Review and Variance Request by Lavesta Area Group on Utility Cost Order December 19, 2008

Size: px
Start display at page:

Download "Review and Variance Request by Lavesta Area Group on Utility Cost Order December 19, 2008"

Transcription

1 Decision Request for Review and Variance of Decision : Alberta Electric System Operator, Needs Identification Document Application, Edmonton Calgary 500 kv Electric Transmission Facilities Review and Variance Request by Lavesta Area Group on Utility Cost Order December 19, 2008

2 ALBERTA ENERGY AND UTILITIES BOARD Decision : Request for Review and Variance of Decision : Alberta Electric System Operator, Needs Identification Document Application, Edmonton Calgary 500 kv Electric Transmission Facilities Review and Variance Request by Lavesta Area Group On Utility Cost Order Application No December 19, 2008 Published by Alberta Energy and Utilities Board Avenue SW Calgary, Alberta T2P 3G4 Telephone: (403) Fax: (403)

3 Contents 1 DECISION BACKGROUND JURISDICTION THE LAVESTA REVIEW REQUEST FIRST ISSUE View of Lavesta Views of Other Interested Parties Findings of the Review Panel ORDER EUB Decision (December 19, 2008) i

4 ALBERTA ENERGY AND UTILITIES BOARD Calgary, Alberta REQUEST FOR REVIEW AND VARIANCE OF DECISION : ALBERT ELECTRIC SYSTEM OPERATOR, NEEDS IDENTIFICATION DOCUMENTS APPLICATION, EDMONTON- CALGARY 500 KV ELECTRIC TRANSMISSIONS FACILITIES REVIEW AND VARIANCE REQUEST ON Decision UTILITY COST ORDER Application No DECISION Having carefully considered all of the evidence, the Alberta Energy and Utilities Board (EUB/Board) hereby varies Utility Cost Order (UCO ) by awarding $13, in fees to Mr. Joseph Anglin, in recognition of activities performed on behalf of the Lavesta Area Group (Lavesta), in the capacity as a representative/coordinator of that group. 2 BACKGROUND The First Need Application and the Review Hearing In May 2004, the Alberta Electric System Operator (AESO) filed an application pursuant to section 34 of the Electric Utilities Act, describing the need for transmission upgrades between Edmonton and Calgary. The application also described the AESO s preferred option (option 5 of 12) to address the identified need; a 500 kv transmission line located within what became known as the West Corridor. The EUB considered the application at a public hearing in December 2004 and January On April 14, 2005, the EUB issued Decision , which approved the AESO s application. Six parties subsequently requested the EUB to review and vary Decision The Board granted a review hearing to consider the suitability of the West Corridor for the proposed transmission line (the R&V Hearing). The R&V Hearing was held in Red Deer, Alberta in July and August of On December 6, 2006, the Board issued EUB Decision in which it upheld its previous decision. On January 26, 2007, the Board issued, UCO , which ruled on costs claimed by participants in the R & V Hearing. On August 2, 2007, the EUB issued an errata to UCO to address three claims by UPTAG and its members that were filed after the issuance of that cost order. Two of the claims were made by UPTAG members who where unaware that they were eligible to file cost claims. The third claim was for a consultant hired by UPTAG who filed its account after the issuance of UCO AESO took no position regarding these additional claims. On March 2, 2007, Lavesta applied for a review and variance (R&V) of UCO Lavesta sought to vary UCO in two instances: EUB Decision (December 19, 2008) 1

5 by increasing the EUB s approved mileage rate; and by awarding in full the costs claimed on behalf of Mr. Joseph Anglin, the Vice-Chairman of Lavesta. Subsequent Events and the Appointment of the Review Panel While reviewing Lavesta s review request and related materials, the EUB was also considering an application by Altalink Management Ltd. (Altalink) for approval for the construction and operation of the 500 kv transmission line within the West Corridor. The Hearing Panel originally set the Altalink hearing down for February 12, 2007; this date was later adjourned to March 12, 2007 and then to April 19, When the hearing re-opened it was disrupted and the Hearing Panel adjourned the proceeding to secure an alternative venue. In light of the events of April 19, 2007, the Hearing Panel decided to change its hearing format. It moved the hearing to the Provincial courthouse in Rimbey. Officials of the Board also hired an outside contractor to assist with hearing security. It later came to light that one of the persons hired engaged in improper conduct that was authorized by a senior EUB official. On September 30, 2007, the Board issued EUB Decision in which it declared that the Altalink hearing, as well as EUB Decisions and , were void for reasonable apprehension of bias. On page 9 of Decision , the EUB stated the following with respect to potential new applications for upgrades to the transmission system: Acting Board Members could be added to the EUB by the Lieutenant Governor in Council to form a panel to consider the applications. Should this occur, the Board would urge that the government ensure that this panel includes judicial or quasi-judicial experience at a high level, as well as relevant experience such as engineering expertise and familiarity with relevant issues affecting persons over whose lands such development would pass. This panel should be made up of persons who have had no involvement whatsoever with the prior hearings or events related to them. On March 12, 2008, the EUB Board members met to decide how to move forward with Lavesta s review request in light of Decision The Board established a new Division consisting of Acting Board Members Mr. John Curran, Q.C., Ms. Donna Tingley, and Mr. James Turner (the Panel ) to consider the Lavesta review request. These individuals were appointed to the EUB s acting Board member list after the issuance of Decision and had no involvement in any of the matters leading up to the issuance of Decision Following its appointment, the Panel reviewed UCO and the submissions and correspondence from interested parties. Recognizing that the matter had been outstanding for some time the Panel wrote to parties on June 4, 2008 and advised as follows: The EUB s review and variance practice normally involves two steps. First the Board decides whether it should review the decision in question on the basis of error of law, jurisdiction or fact or on the basis of new facts or change in circumstances. Parties are not obliged to file evidence at this stage but are merely required to make their case on a prima facie basis. If the Board decides that a review is appropriate it will consider as its second step whether the original decision should be varied. If a review hearing is granted 2 EUB Decision (December 19, 2008)

6 parties will file evidence to support their position in the same manner as if it was a hearing in the first instance. Recognizing that this process has been outstanding for a considerable length of time, the Costs Review Panel asks that parties include with their submissions all the information and evidence that has not been filed previously that they wish the Board to consider for both stages of the review process. In response to this letter, the Panel received additional submissions from Lavesta and Altalink. 3 JURISDICTION EUB s Authority to Consider Lavesta s Request On January 1, 2008, the EUB was replaced by the Energy Resources Conservation Board (ERCB) and the Alberta Utilities Commission (AUC). However, the Lavesta review proceeding commenced prior to the coming into force of the Alberta Utilities Commission Act (AUCA) and thus is a matter to be considered by the EUB. Subsection 80(5) of the AUCA provides for the continuation of the EUB for the purposes of review proceedings commenced prior to the coming into force of the AUCA: (5) On the coming into force of this section, the persons serving as members of the Board continue as members of the Board for the purposes of subsection (3), but unless otherwise appointed or reappointed do not become members of the Alberta Utilities Commission or continue as members of the Energy Resources Conservation Board. EUB s Authority to Review Cost Orders The EUB s authority to review a cost order is described in sections 58 and 46 of its Rules of Practice. Section 58 of the Energy and Utilities Board Rules of Practice states: 58(1) A party to a costs order may, within 30 days of the date of service of the order, apply to the Board for a review of the order. (2) An application for a review of a costs order must be made in accordance with section 46. Section 46 reads in part as follows: 46 (5) The Board shall determine, with or without a hearing in respect of an application for review, the preliminary question of whether the order, decision or direction made by it should be reviewed. (5.1) When determining the preliminary question, the Board shall grant an application for review, (a) with respect to a review of an order, decision or direction other than a review under section 40 of the Energy Resources Conservation Act, if the Board determines that, (i) in the case where the applicant has alleged an error of law or jurisdiction or an error of fact, the applicant has, in the Board s opinion, EUB Decision (December 19, 2008) 3

7 raised a substantial doubt as to the correctness of the Board s order, decision or direction, or (ii) in the case where the applicant has alleged new facts, a change in circumstances or facts not previously placed in evidence, the applicant has, in the Board s opinion, raised a reasonable possibility that new facts, a change in circumstances or facts not previously placed in evidence, as the case may be, could lead the Board to materially vary or rescind the Board s order, decision or direction. 4 THE LAVESTA REVIEW REQUEST Following the close of the R & V Hearing, interveners filed their cost claims with the Board and AESO. On October 31, 2006, AESO wrote to the EUB and specifically commented on the fees claimed by Lavesta on behalf of Mr. Anglin. AESO contended that Mr. Anglin had no legal training and was not an expert, and that the EUB should take this into account when determining the costs awarded to him. AESO also commented on the role played by Mr. Anglin at the hearing. However, AESO did not forward its comments to Lavesta. Further, due to an administrative error, the EUB forwarded the AESO letter to an incorrect mailing list which did not include Lavesta s counsel. As a result, Lavesta never had an opportunity to respond to AESO s concerns. In recognition of this error, the EUB forwarded the AESO s October 31, 2006 letter to interested parties on March 19, 2007, and invited them to respond to the AESO s comments and comment on Lavesta s request for a review. The EUB received 15 responses supporting a review of UCO As noted previously, the Panel wrote to interested parties on June 4, 2008 to advise that it would consider any and all evidence that interested parties wanted to file in support of the review request. In this respect the Review panel gave effective notice to interested parties of its intention to move into the second phase of the EUB s review process, the consideration, based upon the evidence of the parties as to whether UCO should be upheld, varied or rescinded. As the EUB s Costs application process is itself a written proceeding, the Review Panel determined that written submissions from parties on this matter would be appropriate. The Review Panel considered the following documents in making its decision: Correspondence from Julian Bodnar to Richard McKee dated June 5, 2006, June 7, 2006, and June 9, 2006 Lavesta Submission on EPCOR Utilities Inc. Motion, dated June 15, 2006 Correspondence from Julian Bodnar to Richard McKee dated June 27, 2006 Correspondence from Julian Bodnar to JP Mousseau and Doug Larder, dated June 28, 2006 Correspondence from Julian Bodnar to Richard McKee dated June 28, from Joseph Anglin to Richard McKee dated June 30, 2006 Information Request 1 and Information Request 2 to AESO, dated June 30, 2006 and July 3, 2006, respectively 4 EUB Decision (December 19, 2008)

8 Correspondence from Julian Bodnar to JP Mousseau dated July 14, 16, 20, 24, and August 23, 2006 Lavesta Hearing Budget prepared by Mr. J. Bodnar, dated June 16, 2006 Hearing Transcripts from the R&V proceeding Lavesta final argument and reply argument, dated August 28, 2006 and September 11, 2006, respectively Lavesta Cost Claim dated October 12, 2006 UCO Correspondence from James H. Smellie to Holly Lee dated October 31, 2006 Correspondence from Julian Bodnar to JP Mousseau and Richard McKee dated November 17, 2006 Correspondence from Joseph Anglin to JP Mousseau dated November 17 and November 20, 2006 Correspondence from Julian Bodnar to JP Mousseau and Richard McKee dated November 27, 2006 Correspondence from Julian W. Bodnar to the EUB dated March 2, from Jessica Ernst to Richard McKee (EUB) dated April 2, 2007 Correspondence from Jamie Valecourt to Richard McKee (EUB) dated April 9, 2007 Correspondence from Joan Valecourt to Richard McKee (EUB) dated April 9, 2007 Correspondence from Dieter and Lou-Aanne Lohman to Richard McKee (EUB) dated April 9, 2007 Correspondence from Louis Regnier to the EUB dated April 10, 2007 Correspondence from Warren Werner to the EUB dated April 10, 2007 Correspondence from Donna Regnier to the EUB dated April 11, 2007 Correspondence from Lynne Ings to the EUB dated April 11, 2007 Correspondence from C.A. Lee to the EUB dated April 11, 2007 Correspondence from Greg Troitsky to the EUB dated April 11, 2007 Correspondence from Joanne D. Lee to the EUB dated April 12, 2007 Correspondence from Mark Stewart to the EUB dated April 12, 2007 Correspondence from Marie Barkley to Richard McKee (EUB) dated April 12, 2007 Correspondence from Thomas D. Lee to the EUB dated April 13, 2007 Correspondence from Roger Wilson to the EUB dated April 13, 2007 Correspondence from Cindy and Mick McLeod to Richard McKee (EUB) dated April 14, from Marie Barkley to Richard McKee (EUB) dated April 18, 2007 Correspondence from the Lavesta Area Group to JP Mousseau (EUB) dated June 9, 2008 Correspondence from Altalink Management Ltd. to JP Mousseau (EUB) dated June 20, FIRST ISSUE 5.1 View of Lavesta Lavesta applied for review and variance of UCO on two grounds: first, that the EUB s approved mileage rate in the Scale of Costs is unreasonable, and second, that the EUB made an error when it decided to deny Lavesta s claim for Mr. Anglin s professional fees. In support of EUB Decision (December 19, 2008) 5

9 the second ground Lavesta noted that it had no opportunity to respond to the AESO s comments and argued that: The Board disregarded the extent and significance of Mr. Anglin s involvement. The Board disregarded Mr. Anglin s qualifications. The Board discriminated against Mr. Anglin when it awarded substantial costs to other participants, who Mr. Bodnar submits, demonstrated equal or less participation and presented equal or less value in similar evidence. The Board s comments in UCO are unfairly biased against Mr. Anglin s role and effectiveness in the proceedings. The positions expressed by Mr. Anglin are legitimate and are confirmed expressions of Lavesta members. On June 9, 2008, Lavesta filed its supplemental submission in support of the second stage of the review request. Lavesta emphasized that Mr. Anglin s involvement in the proceeding was valuable to the group and Lavesta s counsel. Lavesta contended that the Board misinterpreted the context of Mr. Anglin s testimony in the R & V proceeding. It stated that Mr. Anglin s decision to not provide evidence as an expert was a strategic decision designed to advance Lavesta s argument. Lavesta confirmed that it chose to have Mr. Anglin present evidence as a landowner rather than as an expert. It argued that this decision should not diminish Mr. Anglin s qualifications. Lavesta contended that the Board discriminated against Mr. Anglin by awarding costs to other experts whose evidence was of lesser value than that provided by Mr. Anglin. Lavesta argued that the Board provided evidence of that discrimination when it did not address the concerns raised by Mr. Bodnar, when it issued an errata to UCO Lavesta contended that the EUB Decision validated the concerns raised by Mr. Anglin and Mr. Bodnar and, is further evidence of the EUB s bias against Mr. Anglin. Lavesta confirmed that Mr. Anglin s views represented the legitimate expression of the group s views and should be respected. Finally, Lavesta argued that its review request should be broadened to include full reimbursement to Mr. Bodnar. 5.2 Views of Other Interested Parties The only interested party to respond to the Panel s request for additional submissions was Altalink Management Inc. who took no position with respect to Lavesta s request for review and variance. 5.3 Findings of the Review Panel 1. Discretion to award Costs As a Utility proceeding, the Board s authority to award costs to interveners arises from section 68 of the Public Utilities Board Act. The Panel observes that section 68 of that Act does not establish an inherent right to recover hearing costs. In that respect the Panel notes that section 68(1) states: 6 EUB Decision (December 19, 2008)

10 68 (1) The costs of and incidental to any proceeding before the Board, except as otherwise provided in this Act, are in the discretion of the Board, and may be fixed in any case at a sum certain or may be taxed. (Emphasis added). 2. The EUB s Mileage Rate The Panel finds that the costs awarded to Lavesta for mileage were reasonable in the circumstances, consistent with the EUB s Scale of Costs and consistent with the mileage costs awarded to other participants in the proceeding. The Panel considers that Lavesta and its members know, or ought reasonably to have known, that the EUB would award mileage costs based upon its published rate in the Scale of Costs. The Panel therefore finds that the costs awarded in this respect were reasonable and upholds the mileage costs awarded to Lavesta in UCO Mr. Anglin s Claim for Professional fees As the Panel understands it, Lavesta has alleged that the EUB erred in fact, law or jurisdiction by failing to appreciate the nature and extent of Mr. Anglin s involvement in the hearing and the value of his contribution to the proceeding. To consider this claim, and whether UCO should be varied or amended, the Panel carefully reviewed all of the documents listed in section 5. While the Panel does not intend to comment on every document reviewed, it finds that the inclusion of specific excerpts from the Lavesta budget and cost claim are necessary to fully understand the nature of the activities undertaken by Mr. Anglin and the fees claimed for those activities. On June 19, 2006, Lavesta submitted a budget for its participation in its proceeding. In the covering letter Mr. Bodnar, Counsel to the Lavesta stated the following Lavesta has retained the services of Joe Anglin to facilitate communications amongst its members, administer the Lavesta Area Group and assist it and members in preparation for the Hearing. Mr. Anglin s resume and details of his expected role are attached. Mr. Anglin would claim costs as a consultant, and for administrative assistance in these proceedings. His professional fee rate is $250 per hour. His total anticipated costs claim would be in the range of $40,000, plus applicable, disbursements and taxes. In the budget itself, Lavesta stated that Mr. Anglin s activities on behalf of Lavesta would include the following: Review of the Needs Application (May 7, 2004) document. Review of exhibits and excerpts of the transcripts of the initial hearing. Review of relevant related documents, such as the AESO 10 and 20 year plan and AESO s corridor selection data. Meeting with Lavesta members to identify issues and advise members on potential system impacts and explaining technical information. Additional information gathering/research as required. EUB Decision (December 19, 2008) 7

11 Preparing and filing affidavit evidence/ expert report. Assisting counsel in preparing information requests and analyzing responses. Testifying at the oral hearing (one day). Monitoring proceedings in person (one day) and by way of transcripts (remainder of hearing). Assisting counsel with final argument and reply submissions. In its budget, Lavesta characterized Mr. Anglin as both a research consultant and expert and calculated his anticipated fees to be approximately $40,000 based on the Board s highest hourly rate of $ In its October 12, 2006 cost claim, Lavesta described Mr. Anglin s assistance as professional/expert and stated that it was claiming costs for Mr. Anglin s services in the following three capacities: a) Mr. Anglin assisted Lavesta s members and individuals in the organization, preparation, presentation and arguments of their case in relation to the utility transmission need determination, planning and development. b) Mr. Anglin consulted in assisting Lavesta s members and individuals in the organization, preparation, and arguments of their case in relation to their concerns as affected persons and landholders. c) Mr. Anglin also assisted myself as counsel in matters of preparation, attendance at the Hearing, argument, and reply. You will note that I am a sole practitioner and unlike other counsel throughout this process and at the Hearing did not have the benefit of junior counsel to assist me. We have claimed those costs as a disbursement estimated in the amount of $15,000 in relation to my role as counsel. The Panel understands that the fees claimed on behalf of Mr. Anglin were apportioned as follows: $33,500 (134 for item a, $58,500 (234 for item b, and $15,000(no breakdown, however equates to 60 $250.00/hr.) for item c. In total Mr. Anglin sought to recover $107, in fees for approximately 428 hours of work performed in support of the Lavesta intervention. In it s cost claim Lavesta further explained: His (Mr. Anglin s) role in these three capacities included: i) Review of proceedings and documentation related to the Needs Application and Hearing ii) Review of exhibits and excerpts of the transcripts of the Needs Hearing. iii) Review of relevant related documents, including the AESO 10 and 20 year plan and AESO s corridor selection data. 8 EUB Decision (December 19, 2008)

12 iv) Arranging meetings of Lavesta members. v) Meeting with Lavesta members to identify issues and advise members on potential system impacts and disseminating and explaining technical and economic information. vi) Additional information gathering/research as required. vii) Assisting counsel in preparing correspondence in relation to the information requests and analyzing responses. viii) Assisting counsel in preparing correspondence in relation to the Motions. ix) Monitoring proceedings at the Review Hearing and review of Transcripts in progress at the Review Hearing. x) Assisting counsel with organization, preparation, and attendance of witnesses. xi) Assisting counsel with preparation for cross examination. viii) Testimony and Argument at the Review Hearing. ix) Assisting counsel with final argument and reply submissions. The task for this Panel is to determine whether Mr. Anglin is entitled to claim fees for those activities, as an expert, or otherwise, under the EUB s regulatory scheme for cost recovery. The Panel accepts that the work performed by Mr. Anglin related to the organization of the Lavesta Group and the preparation and presentation of its intervention to the Board. Based on the materials reviewed the Panel understands that Mr. Anglin purports to have undertaken these activities in three capacities: as an expert consultant hired by Lavesta to assist in the preparation and presentation of the Lavesta intervention (category a above) as a principle organizer of the Lavesta group and the Lavesta intervention (category b above), and as a surrogate second counsel to Mr. Bodnar (category c above). The Panel will comment on each capacity in turn. Category a Expert/Consultant ($33,500.00) In its budget submission and in its cost claim Lavesta sought to recover fees on behalf of Mr. Anglin in his capacity as a professional or expert. Accordingly to determine the reasonableness of the fees claimed in this capacity, the Panel must first determine whether Mr. Anglin performed the duties of an expert in this proceeding. Directive 31A states the following with respect to expert or consulting costs: An intervener may choose to be assisted by one or more experts when preparing and presenting a submission at a public hearing. Those experts may be registered professionals, may carry on a consulting business, and/or may be expert in a certain field due to practical experience and/or specialized training. In UCO the EUB ruled on what evidence was relevant to the proceeding on page 10, where it stated: Relevant evidence presented at the hearing related to agricultural impacts, residential impacts, environmental impacts, electrical considerations (including reliability concerns associated with multiple high voltage lines located within a single corridor or right of way), health and safety concerns, and First Nations issues. EUB Decision (December 19, 2008) 9

13 The Panel notes that Lavesta did not challenge this aspect of UCO and the Panel accepts this description of the relevant evidence as accurate. Mr. Anglin s resume was included in the materials reviewed by the Panel. At the time of the proceeding Mr. Anglin was the President of the Anglin Stewart Investment Group Inc., a position he held since The Panel understands that in this capacity Mr. Anglin was involved in the trading of currencies and commodities. From , the panel understands that Mr. Anglin was the President and Managing Director of Anglin Communication Technology in Gibsons, BC. Mr. Anglin described his role in this organization as providing leadership, strategic planning, training and development of continuing education programs for technical trades in highspeed digital data transmission. Prior to that, Mr. Anglin held various positions with the Bell system of telephone Companies from In terms of Education, Mr. Anglin has a Bachelor of Science in Business Management from New Hampshire College and a Masters of Science in Adult Education from National Louis University. Mr. Anglin also has training in electrical engineering from Bell System Engineering, but is not an electrical engineer. Mr. Anglin s resume also states I have in-depth knowledge of landowner s issues as they relate to surface rights and the Alberta Energy Utilities Board (EUB). When the opportunity arises, I voluntarily speak on behalf of landowners negotiating with oil and gas companies. Based upon its review of the materials before it, the Panel finds that Lavesta failed to establish that Mr. Anglin possessed sufficient knowledge or experience in any of the relevant subject matters addressed at the proceeding to qualify as an expert as the EUB has defined that term. The Panel notes the following in this respect: Mr. Anglin is not a professional engineer. Neither his educational background or his work history suggest that he has any formal training in the routing of major high voltage transmission lines or assessing the high level impacts associated with such an endeavor. Mr. Anglin commenced his testimony at the proceeding by stating I am not here as an expert 1 Lavesta stated in its letter to the panel dated June 9, 2008, that the decision to present Mr. Anglin s evidence as landowner evidence was a strategic decision. Considering the above and the nature of the issues raised by the proceeding, the Panel finds that Mr. Anglin lacked the necessary experience and education to be considered an expert or professional consultant at the R&V hearing. However, the Panel recognizes that the EUB has previously awarded costs to individuals who have performed the role of coordinators or representatives to large groups. Based on the materials, the Panel accepts that Mr. Anglin assumed a number of administrative and organizational duties that extended beyond what would normally be performed by a member of an intervener group. In this respect the Panel notes the large size of the Lavesta group and the efforts of Mr. Anglin in coordinating communications amongst the Lavesta members and 1 Transcripts, Volume 4, August 8, page EUB Decision (December 19, 2008)

14 between Lavesta and its lawyer. In the Panel s view, it is appropriate to compensate Mr. Anglin for the 134 hours of work he performed in this capacity. At the time of the proceeding the highest hourly rate awarded by the Board to a representative/coordinator was $ The representative/coordinator in that case had appeared before the Board on numerous occasions over many years and was familiar with and respectful of the EUB s hearing process. The Panel understands that this is the first EUB hearing that Mr. Anglin attended in this capacity and considers that the fees awarded to him must be commensurate with his experience in that role. In the Panel s view an hourly rate of $ is appropriate given his experience with the process and the level of the assistance he provided the Lavesta group. Category b Principal Organizer ($58,500.00) In UCO the ERCB determined that it would award honoraria to interveners in accordance with Directive 31A despite the fact that the R&V hearing was a utility proceeding as that term is defined in the EUB s Rules of Practice. The EUB provided the following reasons for this decision on pages 3 and 4: UPTAG and Lavesta claim honoraria for group organization, hearing preparation, and hearing attendance; LLPG/566 claim honoraria for group organization and hearing attendance. Directive 031B does not provide for the payment of honoraria to individual landowners for their participation in a utilities proceeding. However, the review hearing was granted specifically to hear evidence from landowners regarding the suitability of the West Corridor and was similar to an energy hearing to which Guide 31A, Guidelines for Energy Cost Claims would apply. In Decision , the Review Panel stated the following about the formation of UPTAG, LLPG/566, and Lavesta. The Review Panel recognizes that the formation of UPTAG, LLPG/566 Group, and Lavesta required considerable efforts by their respective members. The Review Panel notes that collectively these three groups represented about 1500 individuals and considers that their cooperation added considerably to the effectiveness of their respective presentations and to the efficiency of the hearing process. The Review Panel thanks the members of these groups for their assistance in this regard. Given the nature of the proceeding and the efficiencies created by the formation of the three landowner groups, the Board considers it appropriate to vary its practice and award honoraria for group organization, hearing preparation, and hearing attendance in accordance with the guidelines provided for in Directive 031A. Having decided to compensate Mr. Anglin for his efforts in the capacity as a representative/coordinator, the Panel finds that it would not be appropriate to additionally compensate Mr. Anglin for activities undertaken by him in his capacity as a principle organizer of Lavesta and its intervention. The Panel notes that the EUB s cost policy is not intended to fully reimburse a party for all the costs associated with an intervention, especially for activities undertaken by an individual intervener or a member of an intervener group. While the Panel recognizes that such individuals may spend considerable time preparing an intervention, the EUB s policy is to award such individuals honoraria rather than an hourly wage. In the Panel s view, participation in a public hearing of this nature is, to some degree, an altruistic exercise where interveners participate to ensure that their position is fairly represented without the expectation that all their time will be compensated for. The panel considers that when Mr. EUB Decision (December 19, 2008) 11

15 Anglin assumed the role of Lavesta s Vice-Chair, he should have accepted that he would not be compensated for some of the work he performed in that capacity. The Panel finds that the organization honoraria of $12,000 and a preparation honoraria of $8, awarded to Lavesta are reasonable, consistent with Directive 31 A and consistent with the organization and preparation honoraria awarded to the other large groups who participated in the proceeding. As noted in Decision , Lavesta was entitled to direct that some or all of the $20,000 honoraria awarded to Lavesta could have been attributed to Mr. Anglin for his efforts. Category c Surrogate Second Counsel ($15,000) As the Panel understands it, this portion of the claim relates to preparatory activities undertaken by Mr Anglin to assist Mr. Bodnar in a manner similar to that of a second counsel. The Panel finds that it must reject this claim for the following reasons: Mr. Anglin is not a lawyer or a paralegal and there is no evidence to suggest that he is qualified to provide any assistance of a legal nature to Mr. Bodnar. Lavesta failed to describe or explain how the preparatory assistance provided by Mr. Anglin in this respect differed from that provided in his other capacities. The claim was based upon an estimate by Mr. Bodnar; Lavesta did not quantify the number of hours incurred or the hourly rate charged. The claim was charged as a disbursement by Mr. Bodnar. However there is no evidence to suggest that Mr. Anglin submitted a bill to Mr. Bodnar or that Mr. Bodnar paid Mr. Anglin for these services. Having regard for the foregoing, the panel finds that Mr. Anglin is not eligible to claim costs for the work performed in this capacity. 12 EUB Decision (December 19, 2008)

16 6 ORDER IT IS HEREBY ORDERED: 1. Alberta Electric System Operator shall pay intervener costs in the amount of $13, to Mr. Joseph Anglin. 2. Alberta Electric System Operator shall record in its Hearing Cost Reserve Account the allowed intervener costs in the amount of $13, Dated in Calgary, Alberta on this 19th day of December, ALBERTA ENERGY AND UTILITIES BOARD (original signed by) John F. Curran, Q.C. Acting Member (Presiding Member) (original signed by) Donna Tingley Acting Member (originally signed by) Jim Turner Acting Member EUB Decision (December 19, 2008) 13

AltaLink Management Ltd.

AltaLink Management Ltd. Decision 21818-D01-2016 Southwest Calgary Ring Road Transmission Project November 4, 2016 Alberta Utilities Commission Decision 21818-D01-2016 Southwest Calgary Ring Road Transmission Project Proceeding

More information

Chief Mountain Gas Co-op Ltd. and County of Cardston

Chief Mountain Gas Co-op Ltd. and County of Cardston Utility Cost Order 2008-067 Chief Mountain Gas Co-op Ltd. and County of Cardston Cost Awards ALBERTA UTILITIES COMMISSION Utility Cost Order 2008-067: Chief Mountain Gas Co-op Ltd. and Cardston County

More information

Decision to Issue a Declaration Naming James W. Glover Pursuant to Section 106 of the Oil and Gas Conservation Act

Decision to Issue a Declaration Naming James W. Glover Pursuant to Section 106 of the Oil and Gas Conservation Act Decision 2006-103 Decision to Issue a Declaration Naming Pursuant to Section 106 of the Oil and Gas Conservation Act October 24, 2006 ALBERTA ENERGY AND UTILITIES BOARD Decision 2006-103: Declaration Naming

More information

Utility Asset Disposition

Utility Asset Disposition Decision 2014-013 Utility Asset Disposition Costs Award January 17, 2014 The Alberta Utilities Commission Decision 2014-013: Utility Asset Disposition Costs Award Application Nos. 1609440, 1609442, 1609445,

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 2011-501 Alberta Electric System Operator Approval of Alberta reliability standard BAL-002-AB-1 December 20, 2011 The Alberta Utilities Commission Decision 2011-501: Alberta Electric System Operator

More information

Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding

Rebasing for the PBR Plans for Alberta Electric and Gas Distribution Utilities. First Compliance Proceeding Decision 23245-D01-2018 Rebasing for the 2018-2022 PBR Plans for Alberta Electric and Gas Distribution Utilities April 27, 2018 Alberta Utilities Commission Decision 23245-D01-2018 Rebasing for the 2018-2022

More information

Decision D

Decision D Decision 22190-D01-2016 Power Renewable Energy Corporation, Alberta Electric System Operator and AltaLink Management Ltd. Jenner Wind Power Project and Interconnection Proceeding 21394 Request for review

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 21717-D01-2016 Distribution 2015-2017 Performance-Based Regulation- Negotiated Settlement Application and Interim X Factor September 26, 2016 Alberta Utilities Commission Decision 21717-D01-2016

More information

ENMAX Power Corporation

ENMAX Power Corporation Decision 23798-D01-2018 ENMAX No. 36 Substation Transformer Capacity Upgrade August 21, 2018 Alberta Utilities Commission Decision 23798-D01-2018 ENMAX No. 36 Substation Transformer Capacity Upgrade Proceeding

More information

Decision D ATCO Electric Ltd Annual Performance-Based Regulation Rate Adjustment Filing. Costs Award

Decision D ATCO Electric Ltd Annual Performance-Based Regulation Rate Adjustment Filing. Costs Award Decision 22281-D01-2017 2017 Annual Performance-Based Regulation Rate Adjustment Filing February 10, 2017 Decision 22281-D01-2017 2017 Annual Performance-Based Regulation Rate Adjustment Filing Proceeding

More information

Salt Box Coulee Water Supply Company Ltd. Customer Complaints - Infrastructure Repair Expense

Salt Box Coulee Water Supply Company Ltd. Customer Complaints - Infrastructure Repair Expense Decision 23401-D01-2018 Customer Complaints - Infrastructure Repair Expense October 22, 2018 Alberta Utilities Commission Decision 23401-D01-2018 Customer Complaints Infrastructure Repair Expense Proceeding

More information

Alberta Electric System Operator. Provost to Edgerton and Nilrem to Vermilion Transmission System Reinforcement Needs Identification Document

Alberta Electric System Operator. Provost to Edgerton and Nilrem to Vermilion Transmission System Reinforcement Needs Identification Document Decision 23137-D01-2018 Provost to Edgerton and Nilrem to Vermilion Transmission System Reinforcement March 8, 2018 Alberta Utilities Commission Decision 23137-D01-2018 Provost to Edgerton and Nilrem to

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 20509-D01-2015 Approval of Alberta reliability standard BAL-002-WECC-AB1-2 June 26, 2015 Alberta Utilities Commission Decision 20509-D01-2015 Approval of Alberta reliability standard BAL-002-WECC-AB1-2

More information

Alberta Electric System Operator

Alberta Electric System Operator Decision 23917-D01-2018 Rejection of Reliability Standard MOD-026-1 November 5, 2018 Alberta Utilities Commission Decision 23917-D01-2018 Rejection of Reliability Standard MOD-026-1 Proceeding 23917 Application

More information

RULES OF PRACTICE OF THE NATURAL RESOURCES CONSERVATION BOARD REGULATION

RULES OF PRACTICE OF THE NATURAL RESOURCES CONSERVATION BOARD REGULATION Province of Alberta NATURAL RESOURCES CONSERVATION BOARD ACT RULES OF PRACTICE OF THE NATURAL RESOURCES CONSERVATION BOARD REGULATION Alberta Regulation 77/2005 With amendments up to and including Alberta

More information

Rule 8400 Rules of Practice and Procedure GENERAL Introduction Definitions General Principles

Rule 8400 Rules of Practice and Procedure GENERAL Introduction Definitions General Principles Rule 8400 Rules of Practice and Procedure GENERAL 8401. Introduction (1) The Rules of Practice and Procedure (the Rules of Procedure ) set out the rules that govern the conduct of IIROC s enforcement proceedings

More information

PROCEDURAL GUIDELINES FOR HEARINGS BEFORE THE MINING AND LANDS COMMISSIONER

PROCEDURAL GUIDELINES FOR HEARINGS BEFORE THE MINING AND LANDS COMMISSIONER PROCEDURAL GUIDELINES FOR HEARINGS BEFORE THE MINING AND LANDS COMMISSIONER Office of the Mining and Lands Commissioner Box 330, 24th Floor, 700 Bay Street Toronto, Ontario M5G 126 Table of Contents PROCEDURAL

More information

REVOKED AS OF APRIL 11, 2016

REVOKED AS OF APRIL 11, 2016 MSA Hearing Procedures Table of Contents PART 1 INTERPRETATION 1 Definitions 2 Application of Procedures PART 2 GENERAL MATTERS 3 Directions 4 Setting of time limits and extending or abridging time 5 Variation

More information

Declaration Pursuant to Section 106 of the Oil and Gas Conservation Act

Declaration Pursuant to Section 106 of the Oil and Gas Conservation Act Decision 2005-040 Declaration Pursuant to Section 106 of the Oil and Gas Conservation Act May 3, 2005 ALBERTA ENERGY AND UTILITIES BOARD Decision 2005-040: May 3, 2005 Published by Alberta Energy and Utilities

More information

Central Alberta Rural Electrification Association Limited

Central Alberta Rural Electrification Association Limited Decision 2012-181 Central Alberta Rural Electrification Association Limited Application for a Declaration under the Hydro and Electric Energy Act July 4, 2012 The Alberta Utilities Commission Decision

More information

THE COURTS ACT. Rules made by the Chief Justice, after consultation with the Rules Committee and the Judges, under section 198 of the Courts Act

THE COURTS ACT. Rules made by the Chief Justice, after consultation with the Rules Committee and the Judges, under section 198 of the Courts Act THE COURTS ACT Rules made by the Chief Justice, after consultation with the Rules Committee and the Judges, under section 198 of the Courts Act 1. Title These rules may be cited as the Supreme Court (International

More information

LAW SOCIETY OF ALBERTA IN THE MATTER OF THE LEGAL PROFESSION ACT; AND

LAW SOCIETY OF ALBERTA IN THE MATTER OF THE LEGAL PROFESSION ACT; AND LAW SOCIETY OF ALBERTA IN THE MATTER OF THE LEGAL PROFESSION ACT; AND IN THE MATTER OF A HEARING REGARDING THE CONDUCT OF GEORGE ROSZLER A MEMBER OF THE LAW SOCIETY OF ALBERTA Single Bencher Hearing Committee:

More information

Transmission Common Group Application

Transmission Common Group Application Decision 22632-D01-2017 Transmission Common Group Application November 2, 2017 Alberta Utilities Commission Decision 22632-D01-2017 Transmission Common Group Application Proceeding 22632 November 2, 2017

More information

Riverview Substation Project

Riverview Substation Project Decision 23128-D01-2018 Alberta Electric System Operator Needs Identification Document Application EPCOR Distribution & Transmission Inc. Facility Applications AltaLink Management Ltd. Interconnection

More information

REPORT OF THE HEARING COMMITTEE

REPORT OF THE HEARING COMMITTEE IN THE MATTER OF THE LEGAL PROFESSION ACT AND IN THE MATTER OF A HEARING REGARDING THE CONDUCT OF KENT WONG A MEMBER OF THE LAW SOCIETY OF ALBERTA REPORT OF THE HEARING COMMITTEE [1] On January 29, 2007

More information

ENERGY RESOURCES CONSERVATION ACT

ENERGY RESOURCES CONSERVATION ACT Province of Alberta ENERGY RESOURCES CONSERVATION ACT Revised Statutes of Alberta 2000 Chapter E-10 Current as of December 2, 2010 Office Consolidation Published by Alberta Queen s Printer Alberta Queen

More information

Decision D FortisAlberta Inc. Application for Orders Confirming Boundaries of FortisAlberta Inc. Exclusive Municipal Franchise Areas

Decision D FortisAlberta Inc. Application for Orders Confirming Boundaries of FortisAlberta Inc. Exclusive Municipal Franchise Areas Decision 22164-D01-2018 Application for Orders Confirming Boundaries of Exclusive Municipal Franchise Areas July 16, 2018 Alberta Utilities Commission Decision 22164-D01-2018 Application for Orders Confirming

More information

THE LAW SOCIETY OF ALBERTA. IN THE MATTER OF THE LEGAL PROFESSION ACT, RSA 2000, c L-8, - and -

THE LAW SOCIETY OF ALBERTA. IN THE MATTER OF THE LEGAL PROFESSION ACT, RSA 2000, c L-8, - and - THE LAW SOCIETY OF ALBERTA IN THE MATTER OF THE LEGAL PROFESSION ACT, RSA 2000, c L-8, - and - IN THE MATTER OF A HEARING REGARDING THE CONDUCT OF RICHARD GLENN, A MEMBER OF THE LAW SOCIETY OF ALBERTA

More information

COURT OF QUEEN S BENCH ACT

COURT OF QUEEN S BENCH ACT Province of Alberta COURT OF QUEEN S BENCH ACT Revised Statutes of Alberta 2000 Current as of March 30, 2015 Office Consolidation Published by Alberta Queen s Printer Alberta Queen s Printer Suite 700,

More information

RESPONSIBLE ENERGY DEVELOPMENT ACT

RESPONSIBLE ENERGY DEVELOPMENT ACT Province of Alberta RESPONSIBLE ENERGY DEVELOPMENT ACT Statutes of Alberta, Current as of December 17, 2014 Office Consolidation Published by Alberta Queen s Printer Alberta Queen s Printer Suite 700,

More information

COURT OF APPEAL RULES TABLE OF CONTENTS

COURT OF APPEAL RULES TABLE OF CONTENTS Court of Appeal Rules COURT OF APPEAL RULES TABLE OF CONTENTS APPEALS TO THE COURT OF APPEAL...11.1.3 Definitions, 501...11.1.3 Sittings, 502...11.1.3 Chief Justice to preside, 503...11.1.3 Adjournment

More information

ARBITRATION RULES FOR THE TRANSPORTATION ADR COUNCIL

ARBITRATION RULES FOR THE TRANSPORTATION ADR COUNCIL ARBITRATION RULES FOR THE TRANSPORTATION ADR COUNCIL TABLE OF CONTENTS I. THE RULES AS PART OF THE ARBITRATION AGREEMENT PAGES 1.1 Application... 1 1.2 Scope... 1 II. TRIBUNALS AND ADMINISTRATION 2.1 Name

More information

British Columbia. Health Professions Review Board. Rules of Practice and Procedure for Reviews under the Health Professions Act, R.S.B.C. 1996, c.

British Columbia. Health Professions Review Board. Rules of Practice and Procedure for Reviews under the Health Professions Act, R.S.B.C. 1996, c. British Columbia Health Professions Review Board Rules of Practice and Procedure for Reviews under the Health Professions Act, R.S.B.C. 1996, c. 183 These rules for reviews to the Health Professions Review

More information

Cochrane Lakes Gas Co-op Ltd.

Cochrane Lakes Gas Co-op Ltd. Decision 2009-213 Interim Order Compelling Gas Service November 10, 2009 ALBERTA UTILITIES COMMISSION Decision 2009-213: Interim Order Compelling Gas Service Application No. 1605607 November 10, 2009 Published

More information

Consolidated Arbitration Rules

Consolidated Arbitration Rules Consolidated Arbitration Rules THE LEADING PROVIDER OF ADR SERVICES 1. Applicability of Rules The parties to a dispute shall be deemed to have made these Consolidated Arbitration Rules a part of their

More information

The Small Claims Act, 2016

The Small Claims Act, 2016 1 SMALL CLAIMS, 2016 c S-50.12 The Small Claims Act, 2016 being Chapter S-50.12 of The Statutes of Saskatchewan, 2016 (effective January 1, 2018). *NOTE: Pursuant to subsection 33(1) of The Interpretation

More information

June 7, 2018 FILED ELECTRONICALLY.

June 7, 2018 FILED ELECTRONICALLY. Capital Power Corporation 1200 10423 101 Street NW Edmonton, AB T5H 0E9 www.capitalpower.com June 7, 2018 FILED ELECTRONICALLY capacitymarket@auc.ab.ca Alberta Utilities Commission Eau Claire Tower 1400,

More information

- 1 - Questions? Call:

- 1 - Questions? Call: Patrick Sinay, et al. v. Essendant Co., et al. Superior Court of the State of California, County of Los Angeles, Case No. BC651043 ATTENTION: ALL CURRENT AND FORMER HOURLY-PAID OR NON-EXEMPT EMPLOYEES

More information

IN THE MATTER OF THE LEGAL PROFESSIONS ACT AND IN THE MATTER OF A HEARING REGARDING THE CONDUCT OF MARK FEEHAN, A MEMBER OF THE LAW SOCIETY OF ALBERTA

IN THE MATTER OF THE LEGAL PROFESSIONS ACT AND IN THE MATTER OF A HEARING REGARDING THE CONDUCT OF MARK FEEHAN, A MEMBER OF THE LAW SOCIETY OF ALBERTA IN THE MATTER OF THE LEGAL PROFESSIONS ACT AND IN THE MATTER OF A HEARING REGARDING THE CONDUCT OF MARK FEEHAN, A MEMBER OF THE LAW SOCIETY OF ALBERTA REPORT OF THE HEARING COMMITTEE I. INTRODUCTION 1.

More information

LAW SOCIETY OF ALBERTA IN THE MATTER OF THE LEGAL PROFESSION ACT; AND

LAW SOCIETY OF ALBERTA IN THE MATTER OF THE LEGAL PROFESSION ACT; AND LAW SOCIETY OF ALBERTA IN THE MATTER OF THE LEGAL PROFESSION ACT; AND IN THE MATTER OF A HEARING REGARDING THE CONDUCT OF DONNA HALLETT A MEMBER OF THE LAW SOCIETY OF ALBERTA Single Bencher Hearing Committee:

More information

THE LAW SOCIETY OF ALBERTA HEARING COMMITTEE REPORT

THE LAW SOCIETY OF ALBERTA HEARING COMMITTEE REPORT THE LAW SOCIETY OF ALBERTA HEARING COMMITTEE REPORT Law Society File No.: HE20110049 IN THE MATTER OF THE LEGAL PROFESSION ACT, R.S.A. 2000, C. L-8 AND IN THE MATTER OF A HEARING REGARDING THE CONDUCT

More information

File No. 185-A February 2003 T0: ALL INTERESTED PARTIES

File No. 185-A February 2003 T0: ALL INTERESTED PARTIES File No. 185-A000-19 7 February 2003 T0: ALL INTERESTED PARTIES Update of the Electricity Memorandum of Guidance to Interested Parties Concerning Full Implementation of the September 1988 Canadian Electricity

More information

Enel Alberta Wind Inc. General Partner of the Castle Rock Ridge Limited Partnership

Enel Alberta Wind Inc. General Partner of the Castle Rock Ridge Limited Partnership Decision 22367-D01-2017 General Partner of the Castle Rock Ridge Limited Partnership December 23, 2017 Alberta Utilities Commission Decision 22367-D01-2017 General Partner of the Castle Rock Ridge Limited

More information

STREET SW EDMONTON, AB T6X 1E9 Phone: Fax: SURFACE RIGHTS BOARD RULES

STREET SW EDMONTON, AB T6X 1E9 Phone: Fax: SURFACE RIGHTS BOARD RULES 1229-91 STREET SW EDMONTON, AB T6X 1E9 Phone: 780-427-2444 Fax: 780-427-5798 SURFACE RIGHTS BOARD RULES RULES OF THE SURFACE RIGHTS BOARD TABLE OF CONTENTS Rule # PART 1: PURPOSE, APPLICATION OF RULES,

More information

AMERICAN ARBITRATION ASSOCIATION

AMERICAN ARBITRATION ASSOCIATION USAGE NOTE: Following our preliminary hearing, I commonly enter a scheduling order of this sort in all AAA-administered arbitrations. A similar form is used in NASD-administered arbitrations and in private

More information

Wills and Trusts Arbitration RULES

Wills and Trusts Arbitration RULES Wills and Trusts Arbitration RULES Effective September 15, 2005 Introduction Standard Arbitration Clause Administrative Fees Wills and Trusts Arbitration Rules 1. Incorporation of These Rules into a Will

More information

ICDR INTERNATIONAL CENTRE FOR DISPUTE RESOLUTION ARBITRATION RULES

ICDR INTERNATIONAL CENTRE FOR DISPUTE RESOLUTION ARBITRATION RULES APPENDIX 3.8 ICDR INTERNATIONAL CENTRE FOR DISPUTE RESOLUTION ARBITRATION RULES (Rules Amended and Effective June 1, 2009) (Fee Schedule Amended and Effective June 1, 2010) Article 1 a. Where parties have

More information

The General Teaching Council for Scotland Fitness to Teach Rules 2017 These Rules are available in alternative formats on request

The General Teaching Council for Scotland Fitness to Teach Rules 2017 These Rules are available in alternative formats on request DRIVING FORWARD PROFESSIONAL STANDARDS FOR TEACHERS The General Teaching Council for Scotland Fitness to Teach Rules 2017 These Rules are available in alternative formats on request Table of Contents

More information

Toronto Local Appeal Body Public Guide

Toronto Local Appeal Body Public Guide Toronto Local Appeal Body Public Guide Revised on August 15, 2017 Contact information: Toronto Local Appeal Body 40 Orchard View Boulevard Suite 211 Toronto, ON M4R 1B9 Tel: (416) 392-4697 Web: www.toronto.ca/tlab

More information

CRIMINAL RULES OF THE ONTARIO COURT OF JUSTICE RULE 1 GENERAL. (2) Dealing with proceedings justly and efficiently includes

CRIMINAL RULES OF THE ONTARIO COURT OF JUSTICE RULE 1 GENERAL. (2) Dealing with proceedings justly and efficiently includes CRIMINAL RULES OF THE ONTARIO COURT OF JUSTICE RULE 1 GENERAL Fundamental objective 1.1 (1) The fundamental objective of these rules is to ensure that proceedings in the Ontario Court of Justice are dealt

More information

NOVA SCOTIA PROVINCIAL COURT RULES

NOVA SCOTIA PROVINCIAL COURT RULES NOVA SCOTIA PROVINCIAL COURT RULES (Implementation Date: January 1, 2013) TABLE OF CONTENTS Rule 1 General 1.1 Fundamental Objective 1.2 Scope of Rules 1.3 Definitions Rule 2 Applications 2.1 Notice of

More information

SUPERIOR COURT OF THE STATE OF CALIFORNIA FOR THE COUNTY OF SACRAMENTO

SUPERIOR COURT OF THE STATE OF CALIFORNIA FOR THE COUNTY OF SACRAMENTO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 SUPERIOR COURT OF THE STATE OF CALIFORNIA DAVID SANTIAGO, individually, and on behalf of all others similarly situated, vs. FOR THE

More information

AUC Rule 017: June 14, proposed changes

AUC Rule 017: June 14, proposed changes AUC Rule 017: June 14, proposed changes Stakeholder comments: Alberta Electric System Operator (AESO), AltaLink Management Ltd. (AltaLink), ATCO Electricity Generation (ATCO), Capital Power Corporation

More information

PRACTICE DIRECTIVES FOR CONTESTED APPLICATIONS IN THE PROVINCIAL COURT OF MANITOBA

PRACTICE DIRECTIVES FOR CONTESTED APPLICATIONS IN THE PROVINCIAL COURT OF MANITOBA PRACTICE DIRECTIVES FOR CONTESTED APPLICATIONS IN THE PROVINCIAL COURT OF MANITOBA November 4, 2013 TABLE OF CONTENTS PREAMBLE TO PRACTICE DIRECTIVES FOR CONTESTED APPLICATIONS IN THE PROVINCIAL COURT

More information

RULES OF PROCEDURE OF THE DISCIPLINE COMMITTEE OF THE COLLEGE OF REGISTERED PSYCHOTHERAPISTS AND REGISTERED MENTAL HEALTH THERAPISTS OF ONTARIO INDEX

RULES OF PROCEDURE OF THE DISCIPLINE COMMITTEE OF THE COLLEGE OF REGISTERED PSYCHOTHERAPISTS AND REGISTERED MENTAL HEALTH THERAPISTS OF ONTARIO INDEX RULES OF PROCEDURE OF THE DISCIPLINE COMMITTEE OF THE COLLEGE OF REGISTERED PSYCHOTHERAPISTS AND REGISTERED MENTAL HEALTH THERAPISTS OF ONTARIO INDEX RULE 1 - INTERPRETATION AND APPLICATION... 3 1.01 Definitions...

More information

INFORMATION BULLETIN

INFORMATION BULLETIN INFORMATION BULLETIN #17 REGULATION OF STRIKES, LOCKOUTS AND PICKETING I. INTRODUCTION The Labour Relations Code imposes certain requirements on parties before and during strike or lockout action. This

More information

STATE OF MICHIGAN IN THE CIRCUIT COURT FOR THE COUNTY OF JACKSON BUSINESS COURT DIVISION. via telephone (check one) /

STATE OF MICHIGAN IN THE CIRCUIT COURT FOR THE COUNTY OF JACKSON BUSINESS COURT DIVISION. via telephone (check one) / STATE OF MICHIGAN IN THE CIRCUIT COURT FOR THE COUNTY OF JACKSON BUSINESS COURT DIVISION PLAINTIFF NAME v. DEFENDANT NAME Case No. Hon. Richard N. LaFlamme / PLAINTIFF S COUNSEL NAME, ADDRESS, PHONE AND

More information

GENERAL RULES ABOUT COSTS

GENERAL RULES ABOUT COSTS PRACTICE DIRECTION PART 44 DIRECTIONS RELATING TO PART 44 GENERAL RULES ABOUT COSTS SECTION 7 SOLICITOR S DUTY TO NOTIFY CLIENT: RULE 44.2 7.1 For the purposes of rule 44.2 client includes a party for

More information

AGREEMENT To Establish a Joint Review Panel for the Grassy Mountain Coal Project Between

AGREEMENT To Establish a Joint Review Panel for the Grassy Mountain Coal Project Between AGREEMENT To Establish a Joint Review Panel for the Grassy Mountain Coal Project Between The Minister of the Environment, Canada - and - The Alberta Energy Regulator, Alberta PREAMBLE WHEREAS the Alberta

More information

Costs Order Value Creation Inc. Application to Amend OSCA and EPEA Approvals W4M. Costs Awards

Costs Order Value Creation Inc. Application to Amend OSCA and EPEA Approvals W4M. Costs Awards Costs Order 2018-02 Value Creation Inc. Application to Amend OSCA and EPEA Approvals 10-056-21W4M Costs Awards July 31, 2018 Alberta Energy Regulator Costs Order 2018-02: Value Creation Inc., Application

More information

Brooks Heat and Power Ltd.

Brooks Heat and Power Ltd. Decision 23028-D01-2017 14.9-Megawatt Power Plant Time Extension October 24, 2017 Alberta Utilities Commission Decision 23028-D01-2017 14.9-Megawatt Power Plant Time Extension Proceeding 23028 Application

More information

August 11, To: Parties currently registered on Proceeding 21030

August 11, To: Parties currently registered on Proceeding 21030 August 11, 2016 To: Parties currently registered on Proceeding 21030 Fort McMurray West 500-kV Transmission Project Proceeding 21030 Applications 21030-A001 to 21030-A015 Ruling on standing and participation

More information

Case 1:15-cv WHP Document 148 Filed 06/28/18 Page 1 of 14

Case 1:15-cv WHP Document 148 Filed 06/28/18 Page 1 of 14 Case 1:15-cv-01249-WHP Document 148 Filed 06/28/18 Page 1 of 14 UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK IN RE VIRTUS INVESTMENT PARTNERS, INC. SECURITIES LITIGATION Case No. 15-cv-1249

More information

Pembina Pipeline Corporation

Pembina Pipeline Corporation Costs Order 2016-003 Pembina Pipeline Corporation Applications for Two Pipelines Fox Creek to Namao Pipeline Expansion Project Costs Award Alexander First Nation October 5, 2016 Alberta Energy Regulator

More information

Commercial Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex Commercial Disputes)

Commercial Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex Commercial Disputes) Commercial Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex Commercial Disputes) Rules Amended and Effective October 1, 2013 Fee Schedule Amended and Effective June 1,

More information

ATTENTION: CURRENT AND FORMER EMPLOYEES OF LQ MANAGEMENT L.L.C. ("LA QUINTA") YOU MAY RECEIVE MONEY FROM THIS CLASS ACTION SETTLEMENT

ATTENTION: CURRENT AND FORMER EMPLOYEES OF LQ MANAGEMENT L.L.C. (LA QUINTA) YOU MAY RECEIVE MONEY FROM THIS CLASS ACTION SETTLEMENT Sergio Peralta, et al. v. LQ Management L.L.C, et al. United States District Court for the Southern District of California Case No. 3:14-cv-01027-DMS-JLB ATTENTION: CURRENT AND FORMER EMPLOYEES OF LQ MANAGEMENT

More information

Clause 10.4 of the Legal Aid ACT General Panel Services Agreement requires the practitioner to comply with certain practice standards.

Clause 10.4 of the Legal Aid ACT General Panel Services Agreement requires the practitioner to comply with certain practice standards. Practice Standards About these Practice Standards The Legal Aid Commission (ACT)() has established a panel of private legal practitioners to provide legal services to legally assisted persons (the General

More information

EFFECTIVE DATE: When Published [Information outdated - Feb. 2000]

EFFECTIVE DATE: When Published [Information outdated - Feb. 2000] Financial Services Commission of Ontario Commission des services financiers de l Ontario SECTION: Procedures - Hearings INDEX NO.: P520-780 TITLE: APPROVED BY: PUBLISHED: Pre-Hearing Conference Procedures

More information

RULES FOR EXPEDITED ARBITRATION. of the Finland Chamber of Commerce

RULES FOR EXPEDITED ARBITRATION. of the Finland Chamber of Commerce RULES FOR EXPEDITED ARBITRATION of the Finland Chamber of Commerce RULES FOR EXPEDITED ARBITRATION of the Finland Chamber of Commerce The English text prevails over other language versions. TABLE OF CONTENTS

More information

National Patent Board Non-Binding Arbitration Rules TABLE OF CONTENTS

National Patent Board Non-Binding Arbitration Rules TABLE OF CONTENTS National Patent Board Non-Binding Arbitration Rules Rules Amended and Effective June 1, 2014 TABLE OF CONTENTS Important Notice...3 Introduction...3 Standard Clause...3 Submission Agreement...3 Administrative

More information

The Intellectual Property Regulation Board (incorporating The Patent Regulation Board and the Trade Mark Regulation Board)

The Intellectual Property Regulation Board (incorporating The Patent Regulation Board and the Trade Mark Regulation Board) The Intellectual Property Regulation Board (incorporating The Patent Regulation Board and the Trade Mark Regulation Board) Final Draft Disciplinary Procedure Rules The Patent Regulation Board of the Chartered

More information

EMERGENCY HEALTH SERVICES ACT

EMERGENCY HEALTH SERVICES ACT Province of Alberta Statutes of Alberta, Current as of December 15, 2017 Office Consolidation Published by Alberta Queen s Printer Alberta Queen s Printer Suite 700, Park Plaza 10611-98 Avenue Edmonton,

More information

THE RETIREMENT BOARD OF THE FIREMEN S ANNUITY AND BENEFIT FUND OF CHICAGO

THE RETIREMENT BOARD OF THE FIREMEN S ANNUITY AND BENEFIT FUND OF CHICAGO THE RETIREMENT BOARD OF THE FIREMEN S ANNUITY AND BENEFIT FUND OF CHICAGO Procedural Rules Established Pursuant to 40 ILCS 5/6-191 Governing Applications for and Administrative Hearings upon Applications

More information

ISSUING AGENCY: New Mexico Renewable Energy Transmission Authority ( Authority ). [ NMAC - N, 12/15/2011]

ISSUING AGENCY: New Mexico Renewable Energy Transmission Authority ( Authority ). [ NMAC - N, 12/15/2011] TITLE 17 CHAPTER 8 PART 3 PUBLIC UTILITIES AND UTILITY SERVICES RENEWABLE ENERGY EMINENT DOMAIN 17.8.3.1 ISSUING AGENCY: New Mexico Renewable Energy Transmission Authority ( Authority ). [17.8.3.1 NMAC

More information

JAMS International Arbitration Rules & Procedures

JAMS International Arbitration Rules & Procedures JAMS International Arbitration Rules & Procedures Effective September 1, 2016 JAMS INTERNATIONAL ARBITRATION RULES JAMS International and JAMS provide arbitration and mediation services from Resolution

More information

FREEDOM OF INFORMATION ACT PROCEDURES AND GUIDELINES

FREEDOM OF INFORMATION ACT PROCEDURES AND GUIDELINES FREEDOM OF INFORMATION ACT PROCEDURES AND GUIDELINES I. INTRODUCTION II. The Michigan Freedom of Information Act, 1976 P.A. 442, MCL 15.231 et seq., ( FOIA or the Act ) was enacted by the Michigan Legislature

More information

Case Document 3609 Filed in TXSB on 09/14/15 Page 1 of 17

Case Document 3609 Filed in TXSB on 09/14/15 Page 1 of 17 Case 12-36187 Document 3609 Filed in TXSB on 09/14/15 Page 1 of 17 IN THE UNITED STATES BANKRUPTCY COURT FOR THE SOUTHERN DISTRICT OF TEXAS HOUSTON DIVISION IN RE: ATP OIL & GAS CORPORATION CASE NO. 12-36187

More information

NOTICE OF CLASS ACTION SETTLEMENT AND FINAL APPROVAL HEARING YOUR ESTIMATED PAYMENT INFORMATION

NOTICE OF CLASS ACTION SETTLEMENT AND FINAL APPROVAL HEARING YOUR ESTIMATED PAYMENT INFORMATION SUPERIOR COURT OF CALIFORNIA FOR THE COUNTY OF LOS ANGELES ARTHUR HATTENSTY, ET AL. V. BESSIRE AND CASENHISER, INC., ET AL. CASE NO. BC540657 A court authorized this notice. This is not a solicitation

More information

Wills and Trusts Arbitration RULES

Wills and Trusts Arbitration RULES Wills and Trusts Arbitration RULES Rules Amended and Effective June 1, 2009 Introduction Standard Arbitration Clause Administrative Fees Wills and Trusts Arbitration Rules 1. Incorporation of These Rules

More information

Danell Behrens v. Landmark Credit Union NOTICE OF PENDING CLASS ACTION AND PROPOSED SETTLEMENT

Danell Behrens v. Landmark Credit Union NOTICE OF PENDING CLASS ACTION AND PROPOSED SETTLEMENT Danell Behrens v. Landmark Credit Union NOTICE OF PENDING CLASS ACTION AND PROPOSED SETTLEMENT READ THIS NOTICE FULLY AND CAREFULLY; THE PROPOSED SETTLEMENT MAY AFFECT YOUR RIGHTS! IF YOU HAD A CHECKING

More information

PART I CITATION AND INTERPRETATION 1. Citation Interpretation 4

PART I CITATION AND INTERPRETATION 1. Citation Interpretation 4 DISCIPLINARY COMMITTEE PROCEEDINGS RULES* (Issued September 1986; revised September 2004 (name changed); further revised September 2006) Rule PART I Page CITATION AND INTERPRETATION 1. Citation. 4 2. Interpretation

More information

BY-LAWS OF INTERNATIONAL SWAPS AND DERIVATIVES ASSOCIATION, INC.

BY-LAWS OF INTERNATIONAL SWAPS AND DERIVATIVES ASSOCIATION, INC. BY-LAWS OF INTERNATIONAL SWAPS AND DERIVATIVES ASSOCIATION, INC. (As Amended through August 1, 2017) ARTICLE I - OFFICES The International Swaps and Derivatives Association, Inc. (the "Association"), shall

More information

THE ALBERTA GAZETTE, PART II, JULY 14, Alberta Regulation 102/2001. Oil and Gas Conservation Act OIL AND GAS CONSERVATION AMENDMENT REGULATION

THE ALBERTA GAZETTE, PART II, JULY 14, Alberta Regulation 102/2001. Oil and Gas Conservation Act OIL AND GAS CONSERVATION AMENDMENT REGULATION Alberta Regulation 102/2001 Oil and Gas Conservation Act OIL AND GAS CONSERVATION AMENDMENT REGULATION Filed: June 19, 2001 Made by the Alberta Energy and Utilities Board on June 15, 2001 pursuant to section

More information

Rules of the Legal Fee Arbitration Board of the Massachusetts Bar Association As Amended and Effective September 1, 2012

Rules of the Legal Fee Arbitration Board of the Massachusetts Bar Association As Amended and Effective September 1, 2012 Rules of the Legal Fee Arbitration Board of the Massachusetts Bar Association As Amended and Effective September 1, 2012 20 West Street Boston, MA 02111-1218 TELEPHONE (617) 338-0500 FAX (617) 338-0550

More information

ADR CODE OF PROCEDURE

ADR CODE OF PROCEDURE Last Revised 12/1/2006 ADR CODE OF PROCEDURE Rules & Procedures for Arbitration RULE 1: SCOPE OF RULES A. The arbitration Rules and Procedures ( Rules ) govern binding arbitration of disputes or claims

More information

The Child and Family Services Act

The Child and Family Services Act 1 The Child and Family Services Act being Chapter C-7.2 of the Statutes of Saskatchewan, 1989-90 (consult Table of Saskatchewan Statutes for effective date) as amended by the Statutes of Saskatchewan,

More information

v. No. D-202-CV MAILED NOTICE OF CLASS ACTION SETTLEMENT

v. No. D-202-CV MAILED NOTICE OF CLASS ACTION SETTLEMENT STATE OF NEW MEXICO COUNTY OF BERNALILLO SECOND JUDICIAL DISTRICT VINCENT R. GARCIA, ROBERTO BORBON, MARK MORAN, and KENNETH A. ZIEGLER, on behalf of Themselves and all other similarly situated, Plaintiffs,

More information

Case 1:15-cv ELR Document 60 Filed 09/08/16 Page 1 of 21

Case 1:15-cv ELR Document 60 Filed 09/08/16 Page 1 of 21 Case 1:15-cv-04316-ELR Document 60 Filed 09/08/16 Page 1 of 21 IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF GEORGIA ATLANTA DIVISION BRIDGET SMITH, RENE TAN, VICTOR CASTANEDA, KRISADA

More information

ISLAND REGULATORY AND APPEALS COMMISSION ACT

ISLAND REGULATORY AND APPEALS COMMISSION ACT c t ISLAND REGULATORY AND APPEALS COMMISSION ACT PLEASE NOTE This document, prepared by the Legislative Counsel Office, is an office consolidation of this Act, current to December 15, 2016. It is intended

More information

The Youth Drug Detoxification and Stabilization Act

The Youth Drug Detoxification and Stabilization Act YOUTH DRUG DETOXIFICATION 1 The Youth Drug Detoxification and Stabilization Act being Chapter Y-1.1* of The Statutes of Saskatchewan, 2005 (effective April 1, 2006) as amended by The Statutes of Saskatchewan,

More information

AGENDA. 5. Executive Director s Report Thomas C. Chatmon Jr., Executive Director

AGENDA. 5. Executive Director s Report Thomas C. Chatmon Jr., Executive Director DDB MEETING NOTICE WELCOME! We are very glad you have joined us for today's meeting. If you are not on the agenda and would like to speak at the meeting and address the Board, please fill out an appearance

More information

Roster Lawyers Tariff of Fees

Roster Lawyers Tariff of Fees Roster Lawyers Tariff of Fees December 7, 2015 Schedule 2 Roster Lawyers Tariff of Fees Table of Contents 1. Criminal Certificates 20 2. Criminal Appeal Certificates 27 3. Civil Certificates 30 4. Administrative

More information

STUDENT LEGAL SERVICES TRAFFIC OFFENCES A GUIDE TO THE LAW IN ALBERTA REGARDING OF EDMONTON COPYRIGHT AND DISCLAIMER

STUDENT LEGAL SERVICES TRAFFIC OFFENCES A GUIDE TO THE LAW IN ALBERTA REGARDING OF EDMONTON COPYRIGHT AND DISCLAIMER COPYRIGHT AND DISCLAIMER A GUIDE TO THE LAW IN ALBERTA REGARDING TRAFFIC version: 2009 STUDENT LEGAL SERVICES OF EDMONTON GENERAL All information is provided for general knowledge purposes only and is

More information

Josefina Hernandez v. Logix Federal Credit Union NOTICE OF PENDING CLASS ACTION AND PROPOSED SETTLEMENT

Josefina Hernandez v. Logix Federal Credit Union NOTICE OF PENDING CLASS ACTION AND PROPOSED SETTLEMENT Josefina Hernandez v. Logix Federal Credit Union NOTICE OF PENDING CLASS ACTION AND PROPOSED SETTLEMENT READ THIS NOTICE FULLY AND CAREFULLY; THE PROPOSED SETTLEMENT MAY AFFECT YOUR RIGHTS! IF YOU HAD

More information

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK NOTICE OF PROPOSED SETTLEMENT OF CLASS ACTION

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK NOTICE OF PROPOSED SETTLEMENT OF CLASS ACTION UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK x IN RE REVLON, INC. SECURITIES : Master File No. LITIGATION : 99-CV-10192 (SHS) x This Document Relates to: : All Actions : x NOTICE OF PROPOSED

More information

ORDER PRELIMINARILY APPROVING CLASS SETTLEMENT, DIRECTING THE ISSUANCE OF CLASS NOTICE AND SCHEDULING A FINAL FAIRNESS HEARING

ORDER PRELIMINARILY APPROVING CLASS SETTLEMENT, DIRECTING THE ISSUANCE OF CLASS NOTICE AND SCHEDULING A FINAL FAIRNESS HEARING . FILED IN MY OFFICE DISTRICT COURT CLERK 8/29/2014 2:36:24 PM STEPHEN T. PACHECO Gloria Landin STATE OF NEW MEXICO COUNTY OF SANTA FE FIRST JUDICIAL DISTRICT COURT PIDLLIS IDEAL, JOSE E. AND CLARA E.

More information

/...1 PRIVATE ARBITRATION KIT

/...1 PRIVATE ARBITRATION KIT 1007453/...1 PRIVATE ARBITRATION KIT Introduction This document contains Guidelines, Rules and a Model Agreement in respect of private arbitrations. It is designed to assist practitioners when referring

More information

ACS National Regulations. Australian Computer Society. April 2011

ACS National Regulations. Australian Computer Society. April 2011 ACS National Regulations Australian Computer Society April 2011 This page intentionally left blank Australian Computer Society National Regulations April 2011 Page 2 Contents 1. Preliminary... 5 2. Membership...

More information

THE CHARTERED INSTITUTE OF MANAGEMENT ACCOUNTANTS

THE CHARTERED INSTITUTE OF MANAGEMENT ACCOUNTANTS THE CHARTERED INSTITUTE OF MANAGEMENT ACCOUNTANTS DISCIPLINARY COMMITTEE RULES 2015 RULE CONTENT 1 Introduction 2 Interpretation 3 Jurisdiction 4 Preliminary matters; Notification of referral; Meeting

More information

ARIAS U.S. RULES FOR THE RESOLUTION OF U.S. INSURANCE AND REINSURANCE DISPUTES

ARIAS U.S. RULES FOR THE RESOLUTION OF U.S. INSURANCE AND REINSURANCE DISPUTES 1. INTRODUCTION ARIAS U.S. RULES FOR THE RESOLUTION OF U.S. INSURANCE AND REINSURANCE DISPUTES 1.1 These procedures shall be known as the ARIAS U.S. Rules for the Resolution of U.S. Insurance and Reinsurance

More information