ADJUDICATION AS AN ALTERNATIVE DISPUTE RESOLUTION MECHANISM: AN ANALYSIS OF THE ADJUDICATION STATISTICS IN SINGAPORE

Similar documents
Issues raised from Adjudication Determinations. The Security of Payment (SOP) Act came into effect on 1 April 2005.

CONSTRUCTION BRIEFING November 2016

SINGAPORE MEDIATION CENTRE ADJUDICATION UNDER THE BUILDING AND CONSTRUCTION INDUSTRY SECURITY OF PAYMENT ACT (CAP 30B) (REV ED 2006)

Reinforcing Security of Payment in NSW

IMPORTANT NOTICE. Information that must be set out in notice of adjudication served on residential occupier.

Australia s Last Best Hope for National Security of Payment Legislation?

Adjudication Application (South Australia) Made under the Building and Construction Industry Security of Payment Act 2009 (SA)

Disciplinary & Dispute Resolution Procedures

New Zealand Institute of Chartered Accountants RULES OF THE NEW ZEALAND INSTITUTE OF CHARTERED ACCOUNTANTS EFFECTIVE 26 JUNE 2017 CONTENTS

DISCLAIMER IN EXPERT REPORT DOES NOT VOID ADJUDICATION DETERMINATION - Charles Brannen

CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY -

Construction Industry Security of Payment Legislation. Development Bureau

TERMS OF REFERENCE. Issued Date: 3 January 2011

Provider Contract for the Provision of Legal Aid Services and Specified Legal Services

Claims for benefits.

The NEW Pre-Action Protocol for Construction and Engineering Disputes. Simon Tolson

NOTICE OF ARBITRATION

STANDARD TERMS AND CONDITIONS

THE NEW PRE-ACTION PROTOCOL FOR CONSTRUCTION AND ENGINEERING DISPUTES

FAIR SUBCONTRACT TRANSACTIONS ACT

RESPONSE TO REVIEW OF THE CONSTRUCTION CONTRACTS (SECURITY OF PAYMENTS) ACT (NT): ISSUES PAPER OCTOBER 2017

SUPREME COURT OF QUEENSLAND

R U L E S of the Court of Arbitration at the Centre for Mediation and Arbitration of Transport Sp. z o.o. (ltd) in Warsaw

RECENT CHANGES TO THE HOME BUILDING ACT

Table of Contents. Injury Manual Insurer s Decisions and Appeals. Division Summary Information

Home Building Amendment Act 2014 No 24

THE CONSTITUTION. The objectives of the Association include:

GETTING THE ARBITRATION YOU WANT

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

THE LONDON MARITIME ARBITRATORS ASSOCIATION THE INTERMEDIATE CLAIMS PROCEDURE (2012)

HOW SECURED IS THE SOP ACT IN ASSISTING CONTRACTORS TO GET PAYMENT?

IN THE HIGH COURT OF JUSTICE IN NORTHERN IRELAND PRE-ACTION PROTOCOL FOR COMMERCIAL ACTIONS

London Borough of Hillingdon. - and - Uxbridge BID Ltd BID OPERATING AGREEMENT

JAMS International Arbitration Rules & Procedures

GUIDE TO ARBITRATION

CONSTRUCTION ADJUDICATION. The Basis for Setting Aside Adjudication Determinations

Pre-Action Protocol for Professional Negligence

Resolution Institute. Public consultation: Proposed reforms to the NSW Building and Construction Industry Security of Payment Act 1999

1. This Section E of Part V prescribes the manner in which the BSB may seek to take interim action to:

RULES FOR EXPEDITED ARBITRATION. of the Finland Chamber of Commerce

REQUEST FOR ARBITRATION

ANNEX V PROCEDURAL RULES ON CONCILIATION AND ARBITRATION OF CONTRACTS FINANCED BY THE EUROPEAN DEVELOPMENT FUND (EDF)

CONSTITUTION. A.C.T. BASKETBALL INCORPORATED ( Association ) Approved at A.C.T. Basketball Inc. Annual General Meeting on 9 February 2016

Construction Industry Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex Construction Disputes)

It is hereby notified that the President has assented to the following Act which is hereby published for general information:-

Deed. Lookout Road Hard Rock Quarry. Planning Agreement

IC Chapter 7. Bonding, Escrow, and Retainages

BASKETBALL ARBITRAL TRIBUNAL (BAT) Arbitration Rules. 1 January 2017 Version

Republic of Uganda. Bidding Document for Framework Contracts for Supplies

THE COURTS ACT. Rules made by the Chief Justice, after consultation with the Rules Committee and the Judges, under section 198 of the Courts Act

Document A101 TM. Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

APPENDIX 21 RESIDUAL SECURITIES TRUST DEED

ADJUDICATION: RAISING OBJECTIONS TO THE ADJUDICATOR S JURISDICTION OR BREACH OF SOP ACT AT THE EARLIEST POSSIBLE OPPORTUNITY

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV JUDGMENT OF COOPER J

Protocol Relating to Legal Representation at Public Expense

REGULATIONS FOR GENERAL PRACTICE DIVISION THE HONG KONG INSTITUTE OF SURVEYORS

INVALID CARE ALLOWANCE (JERSEY) ORDER 2008

Model letters for use by the Contractor

DECREE ON EMPLOYMENT AND ADMINISTRATION OF FOREIGNERS WORKING IN VIETNAM

OVERVIEW OF CROATIAN BANKRUPTCY SYSTEM

South Australian Employment Tribunal Bill 2014

Multiparty and multicontract disputes and the impact of the new International Chamber of Commerce (ICC) Rules

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS

LABOUR RELATIONS ACT NO. 66 OF 1995

REPUBLIC OF KENYA KENYA GAZETTE SUPPLEMENT NATIONAL ASSEMBLY BILLS, NAIROBI, 29th December, 2017 CONTENT

Owner and Contractor OCSS101. Agreement Between: Contract Type: where the basis for Payment is a Stipulated Sum. Document No.

The SIAC Arbitration Rules 2016: A detailed look at the new rules 1 August 2016

Decision of the Dispute Resolution Chamber

ALMAC Exploration Contract Conditions

THE SMALL CLAIMS COURT BILL, 2007

Tender Enquiry No: BCL/PUR/ CO2 Gas/SS/CW/VW/18-19/Rehab Dated:

Type of resolution (tick the box as applicable) Ordinary resolution. Text of members statement See attached explanatory memorandum.

SHOP AND OFFICE EMPLOYEES [REGULATION OF EMPLOYMENT AND REMUNERATION] ACT PART I

ICDR INTERNATIONAL CENTRE FOR DISPUTE RESOLUTION ARBITRATION RULES

ACT of 27 June on political parties 1. Chapter 1. General provisions

Constitution of Australian Physiotherapy Association

INSTRUCTIONS TO TENDERERS

THE ARBITRATION IN THE HUNGARIAN LAW

PRACTICE NOTE 4/2015

RENTAL HOUSING AMENDMENT BILL

RULES OF ARBITRATION

ATTACHMENT VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR LOCAL HIRING PROGRAM FOR DESIGN-BUILD PROJECTS

FINANCIAL SERVICES TRIBUNAL

2002 Report to the Legislature: Proposed Mechanics Lien Reforms. Submitted by: The New York State Law Revision Commission

LEGAL COSTS REGIME - ISSUES FOR BARRISTERS

The legal justification for the enforcement of a binding DAB decision under the FIDIC 1999 Red Book

WIPO WORLD INTELLECTUAL PROPERTY ORGANISATION ARBITRATION RULES

ALTERNATIVE DISPUTE RESOLUTION (ADR) PROCEDURES

COSTS SPECIAL CASES COSTS PAYABLE BY OR TO PARTICULAR PERSONS

New Zealand Institute of Quantity Surveyors (Inc.) Constitution and Rules - As at 23 June 2017

ORISSA ELECTRICITY REGULATORY COMMISSION (GRIEVANCES REDRESSAL FORUM AND OMBUDSMAN) REGULATIONS, 2004

REPUBLIC OF SOUTH AFRICA

GENERAL PRE-ACTION PROTOCOL

Standard Terms and Conditions of Lufthansa Technik Logistik GmbH and of Lufthansa Technik Logistik Services GmbH (Version 11/11)

RULES FOR EXPEDITED ARBITRATIONS

TENDER NO. BCL/RD/ 4000 MS Scrap Cutting/2019 March 19, 2019

The member States of the Council of Europe and the other States signatory hereto,

Building and Construction Industry Security of Payment Act 1999 No 46

Labor Chapter ALABAMA DEPARTMENT OF LABOR ADMINISTRATIVE CODE CHAPTER INVESTIGATION AND COLLECTION TABLE OF CONTENTS

ODA REPORTING OF IN-DONOR COUNTRY REFUGEE COSTS. Members methodologies for calculating costs

Transcription:

ADJUDICATION AS AN ALTERNATIVE DISPUTE RESOLUTION MECHANISM: AN ANALYSIS OF THE ADJUDICATION STATISTICS IN SINGAPORE Goh Ngan Hong Senior Consultant (QS & Contracts Management), CPG Consultants Pte. Ltd., Singapore, goh.ngan.hong@cpgcorp.com.sg Key Words: Adjudication, dispute resolution, Security of Payment Act. The Building and Construction Industry Security of Payment Act ( SOP Act ) has been in force in Singapore for more than ten years now. This paper attempts to consider how the SOP Act has benefitted the industry so far and whether we can draw any lessons from the Singapore experience. Looking at the statistics, the influence of the SOP Act has been remarkable. Between April 2005 and December 2013, the number of adjudication applications filed at Singapore Mediation Centre (SMC) is 999 cases. The number of review adjudication adjudications filed is quite small, with a total of 30 filed as at December 2013. These statistics convey significant information. First, out of a total of 999 adjudication applications that have been filed as at December 2013, 240 were eventually withdrawn, representing 24% of all adjudication applications filed. Furthermore, out of 531 valid cases that were determined under the SOP Act, about 94% of these cases were resolved without further review of adjudication determination. In monetary terms, the value of claims adjudicated under the SOP Act as at December 2013 is about $910 million. But the statistics may not capture the full impact and influence of the SOP act. By providing a low cost and efficient adjudication mechanism, the SOP Act has effectively eliminated an avenue for delaying payments without justification. The regime has achieved considerable success in achieving its target of facilitating cash flow within the construction industry. 1. INTRODUCTION The construction industry is an important sector in developing countries including Singapore. Since 2006, the construction industry in Singapore has grown significantly. This is reflected in the amounts of progress payments certified. The total amount of certified progress payments has increased from S$12 billion in 2005 to about $$36 billion in 2014. Before 2005, the construction industry in Singapore faced more difficult times given the shrinking size of the pie and increasing competition. The Building and Construction Industry

Security Payment Act (herein after referred to as the SOP Act ) was enacted in 2004 and came into force on 1 April 2005. The aim of the SOP Act was to facilitate cash flow by establishing a fast and low cost adjudication system to resolve payment disputes. However, it was observed (Chow, 2013) that the SOP Act s overriding legislative objective was to reform payment behavior in the construction industry, such as the intractable problems caused by delay in certifications and payments and, more insidiously, unwarranted deductions and set-offs against payments due to contractors and subcontractors. Chow (2005) found that such opportunistic behavior, which was prevalent amongst certain players in the industry, introduced unnecessary layers of risk in taking on construction work, exacerbating a host of productivity and cost escalation issues that are not unique to Singapore. The main focus of the SOP Act is on the procedure for adjudicating payment claim disputes. The main features of the adjudication procedure are as follows: a) The claimant serves a Payment Claim which must be in writing and contain specific information relating to the claim. b) The respondent has 7 to 21 days to serve his Payment Response. c) There is a 7 day dispute settlement period, during which parties explore a settlement or clarify any matter relating to the Payment Claim. The respondent is also entitled to provide or vary a payment response. d) If there is no settlement, the claimant has 7 days to lodge an Adjudication Application with an authorised nominating body in respect of any disputed amount. e) Upon receipt, the authorised nominating body serves a copy of the adjudication application on the respondent, and within 7 days, appoints an adjudicator. f) The respondent has 7 days after receiving a copy of the adjudication application to serve an Adjudication Response. g) The adjudication commences immediately after the time allowed to serve an Adjudication Response expires. The adjudicator has 14 days after commencement of an adjudication to make his determination, unless the parties agree to extend time. h) A respondent dissatisfied with an adjudication determination has 7 days to apply for a review if the adjudication amount exceeds the response amount by more than $100,000. The SOP Act has been in force in Singapore for a decade now. This paper attempt to consider how the SOP Act has benefitted the industry thus far and whether we can draw any lessons from the Singapore experience.

2. METHODOLOGY This study is based mainly on the statistics on Adjudication Applications and Adjudication Review Applications from April 2005 to December 2013 collated and published by Building and Construction Authority (BCA) of Singapore in its website. Additional statistics from the findings of Lee (2011) and Chow (2011) are used to supplement the BCA statistics in the study. 3. FINDINGS Based on the statistics, the following are the key findings and analyses: 3.1 Case Load Between 2006 and 2009, the number of adjudication applications filed at the SMC doubled each year. It appears to have stabilised at around 170 from 2009 (see Table 3.1). Chow (2011) found that it is possible that the number of cases each year have now reached a steady volume state. In fact, it was dropped to about 135 cases in 2011 and 2012. In 2013, the case load again doubled to 228. The statistics in 2014 has not been published. It is estimated to be about 400. The number of review adjudications filed is quite small, with a total of 30 filed up to December 2013 (see Table 1). It is observed (Lee S.K., 2011) that the number of applications filed in the High Court to review the adjudication determination is also small; only 26 have been filed as at January 2012. Table 1: Case Load from 2005 to 2013 Year Number of Cases No. of Review Cases 2005 1 0 2006 21 0 2007 50 1 2008 92 1 2009 169 3 2010 165 5 2011 135 5 2012 138 5 2013 228 10 Total 999 30 3.2 Status Breakdown

Table 2: No of Applications with status breakdown Status Number % (a) Applications (valid) determined 531 53 - in favour of the claimant*: 519 (98%) - in favour of the respondent: 12 (2%) * include partial payment to claimant (b) Applications determined as invalid 202 20 (c) Applications pending determination 26 3 (d) Applications withdrawn 240 24 Total 999 100 These statistics convey significant information. First, out of a total of 999 adjudication applications that have been filed as at December 2013 (see Table 2), 240 were eventually withdrawn, representing 24% of all adjudication applications filed. Furthermore, out of 531 cases that were determined under the SOP Act, at least 94% of these cases were resolved without further review of adjudication determination. 3.3 Value of claims adjudicated against total progress payments certified It is observed (Lee S.K., 2011) that in monetary terms, the value of claims adjudicated under the SOP Act, measured against the total progress payments certified over the period from April 2005 to August 2011, stands at under 1% (see Table 3). Table 3: Value of claims adjudicated against total progress payments certified Year No. of Claims filed No. Review Adjns of Total Value of Claims ($m) Average value claims ($m) of Total Progress Claims Certified ($m) Claim as a % of total progress claims certified 2005 1 0 0.42 0.42 12.221 0.0034% 2006 21 0 4.12 0.20 12.938 0.03% 2007 50 1 42.60 0.85 17.872 0.24% 2008 91 1 66.30 0.73 26.217 0.25% 2009 169 3 372.78 2.21 30.894 1.21% 2010 164 5 211.20 1.29 26.979 0.78% 2011 105 1 201.20 1.92 N.A. Until Aug Total 601 11 899.14 1.50

Based on statistics published by BCA, from April 2005 to December 2013, the total value of claims for adjudication is $910 million. For the same period, the total progress claims certified is $221.932 billion. The value of claims adjudicated is about 0.4% of the total progress payments certified. 3.4 Number of Applications with and without Payment Response Out of the 999 adjudication applications, about 71% are without payment response (see Table 4). Table 4: No of Applications with and without payment response Number of Applications 999 100% - without payment response : 710 71% - with payment response : 289 29% 3.5 Categories of Dispute Situations It is observed (Lee E., 2011) that 65% of the cases remain situation where no payment response was furnished and 23% relate to disputed payment response (see Table 5). Table 5: Categories of Dispute Situations Categories of Dispute Situations Percentage Failure to issue payment response 65 Disputed payment response 23 Dispute over accepted response 9 Payments for Supply Contracts 3 Total 100 3.6 Categories of Claimants vs. Respondents It is noted that 64% of the cases are subcontractors claiming against the main contractors (see Table 6). About 16% of the cases are main contractors claiming against developers/owners. About 14% of the cases are sub-subcontractors claiming against subcontractors. Only 5% are consultants/designers claiming against contractors/developers/owners. Table 6: No of Applications in terms of categories of claimants vs. respondents Categories of Claimants vs. Respondents (for Number Percentage valid applications) (a) Main contractor claiming 85 16% developer/owner (b) Subcontractor claiming main contractor 342 64% (c) Sub-subcontractor claiming Subcontractor 75 14% (d) Consultant/designer claiming contractor/developer/owner 24 5%

(e) Others (e.g. suppliers claiming 5 1% contractor/developer/owner) Total 531 100.00% 3.7 Number of cases proceeding to merits It is found (Chow, 2011) that only 15% of the cases proceeded to consideration of merits. 55% of the cases involved a non-compliant payment response. 30% of the cases were met with jurisdiction objections (see Table 7). Jurisdiction objections involve one of the following issues: a) Appointment: The adjudicator has to be appointed through the authorised nominating body which is itself regulated by the Act. b) Contract in writing: Existence of contract in accordance with principles of contract formation and definition of contract made in writing in the SOP Act. c) Nature of Contract: The meaning of a construction contract or a supply contract as defined under the SOP Act. d) Territorial Reach: The contract relates to work carried out in Singapore or goods or services supplied in relation to work carried out in Singapore. e) Procedural Compliance: Whether the payment claim was served prematurely, compliance with DSP and Table 7: Number of cases proceeding to merits Percentage Non-compliant Payment Responses 55% Jurisdictional Objections 30% Matters proceeding to Merits 15% 3.8 Disputed and Adjudicated Amounts 3.8.1 Disputed Amounts The disputed amounts for valid applications range from S$4,900.00 to S$116 million (see Table 8). Table 8: Disputed Amounts (for valid applications) Amount S$ Total disputed amount $909,999,862.23 Maximum disputed amount for a case $116,251,933.51

Minimum disputed amount for a case $4,900.00 3.8.2 Adjudicated Amounts The adjudicated amounts for valid applications range from S$0 to S$30.0 million (see Table 9). Table 9: Adjudicated Amounts (for valid applications) Amount S$ Total adjudicated amount $391,810,475.27 Maximum adjudicated amount for a case $30,071,968.64 Minimum adjudicated amount for a case $0.00 3.8.3 Adjudicated Amounts as a % of Claimed Amounts In about 57% of the valid applications, the adjudicated amounts are between 90% and 100% of the claimed amounts (see Table 10).. Table 10: Adjudicated amount as a % of claimed amount Adjudicated amount as a % of claimed amount Number Percentage (%) 90% to 100% 302 57 80% to 89% 39 7 70% to 79% 28 5 60% to 69% 21 4 50% to 59% 22 4 40% to 49% 26 5 30% to 39% 25 5 20% to 29% 22 4 0% to 19% 46 9 531 100 3.9 Review Adjudications A respondent who is aggrieved by an adjudication determination may lodge an adjudication review application with the authorised nominating body. There is no equivalent of the adjudication review procedure in the United Kingdom, Australia or New Zealand. It is therefore unique to the Singapore regime. Under the Act, an adjudication review is essentially an adjudication of the extent to which the adjudicated amount exceeds the relevant response amount. It allows the substantive merits of the original determination to be reconsidered. At the conclusion of the review, if the review adjudicator agrees with the conclusion of the first instance adjudicator, they are expected to refuse the adjudication review application. If the review tribunal arrives at a different result, the Act provides for the tribunal to substitute the original determination with their determination.

3.9.1 Status of Review Adjudications The total number of review adjudication up to December 2013 is only 30 (see Table 11). Out of this, 9 (30%) were determined as invalid. Out of the 17 valid review applications, 7 (41%) were determined in favour of the claimant and 10 (59%) were determined in favour of the respondent. Table 11: Status of Review Adjudication Number of Review Applications 30 100% Status (a) Review Applications (valid) determined 17 57% - in favour of the claimant * : 7 (41%) - in favour of the respondent : 10 (59%) * include partial payment to claimant (b) Review Applications determined as 9 30% invalid (c) Review Applications pending 0 0% determination (d) Review Applications withdrawn 4 13% 3.9.2 No of Review Applications in terms of categories of claimants vs. respondents Out of the 26 review applications which were not withdrawn, 16 (62%) were subcontractor claiming against main contractor, 2 (8%) were sub-subcontractor claiming against subcontractor and 2 (8%) were consultant/designer claiming against contractor/developer/owner (see Table 12), Table 12: No of Applications in terms of categories of claimants vs. respondents Categories of Claimants vs. Respondents (for review Number % applications not withdrawn) (a) Main contractor claiming developer/owner 6 23 (b) Subcontractor claiming main contractor 16 62 (c) Sub-subcontractor claiming Subcontractor 2 8 (d) Consultant/designer claiming 2 8 contractor/developer/owner Total 26 100 3.9.3 Adjudicated review amount as a % of Adjudicated amount Out of the 26 adjudication review which were not withdrawn, 18 (69%) were with adjudicated review amount being 90% to 100% of the adjudicated amount and 7 (27%) were with adjudicated amount being 0%.to 19% of the adjudicated amount (see Table 13).

Table 13: No of Applications in terms of categories of claimants vs. respondents Adjudicated review amount as a % of Adjudicated amount (for Review Applications not withdrawn) Number Percentage (%) 90% to 100% 18 69 80% to 89% 0 0 70% to 79% 0 0 60% to 69% 0 0 50% to 59% 1 4 40% to 49% 0 0 30% to 39% 0 0 20% to 29% 0 0 0% to 19% 7 27 Total 26 100 3.10 Adjudicator s Fees, Time Spent and Composition by Professions 3.10.1 Range of Adjudication fees The adjudication fees (excluding GST) for all applications range from $1,000/- to $95,041.50/- (see Table 14). Table 14: Adjudication Fees (ex GST) (for all applications) Range of adjudication fees for a case Amount S$ Maximum adjudication fees for a case $95,041.50 Minimum adjudication fees for a case $1,000.00 3.10.2 Distribution of Adjudication fees In 54% of the cases, the adjudication fees (excluding GST) fall within the range from $2,000/- to $5,999/- (see Table 15 for fees distribution). Table 15: Distribution of Adjudication Fees Distribution of adjudication fees Number Percentage (%) $750 to $1,999 26 4 $2,000 to $3,999 222 30 $4,000 to $5,999 175 24 $6,000 to $7,999 103 14 $8,000 to $9,999 61 8 $10,000 to $11,999 31 4

$12,000 to $13,999 32 4 $14,000 to $15,999 20 3 $16,000 to $17,999 16 2 $18,000 to $19,999 10 1 $20,000 to $21,999 4 1 $22,000 to $23,999 5 1 $24,000 to $25,999 5 1 above $26,000 23 3 Total 733 100 3.10.3: Range of Adjudication Review fees The adjudication review fees (excluding GST) for all applications range from $3,562.50 to $32,312.50 (see Table 16). Table 16: Adjudication Review Fees (ex GST) (for all Review Applications) Range of adjudication review fees for a case Amount S$ Maximum adjudication review fees for a case $32,312.50 Minimum adjudication review fees for a case $3,562.50 3.10.4 Distribution of Adjudication Review fees In 54% of the cases, the adjudication fees (excluding GST) fall within the range from $2,000/- to $11,999/- (see Table 17 for fees distribution). Table 17: Distribution of adjudication review fees Distribution of adjudication review fees Number Percentage (%) $1,250 to $1,999 0 0 $2,000 to $3,999 5 19 $4,000 to $5,999 2 8 $6,000 to $7,999 1 4 $8,000 to $9,999 4 15 $10,000 to $11,999 2 8 $12,000 to $13,999 2 8 $14,000 to $15,999 2 8 $16,000 to $17,999 1 4 $18,000 to $19,999 0 0 above $20,000 7 27 Total 26 100

3.10.5 Time Spent by Adjudicators Chow (2011) observed that with the exception of one instance, all determinations have been delivered within the stipulated time or extended time. The average time spent by adjudicators is 19.5 hours and the most number of hours spent in a case is 98.7 hours (see Table 18). Table 18: Time Spent by Adjudicators Average Most Hours Time Spent 19.5 hours 98.7 hours 3.10.6 Composition of Adjudicators by Professions It is observed (Chow, 2011) that after the 2009 batch, there were 134 adjudicators. The three main professions of adjudicators are Lawyers (27%), Engineers (27%) and quantity Surveyors (26%) (see Table 19). Table 19: Composition of Adjudicators by Professions Professions Percentage Lawyers 27% Engineers 27% Quantity Surveyors 26% Architects 10% Contractors 9% Others 1% 4. CONCLUSIONS Looking at the statistics, the influence of the SOP Act has been remarkable. The number of adjudication applications filed at Singapore Mediation Centre (SMC) increased from 21 in 2006 to 228 in 2013. The number of review adjudication adjudications filed is quite small, with a total of 30 filed as at December 2013. The number of applications filed in the high court to review the adjudication determination is also small; only 26 have been filed as at Oct 2011. These statistics convey significant information. First, out of a total of 999 adjudication applications that have been filed as at December 2013, 240 were eventually withdrawn, representing 24% of all adjudication applications filed. Furthermore, out of 531 cases that were determined under the SOP Act, at least 94% of these cases were resolved without further review of adjudication w determination. In monetary terms, the value of claims adjudicated under the SOP Act measured against the total progress payment certified over the past six years stands at less than 1%. But the statistics may not capture the full impact and influence of the SOP act. By providing a low cost and efficient adjudication mechanism, the SOP Act has effectively eliminated an avenue for delaying payments without justification. The regime has achieved considerable success in achieving its target of facilitating cash flow within the construction industry.

The SOP Act also encourages parties to negotiate their differences before commencing adjudication proceedings. The provision of the seven-day dispute settlement period provides disputing parties an opportunity to converge on their positions, to minimise the cost of resolving the dispute. 5. REFERENCES Chow K.F. 2013, Security of Payments and Construction Adjudication Second Edition, (LexisNexis). Chow K.F. 2011, Factors Affecting Adjudication Outcomes at the First National Conference on Construction Adjudication Tactics and Strategies, Singapore. Lee E. 2011, Tactics for the Respondents at the First National Conference on Construction Adjudication Tactics and Strategies, Singapore. Lee S.K. 2011, Keynote Address at the First National Conference on Construction Adjudication Tactics and Strategies, Singapore.