regional office of Education District-initiated inspection Inspections done by

9 1 1 ADVISORY COMMITTEE AGENDA

FILED: NEW YORK COUNTY CLERK 09/28/ :27 PM INDEX NO /2016 NYSCEF DOC. NO. 7 RECEIVED NYSCEF: 09/28/2016

MEETING SUMMARY WAKE COUNTY HISTORIC PRESERVATION COMMISSION April 13, Wake County Courthouse, Room 700

Transcription:

CONSTRUCTION COMMITTEE 11/9/2015 304 E. Grand River Ave, Conference Rm 4A, Howell, MI 48843 6:30 PM AGENDA 1. CALL TO ORDER 2. APPROVAL OF MINUTES Minutes of Meeting Dated: October 19, 2015 3. APPROVAL OF AGENDA 4. REPORTS A. Budget Report B. Open PCO Log 5. CALL TO THE PUBLIC 6. ACTION ITEMS A. Clark Pay Application #15: $693,407.75 B. PCO 81 - Credit for T&M work: ($12,095.33) C. PCO 82 - Misc. Drywall Extras: $6,341.00 D. PCO 83 - Sallyport Electrical Demolition: $845.00 E. PCO 84 - Added Sprinkler Heads per RFI 121: $896.00 F. PCO 85 - Rework Fire Protection-Sallyport: $1,563.00 G. PCO 86 - Relocate 2 Sprinkler Heads: $1,099.00 H. PCO 88 - Floor to Wall Joint Caulking: $2,712.00 I. PCO 89 - Replacement Door Savings: ($15,207.00) 7. NEW BUSINESS 8. ADJOURNMENT

MEETING MINUTES LIVINGSTON COUNTY OCTOBER 19, 2015-6:30 PM ADMINISTRATION BUILDING - CONFERENCE ROOM 4 304 E. Grand River Avenue, Howell, MI 48843 CONSTRUCTION COMMITTEE COMM. DOLAN COMM. CHILDS COMM. VANHOUTEN OTHERS: MIKE KENNEDY CHAD RIEHL KEN HINTON HEATHER BRANDENBURG NATALIE HUNT TOM CREMONTE 1. CALL TO ORDER: Meeting called to order by: COMM. DENNIS DOLAN at 6:30 PM. 2. APPROVAL OF MINUTES: MINUTES OF MEETING DATED SEPTEMBER 14, 2015: MOTION TO APPROVE THE MINUTES, AS PRESENTED. MOVED BY: VAN HOUTEN / SECONDED BY: CHILDS ALL IN FAVOR - MOTION PASSED 3. APPROVAL OF AGENDA: MOTION TO APPROVE THE AGENDA, AS MODIFIED. ADD PCO #80 NEW BUSINESS DISCUSS CELL DOORS MOVED BY: CHILDS / SECONDED BY: VAN HOUTEN ALL IN FAVOR - MOTION PASSED 4. REPORTS o STEEL CELL INVOICE RECEIVED LATE, WOULD LIKE TO GET THAT ON THE AGENDA. o INVOICE WILL BE BROUGHT TO NEXT MEETING ON NOVEMBER 9 TH, AGENDA STANDS. A. BUDGET REPORT: o BUYOUT BALANCE OF ASPHALT WILL NOT BE SENT AND BE PUT BACK IN CONTINGENCY AND $13,000 IN CHANGE ORDERS ON TODAY S AGENDA LEAVES A $275,073 CONTINGENCY BALANCE B. CONSTRUCTION PROGRESS UPDATE: MIKE KENNEDY o FURNITURE FOR DAY ROOM HAS BEEN DELIVERED, MATTRESSES HAVE ALSO BEEN DELIVERED. o STARTED FINAL CLEANING IN MECHANICAL CHASE, CELL AREA WILL BE NEXT Page 1 of 4 Pages

o FIXTURES STILL NEED TO BE CAULKED. o SPRINKLER HEADS TO BE CHANGED IN THE 2 ND FLOOR HALLWAY o EXTERIOR FINISH PAVING THIS FRIDAY, STRIPING FOR PARKING LOT WILL BE DONE ON MONDAY o GROUND IS RAKED AND READY FOR SEED, SECURITY FENCES ARE UP, TREES WILL BE PLANTED TOMORROW OR WEDNESDAY o SALLY PORT (EXISTING) FOUNDATION IS IN, MASON STARTED TODAY, STEEL WILL BE SET NEXT WEEK o DISCUSSED HOW TO CONNECT THE SALLY PORT DRAIN TO THE CURRENT PLUMBING o GLAZING MAY ARRIVE AS SOON AS OCTOBER 30 TH o DOOR RENAMING WILL ESTABLISHED THIS THURSDAY o SHOULD GET WITH RICH & ROBERTA TO GET FINAL FURNITURE AND IT COSTS. 5. CALL TO THE PUBLIC: None. 6. ACTION ITEMS: A. ACTION REQUIRED:... Clark Construction Jail Roof Invoice: $7,018.92 REVIEWED AND APPROVED FOR PAYMENT. NO OBJECTIONS. APPROVED FOR PAYMENT: MOVED BY: VAN HOUTEN SECONDED BY: CHILDS B. ACTION REQUIRED:... Clark Construction Pay Application 14: $900,552.95 REVIEWED AND APPROVED FOR PAYMENT. NO OBJECTIONS. APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN C. ACTION REQUIRED:... Clark Construction PCO 67 - Delete Mattresses: ($27,430.00) REVIEWED AND APPROVED PCO. NO OBJECTIONS. APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN D. ACTION REQUIRED:... Clark Construction PCO 68 - Delete VCT: ($875.00) REVIEWED APPROVED PCO 67 & 68 ON SEPTEMBER 14 TH APPROVED FOR PAYMENT: MOVED BY: SECONDED BY: E. ACTION REQUIRED:... Clark Construction PCO 70 - I.T. Room: $15,185.00 REVIEWED AND APPROVED PCO. NO OBJECTIONS. APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN Page 2 of 4 Pages

F. ACTION REQUIRED:... Clark Construction PCO 71 - Data Drop: $998.00 REVIEWED AND APPROVED PCO. NO OBJECTIONS. APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN G. ACTION REQUIRED:... Clark Construction PCO 72 - Smoke Dampers: $1,087.00 REVIEWED AND APPROVED PCO. NO OBJECTIONS. APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN H. ACTION REQUIRED:... Clark Construction PCO 73 - Asphalt Removal: $9,700.00 REVIEWED AND APPROVED PCO. NO OBJECTIONS. APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN I. ACTION REQUIRED:... Clark Construction PCO 74 - Sidewalk Undercutting: $3,700.00 REVIEWED AND APPROVED PCO. NO OBJECTIONS. APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN J. ACTION REQUIRED:... Clark Construction PCO 75 Cut Door: $886.00 REVIEWED AND APPROVED PCO. NO OBJECTIONS. APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN K. ACTION REQUIRED:... Clark Construction PCO 76 - Heater: $888.00 REVIEWED AND APPROVED PCO. NO OBJECTIONS. APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN L. ACTION REQUIRED:... Clark Construction PCO 77 - Raise DAC 1: $1,580.00 REVIEWED AND APPROVED PCO. NO OBJECTIONS. APPROVED FOR PAYMENT: MOVED BY: VAN HOUTEN SECONDED BY: CHILDS Page 3 of 4 Pages

M. ACTION REQUIRED:... Clark Construction PCO 78 BR1 PR 5 & 6: $10,200.00 REVIEWED AND APPROVED PCO. NO OBJECTIONS. APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN N. ACTION REQUIRED:... Clark Construction PCO 79 Raising RTU: ($2,914.00) REVIEWED AND APPROVED PCO. NO OBJECTIONS. APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN O. ACTION REQUIRED:... Clark Construction PCO 80 Dimming Switch: $1,704.00 REVIEWED AND APPROVED PCO. NO OBJECTIONS. APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN 7. NEW BUSINESS: o DISCUSS CELL DOORS COMMISSIONER DOLAN AND COMMITTEE MEMBERS RECEIVED DOCUMENTS FROM MIKE KENNEDY IN REGARDS TO CELL DOORS THAT WERE REPLACED. o NEED DOCUMENTATION THAT CELL DOORS LEFT THE SITE, WHERE, WHEN, AND BY WHOM o CONFIRMATION THAT GLASS WAS RE-USED WITH THE NEW DOORS. o LINDHOUT GAVE STEEL CELL THE DIRECTION TO REMOVE DOORS FROM THE SITE WHEN DELIVERING OTHER MATERIALS. o POTENTIAL CREDIT FROM REICHENBACH COMING 8. ADJOURNMENT: MOTION TO ADJOURN AT 7:24 PM. MOVED BY: CHILDS / SECONDED BY: VAN HOUTEN ALL IN FAVOR - MOTION PASSED Respectfully Submitted NATALIE HUNT RECORDING SECRETARY Page 4 of 4 Pages

Lindhout Associates architects aia pc www.lindhout.com November 5, 2015 Livingston County Jail 150 S. Highlander Way Howell, MI 48855 Our Mission Integrity in architecture and design in client relationships in employee relationships in community relationships Attn: Re: Lt. Tom Cremonte, Jail Administrator Application and Certificate for Payment No.15 advancement in all these efforts Dear Lt. Cremonte: Attached please find the application and certificate for payment No.15 from Clark Construction Company. We find this work to be in general compliance with the requirements of the contract documents and the level of completeness to be equal to or greater than the amount indicated in the attached application. If this action meets with your approval, please proceed with payment to Clark Construction Company in the amount indicated on the application. Feel free to contact our office if you have any questions or comments regarding this application for payment. Michael J. Kennedy, President Lindhout Associates architects aia pc c.c. Chad Riehl, Clark Construction Company william p. lindhout frank l. pierron piet w. lindhout robert j. king michael j. kennedy david a. richardson michael j. o leary bradley m. alvord john w. eckstein d. jason mcintyre holly a. osterhout 10465 citation drive, brighton, michigan 810-227-5668 (fax) 810-227-5855

(Through PCCO #14)

10/21/2015 Mike Kennedy Lindhout Associates Architects 10465 Citation Drive Brighton, MI 48116 RE: PCO No. 081 Livingston County Jail Expansion -14-2664 Dear Mike Kennedy, We have finalized gathering all the required quotations for PCO No. 081 for the following extra work: Credit for T&M work completed in PCO's 53 and 65.. We have reviewed the scopes of work and have verified that all extra work items are in compliance with the Contract Documents. The following is a detailed itemization of all extra costs: Item Budget Code Description Amount Proposed Contractor 001 2664 A 03 Credit for T&M per PR#4 ($1,561.33) William Reichenbach Co. 092000 01000 S 002 2664 A 03 092000 01000 S Drywall, Metal Studs, Acoust Ceilings ($10,534.00) William Reichenbach Co. Total Amount ($12,095.33) This change will require 0 days extension to the contract completion date. This quote is void after 30 days. If you have any questions regarding this Potential Change Order Request, please call me at your earliest convenience. If the above item(s) meet with your approval, please sign a copy of this letter and send back to me. Respectfully, CLARK CONSTRUCTION COMPANY Chad Riehl Project Director Livingston County/Date Page 1 of 1

10/21/2015 Mike Kennedy Lindhout Associates Architects 10465 Citation Drive Brighton, MI 48116 RE: PCO No. 082 Livingston County Jail Expansion -14-2664 Dear Mike Kennedy, We have finalized gathering all the required quotations for PCO No. 082 for the following extra work: Misc. Drywall Extras. We have reviewed the scopes of work and have verified that all extra work items are in compliance with the Contract Documents. The following is a detailed itemization of all extra costs: Item Budget Code Description Amount Proposed Contractor 001 2664 A 03 092000 01000 S Build Chase to cover sprinkler pipe $635.00 William Reichenbach Co. 002 2664 A 03 092000 01000 S Frame wall on lower roof along C line $656.00 William Reichenbach Co. 003 2664 A 03 Build chase around plumbing room $507.00 William Reichenbach Co. 092000 01000 S 696 004 2664 A 03 Install 2hr shaft ceiling in janitor $2,476.00 William Reichenbach Co. 092000 01000 S closet 005 2664 A 03 092000 01000 S Cut roof decking back at skylight locations $2,067.00 William Reichenbach Co. Total Amount $6,341.00 This change will require 0 days extension to the contract completion date. This quote is void after 30 days. If you have any questions regarding this Potential Change Order Request, please call me at your earliest convenience. If the above item(s) meet with your approval, please sign a copy of this letter and send back to me. Respectfully, CLARK CONSTRUCTION COMPANY Chad Riehl Project Director Livingston County/Date Page 1 of 1

10/21/2015 Mike Kennedy Lindhout Associates Architects 10465 Citation Drive Brighton, MI 48116 RE: PCO No. 083 Livingston County Jail Expansion -14-2664 Dear Mike Kennedy, We have finalized gathering all the required quotations for PCO No. 083 for the following extra work: Sallyport electrical demolitioin. We have reviewed the scopes of work and have verified that all extra work items are in compliance with the Contract Documents. The following is a detailed itemization of all extra costs: Item Budget Code Description Amount Proposed Contractor 001 2664 A 03 260000 01000 S Sallyport electrical Demolition $845.00 Superior Electric Total Amount $845.00 This change will require 0 days extension to the contract completion date. This quote is void after 30 days. If you have any questions regarding this Potential Change Order Request, please call me at your earliest convenience. If the above item(s) meet with your approval, please sign a copy of this letter and send back to me. Respectfully, CLARK CONSTRUCTION COMPANY Chad Riehl Project Director Livingston County/Date Page 1 of 1

PROPOSED CHANGE ORDER SUPERIOR ELECTRIC OF LANSING 212 W. SHERIDAN ROAD LANSING, MICHIGAN 48906 CCN # PCO-023 SALLY PORT Date: 10/16/2015 Project Name: LIVINGSTON COUNTY JA Project Number: 18000 Page Number: 1 Client Address: CLARK CONSTRUCTION COMPANY Contact: CHAD RIEHL 3535 MOORES RIVER DRIVE LANSING, MICHIGAN 48911 Work Description PER LIVINGSTON COUNTY/ CLARK CONSTRUCTION REQUEST, DEMO ELECTRICAL IN EXISTING SALLY PORT NOT SHOWN IN DRAWINGS TIME AND MATERIAL We reserve the right to correct this quote for errors and omissions. This quote covers direct costs only and we reserve the right to claim for impact and consequential costs. This price is good for acceptance within 10 days from the date of receipt. We request a time extension of 3 days. We will supply and install all materials, labor, and equipment as per your instructions on CCN # PCO-023 SALLY PORT DEMO. Itemized Breakdown Summary Description Qty Total Mat. MISC DEMO 10 0.00 Totals 10 0.00 ELECTRICAN (10.00 Hrs @ $73.50) 735.00 Subtotal 735.00 Markup 15% 110.25 Subtotal 845.25 Final Amount $845.25 CONTRACTOR CERTIFICATION Name: Date: Signature: I hereby certify that this quotation is complete and accurate based on the information provided. CLIENT ACCEPTANCE ORIGINAL

PROPOSED CHANGE ORDER SUPERIOR ELECTRIC OF LANSING 212 W. SHERIDAN ROAD LANSING, MICHIGAN 48906 Client Address: CLARK CONSTRUCTION COMPANY 3535 MOORES RIVER DRIVE LANSING, MICHIGAN 48911 CCN # PCO-023 SALLY PORT Date: 10/16/2015 Project Name: LIVINGSTON COUNTY JA Project Number: 18000 Page Number: 2 CCN #: PCO-023 SALLY PORT DEMO Final Amount:$845.25 Name: Date: Signature: Change Order #: I hereby accept this quotation and authorize the contractor to complete the above described work. ORIGINAL

10/21/2015 Mike Kennedy Lindhout Associates Architects 10465 Citation Drive Brighton, MI 48116 RE: PCO No. 084 Livingston County Jail Expansion -14-2664 Dear Mike Kennedy, We have finalized gathering all the required quotations for PCO No. 084 for the following extra work: Added spriinkler heads per RFI 121. We have reviewed the scopes of work and have verified that all extra work items are in compliance with the Contract Documents. The following is a detailed itemization of all extra costs: Item Budget Code Description Amount Proposed 001 2664 A 03 Added sprinkler heads per RFI 121 $896.00 210000 01000 S Contractor John E. Green Co Total Amount $896.00 This change will require 0 days extension to the contract completion date. This quote is void after 30 days. If you have any questions regarding this Potential Change Order Request, please call me at your earliest convenience. If the above item(s) meet with your approval, please sign a copy of this letter and send back to me. Respectfully, CLARK CONSTRUCTION COMPANY Chad Riehl Project Director Livingston County/Date Page 1 of 1

10/21/2015 Mike Kennedy Lindhout Associates Architects 10465 Citation Drive Brighton, MI 48116 RE: PCO No. 085 Livingston County Jail Expansion -14-2664 Dear Mike Kennedy, We have finalized gathering all the required quotations for PCO No. 085 for the following extra work: Rework Fire Protection main in Sallyport. We have reviewed the scopes of work and have verified that all extra work items are in compliance with the Contract Documents. The following is a detailed itemization of all extra costs: Item Budget Code Description Amount Proposed Contractor 001 2664 A 03 210000 01000 S Rework Fire Protection main in Sallyport $1,563.00 John E. Green Total Amount $1,563.00 This change will require 0 days extension to the contract completion date. This quote is void after 30 days. If you have any questions regarding this Potential Change Order Request, please call me at your earliest convenience. If the above item(s) meet with your approval, please sign a copy of this letter and send back to me. Respectfully, CLARK CONSTRUCTION COMPANY Chad Riehl Project Director Livingston County/Date Page 1 of 1

10/21/2015 Mike Kennedy Lindhout Associates Architects 10465 Citation Drive Brighton, MI 48116 RE: PCO No. 086 Livingston County Jail Expansion -14-2664 Dear Mike Kennedy, We have finalized gathering all the required quotations for PCO No. 086 for the following extra work: Relocate 2 sprinkler heads out of door swing. We have reviewed the scopes of work and have verified that all extra work items are in compliance with the Contract Documents. The following is a detailed itemization of all extra costs: Item Budget Code Description Amount Proposed Contractor 001 2664 A 03 210000 01000 S Relocate 2 sprinkler heads out of door swing $1,099.00 John E. Green Total Amount $1,099.00 This change will require 0 days extension to the contract completion date. This quote is void after 30 days. If you have any questions regarding this Potential Change Order Request, please call me at your earliest convenience. If the above item(s) meet with your approval, please sign a copy of this letter and send back to me. Respectfully, CLARK CONSTRUCTION COMPANY Chad Riehl Project Director Livingston County/Date Page 1 of 1

11/4/2015 Mike Kennedy Lindhout Associates Architects 10465 Citation Drive Brighton, MI 48116 RE: PCO No. 088 Livingston County Jail Expansion -14-2664 Dear Mike Kennedy, We have finalized gathering all the required quotations for PCO No. 088 for the following extra work: Floor to wall joint caulking. We have reviewed the scopes of work and have verified that all extra work items are in compliance with the Contract Documents. The following is a detailed itemization of all extra costs: Item Budget Code Description Amount Proposed Contractor 001 2664 A 03 040000 01000 S Floor to wall joint caulking $2,712.00 Davenport Masonry Total Amount $2,712.00 This change will require 0 days extension to the contract completion date. This quote is void after 30 days. If you have any questions regarding this Potential Change Order Request, please call me at your earliest convenience. If the above item(s) meet with your approval, please sign a copy of this letter and send back to me. Respectfully, CLARK CONSTRUCTION COMPANY Chad Riehl Project Director Livingston County/Date Page 1 of 1

ATTN: RE: Greg Deuel Clark Construction Company Livingston County Jail We propose to furnish labor, material, and equipment for the following work: Install Dyna Flex SC sealant at the floor to wall conditions were expansion exist Approx 450 LF Clarifications: This quote is for work to be preformed as straight time For the sum of: $ 2,712.00 If you should have any questions, please feel free to contact me at any time. Sincerely, Rick Benner 517-927-9020 P.O. Box 188 1445 Edgar Rd. Holt, MI 48842-0188 Phone: 517.699.4279 Fax: 517.699.6141 www.davenpo EQUAL OPPORTUNITY EMPLOYER

ortmasonry.com

11/4/2015 Mike Kennedy Lindhout Associates Architects 10465 Citation Drive Brighton, MI 48116 RE: PCO No. 089 Livingston County Jail Expansion -14-2664 Dear Mike Kennedy, We have finalized gathering all the required quotations for PCO No. 089 for the following extra work: Replacement door savings. We have reviewed the scopes of work and have verified that all extra work items are in compliance with the Contract Documents. The following is a detailed itemization of all extra costs: Item Budget Code Description Amount Proposed Contractor 001 2664 A 03 130000 01000 S Replacement door savings ($15,207.00) Steel Cell Total Amount ($15,207.00) This change will require 0 days extension to the contract completion date. This quote is void after 30 days. If you have any questions regarding this Potential Change Order Request, please call me at your earliest convenience. If the above item(s) meet with your approval, please sign a copy of this letter and send back to me. Respectfully, CLARK CONSTRUCTION COMPANY Chad Riehl Project Director Livingston County/Date Page 1 of 1