1 IN THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM & ARUNACHAL PRADESH) ARBITRATION PETITION NO.32 OF 2015 Durga Krishna Store Private Limited, a Company incorporated under the Companies Act, 1956, having its registered Office at Club Road, Silchar , Cachar, Assam. -Versus-..Petitioner 1. The Union of India, Represented by the General Manager, N.F. Railway, Maligaon, Guwahati The Deputy Chief Engineer/Con-I, N.F. Railway, Silchar. 3. The Deputy Chief Engineer CON/Tender, N.F. Railway, Maligaon, Guwahati Respondents B E F O R E HON BLE MR. JUSTICE ARUP KUMAR GOSWAMI For the petitioner For respondents : Mr. R. Hussain, Advocate. : Mr. D.K. Dey, Standing Counsel, N.F. Railway. Date of hearing : 15 th May, Date of Judgment & Order : 30 th May, JUDGMENT & ORDER Heard Mr. R. Hussain, learned counsel for the petitioner. Also heard Mr. D.K. Dey, learned standing counsel, N.F. Railway, appearing for all the respondents. 2. By this application under Section 11 of the Arbitration and Conciliation Act, 1996 (for short, 1996 Act ), the petitioner prays for appointment of an Arbitrator. Arb. Petition No.32/2015 Page 1 of 12

2 3. The case of the petitioner as projected in the petition is that the respondents floated a tender Notice No.CON/2012/FEB/04 in tender No.CE/CON/LMG-SCL/EMB/ 2012/05 for construction of Bridge No.497 (2 X 6.10 m RCC Box), 505 (2 X 3.50 m RCC Box), 515 (2 X 5.10 m RCC Box) on alignment adjacent to MG track in between Chainage KM to 137/ KM (New Chainage) and other ancillary works in between stations Ditokcherra Damcherra in connection with LMG-SCL-GC Project. The date of opening of the tender was fixed on and the petitioner participated in the said tender process along with other tenderers. By an acceptance letter dated issued by the respondent No.3, it was communicated to the petitioner that the petitioner s negotiated offer for the work in question had been accepted at a total cost of Rs.6,69,15, By the said letter, the petitioner was authorised to commence the work so as to ensure completion of the work within 15(fifteen) months. The petitioner mobilised resources for the purpose of completion of the work. Though the petitioner was required to submit a Performance Guarantee in the form of an irrevocable bank guarantee for an amount equal to 5% of the contract value within a maximum period of 60(sixty) days, the same could not be submitted due to unavoidable circumstances but later on, on , the petitioner submitted the Bank guarantee, valid up to , which was also accepted by the respondents. On , the Deputy Chief Engineer/CON-I requested the petitioner to start the work on war footing so that the work can be completed within the stipulated period. However, in a turn of events, by a communication dated issued by the respondent No.3, the contract of the petitioner was terminated on the ground of delay in submission of Performance Guarantee. 4. Aggrieved by the aforesaid termination of the contract, the petitioner lodged a claim on for a sum of Rs.1,09,50, but the respondents failed to respond to the same. As there was a clause being Clause-45 in the Tender Documents for settlement of dispute through arbitration, the petitioner invoked Arbitration Clause by notice dated But as the respondents failed to appoint the Arbitrator within the stipulated time, recourse is taken by filing this application for appointment of an Arbitrator. 5. In the affidavit filed by the respondents, it is stated that the plea that the petitioner had mobilised resources is factually not correct since for construction of site Arb. Petition No.32/2015 Page 2 of 12

3 office, labour shed etc., over Railway land, it is necessary to obtain permission from the Railways, which the petitioner had not taken. In terms of the acceptance letter dated as well as Clause-36(a) of the Tender Documents, the petitioner was required to submit a Performance Guarantee in the form of an irrevocable bank guarantee within 30(thirty) days (60 days with penal interest of 15% per annum) of receiving the letter of acceptance and, therefore, there was no question of accepting the bank guarantee after 98(ninety-eight) days. It is stated that it was the duty of the petitioner to have started the work after receiving the acceptance letter by submitting a Performance Guarantee. The contract work with the petitioner was terminated in terms of the letter dated on failure to submit the bank guarantee within the stipulated period of time. It is asserted that the Railway authorities are authorised to terminate the contract at any stage in terms of the General Conditions of Contract, N.F. Railway, It is also asserted that there is no dispute as the claims raised by the petitioner, numbering 9(nine), are not acceptable and as there is no dispute between the parties, the question of appointment of Arbitrator does not arise. 6. Mr. Hussain, learned counsel for the petitioner has submitted that Clause-45 of the Tender Documents of the tender in question provides for settlement of disputes through arbitration, which is governed by Clauses-63 and 64 of the General Conditions of Contract, N.F. Railway, 1998 and that in the instant case, Clause-64(3)(a)(ii) thereof is attracted. It is submitted that absence of a formal agreement is of no consequence as the acceptance letter itself provides that the same will be enforceable contract in between the parties. It is submitted by him that even though the petitioner could not submit the Performance Guarantee within the stipulated time and had also not executed the formal agreement, the petitioner had started mobilizing resources and the respondent authorities had also, notwithstanding the fact that the Performance Guarantee was yet to be submitted, had asked the petitioner to proceed with the work on war footing and, therefore, termination of the contract on the ground that the Performance Guarantee was not submitted within the stipulated time, cannot withstand the scrutiny of law and, therefore, the same had given rise to a legitimate dispute. In support of his contention, he has placed reliance on the decisions of the Apex Court in UNISSI (India) Private Limited -Vs- Post Graduate Institute of Medical Education & Research, reported in (2009) 1 SCC 107, Trimex International FZE Limited, Dubai -Vs- Vedanta Aluminium Limited, India, reported in (2010) Arb. Petition No.32/2015 Page 3 of 12

4 3 SCC 1, Oil & Natural Gas Corporation Petro Additions Limited -Vs- Daelim Industrial Company Limited, Korea, reported in (2015) 13 SCC 176 and State of Uttar Pradesh & Ors. -Vs- Combined Chemicals Company Private Limited, reported in (2011) 2 SCC Abiding by the stand taken in the affidavit, Mr. Dey has vehemently argued that the petitioner having not furnished the bank guarantee within the time prescribed, which is the basis for execution of the formal contract agreement, the petitioner cannot raise any dispute with regard to termination of the contract and, therefore, there is no question of appointment of any Arbitrator. He has also submitted that in absence of a formal agreement, no arbitration can be resorted to as there is no agreement between the parties. That apart, the claims made by the petitioner are also without any basis. He has submitted with reference to Section 37 of the Indian Contract Act, 1872 that the parties to a contract must either perform or offer to perform their respective promises and in the instant case the petitioner had failed to perform its obligations although such obligation and/or performance was not dispensed with or excused. He has placed reliance on the decisions of the Apex Court in Payal Chawla Singh -Vs- Coca-Cola Company & Anr., reported in (2015) 13 SCC 699 and Jagdish Chander -Vs- Ramesh Chander & Ors., reported in (2007) 5 SCC I have considered the submissions advanced by the learned counsel appearing for the parties and have also perused the materials on record. 9. At the outset, having regard to the contours of the argument advanced by the learned counsel appearing for the parties, it will be expedient to consider Section 7 of the 1996 Act, which defines Arbitration Agreement so far as it relates to Chapter-II. Section 7(1) defines arbitration agreement to mean an agreement by the parties to submit to arbitration all or certain disputes which have arisen or which may arise between them in respect of a defined legal relationship, whether contractual or not. Section 7(2) lays down that an arbitration agreement may be in the form of an arbitration clause in a contract or in the form of a separate agreement. Section 7(3) provides that an arbitration agreement shall be in writing. Section 7(4) provides that an arbitration agreement is in writing if it is contained in (a) a document signed by the parties; (b) an exchange of letters, telex, telegrams or other means of telecommunication including communication through electronic means, which provide a Arb. Petition No.32/2015 Page 4 of 12

5 record of the agreement or (c) an exchange of statements of claim and defence in which the existence of the agreement is alleged by one party and not denied by the other. Section 7(5) provides that the reference in a contract to a document containing an arbitration clause constitutes an arbitration agreement if the contract is in writing and the reference is such as to make that arbitration clause part of the contract. 10. In Jagdish Chander (supra), the question that had fallen for consideration was as to whether Clause-16 of the Deed of Partnership providing that, if during the continuance of the partnership or at any time afterwards any dispute touching the partnership arises between the partners, the same shall be mutually decided by the partners or shall be referred for arbitration if the parties so determined, is an arbitration agreement within the meaning of Section 7 of the 1996 Act. The Supreme Court, interpreting the aforesaid Clause-16, had held that Clause-16 is not an arbitration agreement as defined under Section 7 of the 1996 Act. It was observed that if the Clause had merely said that in the event of disputes arising between the parties, they shall be referred to arbitration, it would have been an arbitration agreement but the use of the words shall be referred to arbitration if the parties so determined completely change the complexion of the provision, as it indicates that the parties are required to reach a decision as to whether the disputes should be referred to arbitration or not. The Supreme Court, at Paragraph-8 of the said judgment, also set out the principles in regard to what constitutes an arbitration agreement. The paragraph is quoted below: 8. This Court had occasion to refer to the attributes or essential elements of an arbitration agreement in K.K. Modi v. K.N. Modi, Bharat Bhushan Bansal vs. U.P. Small Industries Corporation Ltd. and Bihar State Mineral Development Corporation v. Encon Builders (I) (P) Ltd. In State of Orissa v. Damodar Das, this Court held that a clause in a contract can be construed as an 'arbitration agreement' only if an agreement to refer disputes or differences to arbitration is expressly or impliedly spelt out from the clause. We may at this juncture set out the well settled principles in regard to what constitutes an arbitration agreement: (i) The intention of the parties to enter into an arbitration agreement shall have to be gathered from the terms of the agreement. If the terms of the agreement clearly indicate an intention on the part of the parties to the agreement to refer their disputes to a private tribunal for adjudication and an Arb. Petition No.32/2015 Page 5 of 12

6 willingness to be bound by the decision of such tribunal on such disputes, it is arbitration agreement. While there is no specific form of an arbitration agreement, the words used should disclose a determination and obligation to go to arbitration and not merely contemplate the possibility of going for arbitration. Where there is merely a possibility of the parties agreeing to arbitration in future, as contrasted from an obligation to refer disputes to arbitration, there is no valid and binding arbitration agreement. (ii) Even if the words 'arbitration' and 'arbitral tribunal (or arbitrator)' are not used with reference to the process of settlement or with reference to the private tribunal which has to adjudicate upon the disputes, in a clause relating to settlement of disputes, it does not detract from the clause being an arbitration agreement if it has the attributes or elements of an arbitration agreement. They are : (a) The agreement should be in writing. (b) The parties should have agreed to refer any disputes (present or future) between them to the decision of a private tribunal. (c) The private tribunal should be empowered to adjudicate upon the disputes in an impartial manner, giving due opportunity to the parties to put forth their case before it. (d) The parties should have agreed that the decision of the Private Tribunal in respect of the disputes will be binding on them. (iii) Where the clause provides that in the event of disputes arising between the parties, the disputes shall be referred to Arbitration, it is an arbitration agreement. Where there is a specific and direct expression of intent to have the disputes settled by arbitration, it is not necessary to set out the attributes of an arbitration agreement to make it an arbitration agreement. But where the clause relating to settlement of disputes, contains words which specifically excludes any of the attributes of an arbitration agreement or contains anything that detracts from an arbitration agreement, it will not be an arbitration agreement. For example, where an agreement requires or permits an authority to decide a claim or dispute without hearing, or requires the authority to act in the interests of only one of the parties, or provides that the decision of the Authority will not be final and binding on the parties, or that if either party is not satisfied with the decision of the Authority, he may file a civil suit seeking relief, it cannot be termed as an arbitration agreement. Arb. Petition No.32/2015 Page 6 of 12

7 (iv) But mere use of the word 'arbitration' or 'arbitrator' in a clause will not make it an arbitration agreement, if it requires or contemplates a further or fresh consent of the parties for reference to arbitration. For example, use of words such as parties can, if they so desire, refer their disputes to arbitration or in the event of any dispute, the parties may also agree to refer the same to arbitration or if any disputes arise between the parties, they should consider settlement by arbitration in a clause relating to settlement of disputes, indicate that the clause is not intended to be an arbitration agreement. Similarly, a clause which states that if the parties so decide, the disputes shall be referred to arbitration or any disputes between parties, if they so agree, shall be referred to arbitration is not an arbitration agreement. Such clauses merely indicate a desire or hope to have the disputes settled by arbitration, or a tentative arrangement to explore arbitration as a mode of settlement if and when a dispute arises. Such clauses require the parties to arrive at a further agreement to go to arbitration, as and when the disputes arise. Any agreement or clause in an agreement requiring or contemplating a further consent or consensus before a reference to arbitration, is not an arbitration agreement, but an agreement to enter into an arbitration agreement in future. 11. In Trimex International FZE Limited (supra), the Supreme Court had observed that once the contract is concluded orally or in writing, the mere fact that a formal contract has to be prepared and initialled by the parties would not affect either the acceptance of the contract so entered into or implementation thereof, even if the formal contract has never been initialled. It was observed by the Supreme Court that unless an inference can be drawn from the facts that the parties intended to be bound only when a formal agreement had been executed, the validity of the agreement would not be affected by its lack of formality. 12. In UNISSI (India) Private Limited (supra), the appellant had sent an agreement containing an arbitration clause as per the format provided by the respondent, after duly signing the same on requisite value of stamp papers for signing of the same by the respondent. Though the respondent had received the same, it did not send back the agreement to the appellant after signing it as per the agreement between the parties. The respondent had used machines supplied by the appellant for about a year and had thereafter, returned the same to the appellant. The bank guarantee Arb. Petition No.32/2015 Page 7 of 12

8 furnished and the earnest money deposited were encashed and forfeited by the respondent. Taking note of the aforesaid facts and the correspondences between the parties including the tender offer as well as the supply order issued by the respondent, it was held that there existed an arbitration agreement between the parties. 13. In Combined Chemicals Company Private Limited (supra), one of the appellants had issued a tender notice for supply of Zinc Sulphate of Agriculture Grade to meet the requirement of the Agriculture Department and Clause-16 of the said tender form provided, amongst others, that in the event of any dispute arising out of or concerning the agreement, the same shall be referred to the arbitration. The bid given by the respondents, having been found to be lowest, acceptance letter was issued providing for execution of a formal agreement, if so required. The Supreme Court on the basis of contents of the acceptance letter along with other documents as well as the conduct of the parties concluded that an agreement was executed between the competent authority and the respondent. 14. In Oil & Natural Gas Corporation Petro Additions Limited (supra), having regard to the language adopted in the NIT with regard to acceptance of the bid, it was held that with the acceptance of the bid by the applicant, would by itself, conclude the contract. 15. In Payal Chawla Singh (supra), the petitioner had issued a legal notice invoking arbitration mechanism under what is called as Solutions Programme. While negating the claim, the Supreme Court observed that what is contemplated under the Solutions Programme is a mere possibility of the employee seeking arbitration as opposed to an obligation to refer all disputes to arbitration. It is in this context, it was emphasised that under Section 7 of the 1996 Act, the parties to an arbitration agreement must agree to submit their disputes to arbitration. 16. In the instant case, tender form (second sheet) under the heading Regulations for the Guidance of Tenderers has laid down, amongst others, that (a) tender form (first and second sheet) and (b)(i) N.F. Railway General Conditions of Contract and Standard Special Conditions of Contracts, 1998, (ii) Indian Railway Unified Standard Specification Volume I and II, 2010 edition and USSOR Schedule of Rates (for Labours and Materials) of Northeast Frontier Railway, 2010 edition, shall form part of the Arb. Petition No.32/2015 Page 8 of 12

9 contract. In the first sheet at Clause-4, it is provided that until a formal agreement is prepared and executed, acceptance of the tender shall constitute a binding contract subject to modifications, as may be mutually agreed to between the parties and indicated in the letter of acceptance of the tenderers offered for the work. 17. Clause-36 of the Tender Documents provided that the successful bidder shall have to submit a Performance Guarantee within 30(thirty) days from the date of issue of the letter of acceptance. Extension of time for submission of Performance Guarantee beyond 30(thirty) days and up to 60(sixty) days from the date of issue of the letter of acceptance may be given by the authority, who is competent to sign the contract agreement but a penal interest of 15% per annum shall be charged for the delay beyond 30(thirty) days. It is also provided that in case the contractor fails to submit the requisite Performance Guarantee even after 60(sixty) days from the date of the letter of acceptance, the Contract shall be terminated duly forfeiting the Earnest Money Deposit (EMD) and other dues, if any, payable against that contract. It is also provided that the failed contractors shall be debarred from participating in re-tender for that work. At Clause-45.1 of the Tender Documents, it is provided that arbitration and settlement of disputes shall be governed vide Clauses-63 and 64 of the General Conditions of Contract, N.F. Railway, The respondents have not denied existence of arbitration clause. 18. At this juncture, it will be appropriate to quote the relevant extract of the letter dated :- No.W/362/CONT/LMG-SCL/EMB/2012/05 Dated: To, Durga Krishna Store Pvt. Ltd., Club Road, Silchar , Cachar, Assam. Sub: Construction of Bridge No.497 (2x6.10m RCC Box), 505 (2x3.50m RCC Box), 515 (2x6.10m RCC Box), 518 (2x6.10m RCC Box), on alignment adjacent to MG track in between Chainage 132/ KM to 137/ KM (New Chainage) and other ancillary works in between stations Ditokcherra- Damcherra in connection with LMG-SCL GC Project (Tender No.CE/CON/LMG-SCL/EMB/2012/05). Arb. Petition No.32/2015 Page 9 of 12

10 Ref: (i) Your original offer dated , (ii) Your negotiated offer dated Dear Sir(s), Your negotiated offer for the above noted work has been accepted by the competent authority for and on behalf of the President of India at a total cost of Rs.6,69,15, (Rupees Six Crores Sixty nine lakhs Fifteen thousand Eight hundred Eighty nine & paisa Sixty four only) as per the enclosed schedule of rates & quantities. You are hereby authorised to commence the work on the strength of this letter to ensure completion of the work within 15(Fifteen) months time as per conditions of the tender and in this regard you may contact Dy. CE/CON- 1/Silchar, N.F. Rly. early. You are required to submit a Performance Guarantee in the form of an irrevocable Bank Guarantee (proforma enclosed) for an amount equal to 5% of the contract value (i.e. for Rs.33,45,794.00) within 30 days time (60 days with penal interest of 15% per annum) as per clause 36(a) (Performance Guarantee) of the tender document from the date of issue of this letter of acceptance. In case you fail to submit the requisite Performance Guarantee within the prescribed time limit, the contract shall be terminated duly forfeiting EMD and other dues against the contract and you will be debarred from participating in re-tender for this work. Please note that the validity of BG bond should be 60 days beyond stipulated completion period of the contract as per tender condition. The total security deposit for this work will be Rs.33,45, (i.e. 5% of the contract value). The Earnest Money of Rs.4,25, deposited by you along with the tender has been retained as part of initial security deposit. The balance security deposit money of Rs.29,20, may be deposited by you in cash, otherwise it will be recovered from the running bills of the contract as per condition of the tender. You are required to submit a programme of work as to how you propose to complete the work within the stipulated time in accordance with the acceptance letter. Arb. Petition No.32/2015 Page 10 of 12

11 You are requested to attend this office to execute formal Contract Agreement of the work, only after acceptance of the performance guarantee for which the documents are being made ready for your signature. This acceptance letter shall be legal and enforceable contract between you and Railway. If you fail to execute the work or fail to execute formal Contract Agreement in accordance with the stipulation in the acceptance letter, it would make you liable for breach of the contract and Railway Administration shall be entitled to take recourse to and action as deemed fit in accordance with stipulation of the tender. While every care has been taken to fully incorporate the decision of the accepting authority regarding acceptance of your offer, the Railway administration reserves the right to correct the inadvertent mistakes which may have occurred in communication of the accepted rates and other terms and conditions at the time of signing the formal contract agreement between the contractor and the Railway administration. An additional copy of this acceptance letter is also enclosed herewith which may be returned duly signed in all pages for binding contract. 19. Perusal of the said letter dated goes to show that the letter was issued on the basis of the negotiated offer dated The letter demonstrates that the petitioner was authorised to commence work on the strength of the acceptance letter to ensure completion of the work within 15(fifteen) months. Third Sub-paragraph of the letter is in consonance with Clause-36 of the Tender Documents. The acceptance letter also goes to show that the acceptance letter itself shall be legal and enforceable contract between the petitioner and the Railway. Though the petitioner was obliged to execute a formal contract agreement of the work after acceptance of the Performance Guarantee, it is provided that if the petitioner failed to execute the work or failed to execute formal contract agreement in accordance with the stipulation in the acceptance letter, it would make it liable for breach of the contract. Both Clause-36 and the letter dated speak about the termination of the contract if there is a failure to submit requisite Performance Guarantee. Unless a contract is concluded, there can be no occasion for termination of contract. This position is further made clear by the fact that acceptance letter is construed to be legal and enforceable contract. The fact that on the strength of the acceptance letter, the petitioner is asked to proceed and commence Arb. Petition No.32/2015 Page 11 of 12

12 with the work is also a pointer to the fact that there is a concluded contract. Not only that, the petitioner was also asked to start the work with full swing on , which is almost 4½ months from the date of issue of the acceptance letter. In the meantime, on , the petitioner had submitted the bank guarantee for an amount of Rs.33,45,794/ Thus, it appears to me that merely because the Performance Guarantee and consequently, the formal contract agreement were not executed between the parties, it cannot be said that there is no concluded contract between the parties. Clause-4 of the first sheet of the Tender Documents also supports the view that acceptance of the tender shall constitute a binding contract until a formal agreement is prepared. 21. The question that arises as to whether there is a written agreement between the parties incorporating an agreement to refer the disputes to arbitration. 22. It is already noticed that first and second sheet of the Tender Documents shall form part of the contract. The General Conditions of Contract, N.F. Railway, 1998, which is referred to in the second sheet, contains an arbitration clause which is also incorporated in the Tender Documents. 23. In that view of the matter, on the basis of the law laid down by the Supreme Court, as discussed above, there is no escape from the conclusion that there exists an arbitration agreement for referring the disputes to Arbitrator. 24. Resultantly, on failure of the respondents to appoint Arbitrator, I appoint Mr. Hirendra Nath Sarma, a retired Judge of this Court, as Arbitrator to adjudicate the dispute between the parties. 25. This application is, accordingly, allowed. J U D G E M. Sharma Arb. Petition No.32/2015 Page 12 of 12

Review Petition No.116/2015 In Arb. Pet. No.17/2013 (D/O). 1. The Gauhati Municipal Corporation. Panbazar, Guwahati.

Review Petition No.116/2015 In Arb. Pet. No.17/2013 (D/O). 1. The Gauhati Municipal Corporation. Panbazar, Guwahati. IN THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) Review Petition No.116/2015 In Arb. Pet. No.17/2013 (D/O). 1. The Gauhati Municipal Corporation Panbazar, Guwahati,

More information

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL No.11249/2018 [Arising out of SLP (CIVIL) No.

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL No.11249/2018 [Arising out of SLP (CIVIL) No. REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL No.11249/2018 [Arising out of SLP (CIVIL) No. 23139 of 2016] South Delhi Municipal Corporation...Appellant Versus SMS

More information

CRP No. 216/2014 VERSUS. Mahendra Kumar Choukhany & Ors. CRP No. 220/2014 VERSUS. Bajrang Tea manufacturing Co. [P] Ltd.

CRP No. 216/2014 VERSUS. Mahendra Kumar Choukhany & Ors. CRP No. 220/2014 VERSUS. Bajrang Tea manufacturing Co. [P] Ltd. IN THE GAUHATI HIGH COURT (High Court of Assam, Nagaland, Mizoram and Arunachal Pradesh) The Federal Bank Ltd. Petitioner VERSUS Mahendra Kumar Choukhany & Ors. Respondents CRP No. 220/2014 The Federal

More information

IN THE GAUHATI HIGH COURT

IN THE GAUHATI HIGH COURT IN THE GAUHATI HIGH COURT ( THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH ) WRIT PETITION (C) NO. 2973/2006 Sri Ajit Kumar Kakoti Lecturer, Son of Late Padmadhar Kakoti, Assam Textile

More information

IN THE GAUHATI HIGH COURT (The High Court of Assam, Nagaland, Mizoram and Arunachal Pradesh) Small Industries Development Bank of India ( SIDBI)

IN THE GAUHATI HIGH COURT (The High Court of Assam, Nagaland, Mizoram and Arunachal Pradesh) Small Industries Development Bank of India ( SIDBI) Review Petition No. 73/2013 (Arising out of Misc. Case No. 705/2013 In FAO 6/2013) IN THE GAUHATI HIGH COURT (The High Court of Assam, Nagaland, Mizoram and Arunachal Pradesh) Small Industries Development

More information

TENDER FOR INTERIOR WORKS AT BANK OF INDIA, JAUNPUR (ALTERNATE PREMISES), Distt.JAUNPUR

TENDER FOR INTERIOR WORKS AT BANK OF INDIA, JAUNPUR (ALTERNATE PREMISES), Distt.JAUNPUR Ref. No.: ZO:CSD:PP:2013-14: Date: 13/08/2013 TENDER FOR INTERIOR WORKS AT BANK OF INDIA, JAUNPUR (ALTERNATE PREMISES), Distt.JAUNPUR Sealed item rate tenders are invited for Interior works on behalf of

More information

ONGC PETRO ADDITIONS LTD. Vs. DAELIM INDUSTRIAL COMPANY LTD. KOREA

ONGC PETRO ADDITIONS LTD. Vs. DAELIM INDUSTRIAL COMPANY LTD. KOREA ONGC PETRO ADDITIONS LTD. Vs. DAELIM INDUSTRIAL COMPANY LTD. KOREA IN THE SUPREME COURT OF INDIA CIVIL ORIGINAL JURISDICTION ARBITRATION CASE NO.22 OF 2013 ONGC Petro Additions Limited..Applicant versus

More information

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) WP(C) No. 2882/2005 M/s. Ladi Steel Industries Pvt. Limited, a private limited company duly incorporated under

More information

HINDUSTAN CONSTRUCTION COMPANY LTD... Petitioner Through Mr.Dherainder Negi, Adv. with Ms.Smita Bhargava, Adv.

HINDUSTAN CONSTRUCTION COMPANY LTD... Petitioner Through Mr.Dherainder Negi, Adv. with Ms.Smita Bhargava, Adv. IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION AND CONCILIATION ACT, 1996 Judgment Reserved on: May 24, 2013 Judgment delivered on: July 01, 2013 Arb.P.No.31/2013 HINDUSTAN CONSTRUCTION

More information

THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM: NAGALAND: MIZORAM AND ARUNACHAL PRADESH)

THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM: NAGALAND: MIZORAM AND ARUNACHAL PRADESH) 1 THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM: NAGALAND: MIZORAM AND ARUNACHAL PRADESH) Sri Rajesh Jaiswal, S/o Sri Radha Raman Jaiswal, Resident of Thana Back Road, Ward No. 11, New Amolapatty, Golaghat-785621.

More information

Downloaded From

Downloaded From CHAPTER I Preliminary 1. Short title, extent, commencement and application. 2. Definitions. CHAPTER II Establishment of tribunal and appellate tribunal 3. Establishment of Tribunal. 4. Composition of Tribunal.

More information

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM: NAGALAND: MIZORAM AND ARUNACHAL PRADESH)

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM: NAGALAND: MIZORAM AND ARUNACHAL PRADESH) IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM: NAGALAND: MIZORAM AND ARUNACHAL PRADESH) WP(C)No.5570/2016 1. Md. Nur Uddin Vs. The State of Assam and 4 Ors. Petitioner Respondents WP(C)No.5217/2016

More information

IN THE GAUHATI HIGH COURT

IN THE GAUHATI HIGH COURT IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) PRINCIPAL SEAT AT GUWAHATI (CIVIL REVISIONAL JURISDICTION) CRP No. 380 of 2014 M/S Shriram Transport Finance

More information

M/S. SAIPEM TRIUNE ENGINEERING PVT. LTD. Plaintiff. - versus - INDIAN OIL PETRONAS PVT. LTD.

M/S. SAIPEM TRIUNE ENGINEERING PVT. LTD. Plaintiff. - versus - INDIAN OIL PETRONAS PVT. LTD. IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION AND CONCILIATION ACT, 1996 Judgment Reserved on: January 07, 2011 Judgment Pronounced on: January 10, 2011 CS(OS) No. 2340/2008 & I.A. No.

More information

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SUIT FOR DECLARATION. Date of Reserve: January 14, Date of Order: January 21, 2009

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SUIT FOR DECLARATION. Date of Reserve: January 14, Date of Order: January 21, 2009 IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SUIT FOR DECLARATION Date of Reserve: January 14, 2008 Date of Order: January 21, 2009 CS(OS) No.2582/2008 and IA No.425/2009 M/S DRISHTICON PROPERTIES

More information

THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM & ARUNACHAL PRADESH) CRP 17 of 2017

THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM & ARUNACHAL PRADESH) CRP 17 of 2017 THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM & ARUNACHAL PRADESH) 1. KANHAIYA LAL KANKANI CRP 17 of 2017 2. SMT. RAJ KUMARI KANKANI..Petitioners -Versus- 1. AMBIKA SUPPLY AND SERVICES

More information

AGRICULTURAL PRODUCE MARKETING COMMITTEE (Market Of National Importance) New Office Complex, NFM- Ph.-II, Sarai Pipal Thalla, Azadpur, Delhi-33.

AGRICULTURAL PRODUCE MARKETING COMMITTEE (Market Of National Importance) New Office Complex, NFM- Ph.-II, Sarai Pipal Thalla, Azadpur, Delhi-33. AGRICULTURAL PRODUCE MARKETING COMMITTEE (Market Of National Importance) New Office Complex, NFM- Ph.-II, Sarai Pipal Thalla, Azadpur, Delhi-33. Ref. No. APMC/ED(C)/2014-15/ Issued to M/s............ NOTICE

More information

IN THE GAUHATI HIGH COURT (The High Court of Assam, Nagaland, Mizoram & Arunachal Pradesh)

IN THE GAUHATI HIGH COURT (The High Court of Assam, Nagaland, Mizoram & Arunachal Pradesh) 1 IN THE GAUHATI HIGH COURT (The High Court of Assam, Nagaland, Mizoram & Arunachal Pradesh) Review. Pet. 155/2013 In WP(C) 3838/10 With WP(C) 520/11 1. Sri Ghana Pegu Son of late Gomeswar Pegu Resident

More information

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) Writ Petition No of 2016

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) Writ Petition No of 2016 IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) Writ Petition No. 1246 of 2016 Shri Abdul Kadir Mazumdar, Son of late Basir Uddin Mazumdar, Village Uttar Krishnapur,

More information

1. Writ Petition (C) No.3638 of 2015

1. Writ Petition (C) No.3638 of 2015 IN THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM & ARUNACHAL PRADESH) 1. Writ Petition (C) No.3638 of 2015 1. Bahari Reserve Gaon Min Samabai Samity Limited, Village & PO- Bahari, PS-

More information

IN THE GAUHATI HIGH COURT. Writ Petition (C) No.606 of 2016

IN THE GAUHATI HIGH COURT. Writ Petition (C) No.606 of 2016 IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) Writ Petition (C) No.606 of 2016 Sri Bhabesh Das Son of Late Dhruba Das Vill Kulhati, No.2 Hidalghurisupa Police

More information

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NOS OF 2017 M/S LION ENGINEERING CONSULTANTS VERSUS O R D E R

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NOS OF 2017 M/S LION ENGINEERING CONSULTANTS VERSUS O R D E R 1 IN THE SUPREME COURT OF INDIA REPORTABLE CIVIL APPELLATE JURISDICTION CIVIL APPEAL NOS. 8984-8985 OF 2017 M/S LION ENGINEERING CONSULTANTS APPELLANT(S) VERSUS STATE OF M.P. & ORS. RESPONDENT(S) O R D

More information

IN THE GAUHATI HIGH COURT

IN THE GAUHATI HIGH COURT Page 1 of 15 IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) WP(C) NO.4448/2007 1. Sri Abhiram Pegu, S/o Damodar Pegu, R/O- Nalipipar, P.O & P.S- Dhemaji, District-

More information

PART I ARBITRATION - CHAPTER I

PART I ARBITRATION - CHAPTER I INDIAN BARE ACTS THE ARBITRATION AND CONCILIATION ACT, 1996 No.26 of 1996 [16th August, 1996] An Act to consolidate and amend the law relating to domestic arbitration, international commercial arbitration

More information

Source: BOOK: International Handbook on Commercial Arbitration, J. Paulsson (ed.), Suppl. 30 (January/2000)

Source: BOOK: International Handbook on Commercial Arbitration, J. Paulsson (ed.), Suppl. 30 (January/2000) Source: BOOK: International Handbook on Commercial Arbitration, J. Paulsson (ed.), Suppl. 30 (January/2000) The Arbitration and Conciliation Act, 1996 (No. 26 of 1996), [16th August 1996] India An Act

More information

$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI REHABILITATION MINISTRY EMPLOYEES CO-OPERATIVE. versus

$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI REHABILITATION MINISTRY EMPLOYEES CO-OPERATIVE. versus $~ * IN THE HIGH COURT OF DELHI AT NEW DELHI + W.P.(C) 8444/2011 Date of Decision: 29 th September, 2015 REHABILITATION MINISTRY EMPLOYEES CO-OPERATIVE HOUSE BUILDING SOCIETY... Petitioner Through Mr.

More information

THE ADMINISTRATIVE TRIBUNALS ACT, 1985 ACT NO. 13 OF 1985 [27th February, 1985.]

THE ADMINISTRATIVE TRIBUNALS ACT, 1985 ACT NO. 13 OF 1985 [27th February, 1985.] THE ADMINISTRATIVE TRIBUNALS ACT, 1985 ACT NO. 13 OF 1985 [27th February, 1985.] An Act to provide for the adjudication or trial by Administrative Tribunals of disputes and complaints with respect to recruitment

More information

DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY Introductory Provisions. Article (1) Definitions

DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY Introductory Provisions. Article (1) Definitions DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY 2011 Introductory Provisions Article (1) Definitions 1.1 The following words and phrases shall have the meaning assigned thereto unless

More information

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) Co. Pet. 8/2015

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) Co. Pet. 8/2015 IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) Co. Pet. 8/2015 Madhusudan Mandal, Residing at 35E Mahanirban Road, Ground Floor, Post Office- Gariahat, Kolkata-700029,

More information

THE GAUHATI HIGH COURT (The High Court of Assam: Nagaland: Mizoram and Arunachal Pradesh) RSA No.55/2004

THE GAUHATI HIGH COURT (The High Court of Assam: Nagaland: Mizoram and Arunachal Pradesh) RSA No.55/2004 THE GAUHATI HIGH COURT (The High Court of Assam: Nagaland: Mizoram and Arunachal Pradesh) RSA No.55/2004 1. Smti Jaya Handique, W/o. Late Dimbeswar Handique, 2. Sri Pradip Handique, 3. Sri Bipul Handique,

More information

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MEGHALAYA, MANIPUR,

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MEGHALAYA, MANIPUR, IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MEGHALAYA, MANIPUR, TRIPURA, MIZORAM AND ARUNACHAL PRADESH) WP (C) No. 3522/2000 1. Dhansiri Valley Project Oil and Natural Gas Commission

More information

Re-Tender. for. Supply & Installation of the Water Chiller. Indian Institute of Technology Jodhpur

Re-Tender. for. Supply & Installation of the Water Chiller. Indian Institute of Technology Jodhpur Re-Tender for Supply & Installation of the Water Chiller at Indian Institute of Technology Jodhpur NIT No. : IITJ/SPS/ENERGY/2/1(I)/2014-15/3 NIT Issue Date : 12 May 2014 Last Date of Submission : 20 May

More information

QUOTATION FOR DISPOSAL OF OLD & OBSELETE COMPUTER H/W SYETEM, PRINTERS ETC. Only through

QUOTATION FOR DISPOSAL OF OLD & OBSELETE COMPUTER H/W SYETEM, PRINTERS ETC. Only through Quotation No: REC/IT/93/COMPUTER(SCRAP)/2008/9 QUOTATION FOR DISPOSAL OF OLD & OBSELETE COMPUTER H/W SYETEM, PRINTERS ETC. Only through Recyclers/Re-Processors registered under Central Pollution Control

More information

MAC App.7/2011 United India Insurance Co. Ltd. Versus BEFORE HON BLE MR. JUSTICE KALYAN RAI SURANA

MAC App.7/2011 United India Insurance Co. Ltd. Versus BEFORE HON BLE MR. JUSTICE KALYAN RAI SURANA THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) MAC App.7/2011 United India Insurance Co. Ltd. Md. Nur Mohammad & ors. Versus Appellants Respondents BEFORE HON

More information

Tender. for. Supply & Installation of the Xenon-Arc Lamp. Indian Institute of Technology Jodhpur

Tender. for. Supply & Installation of the Xenon-Arc Lamp. Indian Institute of Technology Jodhpur Tender for Supply & Installation of the Xenon-Arc Lamp at Indian Institute of Technology Jodhpur NIT No. : IITJ/SPS/ENERGY/2/1(I)/2014-15/54 NIT Issue Date : 03 November 2014 Last Date of Submission :

More information

SOCIAL INFRASTRUCTURE DEVELOPMENT FUND

SOCIAL INFRASTRUCTURE DEVELOPMENT FUND GOVERNMENT OF ARUNACHAL PRADESH DEPARTMENT OF POWER BID DOCUMENT PART-I (BID GUARANTEE AND BID PROPOSAL) OF CONSTRUCTION OF 132 KV SINGLE CIRCUIT TRANSMISSION LINE FROM KHUPPI TO TAWANG INCLUDING 132/33

More information

TENDER DOCUMENT FOR SUPPLY OF TATA MAGIC VEHICLES TO INDIAN INSTITUTE OF TECHNOLOGY HYDERBAD. Ref. No: IITH/101/Tender/Admin Date: Aug 23, 2018

TENDER DOCUMENT FOR SUPPLY OF TATA MAGIC VEHICLES TO INDIAN INSTITUTE OF TECHNOLOGY HYDERBAD. Ref. No: IITH/101/Tender/Admin Date: Aug 23, 2018 TENDER DOCUMENT FOR SUPPLY OF TATA MAGIC VEHICLES TO INDIAN INSTITUTE OF TECHNOLOGY HYDERBAD Ref. No: IITH/101/Tender/Admin Date: Aug 23, 2018 NOTICE INVITING TENDERS Director, IITH invites sealed tenders

More information

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION & CONCILIATION ACT, 1996 Judgement delivered on: O.M.P.

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION & CONCILIATION ACT, 1996 Judgement delivered on: O.M.P. IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION & CONCILIATION ACT, 1996 Judgement delivered on: 04.12.2014 O.M.P. 412/2012 HARYANA STATE SMALL INDUSTRIES & EXPORT CORPORATION LTD. Through:

More information

INDIAN MARITIME UNIVERSITY (A Central University) Ministry of Shipping, Govt. of India EAST COAST ROAD, UTHANDI CHENNAI CAMPUS

INDIAN MARITIME UNIVERSITY (A Central University) Ministry of Shipping, Govt. of India EAST COAST ROAD, UTHANDI CHENNAI CAMPUS INDIAN MARITIME UNIVERSITY (A Central University) Ministry of Shipping, Govt. of India EAST COAST ROAD, UTHANDI CHENNAI CAMPUS 600 119 TENDER FOR DISMANTLING & REMOVING OF BOATS, DAVITS & RELATED ACCESSORIES

More information

IN THE HIGH COURT MANIPUR AT IMPHAL. Writ Petition(C) No. 543 Of 2013

IN THE HIGH COURT MANIPUR AT IMPHAL. Writ Petition(C) No. 543 Of 2013 IN THE HIGH COURT MANIPUR AT IMPHAL Writ Petition(C) No. 543 Of 2013 Shri Ngairangbam Somorendro Singh, Aged about 53 years, s/o Ng. Ibochou Singh, resident of Malom Tulihal, PO Tulihal, PS Nambol, District-Bishnupur

More information

IN THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM & ARUNACHAL PRADESH) CRP NO.6 OF 2017

IN THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM & ARUNACHAL PRADESH) CRP NO.6 OF 2017 IN THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM & ARUNACHAL PRADESH) CRP NO.6 OF 2017 1. SMTI. TETERI DEVI, Wife of Late Mohendra Harizon. 2. SHRI RAMANANDA HARIZON, Son of Late Mohendra

More information

IN THE HIGH COURT OF DELHI AT NEW DELHI. AA No.396/2007. Date of decision: December 3, Vs.

IN THE HIGH COURT OF DELHI AT NEW DELHI. AA No.396/2007. Date of decision: December 3, Vs. IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : Arbitration and Conciliation Act, 1996 AA No.396/2007 Date of decision: December 3, 2007 AKG Associates Through: Mr.Rajiv Kumar, Advocate....Petitioner

More information

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) WP(C) No. 3307/2005

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) WP(C) No. 3307/2005 IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) WP(C) No. 3307/2005 Md. Intajur Rahman Laskar, S/o. Md. Siddique Ali Laskar, Vill- Banskandi Part-III, P.O.

More information

VOLUME I GENERAL CONDITIONS OF CONTRACT (GCC)

VOLUME I GENERAL CONDITIONS OF CONTRACT (GCC) TENDER DOCUMENT NO: PSER:HRM:PEST CONTROL:14 VOLUME I GENERAL CONDITIONS OF CONTRACT (GCC) PEST AND RODENT SERVICES AT BHEL PSER EHQ, GOLF GREEN TRANSIT FLAT, MONOHARPUKUR HOUSING COMPLEX & CIC BUILDING

More information

LAKWA THERMAL POWER STATION

LAKWA THERMAL POWER STATION Assam Power Generation Corporation Limited (A Company Constituting the Generation Wing of former ASEB) Office of the General Manager LAKWA THERMAL POWER STATION P.O. SUFFRY-785689, MAIBELLA DIST-CHARAIDEO,

More information

NATIONAL COMPANY LAW APPELLATE TRIBUNAL, NEW DELHI. Company Appeal (AT) (Insolvency) No. 788 of 2018

NATIONAL COMPANY LAW APPELLATE TRIBUNAL, NEW DELHI. Company Appeal (AT) (Insolvency) No. 788 of 2018 NATIONAL COMPANY LAW APPELLATE TRIBUNAL, NEW DELHI (Arising out of Order dated 10 th October, 2018 passed by the Adjudicating Authority (National Company Law Tribunal), Kolkata Bench, Kolkata, in C.P.

More information

INDIAN INSTITUTE OF TECHNOLOGY INDORE

INDIAN INSTITUTE OF TECHNOLOGY INDORE INDIAN INSTITUTE OF TECHNOLOGY INDORE Notice Inviting Tender 1. Item rate tenders are invited from eligible contractors registered/enlisted with Central Government Department/State Government Department/

More information

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) WP(C) 1140/2015 & WP(C) 2945/2015. Sri Vidyut Bikash Bora

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) WP(C) 1140/2015 & WP(C) 2945/2015. Sri Vidyut Bikash Bora IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) WP(C) 1140/2015 & WP(C) 2945/2015 Sri Vidyut Bikash Bora -Vs-...Petitioner M/s. Indian Oil Corporation Ltd.

More information

THE BANKING OMBUDSMAN SCHEME 2006 (including May 24, 2007 Amendments) NOTIFICATION. Ref.RPCD.BOS.No. 441 / / December 26, 2005

THE BANKING OMBUDSMAN SCHEME 2006 (including May 24, 2007 Amendments) NOTIFICATION. Ref.RPCD.BOS.No. 441 / / December 26, 2005 THE BANKING OMBUDSMAN SCHEME 2006 (including May 24, 2007 Amendments) NOTIFICATION Ref.RPCD.BOS.No. 441 /13.01.01/2005-06 December 26, 2005 In exercise of the powers conferred by Section 35A of the Banking

More information

IN THE HIGH COURT OF. (The High Court of Assam, Nagaland, Meghalaya, Manipur, Tripura, Mizoram and Arunachal Pradesh) W.P. (C) No.

IN THE HIGH COURT OF. (The High Court of Assam, Nagaland, Meghalaya, Manipur, Tripura, Mizoram and Arunachal Pradesh) W.P. (C) No. IN THE HIGH COURT OF (The High Court of Assam, Nagaland, Meghalaya, Manipur, Tripura, Mizoram and Arunachal Pradesh) W.P. (C) No. 1343/2012 Shri Sanjib Saikia, S/o. Late Muhiram Saikia R/o. House No. 12,

More information

THE ARBITRATION AND CONCILIATION (AMENDMENT) BILL, 2015

THE ARBITRATION AND CONCILIATION (AMENDMENT) BILL, 2015 1 AS INTRODUCED IN LOK SABHA Bill No. 252 of 2015. THE ARBITRATION AND CONCILIATION (AMENDMENT) BILL, 2015 A BILL to amend the Arbitration and Conciliation Act, 1996. BE it enacted by Parliament in the

More information

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION AND CONCILIATION ACT, 1996 ARB.P. 63/2012 Date of Decision : December 06, 2012

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION AND CONCILIATION ACT, 1996 ARB.P. 63/2012 Date of Decision : December 06, 2012 IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION AND CONCILIATION ACT, 1996 ARB.P. 63/2012 Date of Decision : December 06, 2012 M/S RURAL COMMUNICATION & MARKETING PVT LTD... Petitioner Through:

More information

Re-Tender. for. Supply & Installation of Low Current Dual Channel Source Meter at. Indian Institute of Technology Jodhpur

Re-Tender. for. Supply & Installation of Low Current Dual Channel Source Meter at. Indian Institute of Technology Jodhpur Re-Tender for Supply & Installation of Low Current Dual Channel Source Meter at Indian Institute of Technology Jodhpur NIT No. : IITJ/SPS/EE/2/2015-16/49 NIT Issue Date : 03 November 2015 Last Date of

More information

JUDGEMENT AND ORDER (CAV)

JUDGEMENT AND ORDER (CAV) IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) RFA 08/2013 1. Manoj Lala, son of Late Mohanlal Lala, R/o. Central Road, Silchar, PO & PS- Silcahr, District-

More information

Bar & Bench (www.barandbench.com)

Bar & Bench (www.barandbench.com) IN THE HIGH COURT OF UTTARAKHAND AT NAINITAL Arbitration Petition No. 21 of 2017 KLA Const. Technologies Private Limited..Petitioner Versus Kajima India Private Limited Respondent Present:- Dr. Amit George,

More information

Tender. for. Indian Institute of Technology Jodhpur

Tender. for. Indian Institute of Technology Jodhpur Tender for Supply & Installation of the Shaper at Indian Institute of Technology Jodhpur NIT No. : IITJ/SPS/ENERGY/2/1(I)/2014-15/22 NIT Issue Date : 04 August 2014 Last Date of Submission : 28 August

More information

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) AIZAWL BENCH W.P.(C) No. 86 of 2012 1. Mr. C.Rohmingliana, Proprietor of C.R. Store Champhai Bethel Veng, Champhai.

More information

INDIAN MARITIME UNIVERSITY (A Central University) Ministry of Shipping, Govt. Of India EAST COAST ROAD, UTHANDI CHENNAI TENDER FOR

INDIAN MARITIME UNIVERSITY (A Central University) Ministry of Shipping, Govt. Of India EAST COAST ROAD, UTHANDI CHENNAI TENDER FOR INDIAN MARITIME UNIVERSITY (A Central University) Ministry of Shipping, Govt. Of India EAST COAST ROAD, UTHANDI CHENNAI 600 119 TENDER FOR PROVIDING HOUSE KEEPING SERVICES AT IMU CHENNAI CAMPUS TENDER

More information

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) MAC APPEAL No. 95/2014 NEW INDIA ASSURANCE CO. LTD...(APPELLANT) -VERSUS- JOGEN BORA @ JOGENDRA NATH BORA &

More information

No:532/Z/17/11/ /10/2014 RE-TENDER NOTICE FOR REMOVAL OF NON BIO MEDICAL WASTE

No:532/Z/17/11/ /10/2014 RE-TENDER NOTICE FOR REMOVAL OF NON BIO MEDICAL WASTE Employees State Insurance Corporation Model Hospital, PGIMSR & MEDICAL COLLEGE (Ministry of Labour & Employment, Govt. of India) Rajaji Nagar, Bangalore - 10 Ph No.: 080-23320271/23528611 Fax: 080-23325130

More information

5.1 LETTER OF ACCEPTANCE

5.1 LETTER OF ACCEPTANCE Construction of New Buildings for IIT Madras Research Park Phase II, SH: - Connecting Bridge and Pergola Works Annexure - I 5.1 LETTER OF ACCEPTANCE Reference No: Date: To Contactors address Project: Construction

More information

ASSAM UNIVERSITY SILCHAR (A Central University Constituted under Act. XXIII of 1989) TENDER DOCUMENT

ASSAM UNIVERSITY SILCHAR (A Central University Constituted under Act. XXIII of 1989) TENDER DOCUMENT ASSAM UNIVERSITY SILCHAR (A Central University Constituted under Act. XXIII of 1989) TENDER DOCUMENT Name of work: - Replacement of new damaged C.G.I. sheet, valleys of old examination building to control

More information

Union of India, represented by the Assistant Commissioner of Guwahati Custom Division, Nilomani Phukan Path, Christianbasti, Guwahati - 5

Union of India, represented by the Assistant Commissioner of Guwahati Custom Division, Nilomani Phukan Path, Christianbasti, Guwahati - 5 1 THE GAUHATI HIGH COURT (The High Court of Assam : Nagaland: Mizoram and Arunachal Pradesh) Union of India, represented by the Assistant Commissioner of Guwahati Custom Division, Nilomani Phukan Path,

More information

Tender. for. Supply and Installation of. Indian Institute of Technology Jodhpur

Tender. for. Supply and Installation of. Indian Institute of Technology Jodhpur Tender for Supply and Installation of UV-Visible Spectrophotometer at Indian Institute of Technology Jodhpur NIT No. : IITJ/SPS/BIO/2/1(I)/2015-16/18 NIT Issue Date : 11 June 2015 Last Date of Submission

More information

Special Conditions of Contract (SCC) Rev-01 dated ( Bidders to fill SCC Rev-01 and send with their technical offer)

Special Conditions of Contract (SCC) Rev-01 dated ( Bidders to fill SCC Rev-01 and send with their technical offer) : BHEL Tender Ref : 88/16/ 6068/KVS Project : 2X250 MW SIKKA TPS Expansion Project. UNIT 3 & 4 Description of Work Execution of Balance Works, CHP & AHP, Sikka TPS Project UNIT 3 & 4 These Special conditions

More information

IN THE GAUHATI HIGH COURT

IN THE GAUHATI HIGH COURT IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) PRINCIPAL SEAT AT GUWAHATI (EXTRAORDINARY WRIT JURISDICTION) WP(C) No.2855 of 2010 Ramesh Goswami Writ Petitioner

More information

BHARAT HEAVY ELECTRICALS LIMITED,

BHARAT HEAVY ELECTRICALS LIMITED, Electroporcelains - 1 - Division, IISc Post - 1 - DOCUMENT CONTENTS SL. No. Description Page Nos 1.0 Notice Inviting Tender 2 1a Bid Application 3 1b Bid questionnaire - A 4 1c Bid questionnaire - B 5

More information

IN THE SUPREME COURT OF INDIA ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION NO. 20 OF Vs. DEVAS MULTIMEDIA P. LTD...

IN THE SUPREME COURT OF INDIA ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION NO. 20 OF Vs. DEVAS MULTIMEDIA P. LTD... 1 REPORTABLE IN THE SUPREME COURT OF INDIA ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION NO. 20 OF 2011 ANTRIX CORP. LTD....PETITIONER Vs. DEVAS MULTIMEDIA P. LTD....RESPONDENT J U D G M E N T ALTAMAS

More information

* IN THE HIGH COURT OF DELHI AT NEW DELHI. % Judgment pronounced on: 27 th January, ARB. P. No.373/2015. versus

* IN THE HIGH COURT OF DELHI AT NEW DELHI. % Judgment pronounced on: 27 th January, ARB. P. No.373/2015. versus * IN THE HIGH COURT OF DELHI AT NEW DELHI % Judgment pronounced on: 27 th January, 2016 + ARB. P. No.373/2015 CONCEPT INFRACON PVT. LTD... Petitioner Through: Mr.Balaji Subramanium, Adv. with Mr.Samar

More information

UV-Visible Spectrophotometer

UV-Visible Spectrophotometer Tender for Supply & Installation of UV-Visible Spectrophotometer at Indian Institute of Technology Jodhpur NIT No. : IITJ/SPS/BIO/RD/1/1(I)/2015-16/12 NIT Issue Date : 30 April 2015 Last Date of Submission

More information

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MEGHALAYA, MANIPUR, TRIPURA, MIZORAM AND ARUNACHAL PRADESH) WP(C) No.

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MEGHALAYA, MANIPUR, TRIPURA, MIZORAM AND ARUNACHAL PRADESH) WP(C) No. IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MEGHALAYA, MANIPUR, TRIPURA, MIZORAM AND ARUNACHAL PRADESH) -Vs- WP(C) No. 1846/2010 Sri Ram Prakash Sarki, Constable (Since dismissed from

More information

Writ Petition (C) No.1208 of 2011

Writ Petition (C) No.1208 of 2011 IN THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MEGHALAYA, MANIPUR, TRIPURA, MIZORAM AND ARUNACHAL PRADESH) Writ Petition (C) No.1208 of 2011 Md. Muktar Hussain, Son of Md. Rajab Ali, Resident

More information

Government of West Bengal Office of the Director General, West Bengal Fire & Emergency Services 13-D, Mirza Ghalib Street, Kolkata

Government of West Bengal Office of the Director General, West Bengal Fire & Emergency Services 13-D, Mirza Ghalib Street, Kolkata Government of West Bengal Office of the Director General, West Bengal Fire & Emergency Services 13-D, Mirza Ghalib Street, Kolkata 700 016. Notice inviting e-tender Notice Inviting e-tender No. 22/2014-2015

More information

NOTICE INVITING TENDER

NOTICE INVITING TENDER (A Government of India Undertaking and Subsidiary of BBUNL) 27, RAJENDRA NATH MUKHERJEE ROAD KOLKATA - 700 001 (WEST BENGAL) PHONE NO. (033) 2248 5841-44; FAX: (033) 2210 3961 E-MAIL: bbjproj@vsnl.net

More information

TENDER DOCUMENT. Sub: Tender for Supply, Installation & Commissioning of Fujitsu RAM for Server Hardware

TENDER DOCUMENT. Sub: Tender for Supply, Installation & Commissioning of Fujitsu RAM for Server Hardware TENDER DOCUMENT Sub: Tender for Supply, Installation & Commissioning of Fujitsu RAM for Server Hardware Tender No. : Purchase: 2016-17 (FUJITSU RAM) August 26, 2016 PART A Sealed tenders are invited for

More information

PART VI. Pre Contract Integrity Pact (IP) HINDUSTAN AERONAUTICS LIMITED Transport Aircraft Division Kanpur (India)

PART VI. Pre Contract Integrity Pact (IP) HINDUSTAN AERONAUTICS LIMITED Transport Aircraft Division Kanpur (India) PART VI Pre Contract Integrity Pact (IP) HINDUSTAN AERONAUTICS LIMITED Transport Aircraft Division Kanpur (India) Tender Ref. No.:. Integrity Pact Whereas Hindustan Aeronautics Ltd. ( HAL ) having its

More information

BANK OF BARODA. Regional Office 129-D, Civil Lines Bareilly

BANK OF BARODA. Regional Office 129-D, Civil Lines Bareilly BANK OF BARODA Regional Office 129-D, Civil Lines Bareilly TENDER DOCUMENT FOR SUPPLY AND INSTALLATION OF UPS BATTERIES AT DIFFERENT BRANCHES OF BAREILLY REGION LAST DATE OF SUBMISSION : 08.01.2014 TECHNICAL

More information

IN THE GAUHATI HIGH COURT

IN THE GAUHATI HIGH COURT IN THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM; NAGALAND; MIZORAM & ARUNACHAL PRADESH) I.A. (Civil) 82/2016 In MAC APP SL. NO. 272049, I.A. (C) /2016, CAVT. 410/2016 Cholamandalam MS General Insurance

More information

URANIUM ORE PROCESSING PROJECT AT TUMMALAPALLE, ANDHRAPRADESH TENDER DOCUMENT FOR NIT. NO: UCIL/TMPL /STORE/18-19/01 NAME OF THE WORK

URANIUM ORE PROCESSING PROJECT AT TUMMALAPALLE, ANDHRAPRADESH TENDER DOCUMENT FOR NIT. NO: UCIL/TMPL /STORE/18-19/01 NAME OF THE WORK URANIUM CORPORATION OF INDIA LIMITED ( A Government of India Enterprise ) Tummalapalle P.O.M.C.PALLE, VEMULA MANDAL, Y.S.R. DISTRICT.A.P.-516349 Ph.No.08588-282701/04, Fax:282704/707 E-mail: uranium_tmpl@yahoo.co.in

More information

1 P a g e. To be generated automatically by the E-procurement portal of the Govt. of Punjab.

1 P a g e. To be generated automatically by the E-procurement portal of the Govt. of Punjab. Tender Notification No : To be generated automatically by the E-procurement portal of the Govt. of Punjab. Nature of work : Short term e- tenders are hereby invited from the Manufacturers / Cost of the

More information

1. Main & Mini Anganwadis Floor Mats(plastic) (5x7) fts. 9,805

1. Main & Mini Anganwadis Floor Mats(plastic) (5x7) fts. 9,805 GOVERNMENT OF MANIPUR DEPARTMENT OF SOCIAL WELFARE --- No. 5/1/14-SW(ICDS-Proc) Dated, Imphal, the 2014 INVITATION FOR BID 1. Quotations in Two Bids system, (Technical & Price Bid) are invited from reputed

More information

NON JUDICIAL STAMP PAPER OF Rs.100/- AGREEMENT FOR TRANSPORTATION OF NEEM SEEDS. THIS AGREEMENT MADE AT on (day) of 2017.

NON JUDICIAL STAMP PAPER OF Rs.100/- AGREEMENT FOR TRANSPORTATION OF NEEM SEEDS. THIS AGREEMENT MADE AT on (day) of 2017. ANNEXURE IV NON JUDICIAL STAMP PAPER OF Rs.100/- AGREEMENT FOR TRANSPORTATION OF NEEM SEEDS THIS AGREEMENT MADE AT on (day) of 2017 By & Between M/s.Gujarat Narmada Valley Fertilizers & Chemicals Limited,

More information

MAHARASHTRA RAJYA SAHAKARI DUDH MAHASANGH MARYADIT, MUMBAI MAHANAND DAIRY, GOREGAON (EAST), MUMBAI

MAHARASHTRA RAJYA SAHAKARI DUDH MAHASANGH MARYADIT, MUMBAI MAHANAND DAIRY, GOREGAON (EAST), MUMBAI MAHARASHTRA RAJYA SAHAKARI DUDH MAHASANGH MARYADIT, MUMBAI MAHANAND DAIRY, GOREGAON (EAST), MUMBAI- 400065. NOTE: TENDER FORM NO -02-0 COST RS. 750.00 ONLY Last Date of Submission : 03.07.2014 Up to 13.00

More information

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL NOS OF 2018 (Arising out of SLP(C) Nos.

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL NOS OF 2018 (Arising out of SLP(C) Nos. IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NOS. 11824-11825 OF 2018 (Arising out of SLP(C) Nos.1274-75 of 2015) REPORTABLE SP SINGLA CONSTRUCTIONS PVT. LTD. Appellant VERSUS

More information

Tender. for. Indian Institute of Technology Jodhpur

Tender. for. Indian Institute of Technology Jodhpur Tender for WatchGuard (XTM-1050) Security License Renewal at Indian Institute of Technology Jodhpur NIT No. : IITJ/SPS/IT/2016-17/37 NIT Issue Date : 25 January 2017 Last Date of Submission : 13 February

More information

THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM: NAGALAND: MIZORAM AND ARUNACHAL PRADESH)

THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM: NAGALAND: MIZORAM AND ARUNACHAL PRADESH) 1 THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM: NAGALAND: MIZORAM AND ARUNACHAL PRADESH) WP(C) No. 4022/2016 Sri David Brahma Son of Sri Biraj Brahma Resident of Kahilipara Journalist Colony Dakhin

More information

NOTICE INVITING TENDER

NOTICE INVITING TENDER Page 1 of 13 ENGINEERING PROJECTS (INDIA) LTD (A Govt. of India Enterprise) 5, 1st Floor, 9 th Main, RMV Extension Sadashivnagar, Bangalore 560080 Phone No. 080-23600542 NOTICE INVITING TENDER Sub:- Tender

More information

TENDER FOR SUPPLY OF HAND BOOK

TENDER FOR SUPPLY OF HAND BOOK 1 KERALA FEEDS LTD. (A Govt. of Kerala Undertaking) Kallettumkara, Thrissur Dist. Pin: 680 683 Phone: 0480-2713550,Fax: 0480-2720194, E-mail: purchase.kfl@kerala.gov.in Website: www.keralafeeds.com No.KFL/381/98/OT-179

More information

IN THE GAUHATI HIGH COURT

IN THE GAUHATI HIGH COURT IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND,MEGHALAYA, MANIPUR, TRIPURA, MIZORAM AND ARUNACHAL PRADESH) WP(C) No. 157(AP) of 2012 M/S JORAM MPCS LTD. - Vs... Petitioner STATE OF ARUNACHAL

More information

CEYLON PETROLEUM STORAGE TERMINALS LIMITED

CEYLON PETROLEUM STORAGE TERMINALS LIMITED CEYLON PETROLEUM STORAGE TERMINALS LIMITED BIDDING DOCUMENT KPR/15/2018 BID FOR THE SUPPLY OF 15000 NOS BAR SOAP (WEIGHT 650 GRAMS MINIMUM/EACH) MANAGER PROCUREMENT PROCUREMENT FUNCTION CEYLON PETROLEUM

More information

$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI % Reserved on: 29 th November, 2017 Pronounced on: 08 th December versus

$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI % Reserved on: 29 th November, 2017 Pronounced on: 08 th December versus $~ * IN THE HIGH COURT OF DELHI AT NEW DELHI % Reserved on: 29 th November, 2017 Pronounced on: 08 th December 2017 + ARB.P. 9/2017 CVS INSURANCE AND INVESTMENTS... Petitioner Through : Ms.Pritha Srikumar

More information

THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION AND CONCILIATION ACT, 1996 Judgment delivered on:

THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION AND CONCILIATION ACT, 1996 Judgment delivered on: THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ARBITRATION AND CONCILIATION ACT, 1996 Judgment delivered on: 10.10.2013 OMP 234/2013 NSSL LIMITED...PETITIONER Vs HPCL-MITTAL ENERGY LIMITED & ANR....RESPONDENTS

More information

IN THE HIGH COURT OF KARNATAKA AT BANGALORE BEFORE THE HON BLE MR.JUSTICE B.S.PATIL. W.P.Nos.50029/2013 & 51586/2013 (CS-RES)

IN THE HIGH COURT OF KARNATAKA AT BANGALORE BEFORE THE HON BLE MR.JUSTICE B.S.PATIL. W.P.Nos.50029/2013 & 51586/2013 (CS-RES) 1 IN THE HIGH COURT OF KARNATAKA AT BANGALORE DATED THIS THE 5 TH DAY OF APRIL, 2014 BEFORE THE HON BLE MR.JUSTICE B.S.PATIL W.P.Nos.50029/2013 & 51586/2013 (CS-RES) BETWEEN 1. SRI H RAGHAVENDRA RAO S/O

More information

IN THE HIGH COURT OF GUJARAT AT AHMEDABAD Special Civil Application No of 2015 AUTOMARK INDUSTRIES (I) LTD Vs STATE OF GUJARAT AND 3 Harsha Deva

IN THE HIGH COURT OF GUJARAT AT AHMEDABAD Special Civil Application No of 2015 AUTOMARK INDUSTRIES (I) LTD Vs STATE OF GUJARAT AND 3 Harsha Deva IN THE HIGH COURT OF GUJARAT AT AHMEDABAD Special Civil Application No.13641 of 2015 AUTOMARK INDUSTRIES (I) LTD Vs STATE OF GUJARAT AND 3 Harsha Devani & A G Uraizee, JJ Appellants Rep by: Mr SN Soparkar,

More information

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO OF 2018 RAMESHWAR PRASAD SHRIVASTAVA AND ORS.

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO OF 2018 RAMESHWAR PRASAD SHRIVASTAVA AND ORS. 1 Reportable IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 5802 OF 2018 RAMESHWAR PRASAD SHRIVASTAVA AND ORS. Appellants VERSUS DWARKADHIS PROJECTS PVT. LTD. AND ORS.... Respondents

More information

Divisional Engineer, DIGITAL TRANSMISSION CENTER Southern Telecom Sub Region, 3 rd Floor, Telephone Bhavan, Saifabad, Hyderabad ,

Divisional Engineer, DIGITAL TRANSMISSION CENTER Southern Telecom Sub Region, 3 rd Floor, Telephone Bhavan, Saifabad, Hyderabad , 1 Tender Form No.. Issued to:. Divisional Engineer, DIGITAL TRANSMISSION CENTER Southern Telecom Sub Region, 3 rd Floor, Telephone Bhavan, Saifabad, Hyderabad 500 004, Cost of form fee paid details: DD

More information

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM; NAGALAND; MIZORAM AND ARUNACHAL PRADESH)

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM; NAGALAND; MIZORAM AND ARUNACHAL PRADESH) Page 1 IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM; NAGALAND; MIZORAM AND ARUNACHAL PRADESH) Writ Petition (C) No. 1961 of 2010 Smt. Padma Rani Mudai Hazarika - Versus - - Petitioner Union of India

More information

THE HON BLE MR. JUSTICE B.K. SHARMA

THE HON BLE MR. JUSTICE B.K. SHARMA IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MEGHALAYA, MANIPUR, TRIPURA AND ARUNACHAL PRADESH) W.P(C) 4494/2004 NLK-204 Anuj Sonowal Son of Late Jadunath Sonowal C/o Sri Ratul Das, Vill-Khajuabeel,

More information

HONOURABLE MR.JUSTICE D.A.MEHTA HONOURABLE MS.JUSTICE H.N.DEVANI. KANUBHAI M PATEL HUF - Petitioner(s) Versus

HONOURABLE MR.JUSTICE D.A.MEHTA HONOURABLE MS.JUSTICE H.N.DEVANI. KANUBHAI M PATEL HUF - Petitioner(s) Versus IN THE HIGH COURT OF GUJARAT AT AHMEDABAD SPECIAL CIVIL APPLICATION No. 5295 of 2010 WITH SPECIAL CIVIL APPLICATION NO.5296 OF 2010 AND SPECIAL CIVIL APPLICATION NO.5297 OF 2010 HONOURABLE MR.JUSTICE D.A.MEHTA

More information

THE COMMERCIAL COURTS, COMMERCIAL DIVISION AND COMMERCIAL APPELLATE DIVISION OF HIGH COURTS (AMENDMENT) BILL, 2018

THE COMMERCIAL COURTS, COMMERCIAL DIVISION AND COMMERCIAL APPELLATE DIVISION OF HIGH COURTS (AMENDMENT) BILL, 2018 AS INTRODUCED IN LOK SABHA Bill No. 123 of 2018 5 THE COMMERCIAL COURTS, COMMERCIAL DIVISION AND COMMERCIAL APPELLATE DIVISION OF HIGH COURTS (AMENDMENT) BILL, 2018 A BILL to amend the Courts, Division

More information