UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Governors of the States of Arizona, California, Colorado, Montana, Nevada, New Mexico, Oregon, Utah, Washington and Wyoming, Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

IS0 CALIFORNIA. February 2,2004

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

California lndependent System Operator Corporation Docket No. ER Compliance Filing

November 10,2004. The Honorable Magalie R. Salas Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

February 12, Notice of Certificate of Concurrence Regarding Agua Caliente Solar LGIA

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Pacific Gas end Eiecb'ic Company Docket Nos. ER , ER , ER , ER , ER , ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. J.P. Morgan Ventures Energy ) Docket No. EL Corporation )

The Atlantic Building 950 F Street, N. W. Washington, DC Fax: Direct Dial:

October 10, FERC Electric Tariff No. 7, Transmission Control Agreement

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

July 28, Please do not hesitate to call if you have any questions in regard to the enclosed. Very truly yours, /s/ James William Litsey

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION MOTION FOR ISSUANCE OF A PROTECTIVE ORDER

December 18, Filing of PSP Agreement with Placer County Water Agency

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

April 16, Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Pacific Gas and Electric Company ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Vineyard Wind LLC ) Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Lathrop Irrigation District ) Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) )

November 29, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) Southern California Edison Company ) Docket No.

June 2, The documents submitted with this filing consist of this letter of transmittal, and all attachments thereto.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

April 10, Via etariff. Hon. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

F I L E D :45 PM

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) )

UNITED STATES OF AMERICA 94 FERC 61,141 FEDERAL ENERGY REGULATORY COMMISSION

PARTICIPATING GENERATOR AGREEMENT (PGA)

January 4, Filing of Service Agreement No Docket No. ER

main. July 6, 2017

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

166 FERC 61,098 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC February 8, In Reply Refer To:

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) ) ) ) ) ) ) ) )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Berry Petroleum Company ) Docket No. ER _

September 29, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

124 FERC 61,004 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA105 FERC 61,307 FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C. and Progress Energy Carolinas, Inc. Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Southwest Power Pool, Inc. ) Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Southern California Edison Company ) Docket No.

Public Service Commission

PSEG Energy Resources & Trade LLC

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) )

130 FERC 61,051 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER APPROVING RELIABILITY STANDARD. (Issued January 21, 2010)

February 20, Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C Magalie R. Salas, Secretary

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

October 1, PJM Interconnection, L.L.C., Docket No. ER Default Allocation Assessment Clarifying Revisions

Reliability Must-run Settlement Agreement Among California ISO, Northern California Power Agency and Pacific Gas and Electric Company

Via Electronic Filing

Arizona Public Service Company, Docket No. ER , Agency Agreement

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) )

BEIJING BOSTON BRUSSELS CENTURY CITY CHICAGO DALLAS GENEVA FOUNDED May 1, 2017

August 31, Generator Scheduling Agreement CAISO Service Agreement No Docket No. ER

June 10, Filing of non-conforming Service Agreement No Docket No. ER

March 27, Tariff Amendment to Modify Administrative Oversight of the Department of Market Monitoring

March 15, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

March 22, The documents submitted with this filing consist of this letter of transmittal, and all attachments thereto.

A. Zonal Agreements and Termination of the GFA

AMENDED AND RESTATED TRANSMISSION CONTROL AGREEMENT. Among The California Independent System Operator Corporation and Transmission Owners

April 20, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

October 21, 2005 RE: APPLICATION /INVESTIGATION

THE UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

March 1, 2018 Advice Letter 5250-G

March 25, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) ) ) ) ) )

John R Liskey Attorney At Law 921 N. Washington Ave Lansing, MI (voice) (fax)

NorthWestern Energy requests an effective date of March 12, 2016, for the proposed revisions.

131 FERC 61,217 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, D.C June 4, 2010

November 21, Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C Attention: Ms. Kimberly D.

Mailing Address: P.O. Box 1642 Houston, TX

152 FERC 61,253 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

June 30, Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C Attention: Magalie R.

129 FERC 61,075 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

October 4, 2005 RE: APPLICATION /INVESTIGATION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) )

BILLING CODE P. Notice of Commission Staff Attendance at MISO Meetings

Re: Errata Filing for Joint Submittal of Motion for Leave to Respond and Response to Indicated LSEs Comments, Docket No. ER09-40S-000.

UNITED STATES OF AMERICA 82 ferc 61, 223 FEDERAL ENERGY REGULATORY COMMISSION

April 3, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms.

July 10, Operating Agreement, CAISO Rate Schedule No. 94 Docket No. ER

Transcription:

California Independent System Operator November 12, 2004 VIA ELECTRONIC FILING The Honorable Magalie R. Salas Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: CalPeak Power-El Cajon, LLC Docket No. ER05-83-000 Dear Secretary Salas: Transmitted herewith for electronic filing in the above-referenced proceeding is the Motion to Intervene of the. Thank you for your attention to this matter. Yours truly, /s/ Regulatory Counsel Counsel for the California Independent System Enclosure cc: Service List

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION CalPeak Power-El Cajon, LLC ) Docket No. ER05-83-000 MOTION TO INTERVENE OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION Pursuant to Rule 214 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission ( Commission ), 18 C.F.R. 385.214, and the Commission s November 1, 2004 Notice of Filing, the California Independent System ( ISO ) submits this Motion to Intervene in the above captioned proceeding. In support thereof, the ISO states as follows: I. DESCRIPTION OF THE PROCEEDING On October 27, 2004, CalPeak Power-El Cajon, LLC ( El Cajon ) submitted, pursuant to Section 205 of the Federal Power Act ( FPA ), its annual update filing proposing revised rate schedule sheets to its Reliability Must Run Agreement ( RMR Agreement ) with the ISO. II. DESCRIPTION OF THE ISO AND COMMUNICATIONS The ISO is a non-profit public benefit corporation organized under the laws of the State of California with a principal place of business at 151 Blue Ravine Road, Folsom, CA 95630. The ISO is the Control Area Operator responsible for the reliable operation of the electric grid comprising the transmission systems of

a number of utilities including San Diego Gas & Electric Company ( SDG&E ), as well as the coordination of the ancillary services and real-time electricity markets in California. The ISO requests that all communications and notices concerning this motion and these proceedings be provided to: Regulatory Counsel 151 Blue Ravine Road 151 Blue Ravine Road Folsom, CA 95630 Folsom, CA 95630 916-608-7144 (tel) 916-608-5804 (tel) Robert C. Kott Manager of Reliability Contracts 916-608-7222 (fax) 916-351-2487 (fax) sjubien@caiso.com rkott@casio.com III. ISO S INTEREST El Cajon s RMR Unit is located within SDG&E s transmission system and is needed to maintain the reliability of the ISO-Controlled grid. As the Control Area Operator and as the counter party to the RMR Agreement, the ISO has a unique interest in any Commission proceeding that affects an RMR Agreement. Accordingly, the ISO has a direct and substantial interest in this proceeding and requests that it be permitted to intervene. Because no other party can adequately represent the ISO s interests in this proceeding, the ISO s intervention is in the public interest and should be granted. 2

IV. CONCLUSION For the foregoing reasons, the ISO respectfully requests that the Commission grant this Motion to Intervene and make the ISO a party in the above-caption proceeding with full rights of participation. Dated: November 12, 2004 Respectfully submitted 151 Blue Ravine Road Folsom, CA 95630 3

CERTIFICATE OF SERVICE I hereby certify that I have this 12 th day of November, 2004 caused to be served a copy of the forgoing Motion to Intervene and Protest upon all parties listed on the official service list compiled by the Secretary of the Federal Energy Regulatory Commission in this proceeding. /s/ 151 Blue Ravine Road Folsom, CA 95630 (916) 608-7144 (tel) (916) 608-7222 (fax)