Developments in Construction Law in Singapore (2014)

Size: px
Start display at page:

Download "Developments in Construction Law in Singapore (2014)"

Transcription

1 Developments in Construction Law in Singapore (2014) Ho Chien Mien Partner Litigation and Dispute Resolution 20 January H P Construction & Engineering Pte Ltd v Chin Ivan [2014] SGHC 137 Architect certificate issued under SIA Conditions allegedly affected by fraud Issues: Standard of proof required to obtain stay of proceedings in favour of arbitration Whether certificates wholly invalid due to architect acting outside scope of his authority Possibility of granting partial stay of proceedings in favour of arbitration

2 H P Construction Engineering Pte Ltd v Chin Ivan [2014] SGHC Facts Chin ( D ) employed H P ( P ) in May 2009 as main contractor to build two detached houses in Sentosa Cove Contract used was the SIA Conditions (Lump Sum Contract) (7 th Ed, April 2005). Cl 31(13) of the SIA Conditions provided that: No certificate of the Architect under this Contract shall be final and binding in any dispute between the Employer and the Contractor, whether before an arbitrator or in the Courts, save only that, in the absence of fraud or improper pressure or interference by either party, full effect by way of Summary Judgment or Interim Award or otherwise shall, in the absence of express provision, be given to all decisions and certificates of the Architect (other than a Cost of Termination Certificate or a Termination Delay Certificate (continued at next page) H P Construction Engineering Pte Ltd v Chin Ivan [2014] SGHC under clause 32(8) of these Conditions), whether for payment or otherwise, until final judgment or award, as the case may be, and until such final judgment or award such decision or certificates shall (save as aforesaid and subject to sub-clause (6) of this condition) be binding on the Employer and the Contractor in relation to any matter which, under the terms of the Contract, the Architect has a fact taken into account or allowed or disallowed, or any disputed matter upon which under the terms of the Contract he has as a fact ruled, in his certificates or otherwise. The Architect shall in all matters certify strictly in accordance with the terms of the Contract. In any case of doubt the Architect shall, at the request of either party, state in writing within 28 days whether he has as a fact taken account of or allowed or disallowed or ruled upon any matter in his certificates, if so identifying any certificate and indicating the amount (if any) taken into account or allowed or disallowed, or the nature of any ruling made by him, as the case may be.

3 H P Construction Engineering Pte Ltd v Chin Ivan [2014] SGHC Facts (cont d) Architect issued two Architect s Instructions ( AIs ) (which formed the basis for certificates later) approving some variations on P s list of proposed variation works, including items relating to claims for: Preliminaries for an alleged extension of time granted to the P to complete the project; and An alleged extension of the defects liability period (cumulatively, the Disputed Items ). P raised an interim payment claim and final payment claim. Architect issued Progress Certificate for $321, and Final Certificate for $720, Total amount certified was $1,041,801.22, of which QS valued the Disputed Items at S$334, D did not pay the certified sum of $1,041, P brought a suit against D claiming this payment. H P Construction Engineering Pte Ltd v Chin Ivan [2014] SGHC Facts (cont d) D applied for a stay of proceedings under section 6 of Arbitration Act on the basis that the certificates had been procured by fraud. To support this argument, D relied on a letter dated March 2014 from the Architect stating that the Architect relied on P s representation that D had agreed to various proposed variations (including the Disputed Items) in issuing the AIs ( the Letter ). D alleged that P fraudulently made this representation as D had not given such consent. P denied ever making the representation to the architect The Assistant Registrar granted D s application to stay the proceedings in favour of arbitration on the basis that there appeared to be a bona fide dispute as to whether the certificates were procured by fraud. P appealed the decision

4 H P Construction Engineering Pte Ltd v Chin Ivan [2014] SGHC Issue 1: What is the standard of proof that D is required to show to obtain a stay of proceedings in favour of arbitration on the basis that a certificate issued by an architect under SIA Conditions was affected by fraud? This is a novel point of law as there have not been any decided cases in the Singapore High Court where allegation of fraud has been raised as a ground for such a stay [26] D s argument: A stay of proceedings in favour of arbitration can be granted if D can show there is, prima facie, a bona fide dispute as to whether there was improper pressure or interference: Anwar Siraj v Teo Hee Lai Building Construction Pte Ltd [2007] 2 SLR(R) 500 Argued this standard should be applied to the instant case to determine whether to stay proceedings on the basis that certificates were fraudulently procured H P Construction Engineering Pte Ltd v Chin Ivan [2014] SGHC 137 P s argument: 7 Anwar Siraj is authority only for the standard of proof required to stay proceedings due to improper influence or interference, so is distinguishable from the instant case. Fraud vis-à-vis an architect s certificate requires the party applying for stay of proceedings in favour of arbitration to meet a higher threshold D must make out an arguable case that certificates were procured by fraud Higher standard of proof required because fraud has serious implications. Cogent evidence is required before court is satisfied that an allegation of fraud is established [36] Analogised the standard of proof required for a stay of proceedings for fraud to the high standard of proof required to obtain injunctions to restrain calls on a performance bond: must show that it is seriously arguable that, on the material available, the only realistic inference is that the beneficiary could not honestly have believed in the validity of its demands on the performance bond (Shanghai Electric Group Co Ltd v PT Merak Energi Indonesia [2010] 2 SLR 329 at [36]-[37])

5 H P Construction Engineering Pte Ltd v Chin Ivan 8 [2014] SGHC 137 Held: Party applying for stay of proceedings in favour of arbitration on the basis that a certificate issued by an architect under SIA Conditions was affected by fraud must establish that there is a bona fide dispute as to fraud on a prima facie basis, where there must be credible evidence of fraud and not mere allegations. [40 and 42] Acknowledged that fraud is a serious allegation, but does not necessitate a different standard of proof to obtain a stay in favour of arbitration [37] Rejected P s analogy of stay of proceedings in favour of arbitration on architect s certificates and obtaining injunction to restrain calls on performance bonds on grounds of fraud as (1) unlike a performance bond, architect s certificates not intended to be security and is connected to an underlying contract; and (2) there are doctrinal differences between injunctive relief and stay of proceedings [38] H P Construction Engineering Pte Ltd v Chin Ivan 9 [2014] SGHC 137 So, applying the law to the facts was there a bona fide dispute as to whether there was fraud? Acknowledged arguments by P and D as to whether there existed a bona fide dispute of fraud BUT refused to make a finding on the merits; confirmed approach of Andrew Ang J in Anwar Siraj at [36] that: I [do not] have to make a finding on the merits that there was indeed improper pressure or interference by the plaintiffs. It suffices for me to say that prima facie there is a bona fide dispute whether there is improper pressure or interference. Merely found that there was a bona fide dispute as to whether there was fraud: It cannot be said that the Defendant s allegation of fraud is a mere assertion or that the Letter is not credible. I therefore find that it is not indisputable that the Certificates are not affected by fraud [49]

6 H P Construction Engineering Pte Ltd v Chin Ivan 10 [2014] SGHC 137 Issue 2: Are the certificates, as a result of the architect acting outside the scope of his authority, wholly invalid such that a stay of proceedings in favour of arbitration should be granted? D s argument: Certificates were not issued in accordance with terms of contract in that they included claims for the Extended Preliminaries A claim for extended preliminaries is in the nature of a claim for loss and damage (Pitchmastic plc v Birse Construction Ltd (19 May 2000)) and is outside the certifying power of the Architect, because the architect shall, in the absence of express provision, have no power to decide or certify any claim for breach of contract (emphasis added) (Cl 31(14) SIA Conditions) the architect had no power to issue instructions to authorise payment for extended preliminaries (Cl 1(4) SIA Conditions), so certificates which relied on AIs were similarly infected [50] Architect failed to apply his mind to whether he had the right to issue instructions for the items on the AIs by relying on the alleged misrepresentations and on the project manager s silence P s argument: Pitchmastic is distinguishable Under SIA Conditions, architect was empowered to issue instructions ordering variations to the works under cl 12(1) which included the valuation of preliminary items under cl 12(4) H P Construction Engineering Pte Ltd v Chin Ivan 11 [2014] SGHC 137 Held: A certificate not issued in accordance with the underlying contract can be regarded as a nullity (and therefore sufficient to stay proceedings); however, non-compliance is not fatal where there is evidence of waiver in the absence of substantial vitiating factors I accept that if a certificate is not issued in accordance with the contract, it can be regarded as a nullity. This seems to have been treated as an additional exception to the exceptions of fraud, improper pressure and interference. However, non-compliance is not always fatal, such as where there is evidence of waiver, in the absence of substantial vitiating factors. [53] Policy reasoning: Khoo J in China Construction (South Pacific) Development Co Pte Ltd v Leisure Park (Singapore) Pte Ltd [1999] 3 SLR(R) 583 at [29]: To prevent employers from relying on and taking advantage of lapses on the part of architects (such as the form and timing of certifications of payments to the contractor)

7 H P Construction Engineering Pte Ltd v Chin Ivan 12 [2014] SGHC 137 (Having established prima facie a bona fide dispute of fraud) Issue 3: To stay whole of P s claim, or to grant D a partial stay of proceedings? A novel point of law [T]here do not appear to be any cases in Singapore where only part of an architect s certificate has been found to be valid the Defendant has also not provided any cases which concluded that it is not possible to accord temporary finality to part of an architect s certificate. It is still open to me to decide. [63] P s argument: Lojan Properties (CA) is authority that a stay can be granted on a sum that forms only part of a certificate (HC rejected as an incorrect reading of the case) D s argument: Wording of cl 31(13) of SIA Conditions (that a certificate should only be given full effect by way of summary judgment in the absence of fraud) does not contemplate that only part of a certificate may be given temporary effect. Arguably, any fraud, even if it relates to a part of the certificate, means that fraud is present and full effect cannot be given to the certificate H P Construction Engineering Pte Ltd v Chin Ivan 13 [2014] SGHC 137 The objective and spirit of cl 31(13) SIA Conditions (the importance of temporary finality of architect s certificates to the construction industry) should not be disregarded. No suggestion that other items on the Certificates were infected by fraud and they could have just easily been certified on a different certificate. Disputed Items were clearly quantified and severable if found to be affected by fraud Re objective and spirit of cl 31(13) SIA Conditions I recognise that temporary finality under the SIA Conditions serves an important purpose in ensuring that contractors are paid on time. Contractors faced the problem of being kept out of their moneys for extended periods of time by unscrupulous employers invoking technical grounds to avoid payment The importance of progress payments to contractors cannot be understated in an industry beset by cashflow problems. [27 and 29] Conclusion: Granted stay of part of P s claim that relates to the Disputed Items, no stay in respect of the remaining claimed sums

8 14 Poh Cheng Chew v K P Koh & Partners Pte Ltd and another [2014] SGHC 20 Breaches of Settlement Agreement in relation to rectification works to a property Issues: Whether appointment of and award by the Professional Engineer should be set aside Whether clause in Settlement Agreement prohibiting parties from complaining to the Professional Engineers Board is illegal and unenforceable Poh Cheng Chew v K P Koh & Partners Pte Ltd and another [2014] SGHC Facts On 8 April 2010, Poh Cheng Chew ( P ) engaged 1D as Architect and 2D as Contractor to carry out additions and alterations to a property owned by P ( the A&A Works ) 1D and 2D owned by Koh Kok Peng ( Koh ), a professional engineer Dispute arose regarding the A&A Works, which were alleged by P to be defective and incomplete P commissioned 2 reports to be produced on the A&A Works On 8 February 2012, P issued a letter of demand to the 1D and made complaints to the Professional Engineers Board ( PEB ) and BCA On 12 March 2012, Parties entered into a Settlement Agreement through mediation

9 Poh Cheng Chew v K P Koh & Partners Pte Ltd and another [2014] SGHC 20 Facts (cont d) 16 As part of the Settlement Agreement, 1) A Professional Engineer ( PE ) was to be appointed to: Set out the scope and specifications of the rectification works Prepare and call for a tender for the said works Evaluate the tenders and award the contract 2) Ds were to pay the fees of the PE, the costs of the rectification works, the costs of 2 service apartments for the duration of the rectification works, and $20,000 to P as compensation for moving and costs 3) P was to refrain from filing complaints against Koh or the Ds with the PEB Chan Yaw Fai ( Chan ) was appointed as PE and awarded the contract to Crystallite Construction & Engineering Pte Ltd ( Crystallite ) for $498,000 to carry out the rectification works. Ds disagreed with Chan s decision and did not make further payment to P Poh Cheng Chew v K P Koh & Partners Pte Ltd and another [2014] SGHC Facts (cont d) P claimed the sum of $718, for the loss and damage suffered as a result of Ds breach of the Settlement Agreement, and made a complaint to the PEB on 16 August 2012 against Koh Ds denied that P was entitled to any payment, prayed for Chan s appointment and the award of the contract to Crystallite to be set aside, and claimed that P had breached a fundamental term of the Settlement Agreement by making a complaint to the PEB.

10 Poh Cheng Chew v K P Koh & Partners Pte Ltd and another [2014] SGHC Issue 1: Could: (i) Chan s appointment as PE; and (ii) Chan s award of the rectification works to Crystallite, be set aside solely because he acted in a biased manner and chose to align his interests with those of P? D s argument: Chan was not independent, but acting under the influence of P and/or his agents, and had materially departed from his instructions in awarding the contract. Alternatively, P had conspired with Chan to increase the scope and specifications of the rectification works. Poh Cheng Chew v K P Koh & Partners Pte Ltd and another [2014] SGHC Held: The starting point for ascertaining the validity of an expert's appointment is the contract itself. (i) Re Chan s appointment as PE Lionel Yee JC: To my mind, [D s] concerns do not relate to the circumstances of Chan s appointment. They are more relevant to the issue of whether Chan acted properly in making his determinations under the Settlement Agreement Ds should have (but did not) contend that: Chan s appointment was not in accordance with the Settlement Agreement Chan was in a position of conflict of interest in that he had prior dealings with any interested parties, as in HSBC Institutional Trust Services (Singapore) Ltd v Toshin Development Singapore Pte Ltd [2012] 4 SLR 738 Conclusion: No reason to set aside Chan s appointment as PE

11 Poh Cheng Chew v K P Koh & Partners Pte Ltd and another [2014] SGHC High Court (cont d): (ii) Re Chan s award to Crystallite As a general rule, the only grounds to challenge an expert s determination are:- a) Material departure from instructions; b) Manifest error; or c) Fraud, collusion, partiality and the like. [See The Oriental Insurance Co Ltd v Reliance National Asia Re Pte Ltd [2009] 2 SLR(R) 385] The Court proceeded to examine ground a) and c) in relation to the instant case Poh Cheng Chew v K P Koh & Partners Pte Ltd and another [2014] SGHC High Court examining issue of Chan s award to Crystallite (cont d): Material departure from instructions? As to the test of materiality, any departure from instructions must generally be regarded as material unless it can truly be characterised as trivial or de minimis Once a material departure from instructions is established, the court is not concerned with its effect on the result A distinction should be drawn between mistakes made by the expert and a departure from the instructions, as in Nikko Hotels (UK) Ltd v MEPC plc [1991] 2 EGLR 103: If he has answered the right question in the wrong way, his decision will be binding. If he has answered the wrong question, his decision will be a nullity. In this case, a holistic view of the Settlement Agreement shows that the parties intended to give the PE a measure of discretion in preparing the scope of the rectification works Chan did not depart from his instructions by including other works that were not stated in the Consultants Reports

12 Poh Cheng Chew v K P Koh & Partners Pte Ltd and another [2014] SGHC High Court examining issue of Chan s award to Crystallite (cont d): Fraud, collusion, and partiality? The test of partiality is one of actual bias and not apparent bias (Macro v Thompson (No 3) [1997] 2 BCLC 36 Chan failed to act impartially as: Chan was of the view that the rectification works were to be carried out to the Plaintiff s satisfaction Chan expanded the scope of the rectification works on P s request Chan did not take into account the Ds interests at all and admitted his evaluation of the tenderers was not objective. Conclusion: The Court set aside the award of the contract to Crystallite Poh Cheng Chew v K P Koh & Partners Pte Ltd and another [2014] SGHC Issue 2: Was the clause in the Settlement Agreement which prohibited P from complaining about D to the PEB valid? Ds argument: P did not plead that Clause 12 of the Settlement Agreement, prohibiting P from making a complaint to the PEB, was against public policy There is nothing in the legislation to compel someone to file a complaint to PEB Such a clause prohibiting a complaint is akin to a compromise by a party not to commence legal proceedings against another party in exchange for compensation Clause 12 is like an agreement not to volunteer to give evidence Public policy requires that contracts freely entered into be upheld

13 Poh Cheng Chew v K P Koh & Partners Pte Ltd and another [2014] SGHC Held: A clause in the Settlement Agreement prohibiting P from making a complaint to the PEB is illegal and unenforceable, as it would allow an engineer to effectively contract out of regulatory oversight of his professional conduct by the PEB under the Professional Engineers Act Simply because the Professional Engineers Act does not impose a duty on persons to make complaints but allows for complaints to be made is thus not conclusive; the essential inquiry is parliamentary intention and the purpose of the statute This reflects a wider public interest to prevent misconduct on the part of those who hold themselves out to the public at large as professional engineers Poh Cheng Chew v K P Koh & Partners Pte Ltd and another [2014] SGHC High Court (cont d): There is no provision in the Professional Engineers Act which allows professional engineers to release or exempt themselves from disciplinary proceedings by paying compensation in an agreement between private parties The need to uphold professional accountability outweighs any public policy to allow business to be transacted freely and to uphold commercial bargains The finding of illegality does not render the Settlement Agreement void as the offending portion is severable

14 26 Tech-System Design & Contract (S) Pte Ltd v WYWY Investments Pte Ltd [2014] SGHC 57 Application for injunction to restrain call on performance bonds until determination of arbitration proceedings Issue: Whether call on bonds unconscionable Tech-System Design & Contract (S) Pte Ltd v WYWY Investments Pte Ltd [2014] SGHC Facts: Dispute concerned a property developer ( D ) and main contractor ( P ) for the development of three apartment blocks Under the main contract, P was required to provide, and did provide two performance bonds for 10% of the total contract price in lieu of a deposit Two disputes subsequently arose regarding (a) delay in completion and (b) the remedy of defects which was referred to arbitration Arbitration had not begun when D issued demands to the insurer for the total amount of the bonds P applied for an injunction to restrain D from calling on the performance bonds P argued that the calls were unconscionable since they were made before the determination or outcome of the arbitration D argued that it was entitled to call because it was claiming from P a sum greater than that secured by the bonds The contract entitled D to call on the bonds without furnishing any proof

15 Tech-System Design & Contract (S) Pte Ltd v WYWY Investments Pte Ltd [2014] SGHC Issue: Whether the call on the performance bonds was unconscionable based on a prima facie assessment of the context Court held that it was P s burden to prove on a strong prima facie basis that the call was unconscionable: Thus a call that was genuinely made in the honest belief that the obligor was in breach of its obligations would be respected unless unconscionability was shown Unconscionability would include elements of abuse, unfairness and dishonesty The applicant would have to establish unconscionability to the high threshold of a strong prima facie case BS Mount Sophia Pte Ltd v Join-Aim Pte Ltd [2012] 3 SLR 352 The court would consider thoroughly the entire context of the case and would only grant an injunction if the entire context of the case was particularly malodorous - BS Mount Sophia Pte Ltd v Join-Aim Pte Ltd [2012] 3 SLR 352 The fact that disputes arising from the contract were referred to arbitration would not preclude a call on the bond The purpose of a performance bond was for a party to obtain security for its claim in damages, even if it was disputed. When the dispute was finally determined, the obligor could claim compensation for overpayment due to the call. Tech-System Design & Contract (S) Pte Ltd v WYWY Investments Pte Ltd [2014] SGHC P put forward 5 arguments to substantiate its claim that the call was unconscionable. P s argument 1: Architect Failed to Properly Grant EOT: P pleaded that he had carried out substantial variation works even before receiving written instructions or an extension of time and he trusted the architect to do the right thing when he applied for an extension. When P did apply for an extension, he alleged that he had provided sufficient documentation supporting his applications. Held: Correspondence between P and architect revealed prima facie that there were insufficient reasons to grant an extension of time. Architect s directions revealed on a prima facie level that the delay had been brought to P s attention numerous times before the actual completion of works

16 Tech-System Design & Contract (S) Pte Ltd v WYWY Investments Pte Ltd [2014] SGHC P s argument 2: Architect Subject to Defendant s Pressure: P also claimed that the architect subsequently confided to him that he had been pressured by the defendant not to grant any extension of time Held: Allegations that the architect was being pressured not to grant an extension were hearsay P s argument 3: Improper Appointment of Architect s Assistant: P claimed that one Mr Kevin Timmons had been improperly appointed to assist the architect to evaluate the extension of time Held: Bare allegation hence claim rejected. Tech-System Design & Contract (S) Pte Ltd v WYWY Investments Pte Ltd [2014] SGHC P s argument 4: Unconscionable Claim on Defects: P pleaded that while the defects were minor, (a) no site inspection had been carried out to ascertain the defects and (b) D was attempting to show that P s work was so unacceptable as to have over 500 items of defects Held: The fact that no site inspection was carried out despite the defendant s allegations was not unconscionable. Even if the lack of an inspection was unconscionable, it would not affect the call as the bulk of the claim was for liquidated damages. The fact that over 500 defects were listed was not unconscionable P s argument 5: Dispute Over Accounts: P disputed D s accounts Held: The accounts justifying the sums behind the call were not apparently dishonest or misleading. The call would be legitimate if made honestly and position was genuine. Any discrepancies were due to a dispute over the amount of liquidated damages

17 Tech-System Design & Contract (S) Pte Ltd v WYWY Investments Pte Ltd [2014] SGHC P s argument 6: Financial Hardship to P: P pleaded that calls put it in a very difficult financial position such that it would be unable to prosecute its claim against the D Held: Financial hardship of the P irrelevant. Unconscionability focused on the conduct of the beneficiary, not on the consequences on the obligor. 33 PT Perusahaan Gas Negara (Persero) TBK v CRW Joint Operation (Indonesia) and Another Matter [2014] SGHC 146 Application to set aside Interim Award giving effect to Dispute Adjudication Board decision and order of court enforcing Interim Award Issue: Whether Interim Award giving effect do Dispute Adjudication Board s decision enforceable as a final and binding award

18 PT PGN v CRW Joint Operation (Indonesia) Facts: 34 PGN ( P ) is a listed, state-owned company established under Indonesian law CRW ( D ) is also an entity established under Indonesian law and comprises three Indonesian limited liability companies. By contract entered into in 2006, P engaged D to design, procure, install, test and re-commission a pipeline to convey natural gas from South Sumatra to West Java. Contract incorporated the 1 st edition of the Conditions of Contract for Construction, published by the International Federation of Consulting Engineers/Fédération Internationale Des Ingénieurs-Conseils ( Red Book ), in particular, cl 20 relating to Claims, Disputes and Arbitration Dispute resolution process envisaged a contractual security of payment regime which required the dispute to be referred to a Dispute Adjudication Board ( DAB ), before referring the dispute to arbitration In 2008, disputes arose on a number of variation claims made by D under the contract, The parties referred their dispute to the DAB constituted by the contract, PT PGN v CRW Joint Operation (Indonesia) 35 Relevant Red Book Clauses ( ): 20.4 Obtaining Dispute Adjudication Board s Decision [1] If a dispute (of any kind whatsoever) arises between the Parties, either Party may refer the dispute in writing to the DAB for its decision. [4] Within 84 days after receiving such reference the DAB shall give its decision, which shall be reasoned and shall state that it is given under this Sub-Clause. The decision shall be binding on both Parties, who shall promptly give effect to it unless and until it shall be revised in an amicable settlement or an arbitral award as described below. [5] If either Party is dissatisfied with the DAB's decision, then either Party may, within 28 days after receiving the decision, give notice to the other Party of its dissatisfaction. If the DAB fails to give its decision within the period of 84 days after receiving such reference, then either party may, within 28 days after this period has expired, give notice to the other Party of its dissatisfaction. [6] Except as stated in Sub-Clause 20.7 neither Party shall be entitled to commence arbitration of a dispute unless a notice of dissatisfaction has been given in accordance with this Sub-Clause. [7] If the DAB has given its decision as to a matter in dispute to both Parties, and no notice of dissatisfaction has been given by either Party within 28 days after it received the DAB's decision, then the decision shall become final and binding upon both Parties.

19 PT PGN v CRW Joint Operation (Indonesia) 36 Relevant Red Book Clauses ( ) (Cont d): 20.5 Amicable Settlement Where notice of dissatisfaction has been given under Sub-Clause 20.4 above, both Parties shall attempt to settle the dispute amicably before the commencement of arbitration. However arbitration may be commenced on or after the fifty-sixth day after the day on which notice of dissatisfaction was given, even if no attempt at amicable settlement has been made Arbitration [1] Unless settled amicably, any dispute in respect of which the DAB's decision (if any) has not become final and binding shall be finally settled by international arbitration. Unless otherwise agreed by both Parties: (a) the dispute shall be finally settled under the Rules of Arbitration of the International Chamber of Commerce. (b) the dispute shall be settled by three arbitrators appointed in accordance with these Rules, and (c) the arbitration shall be conducted in the language for communications defined in Sub- Clause 1.4. PT PGN v CRW Joint Operation (Indonesia) 37 Relevant Red Book Clauses ( ) (Cont d): 20.6 Arbitration [2] The arbitrator(s) shall have full power to open up, review and revise any decision of the DAB, relevant to the dispute.... [3] Neither Party shall be limited in the proceedings before the arbitrator(s) to the evidence or arguments previously put before the DAB to obtain its decision, or to the reasons for dissatisfaction given in its notice of dissatisfaction. Any decision of the DAB shall be admissible in evidence in the arbitration.

20 PT PGN v CRW Joint Operation (Indonesia) 38 Relevant Red Book Clauses ( ) (Cont d): 20.7 Failure to Comply with Dispute Adjudication Board s Decision [1] In the event that: (a) neither Party has given notice of dissatisfaction within the period stated in Sub- Clause 20.4, (b) the DAB's related decision (if any) has become final and binding, and (c) a Party fails to comply with this decision, then the other Party may, without prejudice to any other rights it may have, refer the failure itself to arbitration under Sub-Clause Sub-Clause 20.4 and Sub-Clause 20.5 shall not apply to this reference. PT PGN v CRW Joint Operation (Indonesia) 39 Relevant Red Book Clauses ( ) (Cont d): Combined Effect of Red Book Clauses: If any dispute between the parties arose, the dispute had to be referred to the DAB before arbitration DAB would render a binding decision within 84 days Decision creates a secondary obligation to pay regardless of the underlying liability to pay This would give effect to the contractual security of payment regime pay now, argue later Arbitration could be commenced if the following conditions precedent were satisfied: If the dispute had been referred to the DAB first; If notice of dissatisfaction was given within 28 days of receipt of the decision; and Either parties fail to settle the dispute amicably or 56 days elapse from notice of dissatisfaction without an attempt at amicable settlement

21 PT PGN v CRW Joint Operation (Indonesia) 40 Relevant Red Book Clauses ( ) (Cont d): Combined Effect of Red Book Clauses (Cont d): Exceptionally arbitration could also be commenced if some or all the conditions precedent were disapplied: Under cl. 20.4[5], which dispenses with the requirement for a DAB decision if the DAB fails to determine within 84 days the dispute placed before it; or Under cl read with cl. 20.4[6], which dispenses with all three conditions precedent if neither party has served a notice of dissatisfaction with the DAB decision PT PGN v CRW Joint Operation (Indonesia) 41 Relevant Red Book Clauses ( ) (Cont d): Combined Effect of Red Book Clauses (Cont d): This creates a contractual security of payment regime which promotes a pay now argue later process The regime facilitates the contractor s cash flow by requiring the employer to pay now, pursuant to the DAB decision, while both employer and contractor remain entitled to argue the underlying merits of the payment obligation later at arbitration Arbitration is the sole method for parties to resolve their disputes with finality

22 PT PGN v CRW Joint Operation (Indonesia) 42 Procedural History: Dispute Adjudication Board In November 2008, pursuant to cl. 20 of the contract, D and P referred their disputes over variation claims to the DAB The DAB found in favour of D P refused to comply with the order of the DAB 2009 Arbitration In 2009, D commenced arbitration seeking only to compel P to comply with the DAB decision (the Secondary Dispute ), placing before the tribunal only the payment dispute, but not the underlying dispute regarding liability for the payments (the Primary Dispute ) By a majority, the tribunal found in favour of D and issued a Final Award requiring P to comply with the DAB decision However, the tribunal also expressly noted that P was at liberty to commence a separate arbitration to have the liability dispute heard and determined on the merits PT PGN v CRW Joint Operation (Indonesia) 43 Procedural History (Cont d): High Court (2010), Court of Appeal (2011) P successfully applied to the High Court in 2010 to have the award set aside. D appealed but the appeal was dismissed by the Court of Appeal 2011 Arbitration In 2011, D commenced arbitration, this time placing both the Primary Dispute and the Secondary Dispute before the tribunal P argued that the arbitration agreement and the International Arbitration Act did not permit an arbitration tribunal to compel P to comply with the DAB decision unless the same tribunal in the same award and not merely in the same arbitration hears the determines the liability dispute on the merits The tribunal rejected P s argument, and issued an interim award compelling P to comply with the DAB decision This award was expressly subject to a further final determination on the liability dispute.

23 PT PGN v CRW Joint Operation (Indonesia) 44 Procedural History (Cont d): D then applied to court for leave to enforce the interim award while P applied to set aside the interim award and the order permitting D to enforce that award Present application was to set aside An arbitration award; and the order of court permitting enforcement of the award PT PGN v CRW Joint Operation (Indonesia) 45 Main Issue: Whether D could enforce an interim award to compel payment pursuant to cl 20 of the Red Book, notwithstanding that the Primary Dispute has not been determined Sub-Issue 1: Is D s approach in the 2011 arbitration consistent with the parties agreement and their contractual dispute-resolution regime? This was essentially a matter of contractual interpretation to determine what the parties intended when they incorporated the Red Book conditions of contract. Held: The security of payment regime in cl 20 of the Red Book permitted the court to enforce an interim award compelling payment based on the DAB s decision, even if the liability dispute had not been determined. This would give effect to the pay now, argue later policy inherent in the security of payment regime. D s approach in the 2011 arbitration gave effect to this policy by placing both the Primary Dispute and the Secondary Dispute before the arbitration tribunal.

24 PT PGN v CRW Joint Operation (Indonesia) 46 Sub-Issue 2: Is the 2011 award a provisional award defective for want of finality? P s Arguments: The 2011 award lacked finality since it was an interim award that was subject to a final determination of the Primary Dispute Section 19B of the IAA does not permit a tribunal to issue such an award since only final and binding awards can be recognised S 19(1) IAA, which requires awards to be final and binding, overrides the tribunal s intent to issue an interim award S 19(2) IAA states that no future award can vary an interim award High Court: Held: The 2011 award, as a provisional award, was not defective for want of finality. PT PGN v CRW Joint Operation (Indonesia) 47 Sub-Issue 3: What effect does the IAA have on the 2011 award? P s Arguments: The combined effect of s 19B IAA was to deem the 2011 award to be a final and binding award. This went against the intention of the parties by determining with finality the Primary Dispute without determining or considering the dispute on its merits. This also rendered the tribunal functus officio in respect of the liability dispute Thus the tribunal had no power to issue the 2011 award which stated that P had to pay D pending the final resolution of the Parties dispute raised in these proceedings D s Arguments: 2011 interim award is not a provisional award but is a final and binding award mandated by s 19B(1). It is final and binding on the Secondary Dispute pending the final resolution of the Primary Dispute. The final award in the arbitration need not vary the 2011 interim award because it will determine with finality a different dispute (i.e. the Primary Dispute) 2011 tribunal is not functus officio because it has determined with finality only one dispute (i.e. the Secondary Dispute), leaving the Primary Dispute to be heard later

25 PT PGN v CRW Joint Operation (Indonesia) 48 Held: s. 19B IAA requires every award to have preclusive effect on its subject matter. It thereby precludes the parties and the tribunal from revisiting the subject-matter of that award. However, s, 19B does not prohibit a tribunal from issuing a provisional award, at the very least in a case where (as here) the parties contract gives them a substantive, contractual right to provisional relief. Thus the tribunal could issue a provisional award. The 2011 Interim Award, such an award, was not invalidated by the provisions of the IAA. PT PGN v CRW Joint Operation (Indonesia) 49 Sub-Issue 4: What effect does the 2011 award have on the ability of the tribunal to consider and determine the Primary Dispute? Held: s. 19B(2) IAA disallows the tribunal in any future award to vary, amend, correct, review add or revoke the 2011 interim award. But Tribunal is perfectly able to dispose the Primary Dispute without breaching s. 19B(2) IAA. Judge held that even if he was wrong in that the IAA does in fact prohibit provisional award and the 2011 interim award is in fact such a provisional award, s. 19B operates only with regard to the Secondary Dispute. The Parties right to have the Primary Dispute determined on its merits with finality, not being the subject-matter of the 2011 interim award, remain unaffected. The merits of the Primary Dispute are not res judicata. Red Book deliberately gives the parties dispute two temporal aspects. S. 19A IAA permits a tribunal to issue a series of interim awards, each is both final and binding on its subject-matter. It is no different where parties contract permits tribunal to divide one dispute before it on temporal lines.

26 PT PGN v CRW Joint Operation (Indonesia) 50 Sub-Issue 5: Can P succeed in setting aside the 2011 award on any of the following grounds: Excess of jurisdiction Breach of rules of natural justice Failure to comply with agreed procedure Held: On the fact, the court found that none of the grounds for setting aside were satisfied. 51 Questions?

27 Thank You 52 Ho Chien Mien T E ho.chienmien@allenandgledhill.com Allen & Gledhill LLP One Marina Boulevard #28-00 Singapore Notes: This presentation is intended to provide general information and is not meant to be exhaustive, comprehensive or authoritative. Allen & Gledhill LLP does not warrant its accuracy or completeness or accept any liability for any loss or damage arising from any reliance thereon. The information in this presentation should not be treated as a substitute for specific legal advice concerning particular situations.

Security of payment under FIDIC contracts: more secure, for now

Security of payment under FIDIC contracts: more secure, for now INSIGHT Security of payment under FIDIC contracts: more secure, for now January 28, 2015 Written by Eugene Tan, Tia Starey and Rupert Coldwell The High Court of Singapore recently handed down an important

More information

Arbitral tribunals; Decisions; Dispute adjudication boards; Enforcement; FIDIC forms of contract; Jurisdiction; Singapore

Arbitral tribunals; Decisions; Dispute adjudication boards; Enforcement; FIDIC forms of contract; Jurisdiction; Singapore An Excellent Decision From Singapore Which Should Enhance the Enforceability of Decisions of Dispute Adjudication Boards the Second Persero Case before the Court of Appeal Christopher R Seppälä * Arbitral

More information

THE SINGAPORE APPROACH TO THE ADJOURNMENT OF PROCEEDINGS TO ENFORCE A FOREIGN ARBITRAL AWARD

THE SINGAPORE APPROACH TO THE ADJOURNMENT OF PROCEEDINGS TO ENFORCE A FOREIGN ARBITRAL AWARD Published on 6 September 2018 THE SINGAPORE APPROACH TO THE ADJOURNMENT OF PROCEEDINGS TO ENFORCE A FOREIGN ARBITRAL AWARD Margaret Joan LING LLB (National University of Singapore); Partner, Litigation

More information

Singapore Court Should Not Have Set Aside ICC Award Enforcing Dispute Adjudication Board Decision

Singapore Court Should Not Have Set Aside ICC Award Enforcing Dispute Adjudication Board Decision MEALEY S TM International Arbitration Report Singapore Court Should Not Have Set Aside ICC Award Enforcing Dispute Adjudication Board Decision by Chris Seppälä White & Case LLP Paris A commentary article

More information

The legal justification for the enforcement of a binding DAB decision under the FIDIC 1999 Red Book

The legal justification for the enforcement of a binding DAB decision under the FIDIC 1999 Red Book The legal justification for the enforcement of a binding DAB decision under the FIDIC 1999 Red Book Taner Dedezade Corbett & Co International Construction Lawyers Ltd, London In a previous article, the

More information

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013)

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) 1. Scope of Application and Interpretation 1.1 Where parties have agreed to refer their disputes

More information

The Arbitration Act, 1992

The Arbitration Act, 1992 1 The Arbitration Act, 1992 being Chapter A-24.1* of the Statutes of Saskatchewan, 1992 (effective April 1, 1993) as amended by the Statutes of Saskatchewan, 1993, c.17; 2010, c.e-9.22; 2015, c.21; and

More information

THE COURTS ACT. Rules made by the Chief Justice, after consultation with the Rules Committee and the Judges, under section 198 of the Courts Act

THE COURTS ACT. Rules made by the Chief Justice, after consultation with the Rules Committee and the Judges, under section 198 of the Courts Act THE COURTS ACT Rules made by the Chief Justice, after consultation with the Rules Committee and the Judges, under section 198 of the Courts Act 1. Title These rules may be cited as the Supreme Court (International

More information

CHAPTER 4 THE ARBITRATION AND CONCILIATION ACT. Arrangement of Sections.

CHAPTER 4 THE ARBITRATION AND CONCILIATION ACT. Arrangement of Sections. CHAPTER 4 THE ARBITRATION AND CONCILIATION ACT. Arrangement of Sections. Section 1. Application. 2. Interpretation. PART I PRELIMINARY. PART II ARBITRATION. 3. Form of arbitration agreement. 4. Waiver

More information

THE INTERNATIONAL ARBITRATION ACT OF SINGAPORE

THE INTERNATIONAL ARBITRATION ACT OF SINGAPORE THE INTERNATIONAL ARBITRATION ACT OF SINGAPORE The laws governing private commercial arbitration in Singapore are divided into domestic and international regimes. There is a third regime that deals with

More information

CONTACT US. Background

CONTACT US. Background April 2015 Arbitration Singapore Court of Appeal espouses standards to be met when setting aside an arbitral award; reinforces Singapore s pro-arbitration policy CONTACT US In a judgment delivered on 31

More information

10th Anniversary Edition The Baker McKenzie International Arbitration Yearbook. Singapore

10th Anniversary Edition The Baker McKenzie International Arbitration Yearbook. Singapore 10th Anniversary Edition 2016-2017 The Baker McKenzie International Arbitration Yearbook Singapore 2017 Arbitration Yearbook Singapore Singapore Chan Leng Sun, S.C. 1 and Tan Weiyi 2 A. Legislation and

More information

Case Note. Nicholas POON* LLB (Summa) (Singapore Management University); Justices Law Clerk, Supreme Court of Singapore.

Case Note. Nicholas POON* LLB (Summa) (Singapore Management University); Justices Law Clerk, Supreme Court of Singapore. (2014) 26 SAcLJ on Jurisdiction 269 Case Note SETTING ASIDE PRELIMINARY RULINGS ON JURISDICTION International Research Corp plc v Lufthansa Systems Asia Pacific Pte Ltd [2014] 1 SLR 130 and PT Asuransi

More information

Consolidated text PROJET DE LOI ENTITLED. The Arbitration (Guernsey) Law, 2016 * [CONSOLIDATED TEXT] NOTE

Consolidated text PROJET DE LOI ENTITLED. The Arbitration (Guernsey) Law, 2016 * [CONSOLIDATED TEXT] NOTE PROJET DE LOI ENTITLED The Arbitration (Guernsey) Law, 2016 * [CONSOLIDATED TEXT] NOTE This consolidated version of the enactment incorporates all amendments listed in the footnote below. It has been prepared

More information

A DAB Decision between the Notice of Dissatisfaction and the Enforcement in ICC Arbitration

A DAB Decision between the Notice of Dissatisfaction and the Enforcement in ICC Arbitration A DAB Decision between the Notice of Dissatisfaction and the Enforcement in ICC Arbitration Oana Soimulescu Partner, Soimulescu & Soltan, Bucharest 1 I. Introduction A lot has been said about the issue

More information

Staying court proceedings in favour of arbitration

Staying court proceedings in favour of arbitration On the publication of the second edition of Singapore International Arbitration Law and Practice (2 nd edition) (LexisNexis, 2018), David Joseph QC and David Foxton QC, the editors, offer some thoughts

More information

COURT OF APPEAL RULES, 1997 (C.I 19)

COURT OF APPEAL RULES, 1997 (C.I 19) COURT OF APPEAL RULES, 1997 (C.I 19) IN exercise of the powers conferred on the Rules of Court Committee by Article 157(2) of the Constitution these Rules are made this 24th day of July, 1997. PART I-GENERAL

More information

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) CONTENTS

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) CONTENTS CONTENTS Rule 1 Scope of Application and Interpretation 1 Rule 2 Notice, Calculation of Periods of Time 3 Rule 3 Notice of Arbitration 4 Rule 4 Response to Notice of Arbitration 6 Rule 5 Expedited Procedure

More information

Index. Volume 21 (2005) 21 BCL

Index. Volume 21 (2005) 21 BCL Index Abandoned claims judgment on, principally concerned with costs, 12-13, 33-44 whether cost reduction appropriate because of, 125 Access to the premises AS 4917-2003, 9-10 Acts Interpretation Act 1954

More information

Central Government Act The Trade And Merchandise Marks Act, 1958

Central Government Act The Trade And Merchandise Marks Act, 1958 Central Government Act The Trade And Merchandise Marks Act, 1958 THE TRADE AND MERCHANDISE MARKS ACT, 1958 ACT NO. 43 OF 1958 [ 17th October, 1958.] An Act to provide for the registration and better protection

More information

DEFAULT JUDGMENTS: SETTING ASIDE

DEFAULT JUDGMENTS: SETTING ASIDE DEFAULT JUDGMENTS: SETTING ASIDE ISBN 983-3519-05-9 Author: Nasser Hamid Binding: Softcover/Extent: 575 pp Publication Price: MYR 200.00 The law is stated as of August 31, 2006 CHAPTER 1 RULES OF COURT

More information

TERMS OF REFERENCE. Issued Date: 3 January 2011

TERMS OF REFERENCE. Issued Date: 3 January 2011 TERMS OF REFERENCE Issued Date: 3 January 2011 Last Revised Date: 21 March 2017 List of Revisions Revision No. Revision Date Effective Date Revision 1 23 November 2015 1 December 2015 Revision 2 21 March

More information

Law of Arbitration DR. ZULKIFLI HASAN

Law of Arbitration DR. ZULKIFLI HASAN Law of Arbitration DR. ZULKIFLI HASAN Content Award Extension of time for making an award Enforcement of Award Award AA 1952 and UNCITRAL Model Law do not ascribe any meaning to the term award. S-1: A

More information

Small Claims and Minor Offences Courts Ordinance, 2002.

Small Claims and Minor Offences Courts Ordinance, 2002. ORDINANCE NO. XXVI OF 2002 AN ORDINANCE to consolidate and enact the law relating to small claims and minor offences WHEREAS it is expedient and necessary to consolidate and enact the law relating to small

More information

Table of Contents PART 1 ESTABLISHMENT OF THE COURTS The Courts Seal of Courts... 16

Table of Contents PART 1 ESTABLISHMENT OF THE COURTS The Courts Seal of Courts... 16 ADGM Courts, Civil Evidence, Judgments, Enforcement and Judicial Appointments Regulations 2015 Table of Contents Section Page PART 1 ESTABLISHMENT OF THE COURTS... 16 1. The Courts... 16 2. Seal of Courts...

More information

Dr. Nael Bunni, Chairman, Dispute Resolution Panel, Engineers Ireland, 22 Clyde Road, Ballsbridge, Dublin 4. December 2000.

Dr. Nael Bunni, Chairman, Dispute Resolution Panel, Engineers Ireland, 22 Clyde Road, Ballsbridge, Dublin 4. December 2000. Preamble This Arbitration Procedure has been prepared by Engineers Ireland principally for use with the Engineers Ireland Conditions of Contract for arbitrations conducted under the Arbitration Acts 1954

More information

PART I ARBITRATION - CHAPTER I

PART I ARBITRATION - CHAPTER I INDIAN BARE ACTS THE ARBITRATION AND CONCILIATION ACT, 1996 No.26 of 1996 [16th August, 1996] An Act to consolidate and amend the law relating to domestic arbitration, international commercial arbitration

More information

Uniform Arbitration Act

Uniform Arbitration Act 2-1 Uniform Law Conference of Canada Uniform Act 2-2 Table of Contents INTRODUCTORY MATTERS 1 Definitions 2 Application of Act 3 Contracting out 4 Waiver of right to object 5 agreements COURT INTERVENTION

More information

TRADE UNION. The Trade Union Act. Repealed by Chapter S-15.1 of the Statutes of Saskatchewan, 2013 (effective April 29, 2014)

TRADE UNION. The Trade Union Act. Repealed by Chapter S-15.1 of the Statutes of Saskatchewan, 2013 (effective April 29, 2014) 1 TRADE UNION c. T-17 The Trade Union Act Repealed by Chapter S-15.1 of the Statutes of Saskatchewan, 2013 (effective April 29, 2014) Formerly Chapter T-17 of The Revised Statutes of Saskatchewan, 1978

More information

Investments, Life Insurance & Superannuation Terms of Reference

Investments, Life Insurance & Superannuation Terms of Reference Investments, Life Insurance & Superannuation Terms of Reference These Terms of Reference apply to those members of the Financial Ombudsman Service Limited who have been designated as having the Investments,

More information

Before : MR JUSTICE KNOWLES CBE Between : (1) C1 (2) C2 (3) C3. - and

Before : MR JUSTICE KNOWLES CBE Between : (1) C1 (2) C2 (3) C3. - and Neutral Citation Number: [2016] EWHC 1893 (Comm) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION COMMERCIAL COURT Case No: CL-2015-000762 Royal Courts of Justice Strand, London, WC2A 2LL Date: 29/07/2016

More information

Arbitration Act 1996

Arbitration Act 1996 Arbitration Act 1996 An Act to restate and improve the law relating to arbitration pursuant to an arbitration agreement; to make other provision relating to arbitration and arbitration awards; and for

More information

ARBITRATION IN FINLAND CHARACTERISTIC FEATURES CURRENTLY UNDER DISCUSSION. By Patrik Lindfors 1

ARBITRATION IN FINLAND CHARACTERISTIC FEATURES CURRENTLY UNDER DISCUSSION. By Patrik Lindfors 1 ARBITRATION IN FINLAND CHARACTERISTIC FEATURES CURRENTLY UNDER DISCUSSION By Patrik Lindfors 1 Nordic Journal of Commercial Law issue 2003 #1 1 Patrik Lindfors is Attorney at law and Partner, heading Dispute

More information

Fisher, Stephen J v Sunho Construction Pte Ltd

Fisher, Stephen J v Sunho Construction Pte Ltd This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher s duty in compliance with the law, for publication in LawNet and/or the Singapore

More information

Dispute Resolution Briefing

Dispute Resolution Briefing Dispute Resolution Briefing August 2014 Contents How enforceable is an obligation to negotiate? Introduction 01 The issue 01 The background facts 02 The decision 03 Conclusion 04 Contacts 05 Introduction

More information

FOUNDATIONS LAW CONTENTS

FOUNDATIONS LAW CONTENTS DIFC LAW NO. 3 OF 2018 CONTENTS PART 1: GENERAL... 1 1. Title... 1 2. Legislative authority... 1 3. Application of the Law... 1 4. Scope of the Law... 1 5. Date of enactment... 1 6. Commencement... 1 7.

More information

Winding up by court 568. Application of Chapter 569. Circumstances in which company may be wound up by the court

Winding up by court 568. Application of Chapter 569. Circumstances in which company may be wound up by the court PART 11 WINDING UP CHAPTER 1 Preliminary and interpretation 559. Interpretation (Part 11) 560. Restriction of this Part 561. Modes of winding up general statement as to position under Act 562. Types of

More information

SINGAPORE INTERNATIONAL ARBITRATION CENTRE (SIAC)

SINGAPORE INTERNATIONAL ARBITRATION CENTRE (SIAC) GUIDE TO INTERNATIONAL ARBITRATION IN SINGAPORE INTERNATIONAL ARBITRATION CENTRE (SIAC) Written By S. Ravi Shankar Advocate on Record - Supreme Court of India National President of Arbitration Bar of India

More information

CASE UPDATE. The High Court Considers the Status and Scope of an Arbitration Agreement in the Context of a Termination of the Main Contract

CASE UPDATE. The High Court Considers the Status and Scope of an Arbitration Agreement in the Context of a Termination of the Main Contract The High Court Considers the Status and Scope of an Arbitration Agreement in the Context of a Termination of the Main Contract 6 June 2018 Introduction 1. In the recent decision of Nippon Catalyst Pte

More information

AFRICAN DEVELOPMENT BANK GROUP

AFRICAN DEVELOPMENT BANK GROUP AFRICAN DEVELOPMENT BANK GROUP THE INDEPENDENT REVIEW MECHANISM Operating Rules and Procedures 16 th June 2010 TABLE OF CONTENTS I. Introduction... 1 a. Purpose... 1 b. Functions... 1 c. Composition...

More information

SCHEDULE 1 DATA TRANSFER AGREEMENT (Data Controller to Data Controller transfers)... 16

SCHEDULE 1 DATA TRANSFER AGREEMENT (Data Controller to Data Controller transfers)... 16 DATA PROTECTION REGULATIONS 2015 DATA PROTECTION REGULATIONS 2015 Part 1 General Rules on the Processing of Personal Data... 1 Part 2 Rights of Data Subjects... 7 Part 3 Notifications to the Registrar...

More information

BEFORE THE IMMIGRATION ADVISERS COMPLAINTS AND DISCIPLINARY TRIBUNAL. Decision No: [2015] NZIACDT 79. Reference No: IACDT 020/14

BEFORE THE IMMIGRATION ADVISERS COMPLAINTS AND DISCIPLINARY TRIBUNAL. Decision No: [2015] NZIACDT 79. Reference No: IACDT 020/14 BEFORE THE IMMIGRATION ADVISERS COMPLAINTS AND DISCIPLINARY TRIBUNAL Decision No: [2015] NZIACDT 79 Reference No: IACDT 020/14 IN THE MATTER of a referral under s 48 of the Immigration Advisers Licensing

More information

PART 1 SCOPE AND INTERPRETATION...

PART 1 SCOPE AND INTERPRETATION... ADGM Court Procedure Rules 2016 Table of Contents PART 1 SCOPE AND INTERPRETATION... 1 1. Citation and commencement... 1 2. Scope and objective... 1 3. Interpretation... 1 4. Court documents... 4 5. Forms...

More information

PARLIAMENT OF THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA ARBITRATION ACT NO. 11 OF 1995

PARLIAMENT OF THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA ARBITRATION ACT NO. 11 OF 1995 PARLIAMENT OF THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA ARBITRATION ACT NO. 11 OF 1995 (Certified on 30 th June-1995) Arbitration Act. No. 11 of 1995 1 (Certified on 30 th June-1995) L.D. O.10/93

More information

Client Alert March 2017

Client Alert March 2017 Dispute Resolution Singapore Client Alert March 2017 Rong Shun Engineering & Construction Pte Ltd v C.P. Ong Construction Pte Ltd For More Information: Nandakumar Ponniya Principal +65 6434 2663 nandakumar.ponniya

More information

Source: BOOK: International Handbook on Commercial Arbitration, J. Paulsson (ed.), Suppl. 30 (January/2000)

Source: BOOK: International Handbook on Commercial Arbitration, J. Paulsson (ed.), Suppl. 30 (January/2000) Source: BOOK: International Handbook on Commercial Arbitration, J. Paulsson (ed.), Suppl. 30 (January/2000) The Arbitration and Conciliation Act, 1996 (No. 26 of 1996), [16th August 1996] India An Act

More information

Whistleblowers Protection Act 1994

Whistleblowers Protection Act 1994 Queensland Whistleblowers Protection Act 1994 Reprinted as in force on 1 December 2009 Reprint No. 5D This reprint is prepared by the Office of the Queensland Parliamentary Counsel Warning This reprint

More information

Pilecon Engineering Bhd ABDUL KADIR SULAIMAN, JCA ARIFIN ZAKARIA, JCA NIK HASHIM NIK AB. RAHMAN, JCA 23 FEBRUARY 2007

Pilecon Engineering Bhd ABDUL KADIR SULAIMAN, JCA ARIFIN ZAKARIA, JCA NIK HASHIM NIK AB. RAHMAN, JCA 23 FEBRUARY 2007 COURT OF APPEAL, MALAYSIA Bintulu Development Authority - vs - Coram Pilecon Engineering Bhd ABDUL KADIR SULAIMAN, JCA ARIFIN ZAKARIA, JCA NIK HASHIM NIK AB. RAHMAN, JCA 23 FEBRUARY 2007 Judgment of the

More information

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV [2015] NZHC CHRISTOPHER MAURICE LYNCH First Defendant

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV [2015] NZHC CHRISTOPHER MAURICE LYNCH First Defendant IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV-2014-404-2845 [2015] NZHC 3202 BETWEEN AMANDA ADELE WHITE First Plaintiff ANNE LEOLINE EMILY FREEMAN Second Plaintiff AND CHRISTOPHER MAURICE LYNCH

More information

The new Arbitration (Guernsey) Law, a guide to the key provisions

The new Arbitration (Guernsey) Law, a guide to the key provisions JERSEY GUERNSEY LONDON BVI SINGAPORE GUERNSEY BRIEFING May 2017 The new Arbitration (Guernsey) Law, 2016 - a guide to the key provisions Historically, parties in Guernsey have been reluctant to use arbitration

More information

Project Anti-Corruption System. (Construction Projects) Template 2. Anti-Corruption Agreement

Project Anti-Corruption System. (Construction Projects) Template 2. Anti-Corruption Agreement GIACC Global Infrastructure Anti-Corruption Centre TRANSPARENCY INTERNATIONAL (UK) - PACS - Project Anti-Corruption System (Construction Projects) Template 2 Anti-Corruption Agreement Licence to use: This

More information

Chapter 4 Creditors Voluntary Winding Up Application of Chapter. MKD/096/AC#

Chapter 4 Creditors Voluntary Winding Up Application of Chapter. MKD/096/AC# [PART 11 WINDING UP Chapter 1 Preliminary and Interpretation 549. Interpretation (Part 11). 550. Restriction of this Part. 551. Modes of winding up - general statement as to position under Act. 552. Types

More information

Quarella SpA v Scelta Marble Australia Pty Ltd [2012] SGHC 166

Quarella SpA v Scelta Marble Australia Pty Ltd [2012] SGHC 166 MEALEY S TM International Arbitration Report Quarella SpA v Scelta Marble Australia Pty Ltd [2012] SGHC 166 by Andrew Battisson and Sunil Mawkin Allen & Overy LLP Singapore A commentary article reprinted

More information

Agreement to UOB Banker s Guarantee Terms and Conditions

Agreement to UOB Banker s Guarantee Terms and Conditions Agreement to UOB Banker s Guarantee Terms and Conditions In consideration of United Overseas Bank Limited (the Bank ) agreeing at the Applicant s request to issue the Banker s Guarantee, the Applicant

More information

MEMORANDUM OF DEPOSIT

MEMORANDUM OF DEPOSIT MEMORANDUM OF DEPOSIT THIS MEMORANDUM OF DEPOSIT ( Memorandum ) is made on BETWEEN: (1) KGI SECURITIES (SINGAPORE) PTE. LTD., a company incorporated in the Republic of Singapore and having its registered

More information

Evidence in International Arbitration. Expert Evidence / Expert Determination Clause. 莫世傑 / Danny Mok CILTHK 9 April 2017

Evidence in International Arbitration. Expert Evidence / Expert Determination Clause. 莫世傑 / Danny Mok CILTHK 9 April 2017 Evidence in International Arbitration / Expert Determination Clause 莫世傑 / Danny Mok CILTHK 9 April 2017 1 Why necessary Finding of facts is the duty of the judge / arbitrator, but he or she should not

More information

DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY Introductory Provisions. Article (1) Definitions

DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY Introductory Provisions. Article (1) Definitions DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY 2011 Introductory Provisions Article (1) Definitions 1.1 The following words and phrases shall have the meaning assigned thereto unless

More information

General Rules on the Processing of Personal Data SCHEDULE 1 DATA TRANSFER AGREEMENT (Data Controller to Data Controller transfers)...

General Rules on the Processing of Personal Data SCHEDULE 1 DATA TRANSFER AGREEMENT (Data Controller to Data Controller transfers)... DATA PROTECTION REGULATIONS 2015 DATA PROTECTION REGULATIONS 2015 General Rules on the Processing of Personal Data... 1 Rights of Data Subjects... 6 Notifications to the Registrar... 7 The Registrar...

More information

S P Chua Pte Ltd v Lee Kim Tah (Pte) Ltd

S P Chua Pte Ltd v Lee Kim Tah (Pte) Ltd [1993] 1 SLR(R) SINGAPORE LAW REPORTS (REISSUE) 793 S P Chua Pte Ltd v Lee Kim Tah (Pte) Ltd [1993] SGHC 104 High Court Suit No 1986 of 1991 Amarjeet Singh JC 10 May 1993 Arbitration Stay of court proceedings

More information

Accountancy Scheme Sanctions Guidance

Accountancy Scheme Sanctions Guidance Guidance Financial Reporting Council April 2018 Accountancy Scheme Sanctions Guidance The FRC s mission is to promote transparency and integrity in business. The FRC sets the UK Corporate Governance and

More information

PART 8 ARBITRATION REGULATIONS CONTENTS

PART 8 ARBITRATION REGULATIONS CONTENTS PART 8 ARBITRATION REGULATIONS * CONTENTS Section Page 1 Definitions and Interpretations 8-1 2 Commencement 8-2 3 Appointment of Tribunal 8-3 4 Procedure 8-5 5 Notices and Communications 8-5 6 Submission

More information

TRADE MARKS ACT, 1999

TRADE MARKS ACT, 1999 GOVERNMENT OF THE PEOPLE S REPUBLIC OF BANGLADESH A DRAFT BILL OF THE PROPOSED TRADE MARKS ACT, 1999 Prepared in the light of the complete report made by the Bangladesh Law Commission recommending promulgation

More information

Federal High Court (Civil Procedure) Rules 2000

Federal High Court (Civil Procedure) Rules 2000 Federal High Court (Civil Procedure) Rules 2000 Commencement: 1st May 2000 In exercise of the powers conferred on me by section 254 of the Constitution of the Federal Republic of Nigeria 1999 and all powers

More information

PROCEDURE & PRINCIPLES: ORDER 26A: ORDER 14 & ORDER 14A

PROCEDURE & PRINCIPLES: ORDER 26A: ORDER 14 & ORDER 14A PROCEDURE & PRINCIPLES: ORDER 26A: ORDER 14 & ORDER 14A ISBN 983-41166-7-5 Author: Nasser Hamid Binding: Softcover/Extent: 650 pp Publication Price: MYR 220.00 The law is stated as of July 1, 2004 Chapter

More information

Setting aside an international arbitration award based on deficient pleadings

Setting aside an international arbitration award based on deficient pleadings Setting aside an international arbitration award based on deficient pleadings DARIUS CHAN * Kempinski Hotels SA v PT Prima International Development [2011] SGHC 171 If it isn t pleaded, you can t consider

More information

TERMS AND CONDITIONS FOR NASDAQ NORDIC EXCHANGES SMART ORDER ROUTING

TERMS AND CONDITIONS FOR NASDAQ NORDIC EXCHANGES SMART ORDER ROUTING TERMS AND CONDITIONS FOR NASDAQ NORDIC EXCHANGES SMART ORDER ROUTING 1. AGREEMENT, INTERPRETATION 1.1. The Nasdaq Nordic Exchanges Smart Order Routing Services Agreement consists of these Terms and Conditions

More information

Shanghai International Economic and Trade Arbitration Commission (Shanghai International Arbitration Center) Arbitration Rules

Shanghai International Economic and Trade Arbitration Commission (Shanghai International Arbitration Center) Arbitration Rules Shanghai International Economic and Trade Arbitration Commission (Shanghai International Arbitration Center) Effective as from January 1, 2015 CONTENTS of Shanghai International Economic and Trade Arbitration

More information

Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland

Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland (Royaume-Uni - Royaume-Uni de Grande-Bretagne et d'irlande du Nord) ARBITRATION ACT 1996 1996 CHAPTER 23 An Act to

More information

Evolution of dispute resolution under the FIDIC Red Book. Bill Smith, Partner 10 May 2018

Evolution of dispute resolution under the FIDIC Red Book. Bill Smith, Partner 10 May 2018 Evolution of dispute resolution under the FIDIC Red Book Bill Smith, Partner 10 May 2018 Outline Disputes why a dispute resolution procedure is needed How the dispute resolution provisions in the FIDIC

More information

Administrative Tribunal

Administrative Tribunal United Nations Administrative Tribunal Distr.: Limited 31 January 2005 Original: English ADMINISTRATIVE TRIBUNAL Judgement No. 1214 Case No. 1303: SAM-THAMBIAH Against: The Secretary-General of the International

More information

BUILDING SERVICES CORPORATION ACT 1989 Na 147

BUILDING SERVICES CORPORATION ACT 1989 Na 147 BUILDING SERVICES CORPORATION ACT 1989 Na 147 NEW SOUTH WALES 1. Short title 2. Commencement 3. Definitions TABLE OF PROVISIONS PART 1 - PRELIMINARY PART 2 - REGULATION OF RESIDENTIAL BUILDING WORK AND

More information

Published on e-first 1 June AGENCY LAW

Published on e-first 1 June AGENCY LAW Published on e-first 1 June 2018 3. AGENCY LAW Pearlie KOH LLB (Hons) (National University of Singapore), LLM (University of Melbourne); Advocate & Solicitor (Singapore); Associate Professor, Singapore

More information

(2 August 2017 to date) PROMOTION OF ADMINISTRATIVE JUSTICE ACT 3 OF 2000

(2 August 2017 to date) PROMOTION OF ADMINISTRATIVE JUSTICE ACT 3 OF 2000 (2 August 2017 to date) [This is the current version and applies as from 2 August 2017, i.e. the date of commencement of the Judicial Matters Amendment Act 8 of 2017 to date] PROMOTION OF ADMINISTRATIVE

More information

TRADE MARKS ACT (CHAPTER 332)

TRADE MARKS ACT (CHAPTER 332) TRADE MARKS ACT (CHAPTER 332) History Act 46 of 1998 -> 1999 REVISED EDITION -> 2005 REVISED EDITION An Act to establish a new law for trade marks, to enable Singapore to give effect to certain international

More information

The Specific Relief Act, 1963

The Specific Relief Act, 1963 The Specific Relief Act, 1963 [47 OF 1963] SPECIFIC RELIEF ACT, 1963 [47 OF 1963] An Act to define and amend the law relating to certain kinds of specific relief. BE it enacted by Parliament in the Fourteenth

More information

PROMOTION OF ADMINISTRATIVE JUSTICE ACT 3 OF 2000

PROMOTION OF ADMINISTRATIVE JUSTICE ACT 3 OF 2000 Page 1 of 13 PROMOTION OF ADMINISTRATIVE JUSTICE ACT 3 OF 2000 [ASSENTED TO 3 FEBRUARY 2000] [DATE OF COMMENCEMENT: 30 NOVEMBER 2000] (Unless otherwise indicated) (English text signed by the President)

More information

SH Design & Build Pte Ltd v BD Cranetech Pte Ltd

SH Design & Build Pte Ltd v BD Cranetech Pte Ltd This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher s duty in compliance with the law, for publication in LawNet and/or the Singapore

More information

The Patent Regulation Board and The Trade Mark Regulation Board. Disciplinary Procedure Rules

The Patent Regulation Board and The Trade Mark Regulation Board. Disciplinary Procedure Rules The Patent Regulation Board and The Trade Mark Regulation Board Disciplinary Procedure Rules The Patent Regulation Board of the Chartered Institute of Patent Attorneys and the Trade Mark Regulation Board

More information

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory Arbitration Act 1996 1996 CHAPTER 23 1 Part I Arbitration pursuant to an arbitration agreement Introductory 1. General principles. 2. Scope of application of provisions. 3. The seat of the arbitration.

More information

ENFORCEMENT OF DAB DECISIONS IN ARBITRATION PART I. by Giovanni Di Folco and Mark Tiggeman

ENFORCEMENT OF DAB DECISIONS IN ARBITRATION PART I. by Giovanni Di Folco and Mark Tiggeman ENFORCEMENT OF DAB DECISIONS IN ARBITRATION PART I Enforcement of a DAB Decision in Arbitration, Part I Page 3 of 16 Giovanni Di Folco Giovanni Di Folco is the Senior Partner of the international consulting

More information

BERMUDA BERMUDA INTERNATIONAL CONCILIATION AND ARBITRATION ACT : 29

BERMUDA BERMUDA INTERNATIONAL CONCILIATION AND ARBITRATION ACT : 29 QUO FA T A F U E R N T BERMUDA BERMUDA INTERNATIONAL CONCILIATION AND ARBITRATION ACT 1993 1993 : 29 TABLE OF CONTENTS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 Short Title PART I PRELIMINARY

More information

Trade Marks Ordinance (New Version),

Trade Marks Ordinance (New Version), Trade Marks Ordinance (New Version), 5732 1972 (of May 15, 1972) * TABLE OF CONTENTS Articles Chapter I: Chapter II: Chapter III: Chapter IV: Chapter V: Chapter VI: Interpretation Definitions... 1 Applicability

More information

OMBUDSMAN BILL, 2017

OMBUDSMAN BILL, 2017 Arrangement of Sections Section PART I - PRELIMINARY 3 1. Short title...3 2. Interpretation...3 3. Application of Act...4 PART II OFFICE OF OMBUDSMAN 5 ESTABLISHMENT AND FUNCTIONS OF OFFICE OF OMBUDSMAN

More information

AN OUNCE OF PREVENTION IS WORTH A POUND OF CURE - Benjamin Franklin. Gordon L. Jaynes 24 May 2018

AN OUNCE OF PREVENTION IS WORTH A POUND OF CURE - Benjamin Franklin. Gordon L. Jaynes 24 May 2018 AN OUNCE OF PREVENTION IS WORTH A POUND OF CURE - Benjamin Franklin Gordon L. Jaynes Glj4law@aol.com 24 May 2018 Inspired by the image of Mount Fuji, the slogan of this year s DRBF International Conference

More information

AN BILLE EADRÁNA 2008 ARBITRATION BILL Mar a tionscnaíodh As initiated ARRANGEMENT OF SECTIONS. PART 1 Preliminary and General

AN BILLE EADRÁNA 2008 ARBITRATION BILL Mar a tionscnaíodh As initiated ARRANGEMENT OF SECTIONS. PART 1 Preliminary and General AN BILLE EADRÁNA 2008 ARBITRATION BILL 2008 Mar a tionscnaíodh As initiated ARRANGEMENT OF SECTIONS PART 1 Preliminary and General Section 1. Short title and commencement. 2. Interpretation. 3. Application

More information

557. Hearing of proceedings otherwise than in public Power of court to order the return of assets which have been improperly transferred.

557. Hearing of proceedings otherwise than in public Power of court to order the return of assets which have been improperly transferred. 557. Hearing of proceedings otherwise than in public. 558. Power of court to order the return of assets which have been improperly transferred. 559. Reporting to Director of Corporate Enforcement of misconduct

More information

Zynergy Solar Projects & Services Pvt Ltd v Phoenix Solar Pte Ltd

Zynergy Solar Projects & Services Pvt Ltd v Phoenix Solar Pte Ltd This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher s duty in compliance with the law, for publication in LawNet and/or the Singapore

More information

View Esteem Sdn Bhd v Bina Puri Holdings Bhd*

View Esteem Sdn Bhd v Bina Puri Holdings Bhd* CIDB Construction Law Report 2016 View Esteem Sdn Bhd v Bina Puri Holdings Bhd* COURT OF APPEAL, PUTRAJAYA CIVIL APPEAL NO: W 02(C)(A) 1507 09/2015 HAMID SULTAN BIN ABU BACKER JCA, PRASAD SANDOSHAM ABRAHAM

More information

Kingdom of Saudi Arabia Law of Arbitration

Kingdom of Saudi Arabia Law of Arbitration Kingdom of Saudi Arabia Law of Arbitration Royal Decree No. M/34 Dated 24/5/1433H 16/4/2012 of approving the Law of Arbitration With the Help of Almighty God, We, Abdullah ibn Abdulaziz Al Saud, King of

More information

DRAFT MYANMAR COMPANIES LAW TABLE OF CONTENTS

DRAFT MYANMAR COMPANIES LAW TABLE OF CONTENTS Post-Consultation Law Draft 1 DRAFT MYANMAR COMPANIES LAW TABLE OF CONTENTS PART I PRELIMINARY... 1 PART II CONSTITUTION, INCORPORATION AND POWERS OF COMPANIES... 6 Division 1: Registration of companies...

More information

FIJI ISLANDS HIGH COURT ACT (CHAPTER 13) HIGH COURT (AMENDMENT) RULES 1998

FIJI ISLANDS HIGH COURT ACT (CHAPTER 13) HIGH COURT (AMENDMENT) RULES 1998 FIJI ISLANDS HIGH COURT ACT (CHAPTER 13) HIGH COURT (AMENDMENT) RULES 1998 IN exercise of the powers conferred upon me by Section 25 of the High Court Act, I hereby make the following Rules: Citation 1.

More information

The Intellectual Property Regulation Board (incorporating The Patent Regulation Board and the Trade Mark Regulation Board)

The Intellectual Property Regulation Board (incorporating The Patent Regulation Board and the Trade Mark Regulation Board) The Intellectual Property Regulation Board (incorporating The Patent Regulation Board and the Trade Mark Regulation Board) Final Draft Disciplinary Procedure Rules The Patent Regulation Board of the Chartered

More information

BRIEFING NIL BY MOUTH? EXCLUDING ORAL VARIATION OF CONTRACTS MAY 2018

BRIEFING NIL BY MOUTH? EXCLUDING ORAL VARIATION OF CONTRACTS MAY 2018 BRIEFING NIL BY MOUTH? EXCLUDING ORAL VARIATION OF CONTRACTS MAY 2018 THE UK SUPREME COURT HAS OVERTURNED THE DECISION OF THE COURT OF APPEAL, AND DETERMINED THAT NO ORAL MODIFICATION CLAUSES ARE EFFECTIVE

More information

New Zealand Institute of Chartered Accountants RULES OF THE NEW ZEALAND INSTITUTE OF CHARTERED ACCOUNTANTS EFFECTIVE 26 JUNE 2017 CONTENTS

New Zealand Institute of Chartered Accountants RULES OF THE NEW ZEALAND INSTITUTE OF CHARTERED ACCOUNTANTS EFFECTIVE 26 JUNE 2017 CONTENTS New Zealand Institute of Chartered Accountants RULES OF THE NEW ZEALAND INSTITUTE OF CHARTERED ACCOUNTANTS EFFECTIVE 26 JUNE 2017 CONTENTS Rule no Page no 1. INTERPRETATION...1 2. FUNCTIONS...2 3. MEMBERSHIP...3

More information

BERMUDA RULES OF THE COURT OF APPEAL FOR BERMUDA BX 1 / 1965

BERMUDA RULES OF THE COURT OF APPEAL FOR BERMUDA BX 1 / 1965 QUO FA T A F U E R N T BERMUDA RULES OF THE COURT OF APPEAL FOR BERMUDA BX 1 / 1965 [made under section 9 of the Court of Appeal Act 1964 and brought into operation on 2 August 1965] TABLE OF CONTENTS

More information

ISDA International Swap Dealers Association, Inc.

ISDA International Swap Dealers Association, Inc. (Local Currency Single Jurisdiction) ISDA International Swap Dealers Association, Inc. MASTER AGREEMENT dated as of......... and......... have entered and/or anticipate entering into one or more transactions

More information

Islamic Republic of Pakistan (ICSID Case No. ARB/01/13) Procedural Order No. 2

Islamic Republic of Pakistan (ICSID Case No. ARB/01/13) Procedural Order No. 2 SGS Société Générale de Surveillance S.A. v. Islamic Republic of Pakistan (ICSID Case No. ARB/01/13) Procedural Order No. 2 Introduction In this Procedural Order, the Tribunal addresses the request of

More information

LEGAL 509 to the Government Gazette of Mauritius No. 105 of 3 December 2016

LEGAL 509 to the Government Gazette of Mauritius No. 105 of 3 December 2016 LEGAL 509 to the Government Gazette of Mauritius No. 105 of 3 December 2016 THE LIMITED LIABILITY PARTNERSHIPS ACT 2016 Act No. 24 of 2016 I assent Bibi Ameenah Firdaus Gurib-Fakim 2 December 2016 President

More information

TURKS AND CAICOS ISLANDS THE TRUSTS ORDINANCE 1990 ARRANGEMENT OF SECTIONS. Part 1 - Preliminary

TURKS AND CAICOS ISLANDS THE TRUSTS ORDINANCE 1990 ARRANGEMENT OF SECTIONS. Part 1 - Preliminary TURKS AND CAICOS ISLANDS THE TRUSTS ORDINANCE 1990 ARRANGEMENT OF SECTIONS 1. Citation and commencement 2. Interpretation 3. Existence of a trust 4. Applicable law of a trust 5. Jurisdiction of the Court

More information

I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE CIV [2017] NZHC UNDER the Insolvency Act 2006 PRESCOTT

I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE CIV [2017] NZHC UNDER the Insolvency Act 2006 PRESCOTT IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE CIV-2017-404-1097 [2017] NZHC 2701 UNDER the Insolvency Act 2006 IN THE MATTER OF BETWEEN AND the bankruptcy

More information