It is most unusual and judicially improper for a Court to publish its judgment in the public media

Similar documents
IN THE SUPREME COURT OF JUDICATURE COURT OF APPEAL SUBMISSIONS

IN THE CARIBBEAN COURT OF JUSTICE Appellate Jurisdiction ON APPEAL FROM THE COURT OF APPEAL OF BARBADOS

IN THE CARIBBEAN COURT OF JUSTICE Appellate Jurisdiction ON APPEAL FROM THE COURT OF APPEAL OF BARBADOS

JUDGMENT. Hallman Holding Ltd (Appellant) v Webster and another (Respondents) (Anguilla)

IN THE HIGH COURT OF JUSTICE GARY LEGGE AND MAUREEN LEGGE. Between CHRIS RAMSAWACK AND WESTERN SHIP AND RIG SUPPLIES LIMITED

CONTENTS Page. Lease Of Land By Tender For Development 2-4. Submission Of Tender And Tender Deposit 5-9. Rejection And Disqualification Of Tender 9-10

IN THE HIGH COURT OF JUSTICE (Sub-Registry, Tobago) BETWEEN AND REASONS

CHAPTER PROPERTY TAX ACT and Subsidiary Legislation

IN THE SUPREME COURT OF JUDICATURE HIGH COURT CIVIL DIVISION

IN THE HIGH COURT OF JUSTICE IN THE MATTER OF THE JUDICIAL REVIEW ACT NO. 60 OF 2000 AND

JUDGMENT. Republic Bank Limited (Appellant) v Lochan and another (Respondents) (Trinidad and Tobago)

Sectional Titles Act, 95 of 1986

(Effective August 31, 2018) Cure of obvious description errors in recorded instruments.

IN THE HIGH COURT OF JUSTICE. Between ROBERTO CHARLES AND SHASTRI PRABHUDIAL

IN THE HIGH COURT OF JUSTICE BETWEEN AND

IN THE SUPREME COURT OF VICTORIA AT MELBOURNE COMMERCIAL COURT TECHNOLOGY, ENGINEERING AND CONSTRUCTION LIST

Re: Dr Jonathan Richard Ashton v GMC [2013] EWHC 943 Admin

IN THE COURT OF APPEAL OF BELIZE, A.D CIVIL APPEAL NO. 32 OF 2008

Church Property Measure

Village of Romeoville 1050 West Romeo Road Romeoville, IL (815) NEIGHBORHOOD SIGNAGE GRANT PROGRAM

Proposed Amendment in Section 28 of The Contract Act, 1872

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO OF 2018 RAMESHWAR PRASAD SHRIVASTAVA AND ORS.

c t MECHANICS LIEN ACT

JUDGMENT. Oceania Heights Limited (Appellant) v Willard Clarke Enterprises Limited & others (Respondent)

CHAPTER 33:04 SECTIONAL TITLES

CONVEYANCING (PASSING OF RISK) AMENDMENT ACT 1986 No. 6

BEFORE THE REAL ESTATE AGENTS DISCIPLINARY TRIBUNAL. TRUSTEES OF THE JS & AJ HAMILTON FAMILY TRUST Appellants

Do I need Planning Permission? Frequently Asked Questions

BELIZE LIMITED LIABILITY PARTNERSHIP ACT CHAPTER 258 REVISED EDITION 2011 SHOWING THE SUBSTANTIVE LAWS AS AT 31 ST DECEMBER, 2011

CHAPTER 33:04 SECTIONAL TITLES ARRANGEMENT OF SECTIONS

STATE OF MICHIGAN COURT OF APPEALS

IN THE COURT OF APPEAL. and VIOLA BUNTIN. 2008: August 26.

JUDGMENT OF THE COURT Delivered jointly by The Honourable Mr Justice Adrian Saunders and The Honourable Mr Justice David Hayton

CLOSER SETTLEMENT (AMEND- MENT) ACT. Act No. 48, 1918.

Building and Construction Industry Security of Payment Act 1999

IN THE COURT OF APPEAL OF NEW ZEALAND CA110/05. William Young P, Arnold and Ellen France JJ

Status: This is the original version (as it was originally enacted). ELIZABETH II c. 19. Employment Act CHAPTER 19 PART I TRADE UNIONS

INTERPRETATION OF CONTRACTS

Body Corporate Plan No. PS509946A v VM Romano Construction Group Pty Ltd & Anor (Domestic Building) [2009] VCAT 1662

IN THE EASTERN CARIBBEAN SUPREME COURT IN THE HIGH COURT OF JUSTICE AND

JUDGMENT OF THE LORDS OF THE JUDICIAL COMMITTEE OF THE PRIVY COUNCIL. Delivered the 24 th January 2008

Wassenaar v. Towne Hotel 111 Wis. 2d 518, 331 N.W.2d 357 (1983)

IN THE HIGH COURT OF SOUTH AFRICA FREE STATE DIVISION, BLOEMFONTEIN

THE SUPREME COURT OF APPEAL OF SOUTH AFRICA JUDGMENT RIVERSDALE MINING LIMITED

JUDGMENT DELIVERED ON : 18 OCTOBER 2004

THE EASTERN CARIBBEAN SUPREME COURT IN THE HIGH COURT OF JUSTICE ANTIGUA AND BARBUDA BLONDELLE RICHARDSON WORRELL RICHARDSON. and

1. In these conditions ( these Conditions ) unless the context requires otherwise:

NC General Statutes - Chapter 44A Article 2 1

PARADISE TIMBERS PTY LTD APPLICATION FOR COMMERCIAL CREDIT

STATE OF MICHIGAN COURT OF APPEALS

CONSOLIDATED BANK OF KENYA ACT

AGREEMENT FOR THE CONSTRUCTION OF A DWELLING HOUSE

GST & forfeited deposits High Court decision

APPENDIX FOR MARGIN ACCOUNTS

Uttlesford District Council v Secretary of State for the Environment and another

Alexandria Center for International Arbitration Semi-dried dates case of 10 January 2005

In the Circuit Court for Prince George s County Case No. CT050498X IN THE COURT OF APPEALS OF MARYLAND. No. 93. September Term, 2006

IN THE SUPREME COURT OF FLORIDA CASE NO. SC DISTRICT COURT CASE NO. 4D

THE EASTERN CARIBBEAN SUPREME COURT IN THE HIGH COURT OF JUSTICE ANTIGUA AND BARBUDA

THE SUPREME COURT OF APPEAL OF SOUTH AFRICA JUDGMENT. Auction Alliance (Pty) Ltd

ASSIGNMENT OF RENTAL PROCEEDS. A DEED OF ASSIGNMENT dated the

IN THE SUPREME COURT OF BELIZE, A.D (BRENT C. MISKUSKI SECOND DEFENDANT (DELIA MISKUSKI THIRD DEFENDANT JUDGMENT

CHAPTER 91:01 TRADE ACT ARRANGEMENT OF SECTIONS

MEMORANDUM OF DEPOSIT

IN THE COURT OF APPEAL MOVING TARGET LIMITED. and. Before: The Honourable Mr. Satrohan Singh. [February 22, March 22, 1999] JUDGMENT

BERMUDA LEGAL AID (GENERAL) REGULATIONS 1980 BR 70 / 1980

COURT OF APPEAL FOR BRITISH COLUMBIA Citation: Between: And Bartram v. Glaxosmithkline Inc., 2011 BCCA 539 Date: Docket: CA Meah Bartra

IN THE MATTER OF THE CONSTITUTION OF SAINT VINCENT AND THE GRENADINES

CAYMAN ISLANDS. Supplement No. 1 published with Extraordinary Gazette No. 5 of 22nd January, COURT OF APPEAL LAW.

AGREEMENT WITH BUILDER THIS AGREEMENT MADE BETWEEN:

Paddocks legislation documentation. Sectional Titles Act, No. 95 of 1986

Ombudsman s Determination

THE CYPRUS TOURISM ORGANIZATION (ADMINISTRATIVE AND FINANCIAL) REGULATIONS, 1970 TO 1997

THE CONTRACT FORMATION PROCESS THE PRESENTER INTRODUCTION TOPICS CONTRACT LAW: ESSENTIAL SKILLS FOR NON-LAWYERS HYATT HOTEL CANBERRA 18 JUNE 2014

SECTIONAL TITLES ACT 95 OF 1986 [ASSENTED TO 8 SEPTEMBER 1986] [DATE OF COMMENCEMENT: 1 JUNE 1988]

Republic of South Africa IN THE HIGH COURT OF SOUTH AFRICA (WESTERN CAPE DIVISION, CAPE TOWN) CASH CRUSADERS FRANCHISING (PTY) LTD

COURT OF APPEAL RULES 2009

IN THE COURT OF APPEAL WHITE CONSTRUCTION COMPANY LIMITED. and DCG PROPERTIES LIMITED. 2011: July 25, 26; September 26.

SOUTHERN GLAZER S WINE AND SPIRITS, LLC. EMPLOYMENT ARBITRATION POLICY

R v JAMES BINNING RULING ON COSTS. 1. On 18 October 2012 Dean Henderson-Smith died as a result of falling

NOMZINGSI PRINCESS MNYIPIZA JUDGMENT

The Planning and Development Act

Department of Labor Relations TABLE OF CONTENTS. Connecticut State Labor Relations Act. Article I. Description of Organization and Definitions

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 2017 SESSION LAW HOUSE BILL 584

Small Claims rules are covered in:

The Geographical Indications of Goods (Registration and Protection) Act, 1999

Re ALEXANDRA February, 1, 2, 5 March 1979

BUSINESS NAMES ACT. Act No. 11,1962.

IN THE HIGH COURT OF SOUTH AFRICA (CAPE OF GOOD HOPE PROVINCIAL DIVISION)

BEFORE THE IMMIGRATION ADVISERS COMPLAINTS AND DISCIPLINARY TRIBUNAL. Decision No: [2013] NZIACDT 28. Reference No: IACDT 027/11

IN THE HIGH COURT OF JUSTICE BETWEEN QUANTUM CONSTRUCTION LIMITED AND NEWGATE ENTERPRISES CO. LTD.

Housing (Overcrowding) Bill

J U L Y V O L U M E 6 3

AGREEMENT WITH BUILDER. NAME or COMPANY NAME: ADDRESS:

THE HINDUSTAN TRACTORS LIMITED (ACQUISITION AND TRANSFER OF UNDERTAKINGS) ACT, 1978 ARRANGEMENT OF SECTIONS

PROCEDURE & PRINCIPLES: ORDER 26A: ORDER 14 & ORDER 14A

IN THE SUPREME COURT OF BELIZE, A.D VISION ARCHITECTS & CONTRACTORS LTD MINISTER OF NATURAL RESOURCES & AGRICULTURE

EDWIN M. HUGHES. and LA BAIA LIMITED

CHAPTER 66:01 GUYANA GOLD BOARD ACT ARRANGEMENT OF SECTIONS

No. 49,130-CA COURT OF APPEAL SECOND CIRCUIT STATE OF LOUISIANA * * * * * Versus * * * * *

Transcription:

Re: Systems Sales It is most unusual and judicially improper for a Court to publish its judgment in the public media before it has been delivered and communicated to the litigants and their legal representatives. This is what the Caribbean Court of Justice did in the Caribbean Court of Justice Civil Appeal Case No. BBCV2014/002 Systems Sales Limited v. Arlette O. Browne-Oxley and Sonja Patsena Suttle a procedure that has never occurred in the Supreme Court of Barbados since our independence. The Judgment which on the face of it reads The Judgment of Justices Wit, Hayton and Anderson which was delivered by The Honourable Mr. Justice Hayton on the 25 th day of November 2014 was never read nor delivered to the parties or their Attorneys-at-Law on the 25 th November 2014. The Attorneys-at-Law for the Applicant received an electronic copy of the Judgment on the 26 th November 2014 and the signed hard copy was received by the Applicant from the sub-registry of the Court (the Barbados Supreme Court Registry) on the 4 th December 2014. Strangely enough, a media release number 28-2014 dated the 25 th November 2014 was issued by the Court to the media and published on that same day. It is to be noted that the media release the electronic copy and the signed hard copy all bear the date 25 th November 2014 even though they are not identical documents. What has therefore resulted is that the Court has published three different official judgments on the same case. 1

When the application filed by the Applicant Systems Sales Ltd. came on for hearing on the 14 th October 2014 Mr Vernon O. Smith, Q.C. appeared at the hearing and entered the appearance for himself, Mr Hal Gollop, Q.C. and Mr Steve Gollop as Counsel for the Applicant. When the Court sat on the 25 th November 2014 for the purpose of delivering its decision, Mr Vernon Smith, Q.C. did not attend the hearing on the ground that he was engaged in an urgent matter in the High Court, but Mr Hal Gollop, Q.C. entered an appearance for him and apologized for his absence in the circumstances. In the written judgments of the Caribbean Court of Justice Mr Smith QC s name has been completely omitted from the record of the Court. It must also be noted that the record of the Court omits to show Mr. Hal Gollop s status as Queens Counsel which amounts to an insult to Her Majesty who is the head of state of Barbados. In fact at that hearing the Court did not deliver its judgment but merely stated the Order that it made and that it will give its decision later. At that juncture Mr Hal Gollop submitted to the Court that he insisted to have it recorded in the record of the Court that it is the height of absurdity that his client who had a right of appeal as the Court stated at the hearing of the 14 th October 2014 and because that he had applied for special leave to appeal his client was denied his appeal as of right to which he was entitled by the general law and the rules of the Court. Paragraphs 3 and 4 of the Caribbean Court of Justice s Judgment read as follows: 3. This application was heard on the 14 th October 2014 but was inadequately supported by documentation to establish an arguable case. Normally, this would have led to an immediate refusal of the requested leave. Counsel for the Respondents, however, was content to allow the Applicant (on payment of costs of that day) to file further submissions (with supporting 2

documents) within fourteen days and thereafter to have fourteen days in which to respond. This Court reserved the right then to determine the application on the papers or to schedule a further hearing. Having now before us a copy of the Contract, the relevant Plans, the judgment of Kentish J and her Notes of Evidence in addition to the judgment of the Court of Appeal that had accompanied the Application, we are of the view that no further hearing is necessary and that we can properly determine the application on the papers. 4. We find that the application does not have a realistic chance of success. The first issue concerns the background factual context for determining the plan referred to in the Schedule to the Contract only as a proposed sub-division plan as follows after which is set out the sold Lots 3 to 20 enumerating the square metres for each Lot, but, remarkably and crucially, no plan is identified in the Contract. There is thus uncertainty as to the subject matter of the Contract. It must be borne in mind that the Applicant, as the person seeking to enforce the Contract, bears the burden of resolving this uncertainty. The Applicant s written submissions which the Court on the 14 th October asked to be submitted were filed on the 9 th day of November 2014 are as follows: This is an application for leave to appeal the decision of the Court of Appeal which upheld and confirmed the High Court judgment of Kentish J. It is therefore necessary for us to refer to and consider both judgments if the decision of Kentish J. is wrong it necessarily follows that the decision of the Court of Appeal is wrong unless a totally different line of reasoning and law is taken or different facts are found. The High Court action instituted by the Appellant/Plaintiff Systems Sales Ltd. against the Respondent/defendant was for the specific performance of the sale of the land described in the Schedule to the said agreement dated the 15 th July 1998 and made between the 3

Respondents/Defendants as Vendors of the One Part and the Appellant/Plaintiff as Purchaser of the Other Part. At paragraph 5 of her judgment Kentish J. states that the issues which arose for determination are as follows:- Is the agreement in respect of which specific performances is sought the agreement signed by the defendant Suttle for the sale of the land to System Sales? 1. Is it a fundamental term of the agreement that the Suttle s should retain Lots 1 and 2 as shown on a proposed sub-division Plan dated 28 th February 1993 made and certified by Terrol Inniss, Land Surveyor? 2. If so was there a breach of that term by the Plaintiff which entitled the defendants to treat the agreement as terminated? 3. Was there a unilateral variation of the agreement by the Plaintiff in substituting another Plan for the proposed sub-division plan referred to in the agreement? 4. If so was the variation a material variation? 5. Were the parties ad idem as to the terms of their agreement? and 6. Is the Plaintiff entitled to specific performance of the agreement? The Findings of Fact Issue I There is and has been only one (1) executed agreement in writing for the sale of the land before the Court namely the agreement dated 15 th July 1998 which is duly executed and witnessed by the Suttles and Systems Sales Ltd. This was accepted by the Trial Judge. Issue II The Trial Judge erred in fact in finding/holding that permission was granted to the Suttles by the Chief Town Planner to sub-divide the land into 13 lots as shown on the Suttle plan (the Suttle Plan) certified by the Chief Town Planner only as the application plan it is not an approved plan nor is it a plan for which permission is granted. Paragraph 7 and 8 of the trial judge judgment are not correct in fact. 4

Such a plan cannot be referable to the executed agreement for the following reasons (a) The plan comprises 13 lots where there are 18 lots being purchased under the executed agreement (b) the plan is not a plan approved and stamped as such by the Chief Town Planner. The intrinsic evidence of the contract clearly and unequivocally establishes that the only plan that is referable to the agreement is the sub-division plan which has been approved by the Chief Town Planner, that is to say, the revised sub-division plan (SSL) certified by H.A. King, Land Surveyor which has been duly stamped as approved by the Chief Town Planner on the 26 th March 1998. The descriptions of the (18 lots) Nos. 3-20 being agreed to be sold in the Schedule to the agreement conform with those lots on the SSL Plan. Further and in addition, it is the plan to which clause 12 of the agreement applies in that the grant of a right of way over lot 1 and 2 is required. In the Suttle plan there is no right of way over lot 1 and no such right of way would be required in favour of the other lots in the development Under the Town & Country Planning Act Cap. 240 of the Laws of Barbados no agreement for the sale of any lot in any development can take effect unless the plan of the sub-division has been approved by the Chief Town Planner. The GS 3 Plan certified by H.A. King, Land Surveyor and dated 2 nd February 1999 is totally irrelevant to the agreement on the ground that it was made a year after the agreement was executed. Issue III Lot 1 and 2 were not being sold by the Vendors to the Purchasers. The only references to Lots 1 and 2 in the agreement are (a) in Clause 2 (1) of the agreement which states that in order to give full effect to the agreement the Vendors (the Suttle) agree to remove or shift the dwelling house existing on lots 1 and 2 being retained by them to an extent necessary to avoid encroachment on the roadway (including verge) adjoining the lots and to ensure due compliance with the conditions and stipulations of the Chief Town Planner in respect of the development of the said roadway (including verge) and (b) in Clause 12 of the agreement where it is stated that the said land is subject to a right of way over the lots numbered 1 and 2 on the proposed subdivision plan. 5

Although there is no specific plan mentioned or referred to in the agreement, the details of measurements of the lots set out therein described in the agreement identify the sub-division plan SSL as the plan referrable to the agreement. In the premises, there is no breach whatsoever of the agreement on the part of the Appellants with respect to the retention of lots 1 and 2 by the Suttles. Similarly, there is no variation, material, unilateral or otherwise or substitution of any other plan of the sub-division. Unfortunately, the Court of Appeal at paragraph 15 of its decision adopted the findings of fact of the Trial Judge Kentish J. without any proper examination or analysis of the documents presented in the case. As stated above the GS 3 plan had no relevance to the agreement nor did it at any time replace the SSL plan in the agreement hence there was no variation unilateral or otherwise of the agreement nor was there a change in the size or layout of lots 1 and 2 in the agreement. Accordingly, the Court of Appeal erred in fact and in law in upholding the findings of fact of the Trial Judge. As a general principle for construing and interpreting a contract Lord Denning in the Moorcock Case said a contract must be construed and interpreted in a manner to give it business efficacy. It is submitted that if the Courts below had followed this principle enunciated by Lord Denning they could not have fallen into such grievous error as is evident from the two decisions. In accordance with the above stated principle a number of pertinent observations may now be made in respect of the agreement for sale in the instant matter and which should lead the Honourable Court to conclude that the judge at first instance and the Court of Appeal misled themselves in the interpretation of the Agreement for Sale. Clause 2(1) of the agreement imposed an obligation on the vendor to remove or shift the dwellinghouse existing on the lots 1 & 2 being retained by them to avoid encroachment on the roadway (including verge) adjoining the lots and to ensure due compliance with the conditions and stipulations of the Chief Town Planner in respect of the development of the said roadway (including verge. ) This was in order to give full effect to this Agreement. 6

That is the only reference made to the two lots. It was therefore a gross misinterpretation of the Agreement when both Courts found, in spite of the schedule specifically detailing the Agreement was in respect of 18 lots, i.e. lot 3 to lot 20 that there was a fundamental breach of the Agreement because of some adjustment made to lot 1 and 2. Of particular significance is the provision made by Sec. 2(2) for the Purchaser to retain the sum of Fifty thousand dollars if the Vendor failed to comply with such a removal or shifting of the said dwelling house on lot 1 and 2. This never entered into the contemplation of either Court. By clause 4, the Agreement specifies that the property is believed and shall be taken to be correctly described as to quantity and no error omission mis-description or mis-statement contained in this Agreement shall annul the said sale.. In this regard therefore the Courts fell into error to hold that any reduction in the size of any lots was sufficient to void the contract of sale. In accordance with Clause 9 of the Agreement, the Purchaser was responsible for the development of the property including all necessary plans and the relevant permission from the Chief Town Planner. As a result therefore, the only plan which could legally be construed as the plan upon which this Agreement was based is the SSL Plan; this was the only approved plan. A contract could not therefore be legally construed on the basis of an illegal plan. The GS3 Plan which the Courts held was the correct plan was neither dated nor approved and could not legally satisfy the requirements of this clause. The Agreement for Sale specifically states how any notice given under the contract must be communicated; it must be in writing. The Vendor never gave any notice of any kind to the Purchaser; he chased them from the site. It is noteworthy that the Appellant/Purchaser began the works in May 1998; the Agreement was finally executed in July 1998; he was chased off in December 1998. Mention too must be made of the Courts failure to examine the import of Clause 10 in relation to forfeiture of the deposit or withholding of the deposit. 7

In the present situation the Vendor has retained the deposit, the land and the improvements to the land, while the Purchaser has gone away with nothing. The Courts failure to carefully examine the provisions of the Agreement discussed above caused them to commit a number of errors of Law. This Honourable Court should therefore find little difficulty in holding that the application being made before the Court is plausible and that the Appellant stands a great chance of success in its Application for a grant of specific performance of the Agreement of 15 July 1998. At paragraph 4 of the Judgment it is stated that the first issue concerns the background factual context for determining the plan referred to in the Schedule to the contract only as a proposed Sub-division Plan after which is set out the sold lots 3 to 20 enumerating the square areas for each lot but remarkably and crucially no plan is identified in the Contract. Such a statement is incorrect and makes no sense: (i) The Schedule to the contract is an integral part of the contract (ii) There is only one proposed sub-division plan comprising 20 lots and the square metres of each lot conforms with the plan. It is therefore absurd to state that there is uncertainty as to the subject matter of the contract; moreover this plan is the plan formally approved by the Chief Town Planner and is accordingly the only plan to which the agreement can refer or be applied. This has been clearly stated in the written submissions of the Applicant. Paragraph 6 of the judgment is not correct. The evidence clearly establishes that the SSL Plan was the result of the negotiations and it was agreed that the Vendors Lot 1 and 2 would have 8

access and exit on the eastern border. The definition of fronting used in the evidence of the Land Surveyor, H.A. King is stated as having access. Paragraph 3 of the judgment makes no mention of the applicant s submissions being received. It is clearly evident from the paragraph 3 of the judgment that the applicant s submissions were not included in the papers considered by the Court. In fact, the judgment clearly indicates that the applicant s submissions were not read, considered or referred to since no mention is made to them in the judgment. In paragraph 7 of the judgment the Honourable Justices are wrong in stating that the purchaser insisted upon specific performance of the SSL 2A plan dated 2 nd February 1999 This plan is not and could not be the plan of the agreement for the simple reason that it is drawn 7 months after the agreement. This is one of the cardinal errors in the findings of the Trial Judge. The road and verge on the SSL ( the obvious agreement Plan) Plan encroaches on the land of the neighbouring owner. The SSL 2A Plan indicates that the road and verge would be erected wholly on the land being bought by the purchaser and the lots 1 and 2 owned by the Vendors because the owner of the neighbouring land to the east of the development would not allow any part of the carriageway of the development to be built on his land. The permission of the Chief Town Planning Office stipulated that the carriageway 3.9 metres would be built on the land being developed, that is the land comprising the 20 lots. As indicated in the SSL 2A Plan after the road construction began a proper inspection of the 2 plans will show that the areas of the lots are almost exactly the same (a matter of 2.7 square metres) the difference being that 9

the area of the carriageway contained in the lots 1, 2, 3 and 4 are different because the carriageway is shown on the land being developed. The finding of the High Court, Court of Appeal and the Caribbean Court of Justice that the construction of the carriageway over the lots 1 and 2 owned by the Vendors deprived them of their ownership shows a lack of understanding of conveyancing and the general law of conveyancing. The reason why it was in the Contract that the Vendors would give the purchaser a right of way in favour of the lots 3 to 20 including is because that part of the carriageway was his property. If on the other hand that part of the carriageway was being acquired by the purchaser, the purchaser would not require a way over it because it would be his property. In fact they would have to give the Vendors a right of way over the carriageway for them to go and pass over it to exit and access their 2 lots or alternatively the Vendors would have to reserve a right of way over that part of the land in the road. Paragraph 8 of the Caribbean Court of Justice s judgment is wrong. The negotiations resulted in the executed agreement and there is no evidence or suggestion that such is not the case. In fact, in the evidence of the Land Surveyor, Mr. Horace King with respect to the permission granted the Chief Town Planner objected to the access to Lots 1 and 2 being on the South of the development. Such a finding of fact on the part of the Caribbean Court of Justice literally ignores paragraph 28 and in particular paragraph 35 of the Trial Judge s analysis of the evidence of the Vendors when she states For the reasons set out earlier I reject the evidence of Mr. and Mrs. Suttle as wholly unreliable and entirely self serving on this issue. Paragraphs 38, 39, 40, 41, 42 and 43 of the Trial Judge also reject the suggestion of the Judges of the Caribbean Court 10

of Justice. The final sentence of the Honourable Justices in paragraph 8 in their judgment is highly prejudicial and improper in light of the fact that the Vendors had independent legal advice and representation throughout the whole transaction. Paragraph 9 of the Judgment of the Caribbean Court of Justice clearly shows that the Judges were unable to read the plans for the simple reason that there is no difference in the areas of the land being purchased by the purchaser and in the area which is not being sold but retained by the Vendors. The area being sold is the subject matter of the agreement not the land being retained by the Vendors. Paragraph 11 of the Caribbean Court of Justice s judgment repeats the erroneous finding of the Trial Judge that the GS 3 Plan which came into being 7 months after the agreement is the plan on which the agreement was executed. Paragraph 12 of the judgment continues the fallacy of the Justices. Paragraph 14 of the judgment boggles the mind. At paragraph 86 of her judgment the Trial Judge states as follows: In this case the agreement was a valid and binding agreement; prima facie it was therefore amenable to the order for specific performance as in the particular circumstances not only was it known by the Suttles that the land was being purchased for development but Systems Sales Ltd. also expended monies on perforating works in relation to the infra structure to obtain the Certificate of Compliance with the knowledge and consent (as I do find) of the Suttles etc. 11

Paragraph 14 of the Justices states that the Vendors accepted the conduct of the purchaser as a breach of contract annulling or repudiating of the Contract thus there is no contract to be enforced. The Court has not stated the conduct of the purchaser that constituted the breach of contract and nowhere in the pleadings (affidavits) of the Vendors has breach of contract been pleaded. Besides, the Courts all ignored Section 54 (2) of the Property Act Cap. 236 of the Laws of Barbados which provides that where the Court refuses to grant specific performance of a Contract the Court may, if it thinks fit, order the repayment of any deposit. The Caribbean Court of Justice s findings in fact and in law are different from those of the High Court and Court of Appeal. It can only be concluded therefore that the Caribbean Court of Justice held an appeal without giving the Applicant an opportunity to be heard or without reference to the written submissions filed on behalf of the applicant. 12