CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 119/MP/2013. Date of Hearing: Date of Order :

Similar documents
CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 211/MP/2012

NEW DELHI. Shri M. Deena. to the National Load Despatch e Energy Certificates to

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI

PROCEDURE FOR REGISTRATION OF RENEWABLE ENERGY GENERATION PROJECT BY CENTRAL AGENCY

Case No. 02 of Shri V. P. Raja, Chairman Shri S. B. Kulkarni, Member Shri V. L. Sonavane, Member

Case No.139 of Smt. Chandra Iyengar, Chairperson Shri Azeez M. Khan, Member Shri Deepak Lad, Member

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION

(A Govt. of Maharashtra Undertaking) - CIN: U40109MH2005SGC153645

KERALA STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION

Case No. 135 of Shri Vijay L. Sonavane, Member Smt. Chandra Iyengar, Member. (1) M/s B.S.Channabasappa & Sons...Petitioner 1

Case No. 295 of Coram. Anand B. Kulkarni, Chairperson Mukesh Khullar, Member. Adani Power Maharashtra Limited (APML)

Case No. 17 of Shri. V.P. Raja, Chairman Shri. Vijay L. Sonavane, Member. Reliance Infrastructure Ltd., Santacruz (E).

Distribution List (WRLDC Letter No. WRLDC/MO/RPS/PG-EPMPL/2018) 1. Executive Director, POWER GRID WRTS-1 2. Executive Director, POWER GRID WRTS-2 3.

MADHYA PRADESH ELECTRICITY REGULATIORY COMMISSION BHOPAL. ORDER (Date of Order : 7 th September, 2012)

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (DISTRIBUTION OPEN ACCESS) REGULATIONS, 2015 INDEX

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member

Case No. 2 of Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member

CASE No. 173 of Coram. Shri Anand B. Kulkarni, Chairperson Shri Mukesh Khullar, Member

Case No. 7 of Coram. Anand B. Kulkarni, Chairperson I.M. Bohari, Member Mukesh Khullar, Member

ORDER (Date of hearing 24 th November, 2012) (Date of order 10 th December, 2012)

Case No. 64 of Shri. V. P. Raja, Chairman Shri. Vijay L. Sonavane, Member ORDER

Case No. 166 of The Tata Power Co. Ltd. (Generation) [TPC-G] Brihanmumbai Electric Supply & Transport Undertaking (BEST)...

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION NOTIFICATION (TRANSMISSION OPEN ACCESS) REGULATIONS, 2014

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (TRANSMISSION OPEN ACCESS) REGULATIONS, 2016 INDEX

Case No. 224 of Coram. Shri. I.M. Bohari, Member Shri. Mukesh Khullar, Member. M/s. Vidarbha Industries Power Ltd (VIPL-G)

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member

Case No. 68 of Coram. Shri. I. M. Bohari, Member Shri. Mukesh Khullar, Member. M/s RattanIndia Nasik Power Ltd.

क द र य व द य त न य मक आय ग CENTRAL ELECTRICITY REGULATORY COMMISSION नई द ल ऱ NEW DELHI

Case No. 22 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member ORDER

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

THE TAMIL NADU ELECTRICITY REGULATORY COMMISSION

Draft JSERC (Terms and Conditions for Intra State Open Access) Regulations, 2016

AGREEMENT FOR SALE OF POWER. THIS AGREEMENT FOR SALE OF POWER is made and executed at on the day of, 2017 ( Agreement ) BY AND BETWEEN

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION BHOPAL

ASSAM ELECTRICITY REGULATORY COMMISSION (DEVIATION SETTLEMENT MECHANISM AND RELATED MATTERS) REGULATIONS, 2018 NOTIFICATION

ORDER (Hearing on & )

DETAILED PROCEDURE FOR GRANT OF CONNECTIVITY & OPEN ACCESS IN INTRA-STATE TRANSMISSION SYSTEM

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Shri I. B. Pandey, Member

CASE No. 149 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Shri. Vinod Sadashiv Bhagwat.

Case No. 94 of Shri. V.P. Raja, Chairman Shri. Vijay L. Sonavane, Member

Draft JSERC (Procedure, Terms & conditions for the Grant of Transmission licensee and other related matters) Regulations, 2018

Draft Supplementary Power Purchase Agreement

Grievances No.K/DOS/015/874 of and No. K/DOS/016/875 of

MADHYA PRADESH ELECTRICITY REGULATIORY COMMISSION BHOPAL ORDER

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : CODE OF CIVIL PROCEDURE Date of Judgment: FAO (OS) 298/2010

BIHAR ELECTRICITY REGULATORY COMMISSION

Index. 1. Introduction: Scope of the Guidelines Preparation for inviting bids Tariff Structure 6. 5.

AGREEMENT FOR LONG TERM ACCESS WITHOUT SYSTEM STRENGTHENING BETWEEN POWER GRID CORPORATION OF INDIA LIMITED AND. (Name of Long Term Customer)

M/s. Heer Enterprises - Applicant

UTTARAKHAND POWER CORPORATION LTD. BID DOCUMENT FOR PURCHASE OF POWER COMMERCIAL AND GENERAL CONDITIONS

CASE No. 156 of In the matter of

DELHI HIGH COURT UPHELD JUDGMENT DIRECTING RESTORATION AND RENEWAL OF TRADEMARK MBD, 29 YEARS AFTER DUE DATE OF RENEWAL

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SUIT FOR DECLARATION. Date of Reserve: January 14, Date of Order: January 21, 2009

Shortage / Surplus Power available with TATA POWER -DDL

GUJARAT ELECTRICITY REGULATORY COMMISSION (GERC) LICENSING OF ELECTRICITY TRADING. Notification No. 3 of 2005

IN THE HIGH COURT OF DELHI AT NEW DELHI. 1. Writ Petition (Civil) No of Judgment reserved on: August 30, 2007

THE JHARKHAND GAZETTE EXTRAORIDINARY PUBLISHED BY AUTHORITY 19 ASHUIN, 1928 (S) Ranchi, Wednesday the 11 th October, 2006

I have had the benefit of perusing the judgment of my. esteemed learned brother, Hon ble Justice Shri S.B. Sinha,

Case No. 61 of In the matter of. Petition of Wardha Power Company Ltd. for Review of Order dated 17 January, 2014 in Case No.

BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai

Suo-Motu Petition No. 2/2018

BEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA.

PROCEDURE FOR REDEMPTION OF RENEWABLE ENERGY CERTIFICATE

IN THE HIGH COURT OF DELHI AT NEW DELHI. W.P.(C) No.8693/2014. George. Versus. Advs. for UOI. HON BLE MR. JUSTICE RAJIV SAHAI ENDLAW

Gas Storage Agreement the Inverse Storage (hereinafter referred to as the Agreement )

BEFORE THE CONSUMER GRIEVANCES REDRESSAL FORUM O R D E R

Case No.83 of In the matter of Petition under Section 67 of the E.A, 2003 seeking directions upon MSETCL in regard to erection of Tower.

Shortage / Surplus Power available with TATA POWER -DDL

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ALLOTMENT OF FLAT. W.P.(C) No.5180/2011. Decided on:

Shortage / Surplus Power available with TATA POWER -DDL

Petition No 973 of 2014 and 1036,1037,1038,1039 &1040 of 2015 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW

GUIDELINES/PROCEDURE FOR IMPLEMENTATION OF SHORT TERM OPEN ACCESS (STOA)

CHAPTER I: PRELIMINARY

Case No. 167 of Coram. Smt. Chandra Iyengar, Chairperson Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member

IN THE HIGH COURT OF DELHI AT NEW DELHI. W.P.(C) No.3245/2002 and CM No.11982/06, 761/07. Date of Decision: 6th August, 2008.

Respondents. Present in the Hearing: Respondents

STATE CONSUMER DISPUTES REDRESSAL COMMISSION, MAHARASHTRA, MUMBAI. Complaint No.CC/13/172

IN THE MATTER OF GRIEVANCE NO. K/DOS/001/482 OF OF MRS.

NOTIFICATION MINISTRY OF COMMERCE AND INDUSTRY DEPARTMENT OF INDUSTRIAL POLICY AND PROMOTION INTELLECTUAL PROPERTY APPELLATE BOARD

JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION RANCHI (Case No.23/ ) QUORUM Shri Mukhtiar Singh, Chairperson Shri P. C. Verma, Member.

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION. Investigate and to take appropriate action against M/s Torrent and further to cancel the

TAMIL NADU GOVERNMENT GAZETTE. Part VI --- Section 2 (Supplement)

M/S. Iritech Inc vs The Controller Of Patents on 20 April, % Judgment pronounced on: 20th April, 2017

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ELECTRICITY ACT, 2003 Date of decision: 19th April, 2011 W.P.(C) 8647/2007

PUBLIC WORKS NOTIFICATIONS TELANGANA STATE ELECTRICITY REGULATORY COMMISSION: HYDERABAD

2. Chief Engineer (PPA) UP Power Corporation Limited 14 th Floor, Shakti Bhawan Ext. 14 Ashok Marg, Lucknow.Respondent

Maharashtra Electricity Regulatory Commission (Procedure for filing appeal before the Appellate Authority) Regulations, 2004

SEVENTEENTH AMENDMENT TO MADHYA PRADESH ELECTRICITY SUPPLY CODE, 2004.

THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION AND CONCILIATION ACT, 1996 Judgment delivered on:

.. IN HIGH COURT OF DELHI:AT NEW DELHI SUBJECT : CODE OF CIVIL PROCEDURE. I.A. No /2006 in C.S.(OS) No.795/2004

Case No. CGRF(NZ)/91/2018

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : CODE OF CIVIL PROCEDURE IA No.13139/2011 in CS(OS) 1163/2011 Date of Decision : July 05, 2012

THE HIGH COURT OF DELHI AT NEW DELHI

ORDER Dated: 11 th August, 2004

IN THE HIGH COURT OF DELHI AT NEW DELHI COMPANY JURISDICTION COMPANY PETITION NO. 406 OF 2009

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : CHARTERED ACCOUNTANTS ACT, 1949 W.P.(C) 1345/2011 DATE OF ORDER :

REQUEST FOR SELECTION (RfS) DOCUMENT FOR PROCUREMENT OF 50 MW POWER GENERATED FROM BIOMASS PROJECTS IN MAHARASHTRA ISSUED BY

A FORTNIGHTLY VAT/GST LAW REPORTER 2003 NTN 22) [ALLAHABAD HIGH COURT]

BEFORE THE MAHARASHTRA REAL ESTATE REGULATORY AUTHORIry MUMBAI COMPLAINT NO: CC Avinash Saraf, Neha Duggar Saraf... Complainant. Versus

Transcription:

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Petition No. 119/MP/2013 Coram: Shri V.S. Verma, Member Shri M. Deena Dayalan, Member In the matter of Date of Hearing: 17.09.2013 Date of Order : 03.12.2013 Petition under Section 79 (1) (k) of the Electricity Act, 2003 read with Regulation 3 (4) 14 of the Central Electricity Regulatory Commission ((Terms and Conditions for Recognition and Issuance of Renewable energy certificate for renewable energy generation) Regulations, 2010. And in the matter of M/s Peethambra Granites Private Limited 80, Civil Lines, Jhansi-284 001, Maharashtra National Load Despatch Center B-9, Qutab Institutional Area, Katwaria Sarai, New Delhi-110 016 Maharasthra State Load Despatch Centre Thane-Belpur Road, P.O. Airoli, Navi Mumbai-400 708 Vs Petitioner Respondents Parties Present: Shri Rajiv Yadav, Advocate for the petitioner Shri Kulbhushan Kumar, PGPL Shri Arjun Krishnan, Advocate, NLDC Shri A.Banerjee, Advocate, NLDC Ms. Jyoti Prasad, NLDC Shri Sailendra Verma, MSLDC Order in Petition No.119/MP/2013 Page 1/13

ORDER The petitioner in the present petition filed under Regulations 3 (4) and 14 of the Central Electricity Regulatory Commission (Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations, 2010 (REC Regulations) has made prayer to direct National Load Despatch Centre (NLDC) to issue Renewable Energy Certificates (RECs) in terms of application for the month of May, 2012. 2. By virtue of clause (1) of Regulation 3 of the REC Regulations, the Commission has nominated the National Load Despatch Centre as the Central Agency to perform functions under clause (2), which include issuance of Renewable Energy Certificates (RECs) under these regulations. The Central Agency has, after approval of the Commission, issued the detailed procedure in terms of clause (3). Regulation 5 of the REC Regulations lays down the criteria for registration of the eligible entity for issuance of RECs. In accordance with clause (1) of Regulation 5, a generating company engaged in generation of electricity from renewable energy sources (RE Generator) is eligible to apply for registration to the Central Agency for issuance of RECs on fulfilling the following conditions, namely: (a) It has obtained accreditation from the State Agency, (b) It does not have PPA for the capacity related to such generation to sell electricity at a preferential tariff, and Order in Petition No.119/MP/2013 Page 2/13

(c) It sells electricity generated either (i) to the distribution licensee of the area in which the eligible entity is located, at a price not exceeding the pooled cost of power purchase of such distribution licensee, or (ii) to any other licensee or to an open access consumer at a mutually agreed price, or through power exchange at market determined price. 3. Regulation 7 of the REC Regulations which deals with issuance provides as under: 7. Denomination and issuance of Certificates (1) The eligible entities shall apply to the Central Agency for Certificates within three months after corresponding generation from eligible renewable energy projects: Provided that the application for issuance of certificates may be made on fortnightly basis, that is, on the first day of the month or on the fifteenth day of the month. 4. From clause (1) of Regulation 7 of the REC Regulations it follows that RE Generator is required to apply for issuance of RECs within three months from the corresponding generation date. Further, the application for the purpose has to be made either on first day of the month or fifteenth day of the month. 5. A Detailed Procedure approved by the Commission lays down the actual process of processing of applications for grant of RECs. Clause 7.1 of the Detailed Procedure is extracted below: The Eligible Entity shall apply for issuance of renewable energy certificates within three (3) months from the month in which renewable energy was Order in Petition No.119/MP/2013 Page 3/13

generated and injected into the electricity grid after issuance of the monthly energy injection report by the concerned SLDC. However, the eligible entity shall apply for issuance of RECs for the complete month in sequential manner. For example, in the month of May, the applicant may apply for issuance of RECs for the months of February, March and April. However, since the monthly injection report for May would not be available with the Central Agency before month end, application for issuance of RECs against energy injected during May can be made on a fortnightly basis in the subsequent three months. However, the eligible entity shall ensure that it should apply first for February before applying for March. 6. As per the above provisions, the RE Generator who has obtained accreditation with the State Agency and registration with the Central Agency is required to apply for issuance of RECs for the complete month in sequential manner. 7. The petitioner has set up 2x1.25 MW wind generation unit in the State of Maharashtra. It was granted accreditation by the State Agency, namely Maharashtra Energy Development Agency (MEDA) on 27.7.2011. The project was registered by the Central Agency on 13.9.2012. The petitioner become eligible for issue of RECs for December 2011. 8. The petitioner entered into a contract with Global Energy Private Limited, a trading licensee for supply of wind energy through open access to M/s Essar Steel Limited at negotiated tariff. The petitioner`s transaction for supply of power through the trading licensee commenced from 1.4.2011. After the petitioner obtained accreditation from the State Agency and registration from the Central Agency, Renewable Energy Order in Petition No.119/MP/2013 Page 4/13

Certificates (hereafter RECs ) were issued to it by the Central Agency from time to time. 9. The petitioner has alleged that as per Energy Injection Report (EIR) dated 17.8.2012 issued by Maharashtra SLDC, for the month of May, 2012, it supplied 788.38 MWh of wind energy. The petitioner has submitted that the application submitted to NLDC for issuance of RECs was received in NLDC office on 21.8.2012 within the stipulated time of three months from the date of actual generation in accordance with the REC Regulations. However, the Central Agency has not issued RECs for the month of May, 2012. The status of the said application was shown as 'pending for verification' on the website of Central Agency. 10. The petitioner has submitted that the matter was taken up by it with Central Agency by e-mail dated 8.11.2012 followed by the letter dated 4.3.2013 for issuance of RECs for the month of May, 2012. However, no response was received from Central Agency. The petitioner has submitted that owing to NLDC s failure to conduct itself in accordance with the REC Regulations, it has been deprived of its legitimate RECs entitlement and the revenue that it would have realized there from. 11. Maharashtra State Load Despatch Centre (MSLDC) in its reply dated 20.7.2013 has submitted as under: Order in Petition No.119/MP/2013 Page 5/13

(a) Energy Injection Report (EIR) from MSELDC in respect of the petitioner for the month of April, 2012 was received by MSLDC by fax at 03.02 P.M. on the last day of July 2012. (b) The Open Access (OA) permissions for the respective month were not enclosed with the application. However, the applications for the respective months were processed/approved by MSLDC and EIR was sent to Central Agency by MSLDC considering with following facts: (i) The REC claim would have lapsed after 31.7.2012; (ii) Confirmation to SLDC from M/s. Shivshakti Urja Pvt. Ltd (SUPL), coordinating agency for the petitioner, on telephone that the RE power has not been sold by the RE generator at preferential tariff; (iii) OA permission / Notarized affidavit regarding sale of RE power to 3rd party for the month of April 2012 would be submitted to SLDC immediately in the next month; (iv) Reminder was given to the petitioner for submission of the said affidavit, by email dated 6.8.2012 at 12.02 PM and 04.31 PM; (v) The petitioner did not submit the OA permission and affidavit along with the REC applications for the months of May and June 2012. Based on the assurance given by SUPL to submit the affidavits for the months of May and Order in Petition No.119/MP/2013 Page 6/13

June 2012, REC applications were processed / approved by SLDC and EIRs were sent to NLDC on 18.8.2012; (vi) However, till 31.8.2012 neither the OA permissions nor the said affidavits were submitted by the petitioner to SLDC. A common email therefore, listing out the Renewable Energy Generators including the petitioner who had not submitted/not received the OA permission from MSEDCL was sent to NLDC on 31.8.2012 at 16.55 hrs. (vii) Subsequently, the petitioner submitted OA permission in the month of September, 2012. The same was informed to NLDC vide the email dated 24.9.2012 at 04.59 pm. (viii) There has been no delay or default on the part of MSLDC in sending EIRs of M/s. Peethambra Granites Pvt. Ltd. for the months of April, May and June, 2012 to NLDC. 12. NLDC in its reply dated 18.7.2013 has submitted that the application for issuance of RECs corresponding to Month of May 2012 was received by Central Agency on 21.8.2013. However, during the course of the steps being taken by Central Agency for issuance of RECs, an email dated 31.8.2013 was received from Maharashtra SLDC stating inter- alia that open access permission was not granted to the petitioner and the distribution licensee may claim Renewable Purchase Obligation (RPO) for such power procured from the RE Generators. Therefore, RECs for the month of May 2012, could Order in Petition No.119/MP/2013 Page 7/13

not be issued. Subsequently, Maharashtra, SLDC vide its email dated 24.9.2012 clarified that open access permission was granted to the petitioner with effect from August 2012. In view of the clarification issued by SLDC, RECs for the subsequent month has been issued to the petitioner. The RE Generators are required to apply for issuance of RECs after completing all the formalities like getting the certified Energy Injection Report from the concerned SLDC within the stipulated period of three months. Since the communication from SLDC regarding grant of open access to the petitioner from April, 2012 was by Central Agency vide letter dated 24.9.2012 which was beyond the prescribed time limit of 3 months, the Central Agency did not issue the RECs for the month of May, 2012. 13. The petitioner in its rejoinder dated 4.8.2013 has submitted that no intimation was received from MSLDC regarding non-submission of open access permission. On the contrary, MSLDC itself had granted open access permission on 30.7.2012 and therefore, the same ought to have been within its knowledge while intimating about the non-receipt of open access to NLDC. The petitioner has explained the procedure adopted in the State of Maharashtra regarding injection of wind power and its accounting as under: "8.In addition to the above, it is submitted that the Petitioner has applied for requisite open access permission on 24.7.2012. The open access permission came to be granted to the Petitioner on 30.7.2012 for the period 1.4.2012 to 30.9.2012. In this regard, it may be noted that given the nature of wind transaction, all wind units are injected under the banking protocol, devised by the State Commission. The wind units are not accounted for and financially settled in real time. Banking of units allows a wind generator the flexibility of treating the injected units as 'supply to the discom' or ' sale to a bilateral buyer/consumer'. Order in Petition No.119/MP/2013 Page 8/13

Until open access permission is granted, the wind power is deemed to have been banked to the local discom. It is only after open access is granted, can wind power be deemed to have been supplied to a bilateral buyer, who will then get credits for such power in the monthly electricity bill. It is, therefore, not unusual for open access permissions to b grated post injection of power into the grid. Open access in case of wind generation is primarily for the purpose of 'accounting and financial settlement' of wind units injected into the grid. The grant of open access in a given case determines whether the wind units shall be counted towards the ROP obligation of the local discom or a bilateral sale of HT consumers." 14. The petitioner has further submitted that the wind units generated by it in the month of May, 2012 were indeed supplied to an open access consumer on bilateral terms. However, such units were admittedly, not considered for meeting the renewable power purchase of the local discom. 15. During the hearing on 17.9.2013, learned counsel of petitioner submitted that on 21.8.2013, the petitioner applied to NLDC for issuance of RECs for the month of May, 2012 within the prescribed limit of three month from the date of actual generation. However, NLDC has not issued RECs for the month of May, 2012 till date. The Status of the said application was shown as "pending for verification" on the website of Central Agency. The petitioner was not informed about any deficiency in its REC application for the month of May, 2012 by the Maharashtra, SLDC. However, from the reply of NLDC to the petitioner, it is noticed that MSLDC vide its e-mail dated 31.8.2012 informed NLDC that certain generators, including the petitioner, had not submitted open access permissions, and the distribution licensee might claim the energy injected into the grid for the month of May 2012 for fulfillment of RPO. Subsequently, MSLDC vide its email dated 24.9.2012 confirmed to NLDC that open access permission for the relevant period had been obtained by the petitioner. However, by the time such confirmation was Order in Petition No.119/MP/2013 Page 9/13

communicated to NLDC, the prescribed period of three months under Regulation 7 (1) of the REC Regulations had lapsed and therefore, NLDC refused to issue RECs for the month of May, 2012. The requisite open access permission/noc had been obtained by the petitioner, as early as 30.7.2012, and the same had been duly submitted to SLDC under letter dated 13.8.2012. Since the said letter dated 13.8.2012 bears the receipt stamp of MSLDC and MSLDC never informed the petitioner about any missing enclosure. it evidently follows that the open access permission/noc was indeed provided to SLDC. Since, open access permission was obtained for the purpose of applying for RECs, the petitioner had no reason to withhold the open access permission from MSLDC. 16. The representative of the MSLDC submitted that the petitioner's application dated 13.8.2012 was received by SLDC without any annexure. Even though the open access permission was not received, the energy injection report was issued by MSLDC to M/s Shiv Shakthi Ojha Pvt. Ltd which is the coordinating agency dealing on behalf of the petitioner with SLDC and the non-submission of open access permission was intimated to such coordinating agency on 6.8.2012. He clarified that open access permission has been granted by MSETCL and not by MSLDC. 17. Learned counsel for NLDC submitted that MSLDC`s confirmation regarding petitioner's open access permission was received on 24.9.2012. Since by such date, the prescribed period for issuance of RECs had lapsed, NLDC could not issue RECs for the month of May, 2012. Learned counsel further submitted that the Commission may Order in Petition No.119/MP/2013 Page 10/13

consider whether retrospective permission of open access should be considered to regularize the open access transaction. 18. We have heard learned counsels for the petitioner, Central Agency and the representative of the MSLDC. We have carefully perused the record. The main issue for consideration is whether the RECs can be disallowed to the petitioner on the ground that the petitioner failed to submit the open access permission to the SLDC before the expiry of the period of three months from the month of energy injection. 19. From the pleadings of the parties, it emerges that the petitioner has made online application for grant of REC for the month of May, 2012 on 14.7.2012, based on its own estimation of energy injection in that month. Subsequently, the petitioner has submitted Energy Injection Report for the month of May and June, 2012 to MSLDC vide its letter dated 13.8.2012. Based on the information submitted by the petitioner, MSLDC has issued Energy Injection Report on 17.8.2012. Thereafter, the petitioner has submitted the physical application to NLDC on 21.8.2012. As per the requirements of the REC Regulations, NLDC was required to issue the RECs within 15 days from the date of receipt of the physical application, which happened to be 5.9.2012, in case of the petitioner. During the period of processing the application, NLDC got an email dated 31.8.2012 from the MSLDC, stating that the OA permission was not granted to the petitioner and the distribution licensee may claim RPO. On the basis of the said information, NLDC did not issue REC for the month of May, 2012. Subsequently, MSLDC in its email dated 24.9.2012 clarified to NLDC that the open access permission for the period from April 2012 has not been issued in respect of the petitioner and other Order in Petition No.119/MP/2013 Page 11/13

RE generators. NLDC has not granted REC on the ground that the period for grant of REC for the month May, 2012, has expired by that time. 20. From the factual matrix as discussed in para 19 above, it is noticed that the petitioner has made the online and physical application for the month of May, 2012 before 31.8.2012. MSLDC vide its letter dated 17.8.2012 has forwarded Energy Injection Report to NLDC, with the understanding that the petitioner would submit the open access permission from MSEDCL to MSLDC. In fact, MSLDC has sent two emails on 6.8.2012 to coordinating agency acting on behalf of petitioner one asking for certain reconciliation in the Energy Injection Report and the other conveying that the OA permission for the month of May, 2012 has not been enclosed. The petitioner in para 4 of its rejoinder filed vide its affidavit dated 4.9.2012 has submitted as under :- Specifically, it may be noted that no intimation was received by the petitioner from Maharashtra SLDC regarding the absence of OA permission in its application for issuance of RECs. Further, it is submitted that Maharashtra SLDC, itself had issued the OA permission to the petitioner on 30.7.2012, and, therefore, the same ought to have been within the knowledge of the Maharashtra SLDC. 21. The petitioner has placed on record a copy of the open access permission dated 30.7.2012 as Annexure-P2 of the petition. A perusal of the said permission reveals that it has been issued by Maharashtra State Electricity Distribution Company Ltd. (MSEDCL) and not by Maharashtra State Electricity Transmission Company Ltd. (MSETCL)/MSLDC. Moreover, the permission letter is addressed to the petitioner and no copy thereof has been endorsed to MSLDC/MSETCL. Therefore, the submission of the petitioner that MSLDC has issued OA permission to petitioner is not correct. In fact, it is the responsibility of the petitioner to submit its Energy Injection Report, along with Order in Petition No.119/MP/2013 Page 12/13

OA permission from MSEDCL to MSLDC for further processing of the case. We are, therefore, not inclined to accept the contention of the petitioner that the OA permission was given to MSLDC prior to 31.8.2012, when MSLDC intimated NLDC regarding deficiency in the application of the petitioner. MSEDCL has submitted that only after the petitioner submitted the photocopy of the NOC, it intimated NLDC vide its email dated 24.9.2012 that open access permission has been received. 22. We do not find any infirmity in the action of either MSLDC or NLDC in processing the application of the petitioner. It was incumbent on the petitioner to satisfy MSLDC and NLDC with appropriate information within the specified time, so that the RECs are processed and issued in time. In our view, the petitioner cannot be allowed to take advantage of its own wrong. However, considering the fact that the application for grant of REC for the month of May, 2012 has been submitted in time and even the NOC from MSEDCL for grant to third party has been issued within time i.e. on 30.7.2012 and keeping in view the objectives of the REC Regulations, we take a lenient view in the matter and direct NLDC to process the case of the petitioner for grant of REC for the month of May, 2012 within 15 days form the date of issue of this order. We also administer a strong warning to the petitioner to be careful in future regarding the factual accuracy of its submission before the Commission. 23. With the above directions, the petition stands disposed of. sd/- (M. Deena Dayalan) Member sd/- (V.S.Verma) Member Order in Petition No.119/MP/2013 Page 13/13