1 Piped Gas Regulation Gas Licensing, Compliance & Dispute Resolution Procedure for Processing Licence Applications Procedure # 1/GLC of 2011 Page 1 of 24

2 PURPOSE The document outlines the procedure that will be followed by the GLC staff when processing licence applications. The procedure will assist staff members to understand the licensing process; ensure that staff members adhere to all applicable internal rules, piped gas rules and statutory deadlines; and ensure that proper and complete records on each application are kept. PROBLEM STATEMET The procedures for processing licence applications are detailed in the Gas Act, 2001 (Act o. 48 of 2001) and the Gas Act Rules. This document seeks to simplify and consolidate the procedures into a single document. IMPORTAT DOCUMETS 1. The documents to be prepared during the course of processing an application are: a) A submission with recommendations regarding a request by an applicant for confidential treatment of information contained in its application (If any); b) An application adequacy report; c) A notice of complete/incomplete application d) A letter requesting additional information /clarification (where necessary); e) An Aide Memoire, including a summary and analysis of objections; f) Draft licence certificate including the licence conditions; g) An advert with the notice of the public hearing; h) A letter informing the applicant of the public hearing; i) A letter or letters informing the objectors to the application about the public hearing (If applicable); j) A panel discussion document (If required); k) A two pager/chairpersons report introducing the application and Reason for Decision, draft licence certificate and licence conditions documents to the committee; l) A licence pack to be handed to the applicant, consisting of: A cover letter to be signed by the CEO; Reason for Decision Final licence conditions and A copy of the final licence certificate Page 2 of 24

3 DETAILED PROCEDURE Step 1 1. Receipt of application, scanning for archiving and acknowledgement of receipt of the licence application (Within first 7 working days after receipt of the application) Step 2 2. Allocation of a licence application to Application Processor (AP) (Within 3 working days after the application has been scanned and archived) Step 3 Processing Confidentiality request (Within 30 days from date of receipt of the application) Compiling a submission to REC (see Annexure A for the format) Inform the applicant of the Energy Regulator s decision and inform the applicant to submit a public version of the application Step 4 Check for completeness and adequacy of the licence application (see Annexure B for the format) (Within 14 days from date of receipt) Step 5 (a) If application complete Inform the applicant of official date of the licence application; and Inform the applicant to advertise the licence application (as per Rule 8 of the Gas Act Rules Step 5 (b) If application is incomplete Issue a notice of incomplete licence application to the applicant; and Give the applicant 14 days to submit the outstanding information Step 6 (a) If Objections are received Provide the applicant with the objections received; and Give the applicant 30 days to respond Page 3 of 24

4 Step 7 Finalisation of a licence application (Within 60 days after a. the date of expiration of the period within which any objections to the issue of the licence may be lodged; or b. the date of receipt of the applicant s response to the objections as contemplated in section 18(c) of the Gas Act) Prepare Aid Memoire (see Annexure C ) including draft licence conditions and draft licence certificate o Generate an advert for public hearing and advertise the application for seven (7) days before public hearing; o Publish the draft licence conditions on ERSA s website seven (7) days prior to the public hearing; o Invite the applicant to the public hearing; o Conduct the public hearing; Prepare and submit the following documents to the relevant subcommittee: o Chairpersons report; o Reasons for Decision (see Annexure D ): o Draft licence conditions and draft licence certificate Implement Energy Regulator s decision by issuing the following: o Signed licence certificate; o Copy of licence conditions; o Reasons for Decision. Post the approved Reasons for Decision and the licence conditions on ERSA s website REVIEW This procedure shall be reviewed annually or at any time as the Piped Gas Sub-Committee may deem necessary. APPLICATIO The procedures shall apply to all licence applications in terms of section 16 of the Gas Act. RESPOSIBILIT All GLC personnel that process licence applications in terms of the Gas Act, 2001 (Act o. 48 of 2001) are required to comply with the processes outlined in this procedure manual. The Head of Department: GLC is responsible for management of the implementation of this procedure. Page 4 of 24

5 TABLE 1: CHECKLIST FOR THE PROCESSIG OF LICECE APPLICATIOS Particulars of the applicant Full registered name of the applicant: Trading name of the applicant (if different from registered name): Physical and postal addresses of the principal place of business of the applicant Physical and postal addresses of the registered office of the applicant (if different from the principal place of business) Telephone number: Fax number: address: Details of the mandated representative of the applicant including: a. Designation, b. Family ame, c. First ame, d. Telephone number, e. Fax number, and f. address Checklist question Respons e (es/o) 1. Has receipt of the application been acknowledged within 7 working days? 2. Has the licence application been assigned to the AP within 3 working days? 3. Does the application lodged include request for confidential treatment of information? 3.1 If yes, use Annexure A 3.2 Was the request for confidential treatment approved by the relevant subcommittee within 30 days? Page 5 of 24

6 4. Has the adequacy report been produced within 14 days? 4.1 Was the application submitted in a prescribed form and manner, and was it complete? If no, was the applicant informed of the incomplete application within 14 days? If yes, was the applicant informed of the completeness and official date of the application within 7 days? 5. Were any objections received? 5.1 If yes, was the applicant informed and given 30 days to respond? 6. Was the public hearing advertised within at least 7 days prior to the date of the hearing? 6.1 Was the Aide Memoire prepared prior to advertising the public hearing? 6.2 Was the applicant and objectors, if any, invited to the public hearing? 6.3 Were the draft licence conditions published on ERSA s website and sent to the applicant for comment within seven (7) days prior to the public hearing? 7. Were the decision documents compiled within 14 days of the public hearing? 7.1 Were the decision documents submitted to the relevant subcommittee for approval within 60 days from the last date of the publication of the notice for comments or if comments were received, then the last date of such receipt of comments? 8. Was the Energy Regulator s decision implemented within 14 days after approval? 9. Were all the documents scanned and archived? Duly completed and signed by: DEPARTMET : DESIGATIO : DATE : SIGATURE : Page 6 of 24

7 Annexure: Annexure A: Example of Table of Recommendations for Confidentiality Requests. Annexure B: Example of Licence Application Adequacy Report template Annexure C: Example of Aide Memoire Format Annexure D: Example of Reasons for Decision Format Page 7 of 24

8 AEXURE A FORMAT FOR TABLE OF RECOMMEDATIOS FOR COFIDETIALIT REQUESTS APPLICAT S (APPLICAT S AME) REQUEST FOR COFIDETIAL TREATMET OF IFORMATIO I THEIR LICECE APPLICATIO Applicant (ame) has requested that the information tabled below be treated as confidential. The table details the information and the ERSA response to the request. 1. LICECE APPLICATIOS FOR THE COSTRUCTIO OF GAS TRASMISSIO AD DISTRIBUTIO FACILITIES B APPLICAT (APPLICAT S AME) Application Item Reference in Licence Application Construction of a Financial Chapter 3, item 2(b) - Transmission statements Page 54 Facility (Gala.t.F1) Operation of a Transmission Facility (Gala.t.F3) Attachment 1 Gigajoule Africa Reasons Summarise reasons provided by applicant for this item Staff Recommendations Recommend whether the information should be kept confidential or not Reasons (Reference to relevant legislation) Provide reasons of your recommendations supported by appropriate section of the Promotion of Access to Information Act, 2000 (Act o. 1 of 2000). Reference previous decision made by the Energy Regulator on the similar issue (if applicable). Construction of a Distribution Facility (Gala.d.F1) Operation of a Distribution Facility (Gala.d.F3) Page 8 of 24

9 Application Item Reference in Licence Application Trading (Gala.tr.F1) Gigajoule Africa Reasons Staff Recommendations Reasons (Reference to relevant legislation) Page 9 of 24

10 AEXURE B LICECE APPLICATIO ADEQUAC REPORT Application Reference umber : Date Received : ame of Assessor : Assessment Date : Signature of Assessor : Signature of HOD : Chapter 1: General Information Rules Reference Information supplied by applicant Comments regarding the completeness and adequacy of information Section A Particulars of applicant Section B Desired commencement date and duration Section C Additional information Section D Preferred licence conditions Section E Solemn declaration Page 10 of 24

11 Chapter 2: Documents to be attached Rules Reference Information supplied Comments regarding the completeness and adequacy of information 2.1 atural person or 2.3 In the case of a non-south African citizen submit a copy of passport, permanent residence permit or employment permit and proof of residence in South Africa 2.3 Local government body, statutory body, juristic person or other legal body or 2.4 If the applicant is not a natural person, attach documents statinga). the title of legislation under which it is registered b). the registration number given to it in terms of such legislation c). the particulars of the owners or shareholders of the applicant if the applicant is not a natural person or similar Page 11 of 24

12 Rules Reference Information supplied Comments regarding the completeness and adequacy of information d). a certified copy of the identity document of the mandated representative authorised to make the application if applicable e). proof of authorisation to make the application 2.5 Provisions to meet any criteria specified by the Minister in terms of section 19(2) of the Gas Act. If applicable 2.6 Documents demonstrating the administrative abilities of the applicant 2.7 Documents demonstrating the financial abilities of the applicant 2.8 Documents demonstrating the technical abilities of the applicant Page 12 of 24

13 Rules Reference Information supplied Comments regarding the completeness and adequacy of information 2.9 Where a facility is owned by more than one person, provide details of ownership and written mandate from each of the owners authorising the applicant to apply 2.10 A certified copy of the Record of Decision of the relevant environmental authorities in accordance to EMA, if applicable 2.11 If the ROD in 10 above has not been obtained, submit: proof of application, solemn declaration for applicant s plans and ability to comply with all applicable labour, health and environmental legislation 2.12 If 10above is not applicable, state the reasons thereof 2.13 List of applicable regulations, operating and technical standards, codes and specifications including those relating to safety to be used in the activities for which this Page 13 of 24

14 Rules Reference Information supplied Comments regarding the completeness and adequacy of information application is made 2.14 Detailed specification of the gas that will handled at the facility for which this application is made 2.15 Information required in terms of the Regulations regarding mechanisms to promote HDSAs Page 14 of 24

15 Chapter 3: Details of Application ote: In the Rules Reference column, the references must be changed according to the type of application processed. Rules Reference Information supplied by applicant Comments regarding the completeness and adequacy of information 3.1 Description of the proposed facility 3.2 Mechanical diagram for the proposed facility 3.3 Proof of financial viability of the proposed facility, including: (a) commercial structure (b) projected financial statements and/or DCF model (c) status and/or proof of equity financing agreements and finance including terms and conditions (d) other costs incidental to the project (e) tariffs to be charged for Page 15 of 24

16 the facility and details of the methodology used for these calculations 3.4 Details of gas sources, including (a) a copy of an independent reservoir engineer s assessment of proven and recoverable gas reserves in TCF and the basis for the reserves determination; and (b) gas production program to supply gas for the project; OR (c) copy of the gas importation agreement 3.5 Details of any existing and/or potential customers for the proposed facility, including: (a) the names and physical addresses of existing customers (b) The names and physical addresses of potential customers (c) The categorization of each customer, for example, as a distributor, power Page 16 of 24

17 generator or large user; and (d) For each customer, the average or anticipated gas consumption in Gigajoules per annum. 3.6 Copies of all GTAs pertaining to the facility to be constructed 3.7 A description of the proposed allocation mechanism in terms of which TPA will be granted to the proposed facility, including (a) grounds for refusal of access; and (b) measures to ensure non-discrimination between customers. 3.8 If applicable, details of planned changes to the pipeline after commencement of operations regarding: (a) pipeline capacity such as additions of compressor stations or any other Page 17 of 24

18 infrastructure that may require a new licence; (b) investment plans and the schedule of implementation; and (c) timelines for service commencement. 3.9 If the applicant is Sasol Limited or its subsidiary, evidence of compliance with clauses 3, 4, 6 and 8.3 of Schedule One to the Agreement Page 18 of 24

19 AEXURE C Aide Memoire Format (Cover Page) ATIOAL EERG REGULATOR PGS Public Hearing (date) (month) (year) AIDE MEMOIRE Subject Licence application for the construction of.. Applicant Area Application o Prepared by ame Date Contributors List names of contributors Checked by HOD: GLC Date ame EM:GAR ame Date Recommended by PRRM-Piped Gas, ame Date Consulted CEO: ERSA Date ame Document o GLC Reference o: 33/GLC of 2011/12 Page 19 of 24

20 A. Executive Summary Page Summary of Aide Memoire B. Preamble In the matter regarding a LICECE APPLICATIO FOR THE By (Applicant ame) In (area) Application o: (Application Reference) C. The Aide Memoire Headings: Aide Memoire The Application Discuss issues about the application, including when the application was received, compliance with the Rules for Application specifically regarding public viewing requirements, and whether there were any objections received. The Applicant(s) Discuss the applicants, covering amongst other their legal status, BEE status, and shareholding etc. Objectors and Intervening Parties Discuss the objections received: who submitted the objections, summary of the objections, summary of the applicant s response to the objections, and ERSA view on the objections (Legal analysis). Page 20 of 24

21 Applicable Law Specify the applicable laws, ERSA s mandate on the matter under consideration by quoting the applicable sections and their relevance to the application. Request for Confidential Treatment of Information Summarise the applicant s request for confidentiality and ERSA s decision. Details of the Application Give an overview of the application, providing amongst others the details of the facilities under consideration, applicable industry codes, regulations and technical standards, indications on the technical and financial competency of the applicant, the promotion of HDSA by the applicant and compliance with other legislation such as environmental legislation etc. Analysis of Application List and discuss each key issues for consideration. These may include ownership issues, nature of the licence sought, facility status, third party access, tariffs, pricing, financial and technical viability of the facility, any legal issues that should be brought to the attention of the Energy Regulator. Conclusion Provide your conclusion on amongst others the adequacy of the application, the abilities of the applicant, and the status of the facility Recommendation Make a call on whether to grant a licence or not. Page 21 of 24

22 AEXURE D Reasons for Decision Format (Cover Page) ATIOAL EERG REGULATOR PGS/REC meeting of (date) (month) (year) REASOS FOR DECISIO Subject Licence application for the construction of.. Applicant Area Application o. Prepared by ame Date Contributors List names of contributors Checked by HOD: GLC Date ame EM:GAR ame Date Recommended by PRRM-Piped Gas, ame Date Consulted CEO: ERSA Date ame Document o GLC Reference o: 33/GLC of 2011/12 Page 22 of 24

23 A. Preamble In the matter regarding a LICECE APPLICATIO FOR THE By (Applicant ame) In (area) Application o: (Application Reference) B. The decision State date of decision and the decision. C. The RFD Headings: Reasons for Decision The Application Discuss issues about the application, including when the application was received, compliance with the Rules for Application specifically regarding public viewing requirements, and whether there were any objections received. The Applicant(s) Discuss the applicants, covering amongst other their legal status, BEE status, and shareholding etc. Applicable Law Specify the applicable laws, ERSA s mandate on the matter under consideration by quoting the applicable sections and their relevance to the application. Page 23 of 24

24 Objectors and Intervening Parties Discuss the objections received: who submitted the objections, summary of the objections, summary of the applicant s response to the objections, and ERSA view on the objections (Legal analysis). Request for Confidential Treatment of Information Summarise the applicant s request for confidentiality and ERSA s decision. Details of the Application Give an overview of the application, providing amongst others the details of the facilities under consideration, applicable industry codes, regulations and technical standards, indications on the technical and financial competency of the applicant, the promotion of HDSA by the applicant and compliance with other legislation such as environmental legislation etc. Public Hearing Discuss details of public hearing, summary of representations made at the hearing, ERSA s position on key issues raised at the public hearing. Analysis of Application List and discuss each key issues about the application, ERSA s position on those issues. These may include ownership issues, nature of the licence sought, facility status, third party access, tariffs, pricing, financial and technical viability of the facility, any legal considerations that influenced the decision of ERSA. Conclusion Provide your conclusion on amongst others the adequacy of the application, the abilities of the applicant, and the status of the facility, and ERSA s decision to grant or not to grant licence. Page 24 of 24

COMPLAINTS AND DISPUTES RESOLUTION PROCEDURES FOR PIPED GAS INDUSTRY

COMPLAINTS AND DISPUTES RESOLUTION PROCEDURES FOR PIPED GAS INDUSTRY COMPLAITS AD DISPUTES RESOLUTIO PROCEDURES FOR PIPED GAS IDUSTR ovember 2011 TABLE OF COTETS Item Contents 1. BACKGROUD 1.1 Introduction 1.2 Definitions: Complaint, dispute, dispute resolution, mediation

More information

Provincial Gazette Provinsiale Koerant

Provincial Gazette Provinsiale Koerant The Province of Gauteng UNITY IN DIVERSITY Die Provinsie Van Gauteng Provincial Gazette Provinsiale Koerant EXTRAORDINARY BUITENGEWOON Selling price Verkoopprys: R2.50 Other countries Buitelands: R3.25

More information

(1 May 2008 to date) ELECTRICITY REGULATION ACT 4 OF 2006

(1 May 2008 to date) ELECTRICITY REGULATION ACT 4 OF 2006 (1 May 2008 to date) [This is the current version and applies as from 1 May 2008, i.e. the date of commencement of the Electricity Regulation Amendment Act 28 of 2007 - to date] ELECTRICITY REGULATION

More information

LAND USE PLANNING APPLICATION FORM

LAND USE PLANNING APPLICATION FORM LAD USE PLAIG APPLICATIO FORM In terms of the Swartland Municipal By-law on Municipal Land Use Planning, 2017 OTE: Please complete this form using BLOCK capitals and ticking the appropriate boxes. PART

More information

2014/098567/07 SEED ANALYTICS (PROPRIETARY) LIMITED MANUAL. in terms of. Section 51 of. The Promotion of Access to Information Act.

2014/098567/07 SEED ANALYTICS (PROPRIETARY) LIMITED MANUAL. in terms of. Section 51 of. The Promotion of Access to Information Act. 2014/098567/07 SEED ANALYTICS (PROPRIETARY) LIMITED MANUAL in terms of Section 51 of The Promotion of Access to Information Act 2 of 2000 (the ACT ) DATE OF COMPILATION: 22/11/2018 DATE OF REVISION: 20/02/2019

More information

ELECTRICITY REGULATIONS FOR COMPULSORY NORMS AND STANDARDS FOR RETICULATION SERVICES (GN R773 in GG of 18 July 2008)

ELECTRICITY REGULATIONS FOR COMPULSORY NORMS AND STANDARDS FOR RETICULATION SERVICES (GN R773 in GG of 18 July 2008) ELECTRICITY REGULATION ACT 4 OF 2006 [ASSENTED TO 27 JUNE 2006] [DATE OF COMMENCEMENT: 1 AUGUST 2006] (except s. 34: 1 December 2004) (English text signed by the President) as amended by Electricity Regulation

More information

DRAFT GOVERNMENT NOTICE DEPARTMENT OF JUSTICE AND CONSTITUTIONAL DEVELOPMENT. No. R. 2010

DRAFT GOVERNMENT NOTICE DEPARTMENT OF JUSTICE AND CONSTITUTIONAL DEVELOPMENT. No. R. 2010 GOVERNMENT NOTICE hh060310 DEPARTMENT OF JUSTICE AND CONSTITUTIONAL DEVELOPMENT No. R. 2010 SHERIFFS ACT, 1986 (ACT NO. 90 OF 1986): AMENDMENT OF REGULATIONS RELATING TO SHERIFFS, 1990 The Minister of

More information

LICENCE FOR THE OPERATION OF A PETROLEUM STORAGE FACILITY

LICENCE FOR THE OPERATION OF A PETROLEUM STORAGE FACILITY Licence Number: PPL.sf.F3/205/2015 LICENCE FOR THE OPERATION OF A PETROLEUM STORAGE FACILITY This licence is issued by the National Energy Regulator, hereinafter referred to as NERSA, in terms of the Petroleum

More information

Kapara Insurance Brokers (Pty) Ltd

Kapara Insurance Brokers (Pty) Ltd Kapara Insurance Brokers (Pty) Ltd (Registration Number 1998/024464/07) (the Company ) MANUAL in terms of The Promotion of Access to Information Act 2/2000 (the Act ) INDEX 1. Introduction to the Company

More information

INFORMATION MANUAL FOR PIONEER FOODS (PROPRIETARY) LIMITED. Prepared in accordance with section 51 of the Promotion of Access to Information Act

INFORMATION MANUAL FOR PIONEER FOODS (PROPRIETARY) LIMITED. Prepared in accordance with section 51 of the Promotion of Access to Information Act INFORMATION MANUAL FOR PIONEER FOODS (PROPRIETARY) LIMITED Prepared in accordance with section 51 of the Promotion of Access to Information Act Act 2 of 2000 Ref No.: PFG_PAIA_111231 Contents 1. INTERPRETATION...

More information

Promotion of Access to Information Manual

Promotion of Access to Information Manual 1. Introduction The Promotion of Access to Information Act was promulgated in March 2001. The Act was put in place to actively promote a society in which the people of South Africa have effective access

More information

PAIA MANUAL FOR: M-TEK (Pty.) Ltd.

PAIA MANUAL FOR: M-TEK (Pty.) Ltd. Document Number: AC000-000002-94 File Name: 2016.01.04 - PAIA Manual.odt Issue: 1 Issue Date: 4 January 2016 PAIA MANUAL FOR: (Registration Number: 98/15119/07) (the Company ) PREPARED AND COMPILED IN

More information

PROMOTION OF ACCESS TO INFORMATION

PROMOTION OF ACCESS TO INFORMATION PROMOTION OF ACCESS TO INFORMATION MANUAL PREPARED IN TERMS OF SECTION 51 OF THE PROMOTION OF ACCESS TO INFORMATION ACT, NO 2 OF 2000, FOR THE FOLLOWING ENTITIES: This Manual applies to Long Beach Capital

More information

ACCESS TO INFORMATION MANUAL. SASOL INZALO PUBLIC (RF) LIMITED (an investment holding company)

ACCESS TO INFORMATION MANUAL. SASOL INZALO PUBLIC (RF) LIMITED (an investment holding company) ACCESS TO INFORMATION MANUAL Prepared in accordance with section 51 of the Promotion of Access to Information Act, Number 2 of 2000 ( the Act ) SASOL INZALO PUBLIC (RF) LIMITED (an investment holding company)

More information

CARTRACK HOLDINGS LIMITED (Registration number: 2005/036316/06) PROMOTION OF ACCESS TO INFORMATION MANUAL

CARTRACK HOLDINGS LIMITED (Registration number: 2005/036316/06) PROMOTION OF ACCESS TO INFORMATION MANUAL CARTRACK HOLDINGS LIMITED (Registration number: 2005/036316/06) PROMOTION OF ACCESS TO INFORMATION MANUAL 2 THE CARTRACK HOLDINGS LIMITED ( CARTRACK ) PROMOTION OF ACCESS TO INFORMATION MANUAL 1 Introduction

More information

BITOU MUNICIPALITY: LAND USE PLANNING BY-LAW

BITOU MUNICIPALITY: LAND USE PLANNING BY-LAW AEXURE A. AEXURE B. T2 LAD USE PLAIG APPLICATIO FORM BITOU MUICIPALIT: LAD USE PLAIG B-LAW KIDL OTE: Please complete this form using BLOCK capitals and ticking the appropriate boxes. PART A: APPLICAT

More information

Published in terms of Section 51of the Promotion of Access to Information Act, 2 of 2000

Published in terms of Section 51of the Promotion of Access to Information Act, 2 of 2000 INFORMATION Published in terms of Section 51of the Promotion of Access to Information Act, 2 of 2000 Table of Contents 1 INTRODUCTION... 2 2 DEFINITIONS... 3 3 AVAILABILITY OF THIS... 6 4 RECORDS HELD

More information

Government Notices Goewermentskennisgewings

Government Notices Goewermentskennisgewings Trade and Industry, Department of/ Handel en Nywerheid, Departement van Broad-Based Black Empowerment Regulations, 0: Invitation for the public to comment on the draft 0 No. 0 GOVERNMENT GAZETTE, FEBRUARY

More information

No. R December 2014

No. R December 2014 STAATSKOERANT, 8 DESEMBER 2014 No. 38303 11 No. R. 994 8 December 2014 DEPARTMENT OF ENVIRONMENTAL AFFAIRS NATIONAL ENVIRONMENTAL MANAGEMENT ACT, 1 (ACT NO. 107 OF 1998) NATIONAL EXEMPTION REGULATIONS

More information

Act No PETROLEUM PIPELINES ACT, (English text signed by the President.) (Assented to 31 May 2004.) ACT

Act No PETROLEUM PIPELINES ACT, (English text signed by the President.) (Assented to 31 May 2004.) ACT Act No. 60.2003 PETROLEUM PIPELINES ACT, 2003 (English text signed by the President.) (Assented to 31 May 2004.) ACT To establish a national regulatory framework for petroleum pipelines; to establish a

More information

Service level agreement for the supply of medical locums and locum general practitioners under Framework GP

Service level agreement for the supply of medical locums and locum general practitioners under Framework GP The following may be used as a template to assist the parties if they wish to agree service levels in accordance with Schedule 6. This Schedule will only apply where the parties wish to enter into additional

More information

COMPANIES REGULATIONS, 2011

COMPANIES REGULATIONS, 2011 , 2011 The Minister of Trade and Industry intends to publish the draft Regulations, 2011 based on the Companies Act 2008 and the Companies Amendment Bill 2010 published in Gazette No 33695 of 27 October

More information

REPUBLIC OF SOUTH AFRICA

REPUBLIC OF SOUTH AFRICA Government Gazette REPUBLIC OF SOUTH AFRICA Vol. 511 Cape Town 8 January 2008 No. 25721 THE PRESIDENCY No. 37 8 January 2008 It is hereby notified that the President has assented to the following Act,

More information

NATIONAL ENERGY REGULATOR ACT 40 OF 2004

NATIONAL ENERGY REGULATOR ACT 40 OF 2004 NATIONAL ENERGY REGULATOR ACT 40 OF 2004 [ASSENTED TO 30 MARCH 2005] [DATE OF COMMENCEMENT: 15 SEPTEMBER 2005] (English text signed by the President) as amended by Electricity Regulation Act 4 of 2006

More information

MANUAL HUDACO INDUSTRIES LIMITED REGISTRATION NUMBER 1985/004617/06) ( HUDACO ) in terms of

MANUAL HUDACO INDUSTRIES LIMITED REGISTRATION NUMBER 1985/004617/06) ( HUDACO ) in terms of MANUAL OF HUDACO INDUSTRIES LIMITED REGISTRATION NUMBER 1985/004617/06) ( HUDACO ) in terms of Section 51(1) of the Promotion of Access to Information Act 2 of 2000 ( the Act ) THE PURPOSE The purpose

More information

DEPARTMENT OF ENVIRONMENTAL AFFAIRS. No. R December 2014 NATIONAL ENVIRONMENTAL MANAGEMENT ACT, 1998 (ACT NO. 107 OF 1998)

DEPARTMENT OF ENVIRONMENTAL AFFAIRS. No. R December 2014 NATIONAL ENVIRONMENTAL MANAGEMENT ACT, 1998 (ACT NO. 107 OF 1998) STAATSKOERANT, 8 DESEMBER 2014 No. 38303 3 GOVERNMENT NOTICES DEPARTMENT OF ENVIRONMENTAL AFFAIRS No. R. 993 8 December 2014 NATIONAL ENVIRONMENTAL MANAGEMENT ACT, 1998 (ACT NO. 107 OF 1998) NATIONAL APPEAL

More information

ETUDE COMPLIANCE SERVICES (PTY) LTD

ETUDE COMPLIANCE SERVICES (PTY) LTD ETUDE COMPLIANCE SERVICES (PTY) LTD Registration Number: 2012/218488/07 (hereinafter referred to as the Company ) MANUAL in terms of The Promotion of Access to Information Act 2/2000 (the "ACT") Page 1

More information

Code of Practice on Customer Complaints Handling Procedure

Code of Practice on Customer Complaints Handling Procedure Code of Practice on Customer Complaints Handling Procedure First Edition 2018 Approved by LEWA Table of Contents 1. Citation and commencement 2. Abbreviations and De nitions 3. Preamble 4. Background 5.

More information

Communications Act 8 of 2009 sections 38 and 39

Communications Act 8 of 2009 sections 38 and 39 MADE IN TERMS OF sections 38 and 39 Regulations regarding Licence Conditions for Telecommunications Service Licences General Notice 308 of 2012 (GG 5037) came into force on date of publication: 13 September

More information

SMG Auto (Cape Town) (Proprietary) Limited is a motor vehicle dealership company.

SMG Auto (Cape Town) (Proprietary) Limited is a motor vehicle dealership company. MANUAL PREPARED IN ACCORDANCE WITH SECTION 51 OF THE PROMOTION OF ACCESS TO INFORMATION ACT NO 2 OF 2000 ("the Act") FOR SMG AUTO (CAPE TOWN) PROPRIETARY LIMITED (Registration Number 2006/015703/07) Company

More information

MWEB a Division of INTERNET SOLUTIONS DIGITAL PROPRIETARY LIMITED. (Registration number: 2000/021413/07)

MWEB a Division of INTERNET SOLUTIONS DIGITAL PROPRIETARY LIMITED. (Registration number: 2000/021413/07) MWEB a Division of INTERNET SOLUTIONS DIGITAL PROPRIETARY LIMITED (Registration number: 2000/021413/07) MANUAL PREPARED IN ACCORDANCE WITH SECTION 51 OF THE PROMOTION OF ACCESS TO INFORMATION ACT, ACT

More information

ACT. (Signed by the President on 24 January 2000) ARRANGEMENT OF SECTIONS PART I ELECTRICITY CONTROL BOARD PART II FINANCIAL PROVISIONS

ACT. (Signed by the President on 24 January 2000) ARRANGEMENT OF SECTIONS PART I ELECTRICITY CONTROL BOARD PART II FINANCIAL PROVISIONS ACT To provide for the establishment and functions of the Electricity Control Board; and to provide for matters incidental thereto. (Signed by the President on 24 January 2000) ARRANGEMENT OF SECTIONS

More information

PROMOTION OF ACCESS TO INFORMATION ACT SECTION 51 MANUAL FOR MASSDISCOUNTERS T/A GAME AND DION WIRED

PROMOTION OF ACCESS TO INFORMATION ACT SECTION 51 MANUAL FOR MASSDISCOUNTERS T/A GAME AND DION WIRED PROMOTION OF ACCESS TO INFORMATION ACT SECTION 51 MANUAL FOR MASSDISCOUNTERS T/A GAME AND DION WIRED INDEX 1 INTRODUCTION... 3 2 DEFINITIONS... 3 3 OVERVIEW OF THE MASSMART GROUP... 4 4 CONTACT DETAILS...

More information

NOTICE 662 OF 2015 INDEPENDENT COMMUNICATIONS AUTHORITY OF SOUTH AFRICA ELECTRONIC COMMUNICATIONS ACT, 2005 (ACT NO. 36 OF 2005), AS AMENDED:

NOTICE 662 OF 2015 INDEPENDENT COMMUNICATIONS AUTHORITY OF SOUTH AFRICA ELECTRONIC COMMUNICATIONS ACT, 2005 (ACT NO. 36 OF 2005), AS AMENDED: STAATSKOERANT, 26 JUNIE 2015 No. 38921 3 GENERAL NOTICE NOTICE 662 OF 2015 INDEPENDENT COMMUNICATIONS AUTHORITY OF SOUTH AFRICA ELECTRONIC COMMUNICATIONS ACT, 2005 (ACT NO. 36 OF 2005), AS AMENDED: REGULATIONS

More information

THE ENERGY ACT, (No. 12 of 2006)

THE ENERGY ACT, (No. 12 of 2006) Appendix I THE ENERGY ACT, 2006 (No. 12 of 2006) In exercise of the powers conferred by section 102 of the Energy Act, 2006 the Minister for Energy makes the following regulations:- The Energy (Licensing

More information

FRONTIER ASSET MANAGEMENT AND INVESTMENTS (PTY) LIMITED ( Frontier )

FRONTIER ASSET MANAGEMENT AND INVESTMENTS (PTY) LIMITED ( Frontier ) Frontier Asset Management and Investments (Pty) Ltd (2009/015299/07) FRONTIER ASSET MANAGEMENT AND INVESTMENTS (PTY) LIMITED ( Frontier ) REGISTRATION NUMBER 2009/015299/07 MANUAL in terms of Section 51

More information

KGANYA INVESTMENT HOLDINGS (PTY) LTD

KGANYA INVESTMENT HOLDINGS (PTY) LTD KGANYA INVESTMENT HOLDINGS (PTY) LTD ACCESS TO INFORMATION MANUAL KGANYA INVESTMENT HOLDINGS (PTY) LTD, Registration No. 1999/007637/07, comprises the following whollyowned subsidiaries, herein after referred

More information

GOVERNMENT GAZETTE OF THE REPUBLIC OF NAMIBIA

GOVERNMENT GAZETTE OF THE REPUBLIC OF NAMIBIA GOVERNMENT GAZETTE OF THE REPUBLIC OF NAMIBIA N$11.60 WINDHOEK - 6 February 2012 No. 4878 MINISTRY OF ENVIRONMENT AND TOURISM No. 30 2011 ENVIRONMENTAL IMPACT ASSESSMENT REGULATIONS: ENVIRONMENTAL MANAGEMENT

More information

The Committee was established primarily to assist the Board in overseeing the:

The Committee was established primarily to assist the Board in overseeing the: TERMS OF REFERENCE SASOL LIMITED AUDIT COMMITTEE 1. CONSTITUTION The Audit Committee (the Committee) is constituted as a statutory committee of Sasol Limited (the Company) in respect of its statutory duties

More information

Promotion to Access Information Act. SIKA South Africa

Promotion to Access Information Act. SIKA South Africa PAIA Sika South Africa (Pty) Ltd 9 Hocking Place Westmead Tel: +27 031 792 6500 Fax: +27 031 700 1760 Web-site: www.sika.co.za E-mail: headoffice@za.sika.com SIKA South Africa PROMOTION OF ACCESS TO INFORMATION

More information

PHOENIX NATURAL GAS LTD. DISTRIBUTION NETWORK CODE MODIFICATION RULES

PHOENIX NATURAL GAS LTD. DISTRIBUTION NETWORK CODE MODIFICATION RULES PHOENIX NATURAL GAS LTD. DISTRIBUTION NETWORK CODE MODIFICATION RULES 20 th October 2005 Phoenix Natural Gas Ltd 2012 - all rights reserved. Material published in this document is the copyright of Phoenix

More information

GOVERNMENT GAZETTE REPUBLIC OF NAMIBIA

GOVERNMENT GAZETTE REPUBLIC OF NAMIBIA GOVERNMENT GAZETTE OF THE REPUBLIC OF NAMIBIA N$7.60 WINDHOEK - 18 October 2007 No. 3922 CONTENTS GOVERNMENT NOTICE Page No. 187 Promulgation of Electricity Act, 2007 (Act No. 4 of 2007), of the Parliament...

More information

OTEL COMMUNICATIONS REGISTRATION NUMBER : 2015/034240/07 SECTION 14 MANUAL:

OTEL COMMUNICATIONS REGISTRATION NUMBER : 2015/034240/07 SECTION 14 MANUAL: OTEL COMMUNICATIONS REGISTRATION NUMBER : 2015/034240/07 SECTION 14 MANUAL: MANUAL PREPARED IN TERMS OF SECTION 51 OF THE PROMOTION OF ACCESS TO INFORMATION ACT 2000 (ACT 2 OF 2000) 1 P a g e SECTION 14

More information

COMPLAINT HANDLING POLICY OF AMERICAN EXPRESS SERVICES EUROPE LIMITED BRANCH, HUNGARY

COMPLAINT HANDLING POLICY OF AMERICAN EXPRESS SERVICES EUROPE LIMITED BRANCH, HUNGARY COMPLAINT HANDLING POLICY OF AMERICAN EXPRESS SERVICES EUROPE LIMITED BRANCH, HUNGARY The purpose of the present complaint handling policy (hereafter the Policy ) is to ensure that complaints (hereafter

More information

Cito Consult (Pty)Ltd Registration Number: 2009/014313/07. Manual in Terms of Section 51 of the Promotion of Access to Information Act, 2000

Cito Consult (Pty)Ltd Registration Number: 2009/014313/07. Manual in Terms of Section 51 of the Promotion of Access to Information Act, 2000 Last Updated: June 2015 Prepared by NMG Benefits Cito Consult (Pty)Ltd Registration Number: 2009/014313/07 Manual in Terms of Section 51 of the Promotion of Access to Information Act, 2000 T: +27 11 509

More information

Copyright (Collecting Societies) Regulations, 1993

Copyright (Collecting Societies) Regulations, 1993 Copyright (Collecting Societies) Regulations, 1993 TABLE OF CONTENTS Regulations Short Title... 1 Interpretation... 2 Fees... 3 Application for Approval... 4 Address for Applications... 5 Grant of Approval...

More information

Gas Compliance Reporting Manual. Energy Coordination Act 1994

Gas Compliance Reporting Manual. Energy Coordination Act 1994 Gas Compliance Reporting Manual Energy Coordination Act 1994 January 2017 This document is available at the Economic Regulation ERA s website at www.erawa.com.au. For further information, contact: Economic

More information

Snipelisky & Kilian Attorneys

Snipelisky & Kilian Attorneys Suite # 7, First Floor Telephone Numbers: (021) 876-2084/5 La Rue des Roses Fax Number: (021) 876-2572 2 Main Road E-Mail Mr Kilian : antonkill@law.co.za Franschhoek Conveyancing & Estates: sniplaw@mweb.co.za

More information

RESTAURANT FACILITY PPP AGREEMENT

RESTAURANT FACILITY PPP AGREEMENT RESTAURANT FACILITY PPP AGREEMENT FRANCHISOR MEMORANDUM OF UNDERSTANDING FOR THE RESTAURANT FACILITIES IN THE NATIONAL PARK MARCH 2013 Page 1 of 15 TABLE OF CONTENTS 1. INTRODUCTION... 3 2. DEFINITION

More information

BARLOWORLD MOTOR (PTY) LTD

BARLOWORLD MOTOR (PTY) LTD BARLOWORLD MOTOR (PTY) LTD (Company Registration No. 1946/021661/07) And those associated companies listed in Annexure 1 (hereinafter collectively referred to as Barloworld Motor ) MANUAL PREPARED IN ACCORDANCE

More information

(Registration Number: 1998/11796/07) Access to Information Manual

(Registration Number: 1998/11796/07) Access to Information Manual Staluform (Pty) Ltd (Registration Number: 998/796/07) Access to Information Manual PREPARED IN TERMS OF SECTION 5 OF THE PROMOTION OF ACCESS TO INFORMATION ACT NO. 2 OF 2000 A. Particulars in terms of

More information

MULTICHOICE SOUTH AFRICA HOLDINGS (PTY) LTD (Registration number: 2006/015293/07) and various of its subsidiaries ("MultiChoice")

MULTICHOICE SOUTH AFRICA HOLDINGS (PTY) LTD (Registration number: 2006/015293/07) and various of its subsidiaries (MultiChoice) MULTICHOICE SOUTH AFRICA HOLDINGS (PTY) LTD (Registration number: 2006/015293/07) and various of its subsidiaries ("MultiChoice") MANUAL PREPARED IN ACCORDANCE WITH SECTION 51 OF THE PROMOTION OF ACCESS

More information

DEBIT ORDER ABUSE RULES

DEBIT ORDER ABUSE RULES DEBIT ORDER ABUSE RULES Contents 1. INTRODUCTION... 2 2. DEFINITIONS AND INTERPRETATION... 2 3. DEFINITIONS... 3 4. TRIGGERS... 4 5. UDOA Processes... 4 5.1 Dispute Ratios in the EFT PCH Clearing Rules

More information

APPLICATION NUMBER: VA

APPLICATION NUMBER: VA APPLICATION NUMBER: VA Vessel Agent Application for a Vessel agent registration issued in terms of Port Rule 148. (Port Rules issued in terms of section 80(2) of the National Ports Act No. 12 of 2005).

More information

YEBOYETHU BEE CONTRACT FOR USE IN RESPECT OF THE YEBOYETHU OWN-BROKER TRADING PROCESS TERMS AND CONDITIONS. entered into between.

YEBOYETHU BEE CONTRACT FOR USE IN RESPECT OF THE YEBOYETHU OWN-BROKER TRADING PROCESS TERMS AND CONDITIONS. entered into between. YEBOYETHU BEE CONTRACT FOR USE IN RESPECT OF THE YEBOYETHU OWN-BROKER TRADING PROCESS TERMS AND CONDITIONS entered into between "You" 1 (insert full name of the person that is the Beneficial Owner of YeboYethu

More information

as amended by ACT (Signed by the President on 4 September 1998) ARRANGEMENT OF SECTIONS

as amended by ACT (Signed by the President on 4 September 1998) ARRANGEMENT OF SECTIONS (GG 1958) brought into force on 1 November 1998 by GN 261/1998 (GG 1981), with the exception of sections 5-13 and sections 15-18; sections 5-13 and sections 15-18 brought into force on 5 February 1999

More information

TRANSMISSION SYSTEM OPERATOR LICENCE GRANTED TO. Gaslink Independent System Operator Limited. Consultation Paper

TRANSMISSION SYSTEM OPERATOR LICENCE GRANTED TO. Gaslink Independent System Operator Limited. Consultation Paper TRANSMISSION SYSTEM OPERATOR LICENCE GRANTED TO Gaslink Independent System Operator Limited Consultation Paper CER/08/078 [ ] 2008 TABLE OF CONTENTS PART I: PART II: Condition 1: Condition 2: Condition

More information

ACT ARRANGEMENT OF SECTIONS. as amended by

ACT ARRANGEMENT OF SECTIONS. as amended by (GG 2208) brought into force on 25 October 1999 by GN 236/1999 (GG 2220), with the exception of sections 5-9 and 11, which came into force on the transfer date, which is the date set in terms of section

More information

1.000 Development Permit Procedures and Administration

1.000 Development Permit Procedures and Administration CHAPTER 1 1.000 Development Permit Procedures and Administration 1.010 Purpose and Applicability A. The purpose of this chapter of the City of Lacey Development Guidelines and Public Works Standards is

More information

SPILLPRO SOUTH AFRICA (PTY) LTD

SPILLPRO SOUTH AFRICA (PTY) LTD Register Number: 2015/189508/07 SPILLPRO SOUTH AFRICA (PTY) LTD In terms of Section 51 of The Promotion of Acess to Information Act 2/2000 Index 1. Introduction of SPILLPRO SOUTH AFRICA (PTY) LTD 2. Contact

More information

CONSTITUTION FOR THE STATUTORY COUNCIL FOR THE SQUID AND RELATED FISHERIES OF SOUTH AFRICA

CONSTITUTION FOR THE STATUTORY COUNCIL FOR THE SQUID AND RELATED FISHERIES OF SOUTH AFRICA CONSTITUTION FOR THE STATUTORY COUNCIL FOR THE SQUID AND RELATED FISHERIES OF SOUTH AFRICA 1. Name. The name of this statutory council is THE STATUTORY COUNCIL FOR THE SQUID AND RELATED FISHERIES OF SOUTH

More information

Lazer Communications CC

Lazer Communications CC Lazer Communications CC Manual In terms of PROMOTION OF ACCESS TO INFORMATION ACT NO 2 OF 2000 1. INTRODUCTION The Promotion of Access to Information Act 2 of 2000 came into force on the 9 th of March

More information

Hadeda Body Corporate ( body corporate ) INFORMATION MANUAL

Hadeda Body Corporate ( body corporate ) INFORMATION MANUAL Hadeda Body Corporate ( body corporate ) Sectional Scheme Number SS 1154/2008 Registered Sectional Title Number ST1154/2008-9 Pretoria Deeds Office INFORMATION MANUAL Compiled in terms of Section 51 of

More information

TANDA TULA (PTY) LTD (REGISTRATION NO: 2012/087535/07) MANUAL IN TERMS OF SECTION 51 OF THE PROMOTION OF ACCESS TO INFORMATION ACT (Act 2 of 2000)

TANDA TULA (PTY) LTD (REGISTRATION NO: 2012/087535/07) MANUAL IN TERMS OF SECTION 51 OF THE PROMOTION OF ACCESS TO INFORMATION ACT (Act 2 of 2000) TANDA TULA (PTY) LTD (REGISTRATION NO: 2012/087535/07) MANUAL IN TERMS OF SECTION 51 OF THE PROMOTION OF ACCESS TO INFORMATION ACT (Act 2 of 2000) (the ACT ) 1 INDEX 1. Introduction to Tanda Tula (Pty)

More information

BERMUDA ELECTRICITY ACT : 2

BERMUDA ELECTRICITY ACT : 2 QUO FA T A F U E R N T BERMUDA ELECTRICITY ACT 2016 2016 : 2 TABLE OF CONTENTS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 PART 1 PRELIMINARY Citation Interpretation Relationship to the Regulatory Authority

More information

THE ORISSA DISTRIBUTION AND RETAIL SUPPLY LICENCE, 1999 (WESCO)

THE ORISSA DISTRIBUTION AND RETAIL SUPPLY LICENCE, 1999 (WESCO) THE ORISSA DISTRIBUTION AND RETAIL SUPPLY LICENCE, 1999 (WESCO) (NO. 4/99) (Issued under OERC Order Dt. 31.03.99 in Case No. 25/98) Western Electricity Supply Company of Orissa Limited Registered office:

More information

Government Gazette Staatskoerant

Government Gazette Staatskoerant Government Gazette Staatskoerant REPUBLIC OF SOUTH AFRICA REPUBLIEK VAN SUID AFRIKA Regulation Gazette Vol. 629 No. 10177 10 November November Regulasiekoerant 2017 No. 41237 PART 1 OF 3 N.B. The Government

More information

PROMOTION OF ACCESS TO INFORMATION ACT MANUAL

PROMOTION OF ACCESS TO INFORMATION ACT MANUAL PROMOTION OF ACCESS TO INFORMATION ACT MANUAL In terms of the Promotion of Access to Information Act Act 2 of 2000 For New Integrated Credit Solutions 1 1 INTRODUCTION Section 32 of the Constitution of

More information

ONTARIO SECURITIES COMMISSION PRACTICE GUIDELINE

ONTARIO SECURITIES COMMISSION PRACTICE GUIDELINE ONTARIO SECURITIES COMMISSION PRACTICE GUIDELINE 1. APPLICATION AND INTERPRETATION... 1 (1) APPLICATION... 1 2. FILING DOCUMENTS... 1 (1) REDACTIONS... 1 (2) MERITS HEARING FOR AN ENFORCEMENT PROCEEDING...

More information

Disciplinary Regulations

Disciplinary Regulations Disciplinary Regulations 1 Vision Professional financial planning for all. Our Mission The FPI s mission is to advance and promote the pre-eminence and status of financial planning professionals, while

More information

DISCIPLINARY PROCEDURE

DISCIPLINARY PROCEDURE 1 DISCIPLINARY PROCEDURE 1. General 1.1 This is the disciplinary procedure ( Disciplinary Procedure, or Procedure ) and relative regulations ( Regulations ) of The British Association of Snowsport Instructors

More information

OFFICIAL NOTICE 14 OF SOUTH AFRICAN SCHOOLS ACT, 84 OF 1996 as amended

OFFICIAL NOTICE 14 OF SOUTH AFRICAN SCHOOLS ACT, 84 OF 1996 as amended OFFICIAL NOTICE 14 OF 2014 SOUTH AFRICAN SCHOOLS ACT, 84 OF 1996 as amended REGULATIONS FOR THE ELECTION OF SCHOOL GOVERNING BODIES I, Grizelda Cjiekella Lecholo, Member of the Executive Council for Education

More information

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents 1995R2868 EN 23.03.2016 005.002 1 This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents B COMMISSION REGULATION (EC) No 2868/95 of 13 December

More information

INFORMATION MANUAL FOR PIONEER FOODS (PROPRIETARY) LIMITED

INFORMATION MANUAL FOR PIONEER FOODS (PROPRIETARY) LIMITED INFORMATION MANUAL FOR PIONEER FOODS (PROPRIETARY) LIMITED Prepared in accordance with section 51 of the Promotion of Access to Information Act Act 2 of 2000 Ref No.: PFG_PAIA_111231 TABLE OF CONTENTS

More information

MANUAL. [as required by Section 51 of Act No. 2 of 2000, Promotion of Access to Information Act, ("the Act")]

MANUAL. [as required by Section 51 of Act No. 2 of 2000, Promotion of Access to Information Act, (the Act)] 2nd Floor, North Block Thrupps Illovo Centre 204 Oxford Road Illovo 2196 PO Box 78662 Sandton 2146 Docex 264 Randburg e-mail: law@elawnet.co.za website : www.gji.co.za tel : (+27 11) 268 0287 fax : (+27

More information

ANNEXURE K RULES FOR THE CONDUCT OF PROCEEDINGS BEFORE THE BARGAINING COUNCIL FOR THE RESTAURANT, CATERING AND ALLIED TRADES TABLE OF CONTENTS

ANNEXURE K RULES FOR THE CONDUCT OF PROCEEDINGS BEFORE THE BARGAINING COUNCIL FOR THE RESTAURANT, CATERING AND ALLIED TRADES TABLE OF CONTENTS ANNEXURE K RULES FOR THE CONDUCT OF PROCEEDINGS BEFORE THE BARGAINING COUNCIL FOR THE RESTAURANT, CATERING AND ALLIED TRADES TABLE OF CONTENTS PART ONE SERVING AND FILING DOCUMENTS 1. How to contact the

More information

ADMINISTRATIVE DIRECTION NO. 2008/6. The Special Representative of the Secretary-General,

ADMINISTRATIVE DIRECTION NO. 2008/6. The Special Representative of the Secretary-General, UNITED NATIONS United Nations Interim Administration Mission in Kosovo UNMIK NATIONS UNIES Mission d Administration Intérimaire des Nations Unies au Kosovo UNMIK/AD/2008/6 11 June 2008 ADMINISTRATIVE DIRECTION

More information

BERMUDA COPYRIGHT TRIBUNAL RULES 2014 BR 11 / 2014

BERMUDA COPYRIGHT TRIBUNAL RULES 2014 BR 11 / 2014 QUO FA T A F U E R N T BERMUDA COPYRIGHT TRIBUNAL RULES 2014 BR 11 / 2014 TABLE OF CONTENTS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 PART 1 PRELIMINARY Citation Interpretation Overriding objective Tribunal

More information

STANDING ORDER (GENERAL) 101 THE MANAGEMENT OF COMPLAINTS AGAINST THE SOUTH AFRICAN POLICE SERVICE

STANDING ORDER (GENERAL) 101 THE MANAGEMENT OF COMPLAINTS AGAINST THE SOUTH AFRICAN POLICE SERVICE STANDING ORDER (GENERAL) 101 THE MANAGEMENT OF COMPLAINTS AGAINST THE SOUTH AFRICAN POLICE SERVICE 1. Background The purpose of this order is to regulate the management of complaints against the Service.

More information

MANUAL IN TERMS OF SECTION 51 OF THE PROMOTION OF ACCESS TO INFORMATION ACT. ACT No. 2 OF (the "Act") MATRIX FUND MANAGERS (PTY) LTD

MANUAL IN TERMS OF SECTION 51 OF THE PROMOTION OF ACCESS TO INFORMATION ACT. ACT No. 2 OF (the Act) MATRIX FUND MANAGERS (PTY) LTD MANUAL IN TERMS OF SECTION 51 OF THE PROMOTION OF ACCESS TO INFORMATION ACT ACT No. 2 OF 2000 (the "Act") for MATRIX FUND MANAGERS (PTY) LTD (Registration Number: 2007/028504/07) Date of compilation: July

More information

A guide to the six-month process for notified resource consent applications

A guide to the six-month process for notified resource consent applications A guide to the six-month process for notified resource consent applications Incorporating changes as a result of the Resource Management Amendment Act 2013 Disclaimer The information in this publication

More information

BDO Corporate Finance (PTY) LTD

BDO Corporate Finance (PTY) LTD BDO Corporate Finance (PTY) LTD REGISTRATION NUMBER: 1983/002903/07 PROMOTION OF ACCESS TO INFORMATION ACT NO. 2 of 2000 1 P a g e INDEX 1. Foreword Pg 2 2. Contact Person Pg 3 3. HRC Guide Pg 4 4. Automatic

More information

Stakeholder Governance Guide

Stakeholder Governance Guide Stakeholder Governance Guide Effective 2.22.2017 Table of Contents Introduction... 4 Definition of Terms:... 5 1. Leadership... 7 1.1. Entity Leadership Selection... 7 1.1.2. Soliciting Leadership Nominations

More information

AMBER VALLEY BODY CORPORATE

AMBER VALLEY BODY CORPORATE PROMOTION OF ACCESS TO INFORMATION ACT, ACT 2 OF 2000 ("The Act") SECTION 51 MANUAL FOR AMBER VALLEY BODY CORPORATE Table of Contents Preamble 2 Introduction 2 Particulars in terms of Section 51 of the

More information

Rules for the conduct of proceedings before the CCMA. Act. Published under. GN R1448 in GG of 10 October as amended by

Rules for the conduct of proceedings before the CCMA. Act. Published under. GN R1448 in GG of 10 October as amended by Rules for the conduct of proceedings before the CCMA Act Published under GN R1448 in GG 25515 of 10 October 2003 as amended by GN R1512 in GG 25607 of 17 October 2003 GN R1748 of 2003 in GG 25797 of 5

More information

Institute of Mine Seismology Pty Ltd Registration number: 2010/007290/07

Institute of Mine Seismology Pty Ltd Registration number: 2010/007290/07 Registration number: 2010/007290/07 a company with limited liabilities with principal business of research, development, manufacturing, marketing, and support of micro seismic equipment. (the Company )

More information

Registration Number 1994/000272/23 PLATINUM BLACK CC MANUAL. in terms of. Section 51 of. The Promotion of Access to Information Act 2/2000

Registration Number 1994/000272/23 PLATINUM BLACK CC MANUAL. in terms of. Section 51 of. The Promotion of Access to Information Act 2/2000 Registration Number 1994/000272/23 PLATINUM BLACK CC MANUAL in terms of Section 51 of The Promotion of Access to Information Act 2/2000 (the "ACT") Date of Compilation: December 2011 Date of Revision:

More information

DEPARTMENT OF HEALTH

DEPARTMENT OF HEALTH DEPARTMENT OF HEALTH No. R. 20 16 January 2008 NURSING ACT, 2005 (ACT NO. 33 OF 2005) REGULATIONS RELATING TO THE NOMINATION AND APPOINTMENT OF MEMBERS OF THE COUNCIL The Minister of Health has, in terms

More information

Securities Dealer Licence. Application Form

Securities Dealer Licence. Application Form Securities Dealer Licence Application Form FINANCIAL SERVICES AUTHORITY Bois De Rose Avenue P.O. Box 991 Victoria Mahé Seychelles Tel: +248 4380800 Fax: +248 4380888 Website:www.fsaseychelles.sc Email:

More information

The Franchise Association of South Africa. Promotion of Access to Information Act Manuel

The Franchise Association of South Africa. Promotion of Access to Information Act Manuel The Franchise Association of South Africa Promotion of Access to Information Act Manuel REQUEST FOR ACCESS TO RECORDS THE MANUAL HAS BEEN PREPARED FOR FRANCHISE ASSOCIATION OF SOUTH AFRICA (HEREINAFTER

More information

Applicant details. *Please note that an additional charge may apply for special dietry requirements (e.g. vegan, halaal, kosher etc.).

Applicant details. *Please note that an additional charge may apply for special dietry requirements (e.g. vegan, halaal, kosher etc.). Application Form GRAP Financial Statements: Enhancing Quality Through Review 26-27 February 2018 The following application form consists of two sections: Section A: Individual Applicants Section B: Requesting

More information

Certified South African Wagyu Beef Trade Mark Licence Agreement

Certified South African Wagyu Beef Trade Mark Licence Agreement Ver 2 Nov 2018 Certified South African Wagyu Beef Trade Mark Licence Agreement 1. Introduction The Wagyu Society of South Africa (WSA) has established the Certified South African Wagyu Beef (CWB) program

More information

PAIA MANUAL: SA UNDERWRITING AGENCIES (PTY) LTD. SA UNDERWRITING AGENCIES (PTY) LTD (Registration No: 1992/03324/07) Hereafter referred to as SAU

PAIA MANUAL: SA UNDERWRITING AGENCIES (PTY) LTD. SA UNDERWRITING AGENCIES (PTY) LTD (Registration No: 1992/03324/07) Hereafter referred to as SAU Physical: S.A. Underwriters Place, Bond Street Business Park, Randburg Postal: PO Box 3606, Randburg, 2125 Telephone: 011 777 7200 After hours: 0861 727 253 Fax: 011 777 7345 Email: info@saunderwriters.com

More information

Promotion of Access to Information Act. Section 51 Manual. For. FREE 4 ALL (Pty) Ltd

Promotion of Access to Information Act. Section 51 Manual. For. FREE 4 ALL (Pty) Ltd Promotion of Access to Information Act Section 51 Manual For FREE 4 ALL (Pty) Ltd 1. INTRODUCTION This manual is published in terms of Section 51 of the Promotion of Access to Information Act, 200 (act

More information

BENEFIT PAYMENT AGREEMENT. Between ( DF ) A Company duly incorporated in accordance with the laws of. The Republic of South Africa,

BENEFIT PAYMENT AGREEMENT. Between ( DF ) A Company duly incorporated in accordance with the laws of. The Republic of South Africa, BENEFIT PAYMENT AGREEMENT Between THE DATA FACTORY (PTY) LIMITED ( DF ) A Company duly incorporated in accordance with the laws of The Republic of South Africa, Registration number 2000/013055/07 and (

More information

REQUEST FOR PROPOSALS For Blanket Agreement to supply of coffins Boxes RFP #: 14/S/HAAD/PT/2012

REQUEST FOR PROPOSALS For Blanket Agreement to supply of coffins Boxes RFP #: 14/S/HAAD/PT/2012 REQUEST FOR PROPOSALS For Blanket Agreement to supply of coffins Boxes RFP #: 14/S/HAAD/PT/2012 Bid issue date: 14/05/2012 Deadline for submission of proposals: 31/05/2012 Time: 2:00 PM 1 / 21 INDEX CONTENTS

More information

NPO Legal Guides. Practical tools for NPO Leaders. A Basic Guide to the NPO Act

NPO Legal Guides. Practical tools for NPO Leaders. A Basic Guide to the NPO Act NPO Legal Guides Practical tools for NPO Leaders A Basic Guide to the NPO Act A Basic Guide to the Nonprofit Organisations Act Contents 1. Introduction to nonprofit organisations:...2 2. Introduction to

More information

Namibia Financial Institutions Supervisory Authority Act 3 of 2001 section 35 read with section 24

Namibia Financial Institutions Supervisory Authority Act 3 of 2001 section 35 read with section 24 Republic of Namibia 1 Annotated Statutes MADE IN TERMS OF Namibia Financial Institutions Supervisory Authority Act 3 of 2001 section 35 read with section 24 Government Notice 160 of 2006 (GG 3705) came

More information

Office Consolidation Brampton Appeal Tribunal By-law A By-law to create the Brampton Appeal Tribunal and to establish its Rules of Procedure

Office Consolidation Brampton Appeal Tribunal By-law A By-law to create the Brampton Appeal Tribunal and to establish its Rules of Procedure Office Consolidation Brampton Appeal Tribunal By-law 48-2008 A By-law to create the Brampton Appeal Tribunal and to establish its Rules of Procedure (as amended by By-laws 78-2009, 340-2012, 332-2013,

More information

/q: ~:-/ ~,. 1 /. '- H, \ f \!,... :';"~ GOVERNMENT NOTICE DEPARTMENT OF TRADE AND INDUSTRY

/q: ~:-/ ~,. 1 /. '- H, \ f \!,... :';~ GOVERNMENT NOTICE DEPARTMENT OF TRADE AND INDUSTRY STAATSKOERANT, 3 JUNIE 201 1 N o. 34348 3 GOVERNMENT NOTICE DEPARTMENT OF TRADE AND INDUSTRY No. 489 3 June 2011 RULES REGULATING THE FUNCTIONING OF THE NATIONAL CONSUMER COMMISSION IN TERMS OF THE CONSUMER

More information