MEMORANDA FOR THE CLAIMANT

Size: px
Start display at page:

Download "MEMORANDA FOR THE CLAIMANT"

Transcription

1 MEMORANDA FOR THE CLAIMANT TEAM 23 Valentine Chatelier Sophie Li Spyridon Papadas Georgios Rigoutsos 1

2 Table of Contents MEMORANDA FOR THE CLAIMANT... 3 TABLE OF CASES... 3 BIBLIOGRAPHY... 6 STATEMENT OF FACTS... 8 PART ONE: ARBITRATION The Claimant gave the notice on time or alternatively the requirement of giving notice of claim has been waived by the Respondent The Claimant successfully commenced the Arbitration At the time of merger, RTI and the Claimant is one and the same Alternatively, there is a misnomer that the Claimant applies to have corrected PART TWO: MERITS The sum of US$4,945, is due by way of freight Freight is deemed earned upon lifting of subjects Reliable Tankers Standard Terms Clause 4 prevails over ASBATANKVOY Clause Freight is deemed earned upon lifting of subjects There is no lack of consideration The rules of consideration do not apply to advanced freight Alternatively, there is no total failure of consideration Freight is an accrued debt upon lifting on subjects Any loss of the Respondent has arisen in an indirect way and is therefore of a consequential nature The Claimant committed no breach of contract The approach voyage to the loading port had commenced The Respondent s own fault contributed to the non-payment of the security fees There was no misstatement concerning the ETA provision In order for the liability of the Claimant to be established, the condition precedent of gross negligence needs to be met The Tribunal lacks jurisdiction to decide on tortious matter Further or alternatively, no acts or neglects on the part of the Claimant can be interpreted as gross negligence The Respondent s cancellation of the charter relieved both parties from performing any further obligations or liability arising thereunder The charter was cancelled The charter was cancelled by the operation of the Respondent contractual termination, without recourse to either party whatsoever There is no ground for a claim for damage Further or alternatively, the respondent s early repudiation of the charter amounted to a breach of contract There is no anticipatory right to cancel The respondent failed to take reasonable steps to mitigate their loss, which deprived them of any ground to recover nominal damages In any event, the claimant is not liable for any delay occurring out of the ship s arrest by a third party CONCLUSION

3 MEMORANDA FOR THE CLAIMANT TABLE OF CASES A Ackerman v. Lay [2009] 1 WLR Anns v. Merton LBC [1977] 2 WLR B Colonial Bank v. European Grain & Shipping Ltd (The Dominique) [1987] 1 Lloyd s Rep 239; [1988] 1 Lloyd s Rep 215. Bayoil SA v. Seawind Tankers Corp (The Leonidas) [2001] 1 Lloyd s Rep 533. Borries v. Hutchinson (1865) 19 C.B.(N.S.) 445. C Camarata Property Inc v. Credit Suisse Securities (Europe) Ltd [2011] EWHC 479 (Comm). Cheikh Boutros Selim El-Khoury v. Ceylon Shipping Lines (The Madeleine) [1967] 2 Lloyd s Rep 224. Compania Naviera General SA v. Kerametal Ltd (The Lorna I) [1983] 1 Lloyd s Rep 373. D Dakin v. Oxley 143 ER 938. Deutsche Schachtbau-und Tiefbohrgesellschaft mbh v. Ras Al-Khaimah National Oil Co [1987] 2 All ER 769. E Esso Petroleum Co Ltd v. Mardon [1976] QB 801. Evera SA Commercial v. North Shipping Co Ltd (The North Anglia) [1956] 2 Lloyd s Rep 367. F Fercometal Sarl v. MSC Mediterranean Shipping Co SA (The Simona) [1989] AC 788. Financings Ltd v. Baldock [1963] 2 QB

4 H Hedley Byrne & Co Ltd v. Heller & Partners Ltd [1964] AC 465. M Maredelanto Compania Naviera SA v. Bergbau-Handel GmbH (The Mihalis Angelos) [1971] 1 QB 164. Marifortuna Naviera S.A. v. Government of Ceylon [1970] 1 Lloyd s Rep Mutual Life & Citizens Assurance v. Evatt [1971] AC 793. N National Bank of Greece and Athens SA v. Metliss [1958] AC 509. Nea Agrex SA v. Baltic Shipping Co Ltd (The Agios Lazaros) [1976] 2 WLR 925. P Progressive Casualty Insurance Co v. CA Reaseguradora Nacional de Venezuela 991 F 2d 42 (2nd cir 1993). R Red Sea Tankers Ltd v. Papachristidis (The Hellespont Ardent) [1997] 2 Lloyd s Rep 547. Films Rover International Ltd v. Cannon Film Sales Ltd [1987] 1 WLR 670. S Samuel Sanday & Co v. Cox McEuen & Co (1922) 10 LI.L Rep 459. The Satya Kailash [1984] 1 Lloyd s Rep SEB Trygg Holding AB v. Manches [2006] 1 WLR Smith v. Dart & Son (1884) 14 QBD 105. Sotiros Shipping Inc v. Sameiet Soholt (The Soholt) [1983] 1 Lloyd s Rep 605. Stinnes Interoil GmbH v. A Halcoussis & Co (The Yanxilas) [1982] 2 Lloyd s Rep 445. T Tradigrain SA & Ors v. Intertek Testing Services (ITS) Canada Ltd & Anor [2007] EWCA Civ

5 U United Parcel Service of America Inc v. Government of Canada 46 ILM 922 (2007). V Vagres Compania Maritima SA v. Nissho-lwai American Corp (The Karin Vatis) [1988] 2 Lloyd s Rep

6 BIBLIOGRAPHY Statute Arbitration Act 1996 (UK) c. 23. Books Berlingieri F., Berlingieri on Arrest of Ships (5 th ed.), 2011, Informa Law. Burrows A, The Law of Restitution (3 rd ed.), 2010, Oxford. Coghlin T., Baker A., Kenny J., Time Charters (6 th ed.), 2014, Informa Law. Cooke J., Young T., Taylor A., Kimball J., Martowski D., Lambert L., Voyage Charters (3 rd ed.), 2007, Informa Law. Dockray M., Cases & Materials on the Carriage of Goods by Sea (3 rd ed.), 2004, Routledge Cavendish. Eder B., Bennett H., Berry S., Foxton D., Smith C., Scrutton on Charterparties and Bills of Lading (22 nd ed.), 2013, Sweet & Maxwell. Girvin S., Carriage of Goods by Sea (2 nd ed.), 2011, Oxford University Press. Jones M., Dugdale A., Clerk & Lindsell On Torts (20 th ed.), 2013, Sweet & Maxwell. McGregor H., McGregor on Damages (19 th ed.), 2012, Sweet & Maxwell. Merkin R., Flannery L., Arbitration Act 1996 (4 th ed), 2008, Informa Law from Routledge. Stopford M., Maritime Economics (3 rd ed.) 2008, Routledge. Tweeddale A., Tweeddale K., Arbitration of Commercial Disputes: International and English Law and Practice (1 st ed.), 2007, Oxford University Press. Wilson J., Carriage of Goods by Sea (7 th ed.), 2010, Pearson Education. 6

7 Articles Peels W.E., The Termination Paradox (2013) LMCLQ 520. Seng Y., Sweating over an implied duty of good faith (2013) LMCLQ 418. Tettenborn A., Consequential Damages in Contract The Poor Relation (2008) 42 Loy L.A.L. Rev

8 STATEMENT OF FACTS On 10 October 2011, Super Charters (The Respondent) informed Reliable Holdings Inc (The Claimant) that they were interested in chartering one of their VLCC to transport a full cargo of crude oil. A contract evidenced by a Fixture Recap dated 19 November 2011 was concluded between the parties, on amended ASBATANKVOY form with Rider Clauses (The Charter). The Claimant thereby agreed to let their vessel Reliable Butterfly (The Vessel) for a voyage from BlueLand to IndigoLand. The Charter provided for Freight being deemed earned in full discountless non-returnable and 95% of minimum freight payable upon lifting of subjects. Under the contract, the Vessel was to leave Bunker Port by 25 November so as to sail on time from LoadPort. Due to unforeseen events beyond the Claimant s control however, the Vessel was retained at her Bunker Port and it therefore transpired that she would miss her laycan. As a result of the above, the Respondent chose to exercise their contractual right of cancellation under the Charter on 27 November, which had the effect of releasing both parties from performing any obligations or further liabilities arising thereunder. The subjects were lifted on 19 November, hence pursuant to the Charter; the Respondent owes the Claimant the sum of US$4,945, by way of freight. The Respondent refused to pay such sum or any other, as a result of which the Claimant successfully commenced arbitration Proceedings (the Arbitration) on 28 November, claiming the sum of US$4,945, as due and owing under the Charter. 8

9 PART ONE: ARBITRATION The Claimant argues that Arbitration was not time-barred and that they successfully commenced proceedings. 1. The Claimant gave the notice on time or alternatively the requirement of giving notice of claim has been waived by the Respondent. The requirement of giving Notice was in the Respondent s Standard Terms which stated that All claims against Super Charters must be notified to Super Charters within 10 days of discharge/re-delivery and/ or when discharge/ re-delivery would have taken place if for whatever reason it did not (as appropriate) and any suit or proceedings must be commenced within a further 10 days thereafter. The expected discharge date was 10 January. The Claimant gave Notice of their claim on freight on the 28 November; long before the latest date provided for doing so under the Charter (20 January). It is therefore argued that the Claimant duly fulfilled the obligation to give Notice of Claim. Alternatively, if the Tribunal finds that the Claimant has not given Notice on time; it is submitted that the requirement of giving Notice of Claims was in any case waived by the Respondent. Indeed, on 12 February, the Respondent informed the Claimant that the Notice of Appointment was invalid due to the fact that Reliable Tankers no longer existed as an entity, without any mention to the Notice of claims whatsoever. It is argued that the Respondent waived the requirement of Notice of Claims and can therefore only question the parties capacity; any claim regarding the timing of giving Notice would be inadmissible. 9

10 2. The Claimant successfully commenced the Arbitration. According to Clause 24 of ABASTANKVOY, English law and London Arbitration apply to this contract. As a consequence, English law governs the Arbitration Agreement 1. The Claimant successfully sent a Notice of Appointment to the Respondent on 28 January in respect of Article 14(4) of Arbitration Act At the time of merger, RTI and the Claimant is one and the same. In the expert s opinion provided by Mr. Bowman 2, in the case of a merger under the Law of Fruitland, all the rights and liabilities of the constituent companies are transferred to the surviving entity automatically, without more as a matter of law, and there is no requirement of any notice to be given for this process to be effective including arbitration issues. Therefore, it is submitted that the Claimant was under no requirement to inform the Respondent of the change of entity. RTI and the Claimant are one and the same; and an action in the name of RTI is therefore necessarily an action by the Claimant Alternatively, there is a misnomer that the Claimant applies to have corrected. It is stated that English Law regards all matters relating to the status of a new company as being governed by the law of this company s domicile 3. In the present case, the concept of universal succession should be considered under the law of Fruitland. However, the concept of misnomer should be explained under English Law, which governs the underlying contract, rather than the law of Fruitland. 1 Deutsche Schachtbau-und Tiefbohrgesellschaft GmbH v. Ras Al Khaimah National Oil Corporation [1987] 2 All ER Page 113 of the Problem Question. 3 National Bank of Greece & Athens v. Metiliss [1958] AC

11 In SEB v. Manches 4, before arbitration, OAR had ceased to exist and all of its rights and liabilities had been transferred to AMB. However, OAR rather than AMB was named arbitration claimants.. It was held that there was a misnomer, and the test was to determine who would reasonably have been understood to be the entity bringing the claim by the party against whom the claim was asserted. The facts of SEB v. Manches are almost identical to the present case. Indeed, it is clear from the evidences that the Respondent knew who the party against them was. Firstly, it is worth noting that the Respondent brought up the issue of an alleged wrong appointment of arbitrators only two days after 10 February, which under the contract was the last day to commence Arbitration. It is argued that the Respondent deliberately waited until the Arbitration had expired. Moreover, it was held in Lay v. Ackerman 5 that the Notice of Appointment is valid if it leaves the tenant in no doubt that it comes from the landlord. Applying the reasoning to the present case, the Respondent could not have been under any uncertainty as to knowing who the Claimant was. Indeed, the merger between Reliable Holdings and Reliable Tankers was public knowledge, as it had made the front page of a newspaper about twenty-five days before the Notice of Appointment. It is thus submitted that there is a clear and intentional misnomer from the part of the Respondent. More generally, English courts tend to interpret the requirement for a Notice of Appointment commencing arbitral proceedings in a very flexible way. In Nea Agrex SA v. Baltic Shipping Co 6, the learned judge described a flawed Notice of Appointment as irregular but effective, rather than void, as the necessary step was taken, and procedural step whose form and terms do not call for an excessively strict scrutiny. Therefore, the Notice of Appointment given on 28 January by the Claimant is valid. It 4 [2005] EWCA Civ [2004] HLR [1976] 2 Lloyd s Rep

12 follows that the Arbitration was successfully commenced by the Claimant. PART TWO: MERITS 3. The sum of US$4,945, is due by way of freight Freight is deemed earned upon lifting of subjects. It is submitted that Clause 4 of Reliable Tankers Standard Terms is the relevant freight clause, which is incorporated into the contractual arrangement by both recaps between the parties. They mention both parties special terms are fully incorporated as per attached. The Reliable Tankers standard terms are attached, so the recap properly incorporates them, as a part of the contractual arrangement. The stipulation for the freight in the recap itself does not contradict with Standard Terms Clause 4, but specifies the amount of freight that is due Reliable Tankers Standard Terms Clause 4 prevails over ASBATANKVOY Clause 2 Where Reliable Tankers Standard Terms clause 4 (Clause 4) provides for freight being deemed earned upon lifting of subjects, ASBATANKVOY Clause 2 states that payment of freight shall be made upon delivery, The general rule at Common Law in cases of inconsistencies between the standard form and special terms or riders of a contract is that in the absence of a hierarchy clause, the riders will prevail. This rule has long been established by case law 7, the latest of which being The Leonidas 8, where it was stipulated 7 Marifortuna Naviera S.A. v. Government of Ceylon [1970] 1 Lloyd s Rep. 247; The Satya Kailash [1984] 1 Lloyd s 12

13 that the Courts would try to reconcile any conflict, failing which the rider will prevail. The Claimant thus argues that the provision made under Clause 4 prevails over the contract s Standard form. In the recap telex, it is mentioned that ASBATANKVOY along with the 1-61 Super Charters Terms are the basis of the contract, and that they are amended logically and specifically by the terms included therein. Consequently Reliable Tankers Standard terms are riders. What is alleged to be the inconsistency lies in the statement regarding when, and how, freight is earned. Indeed, ASBATANKVOY mentions that freight is earned upon discharge, whereas Clause 4 provides for freight being earned upon lifting of subjects. In the present case, discharge never occurred which is not disputed by either party - and it would logically follow from the interpretation of ASBATANKVOY that freight is not earned. Conversely, it would follow from the interpretation of Clause 4 that the condition precedent to freight being deemed earned, namely the lifting of subjects, occurred on 19 November. On a proper construction of the contract, and following the common law rule aforementioned, it is therefore submitted that freight is deemed earned Freight is deemed earned upon lifting of subjects The Claimant further argues that the Respondent s refusal to pay freight is based on an incorrect understanding of the construction of Clause 2; and that the Respondent fails to address the Claimant s submission on that matter. Clause 2 reads as follows: FREIGHT DEEMED EARNED IN FULL DISCOUNTLESS NON-RETURNABLE AND 95 OF MINIMUM FREIGHT PAYABLE UPON LIFTING Rep Bayoil SA v. Seawind Tankers Corp (The Leonidas) [2001] 1 Lloyd s Rep

14 SUBJECTS [ ]. In the light of relevant case law 9 it is submitted that it would be incorrect to put forward a construction suggesting that lifting of subjects only refers to 95% being payable at that point, as opposed to the previous stipulation on freight being earned containing no time specification. If the Tribunal accepts that freight is earned upon discharge, it will accordingly not give effect to the word deemed. Lord Brandon in The Dominique 10 suggests that freight payable upon discharge is used without any qualifying epithet and is just called freight, whereas freight payable at an early stage of the voyage, such as on completion of signing of bills of lading [...] is called advance freight. It logically follows from this interpretation that the use of deemed earned when freight is actually earned upon discharge is a non-sense, and consequently the Respondent s understanding of Clause 2 has to be disregarded. The reasoning of the Court in The Karin Vatis 11 further supports this submission. Slade L.J there tried to make a construction of a clause Freight deemed earned as cargo loaded, which was followed, after a full stop, by a 95% of freight paid after three days. In his view, the use of the full stop clearly demonstrated a separation between the two provisions; so that the whole freight was earned on cargo loading, and the 95% part indicated that this proportion was payable after three days. In the present there is no full top separating the freight deemed earned from the 95%, so that they share a common time point and consequently, freight is earned in full upon lifting of subjects. Furthermore, it is evident from the drafting of the clause that it was attempted to be as short as possible, and this is, perhaps, why the drafters seem to commingle the time when freight becomes deemed earned and the 95% payable. So in a poorly drafted clause like 9 Dakin v. Oxley 143 ER 938 is the landmark case on actual freight, where the Court held that the Claimant must, unless otherwise agreed, carry the cargo to the destination provided for in the charterparty and be ready to deliver it there, in order to earn freight. The Dominique and the Karin Vatis are also examined. 10 Colonial Bank v. European Grain & Shipping Ltd (The Dominique) [1987] 1 Lloyd s Rep 239; [1988] 1 Lloyd s Rep Vagres Compania Maritima SA v. Nissho-lwai American Corp (The Karin Vatis ) [1988] 2 Lloyd s Rep

15 this, an interpretation, which gives full effect to its words must be sought, so that a construction of a term does not render ineffective other terms of the clause. In contrast with the Respondent interpretation, our construction gives full effect to all the terms of clause 4, and is consistent with the agreement of the parties. Finally, the Claimant s interpretation of Clause 2 is consistent with the view of the House of Lords in the Dominique 12, where the freight clause read Freight shall be prepaid within five days of signing [...], full freight deemed to be earned on signing bills of lading [...]. It was held that the effect of the two phrases taken together was that the claimant s right to the freight accrued on signing, while it was payable at a different point in time. The Court supported that any contrary view would give no effect to the second part of the clause. Accordingly, a provision deemed earned such as in the present case will render advance freight irrecoverable but yet payable even if the voyage is not completed. In a case with similar factual complex and similar clause freight deemed earned on signing of b/ls, the House of Lords held that even though the charter was terminated, the freight was still due There is no lack of consideration The rules of consideration do not apply to advanced freight. The Claimant argues that the freight concerned in the present case is advance freight, to which the normal rules of consideration do not apply, and therefore the Respondent s submission for failure of consideration is inadmissible. Mr. Justice Hobhouse said in the Dominique 13 that advance freight should not be treated as a contractual obligation, to which the rules of failure of consideration or partial failure, apply as in other branches of law. Once earned, advance freight is at the risk of 12 Colonial Bank v. European Grain & Shipping Ltd (The Dominique) [1987] 1 Lloyd s Rep 239; [1988] 1 Lloyd s Rep ibid 15

16 the charterer. It is commonly accepted that advance is the freight that is payable in advance, thus the present freight is an advance freight, as the 95% of it is payable upon lifting subjects. If Lord Justice Mustill held in The Dominique that, where there was an effective failure of consideration, the owners could not recover freight when they did not perform, it is thereby submitted that this view cannot be applied where there is a deemed earned clause. The Claimant argues that it is the view of the House of Lords that should be applied to the present case, i.e. that in such a clause, the right to freight survives the termination of the charterparty. The House of Lords did not deal with the question of consideration itself, but is derives from its argumentation on whether freight was an accrued debt and its survival that it would certainly align with the view of Hobhouse J, thus leaving no room for consideration issues in advance freight Alternatively, there is no total failure of consideration Alternatively, if the Tribunal finds that the rules of consideration do apply to the present case, in the light of Rover v. Cannon 14, they are not applicable in this contractual arrangement. In this case it was stated that The question is whether there was any consideration in the nature of part performance for which the installment was payable. In the present case the approach voyage has begun, as the vessel is heading to the bunkering port, in accordance with her contractual duty to be fully bunkered at the port of loading. Consequently, part of the performance did begin, and thus there cannot be a total failure of consideration. The Courts have consistently held that the lack of consideration needs to be total, and that partial lack of consideration does not suffice. Although criticised, this requirement is necessary, because a contrary rule would cause great uncertainty in 14 Films Rover International Ltd v. Cannon Film Sales Ltd [1987] 1 WLR

17 contract law, as valuation would be very difficult in partial failure. Regardless of its correctness, the requirement for total failure is still the law in the United Kingdom, as the latest decisions indicate, thus if the court accepts that the approach voyage has begun, there would be only partial failure of consideration, which does not suffice Freight is an accrued debt upon lifting on subjects The House of Lords in The Dominique 15 upheld that the right to freight accrued by the time freight was deemed earned. This is consistent with the Karin Vatis 16 that supported that since full freight was deemed earned on loading, it became an accrued debt. Consequently, if the Tribunal holds that freight is deemed earned upon lifting of subjects, it follows than it then became an accrued debt, and therefore the Claimant claim the sum of US$4,945, as due and owing under the Charter Any loss of the Respondent has arisen in an indirect way and is therefore of a consequential nature. As a general rule, losses that are related to and dependent on the position of the particular plaintiff are considered as consequential 17. It has long been established that, in cases where the party interested in on-time delivery suffers a dislocation of their business arrangements and thus are involved in further expenses due to a fault of the Claimant, this expenditure (e.g. extra freight or insurance) is only recoverable in the way of consequential damages 18. In this case, the Respondent alleged losses are not arising directly from any faulty performance or non-performance of the contractual obligations, but are a result of the 15 Colonial Bank v European Grain & Shipping Ltd (The Dominique) [1987] 1 Lloyd s Rep 239; [1988] 1 Lloyd s Rep ibid 17Andrew Tettenborn, Consequential Damages in Contract The Poor Relation, 42 Loy L.A.L. Rev. 177 (2008), p Borries v. Hutchinson (1865) 19 C.B.(N.S.)

18 Respondent own business motives. As long as such motives are extraneous to the charterparty, there cannot be a possibility of direct loss for a subsequent fixture. Any liability of the Claimant in this regard shall therefore be considered as consequential. At any rate it is suggested that the alleged losses of the Respondent concerning damages from their pre-existing obligations towards sellers and buyers of the cargo, as well as the loadport and disport terminals, are not recoverable as for lack of foreseeability. The test applied by Bingham J. in Stinnes v. Halcoussis (The Yanxilas) 19 of whether the loss in question was fairly and reasonably within the contemplation of the parties, as at the date of the contract, as a probable result of the breach which has in fact occurred, is not fulfilled and no damages may thus be awarded on those points The Claimant committed no breach of contract The approach voyage to the loading port had commenced The approach voyage to the loadport commenced on 19 November, which is the day when the contract was concluded. At that time, the vessel was already en route to the bunkering port in order to be supplied for performing her contractual voyage. Moreover, the ASBATANKVOY deviation clause provides that the vessel shall have liberty ( ) to call for fuel at any port or ports in or out of the regular course of the voyage. The call at the bunkering port of Redland was a prerequisite towards delivering a vessel fully bunkered and operational for the purposes of the charterparty and, as a result, such a stop was for the benefit of the Respondent. In any case, the obligation to commence the approach voyage punctually, which is a facet of the paramount obligation to proceed with reasonable dispatch, is an innominate term of 19 [1982] 2 Lloyd s Rep. 445 at p

19 the contract at any rate where the contract contains a cancelling clause 20. In Smith v. Dart & Son 21, the existence of a cancelling clause was explained not to be a contractual promise but a right to be exercised at the will of the Respondent, should the vessel arrive late. Therefore, as long as the option to cancel existed, in the event where the vessel was not able to meet the laycan, the Respondent had an absolute right to terminate the contract. The Claimant was eager to perform their part of the contractual obligations and has it not been for the subsequent cancellation by the Respondent, would have proceeded to the loading port with utmost dispatch as soon as the ship was released from the arrest The Respondent s own fault contributed to the non-payment of the security fees. The arrest of the ship at the bunkering port was an unforeseeable event for the Claimant, who had no knowledge of the existence of such a possibility. From the time the arrest took place, the Claimant made great efforts towards releasing the vessel, rendering thus possible the performance of the contractual voyage. Ultimately, despite the strenuous struggles of the Claimant to this end, the release of the ship could not be concluded in such a time as to meet her laycan. The main reason for this failure to provide the necessary security was the lack of adequate funds available to the Claimant. However, had the Respondent paid the sum that fell due from 19 November, the date where subjects were lifted and where, as per the terms of the charter, 95% freight became payable, the Claimant would have been able to secure the necessary amount of money for the release of the vessel. It is submitted, therefore, that no liability can be allocated to the Claimant for failure to 20 Evera SA Commercial v. North Shipping Co Ltd (The North Anglia) [1956] 2 Lloyd s Rep (1884) 14 QBD

20 provide security in order to release the vessel, as long as the payment of freight remained outstanding. It is the Respondent default in payment of freight that made the release of the vessel impossible There was no misstatement concerning the ETA provision. It has long been established that whether a statement by the Claimant concerning the estimated time of arrival of the vessel is a breach of the expected readiness condition depends on whether the Claimant honestly expected, at the time of entering into the contract, that the vessel would be ready to load at the stipulated date, and had reasonable grounds for that expectation 22. Similarly to the expected readiness clause, an ETA clause looks to the reasonableness of the Claimant estimate at the time when it was given, rather than at subsequent events. The sent to the Respondent on 23 November contained no dishonest or unreasonable statement in relation to the ETA, but rather the truthful expectation on behalf of the Claimant that the vessel would be released on time. As long as it became apparent that such an event would take place at a time that it would not be possible for the ship to make the laycan, the Claimant communicated their thoughts to the Respondent ( on 25 November). Indeed, the fact that the exact date of the vessel s release remained unknown to the Claimant made it impossible for a revised ETA to be provided. Consequently, there was no misstatement by the Claimant that could be interpreted as dishonest or unreasonable and therefore the necessary elements for their liability to be established are not present. 22 Samuel Sanday & Co v. Cox McEuen & Co (1922) 10 LI.L Rep

21 3.6. In order for the liability of the Claimant to be established, the condition precedent of gross negligence needs to be met The Tribunal lacks jurisdiction to decide on tortious matter Under English law, negligence is categorised as a tort, and is therefore dependent on a pre-existing duty of care among the parties. Arbitration, however, is a creature of contract and the jurisdiction of the arbitral tribunal arises out of the arbitration agreement. It is the essence of the arbitration that the tribunal has only the authority conferred on it by the agreement under which it is established 23. The limits of the arbitral tribunal s powers are determined by the wording of the arbitration agreement. Where the parties have made an agreement to arbitrate, therefore, they will be held to that arbitral agreement. 24 Under common law, a detailed analysis of the wording of the arbitration clause is required, in order to ascertain the extent of the arbitral tribunal s jurisdiction. As a result, an arbitral tribunal will not have jurisdiction to deal with claims in tort, such as the tort of negligence, if the arbitration agreement states that only disputes related to the contract can be arbitrated 25. Clause 5 of the Reliable Tankers Standard Terms limits the liability of the Claimant, as far as consequential damages are concerned, to cases where gross negligence is identified. However, as the Arbitral Tribunal has no jurisdiction to rule on tortious matters, no damages may be awarded for any consequential losses whatsoever. 23 United Parcel Service of America Inc v. Government of Canada 46 ILM 922 (2007). 24 Tweeddale A., Tweeddale K., Arbitration of Commercial Disputes: International and English Law and Practice. 25 Progressive Casualty Insurance Co. v. Reaseguradora Bacional de Venezuela 991 F 2d 42 (2nd cir 1993), where the US District Court held that it would apply ordinary contract law principles in order to determine the meaning of these words and whether the dispute in hand was covered by the arbitration clause, therefore adopting a literal and strict interpretation of the wording. 21

22 Further or alternatively, no acts or neglects on the part of the Claimant can be interpreted as gross negligence. Lord Wilberforce in Anns v. Merton L.B.C. 26 opined that in order to establish that a duty of care arises in a particular situation ( ) first, one has to ask whether as between the wrongdoer and the person who has suffered damage there is a sufficient relationship of proximity or neighborhood such that, in the reasonable contemplation of the former, carelessness on his part may be likely to cause damage to the latter, in which case a prima facie duty of care arises. Secondly, if the first question is answered affirmatively, it is necessary to consider whether there are any considerations which ought to negative or to reduce or limit the scope of the duty. Clause 5 of the Reliable Tankers Standard Terms essentially limits the scope of the duty, providing that, in order for consequential damages to be awarded, gross negligence of the Claimant, their servants or their agents must exist. In addition, no special relationship, as introduced in Hedley Byrne & Co. Ltd. v. Heller & Partners Ltd 27 existed between Claimant and Respondent, as the application of this particular case was later confined only to cases where a person carries on the business of giving the type of advice that is sought, or claims to possess considerable skill and competence in it 28. Further to this argument, It is submitted that he presence of both negligence and gross negligence in the contract terms, indicates that some distinction must be intended, as for the parties to have chosen to use these words, they must be given some meaning in special 29. Moreover, English courts have recognised that the concept of gross negligence should be interpreted as a standard requiring a party to act in a manner more negligent than ordinary 26 [1977] 2 WLR [1964] A.C Mutual Life & Citizens Assurance Co. Ltd. v. Evatt [1971] AC 793, Esso Petroleum Co. Ltd. v. Mardon [1976] QB Tradigrain SA & Ors v. Intertek Testing Services (ITS) Canada Ltd & Anor [2007] EWCA Civ

23 negligence, capable thus of embracing not only the conduct undertaken with actual appreciation of the risks involved, but also serious disregard of or indifference to an obvious risk 30. Mr. Justice Mance in The Hellespont Ardent 31 referred to conduct so seriously negligent that the defendant should not be entitled to rely on the exemption clause, acknowledging that the question is very much a matter of degree and judgment. It is therefore suggested that gross negligence is used interchangeably with the terms willful misconduct and deliberate default, which are better understood under English law. As a result of the above, there are no grounds upon which even the possibility of negligent behavior of the Claimant could be based, so the requirement of willful misconduct is a majore ad minus excluded. 4. The Respondent s cancellation of the charter relieved both parties from performing any further obligations or liability arising thereunder The charter was cancelled The charter was cancelled by the operation of the Respondent contractual termination, without recourse to either party whatsoever. It is submitted that the cancellation was not the result of a breach from the part of the Claimant, but the decision of the Respondent to exercise their right under the charter. Therefore, it was a contractual termination of the charterparty. Clause 2 of the Claimant s Standard Terms clearly states If charterers elect to decline, 30 Camarata Property Inc v. Credit Suisse Securities (Europe) Ltd [2011] EWHC 479 (Comm). 31 [1997] 2 Lloyd s Rep

24 then charter to be cancelled without recourse to either party whatsoever. The Respondent have indeed so elected, as evidenced by the Notice of Cancellation dated 27 November, accepted by the Claimant 32. By analogy with the reasoning in The Kurt Illies 33, where in the absence of an effective notice of cancellation, the charter was held to be in full force and effect, a fortiori in the face of the evidences of the present case, the charter is to be held properly cancelled. Therefore, and on a proper construction, both parties were automatically relieved from performing any further obligations and liabilities arising out of the contract There is no ground for a claim for damage It follows from this submission that the Claimant cannot be held liable for damages, as the Respondent suffered no loss of bargain. Indeed, it was held in Financings Ltd v. Baldock 34 that it is only where the contract is terminated for repudiatory breach that a claim may be made for damages as a consequence of the loss of bargain (i.e. loss which accrue as a consequence of the premature determination of the contract 35 ). No such breach occurred here, since, as demonstrated above, the charter was cancelled as a result of the exercise of the Respondent s contractual right. The Claimant did not commit any breach in the performance of their contractual obligations prior to the Respondent s decision to cancel, and therefore the Claimant argues that it is not liable for any sum whatsoever. 32 dated 28 November, page 97 of the Problem Question. 33 The Kurt Illies, SMA 2778 (1991) ; cited in Julian Cooke on Voyage Charters, 3rd ed (thereafter Cooke), Chapter [1963] 2 QB Cooke, Chapter

25 4.2. Further or alternatively, the respondent s early repudiation of the charter amounted to a breach of contract There is no anticipatory right to cancel. Further or alternatively, if any breach were committed, it would be from the part of the Respondent, who cancelled the charterparty before the laycan was actually hit (on the 5-6 December). It is clear from The Madeleine 36, and in particular the judgement of Roskill J, that there is no anticipatory right to cancel at common law. The Respondent was not entitled to exercise a cancelling option before the relevant time had arrived. This view was followed and brought further in The Simona 37, where the Court held that a unilateral attempt to do so might amount to an anticipatory breach and repudiation of the charter. It logically follows from the authorities that the Respondent, by purporting to exercise a right to cancel before the cancelling date had arrived, is to be held in repudiatory breach by the Tribunal as his conduct amounted to an absolute refusal to perform his charter obligations. As a result of this breach, the Claimant is entitled to claim damages The respondent failed to take reasonable steps to mitigate their loss, which deprived them of any ground to recover nominal damages. In The Soholt 38, J Donaldson MR stated that A defendant is only liable for such part of the claimant s loss as is properly to be regarded as caused by the defendant s breach of duty. By dated 28 November, the Claimant offered to provide the Respondent with a sister VLCC. The Respondent did not refer to this offer in any further correspondence, and immediately chose to refer the dispute to Arbitration. It is argued that he failed to act reasonably and take available steps to mitigate his loss; consequently the loss he is 36 Cheikh Boutros Selim El-Khoury v. Ceylon Shipping Lines Ltd (The Madeleine) [1967] 2 Lloyd s Rep 224). 37 Fercometal v. Mediterranean Shipping (The Simona) [1989] A.C Sotiros Shipping Inc v. Sameiet Soholt (The Soholt) [1983] 1 Lloyd s Rep

26 claiming for is not attributable to the Claimant s -alleged, but denied- breach but to his inaction. Had the Claimant s offer been considered, the Respondent might have been able to obtain a better bargain, considering the state of the market at the time 39. It was held in The Mihalis Angelos 40 that the fact that the right to cancel would have accrued and been exercised may affect the owner s damage claim, who therefore may be entitled to nominal damages. Megaw LJ opined In my view, where there is an anticipatory breach of contract, the breach is the repudiation once it has been accepted, and the other party is entitled to recover by way of damages the true value of the contractual rights which he has thereby lost, subject to his duty to mitigate. However as the Claimant previously demonstrated, the Respondent failed to do so and is therefore deprived of any ground to recover even nominal damages In any event, the claimant is not liable for any delay occurring out of the ship s arrest by a third party. In the event where the Respondent s breach was not held to be an anticipatory breach, the Claimant would still not be liable for damages. Indeed, in The North Anglia 41, Devlin J held that If something occurs on the voyage to the port of loading which delays the ship without her fault, then the owners are not liable (under the ETA clause). The arrest of the ship at the bunker port is not imputable to the Claimant, who could note have reasonably foresee the decision of the port authorities to retain the vessel and who, as previously demonstrated, was neither wrongful nor negligent in his conduct. By analogy with Devlin J s reasoning, the Claimant argues that he cannot be held liable for any damages whatsoever, and that the cancellation of the charterparty by the Respondent does not affect the Claimant s claim for freight, which remains due as demonstrated at length above. 39 Market Report p.99 of the Problem Question. 40 Maredelanto v. Bergbau Handel (The Mihalis Angelos) [1971] 1 Q.B [1956] 2 Lloyd s Rep

27 CONCLUSION There are no grounds to argue that the arbitral proceedings were not properly commenced. The Claimants provided a Notice of Arbitration in time and successfully, as there could be no doubt as to the identity of the legal entity that initiated the Arbitration. On the merits, it derives straight from the wording of the Reliable Tankers Standard Terms, clause 4, that the sum of US$4,945, is earned and remains due to be paid by the Respondents by way of freight. The said amount was payable upon lifting of subjects and, although it was not challenged that this moment had passed, no payment whatsoever was made on behalf of the Respondents. In addition, no matter of lack of consideration may arise, as the sum clearly relates to freight that was agreed to be paid in advance. The Claimants were punctual with all the obligations laid up upon them through the charterparty, and therefore no breach of the carriage contract whatsoever may be considered to have arisen on their part. Any action in tort could not be presented in the course of the current proceedings, as the Arbitral Tribunal lacks jurisdiction to decide on tortious matters. Finally, as a matter of fact, the charter was cancelled on 27 November, as per the provisions of the Claimant Standard Terms, clause 2. The cancellation was effected without recourse to either party whatsoever, thus disallowing any subsequent claim for damages that the Respondents may have suffered as a result of their election to cancel the charter. 27

15 th Annual International Maritime Law Arbitration Moot

15 th Annual International Maritime Law Arbitration Moot 15 th Annual International Maritime Law Arbitration Moot Hosted by the School of Law, University of Hong Kong Hong Kong MEMORANDUM On Behalf of : Against : Super Charters Inc. Reliable Tankers Inc. Reliable

More information

FIFTEENTH INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014 MEMORANDUM FOR THE CLAIMANTS IN THE MATTER OF AN ARBITRATION BETWEEN.

FIFTEENTH INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014 MEMORANDUM FOR THE CLAIMANTS IN THE MATTER OF AN ARBITRATION BETWEEN. FIFTEENTH INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014 MEMORANDUM FOR THE CLAIMANTS IN THE MATTER OF AN ARBITRATION BETWEEN RELIABLE TANKERS INC Claimants and SUPER CHARTERS Respondents

More information

MEMORANDUM FOR RELIABLE HOLDINGS INC.

MEMORANDUM FOR RELIABLE HOLDINGS INC. 15th International Maritime Law Arbitration Moot, 2014 IN THE MATTER OF AN ARBITRATION HELD IN HONG KONG MEMORANDUM FOR RELIABLE HOLDINGS INC. ON BEHALF OF Reliable Holdings Inc. Owners AGAINST Super Charters

More information

Uni-Navigation Pte Ltd v Wei Loong Shipping Pte Ltd

Uni-Navigation Pte Ltd v Wei Loong Shipping Pte Ltd [1992] 3 SLR(R) SINGAPORE LAW REPORTS (REISSUE) 595 Uni-Navigation Pte Ltd v Wei Loong Shipping Pte Ltd [1992] SGHC 293 High Court Admiralty in Personam No 489 of 1992 GP SelvamJC 28 November 1992 Arbitration

More information

FIFTEENTH INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014 MEMORANDUM FOR THE RESPONDENTS IN THE MATTER OF AN ARBITRATION BETWEEN.

FIFTEENTH INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014 MEMORANDUM FOR THE RESPONDENTS IN THE MATTER OF AN ARBITRATION BETWEEN. FIFTEENTH INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014 MEMORANDUM FOR THE RESPONDENTS IN THE MATTER OF AN ARBITRATION BETWEEN RELIABLE TANKERS INC Claimants and SUPER CHARTERS Respondents

More information

INTERNATIONAL MARITIME LAW ARBITRATION MOOT. IMLAM Moot organised by School of Law, Murdoch University

INTERNATIONAL MARITIME LAW ARBITRATION MOOT. IMLAM Moot organised by School of Law, Murdoch University INTERNATIONAL MARITIME LAW ARBITRATION MOOT 2014 IMLAM Moot organised by School of Law, Murdoch University Oral rounds hosted by Faculty of Law, University of Hong Kong MOOT SCENARIO RELEASED 18 DECEMBER

More information

FIFTEENTH INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014

FIFTEENTH INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014 FIFTEENTH INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014 UNIVERSITAS PADJADJARAN BANDUNG, INDONESIA IN THE MATTER OF AN ARBITRATION HELD IN HONG KONG Claimant Reliable Holdings Inc Respondent

More information

FIFTEENTH ANNUAL INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014 UNIVERSITAS GADJAH MADA INDONESIA TEAM 6 MEMORANDUM FOR THE RESPONDENT

FIFTEENTH ANNUAL INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014 UNIVERSITAS GADJAH MADA INDONESIA TEAM 6 MEMORANDUM FOR THE RESPONDENT FIFTEENTH ANNUAL INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014 UNIVERSITAS GADJAH MADA INDONESIA TEAM 6 MEMORANDUM FOR THE RESPONDENT ON BEHALF OF: AGAINTS: SUPER CHARTERS INC. RELIABLE

More information

Sydney Law School Rechtsanwalt Yves Heinze. Rathenaustraße 11, D Jena, Germany Phone: , Web:

Sydney Law School Rechtsanwalt Yves Heinze. Rathenaustraße 11, D Jena, Germany Phone: , Web: Sydney Law School Rechtsanwalt Yves Heinze. Rathenaustraße 11, D-07745 Jena, Germany Phone: +49 3641 217310, Web: www.heinze-law.com Conditions, warranties and innominate terms different terms for the

More information

Hague Rules v Hague Visby Rules (II)

Hague Rules v Hague Visby Rules (II) To: Transport Industry Operators 27 January 2017 Ref : Chans advice/193 Hague Rules v Hague Visby Rules (II) Remember our Chans advice/163 about the English High Court s Judgment holding the Hague Visby

More information

Arbitration 187 This Arbitration was governed by the International Arbitration Act 1974 (Cth). Contract type - GTA FOB Contract No.

Arbitration 187 This Arbitration was governed by the International Arbitration Act 1974 (Cth). Contract type - GTA FOB Contract No. Arbitration 187 This Arbitration was governed by the International Arbitration Act 1974 (Cth). Contract type - GTA FOB Contract No. 1 Date of Issue: January 2014 Claimant: & Respondent: Export FOB seller

More information

COURT OF APPEAL CONFIRMS PAYMENT OF HIRE UNDER TIME CHARTERPARTIES IS NOT A CONDITION

COURT OF APPEAL CONFIRMS PAYMENT OF HIRE UNDER TIME CHARTERPARTIES IS NOT A CONDITION BRIEFING COURT OF APPEAL CONFIRMS PAYMENT OF HIRE UNDER TIME CHARTERPARTIES IS NOT A CONDITION DECEMBER 2016 THE OBLIGATION TO PAY HIRE PUNCTUALLY AND IN ADVANCE IS AN INNOMINATE TERM RATHER THAN A CONDITION

More information

UNITED NATIONS CONVENTION ON CONTRACTS FOR THE INTERNATIONAL SALE OF GOODS (1980) [CISG]

UNITED NATIONS CONVENTION ON CONTRACTS FOR THE INTERNATIONAL SALE OF GOODS (1980) [CISG] Go to CISG Table of Contents Go to Database Directory UNITED NATIONS CONVENTION ON CONTRACTS FOR THE INTERNATIONAL SALE OF GOODS (1980) [CISG] For U.S. citation purposes, the UN-certified English text

More information

INTERNATIONAL MARITIME LAW ARBITRATION MOOT

INTERNATIONAL MARITIME LAW ARBITRATION MOOT INTERNATIONAL MARITIME LAW ARBITRATION MOOT 2014 THE UNIVERSITY OF HONG KONG TEAM 3 MEMORANDUM FOR THE CLAIMANTS CECILIA WING YU CHOI PAK HEI LI ADRIAN YIU YEUNG LO MANTONG AMANDA ZHANG i LIST OF ABBREVIATIONS

More information

FIFTEENTH ANNUAL INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014

FIFTEENTH ANNUAL INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014 FIFTEENTH ANNUAL INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014 IN THE MATTER OF ARBITRATION BETWEEN: RELIABLE TANKERS INC SUPER CHARTERS INC Claimants/Owners ers Respondents/Charter RELIABLE

More information

Delay in Commencing an Arbitration

Delay in Commencing an Arbitration Delay in Commencing an Arbitration by ANDREW TWEEDDALE 1. INTRODUCTION Judge Martyn Zeidman recently commented: As stated in Magna Carta, justice delayed is justice denied. 1 The Limitation Acts are intended

More information

HOT TOPICS FOR FINANCE LAWYERS. Jersey Chancery Bar Conference Thursday 16 th October Catherine Gibaud QC

HOT TOPICS FOR FINANCE LAWYERS. Jersey Chancery Bar Conference Thursday 16 th October Catherine Gibaud QC HOT TOPICS FOR FINANCE LAWYERS Jersey Chancery Bar Conference Thursday 16 th October 2014 Catherine Gibaud QC HOT TOPICS FOR FINANCE LAWYERS Catherine Gibaud QC Rewriting History when can non-reliance

More information

IN THE KWAZULU NATAL HIGH COURT, DURBAN

IN THE KWAZULU NATAL HIGH COURT, DURBAN IN THE KWAZULU NATAL HIGH COURT, DURBAN REPUBLIC OF SOUTH AFRICA CASE NO. A71/2009 In the matter between: BROBULK LIMITED APPLICANT and GREGOS SHIPPING LIMITED M V GREGOS SEAROUTE MARITIME LIMITED FIRST

More information

Contract No.106. Copyright THE GRAIN AND FEED TRADE ASSOCIATION

Contract No.106. Copyright THE GRAIN AND FEED TRADE ASSOCIATION Effective 01 st September 2017 Contract No.106 Copyright THE GRAIN AND FEED TRADE ASSOCIATION CONTRACT FOR TRANSHIPMENT FOB GOODS SHIPPED FROM ORIGIN WITH SUBSEQUENT DELIVERY AT DISCHARGE PORT TO BUYERS

More information

LAYTIME AND DEMURRAGE RECENT CASES

LAYTIME AND DEMURRAGE RECENT CASES LAYTIME AND DEMURRAGE RECENT CASES Istanbul April 22, 2008 William J. Honan Holland & Knight LLP 1 Clause 5, Part II, ASBATANKVOY 5. LAYDAYS. Laytime shall not commence before the date stipulated in Part

More information

ERG Raffinerie Mediterranee Spa v Chevron USA Inc [2006] Int.Com.L.R. 06/09

ERG Raffinerie Mediterranee Spa v Chevron USA Inc [2006] Int.Com.L.R. 06/09 JUDGMENT : The Hon. Mr Justice Langley : Commercial Court. 9 th June 2006 INTRODUCTION 1. The Claimant (ERG) operates two oil refineries in Priolo, near Syracuse, in Sicily, known as ISAB Sud and ISAB

More information

Golden Strait Corp v Nippon Yusen Kubishika Kaisha "The Golden Victory" [2005] APP.L.R. 02/15

Golden Strait Corp v Nippon Yusen Kubishika Kaisha The Golden Victory [2005] APP.L.R. 02/15 The Hon Mr Justice Langley : 15 th February 2005 Context 1. This is an appeal by Golden Strait Corporation (GSC) Owners of the "Golden Victory" and the Claimant in an Arbitration to which Nippon Yusen

More information

REMOTENESS OF CONTRACTUAL DAMAGES

REMOTENESS OF CONTRACTUAL DAMAGES The Denning Law Journal Vol 21 2009 pp 173-179 CASE COMMENTARY REMOTENESS OF CONTRACTUAL DAMAGES Transfield Shipping Inc v Mercator Shipping Inc (The Achilleas ) [2008] 2 Lloyd's Rep 275 John Halladay

More information

International Maritime Congress Szczecin, Poland A carrier's liability for loss of or damage to cargo. Eurof Lloyd-Lewis - Partner 8 June 2016

International Maritime Congress Szczecin, Poland A carrier's liability for loss of or damage to cargo. Eurof Lloyd-Lewis - Partner 8 June 2016 International Maritime Congress Szczecin, Poland A carrier's liability for loss of or damage to cargo Eurof Lloyd-Lewis - Partner 8 June 2016 Overview The Superior Pescadores [2016] EWCA Civ 101 Construction

More information

Considering Contract Termination Under English Common Law

Considering Contract Termination Under English Common Law Portfolio Media. Inc. 111 West 19 th Street, 5th Floor New York, NY 10011 www.law360.com Phone: +1 646 783 7100 Fax: +1 646 783 7161 customerservice@law360.com Considering Contract Termination Under English

More information

Discharge of Contract Performance, Breach, Frustration Introduction

Discharge of Contract Performance, Breach, Frustration Introduction Discharge of Contract Performance, Breach, Frustration Introduction Discharge of a valid contract involves the process under which the primary (performance) obligations come to an end. Discharge by breach

More information

Anti-suit injunction (II)

Anti-suit injunction (II) To: Transport Industry Operators 27 February 2015 Ref : Chans advice/170 Anti-suit injunction (II) In our Chans advice/169 last month, we mentioned the English Court s Judgment dated 14/10/2014 holding

More information

INTERNATIONAL SALE OF GOODS ACT

INTERNATIONAL SALE OF GOODS ACT c t INTERNATIONAL SALE OF GOODS ACT PLEASE NOTE This document, prepared by the Legislative Counsel Office, is an office consolidation of this Act, current to December 2, 2015. It is intended for information

More information

Before : THE HON. MR JUSTICE MALES Between : SUPERIOR PESCADORES

Before : THE HON. MR JUSTICE MALES Between : SUPERIOR PESCADORES Neutral Citation Number: [2014] EWHC 971 (Comm) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION COMMERCIAL COURT Case No: 2012 Folio 102 Royal Courts of Justice Strand, London, WC2A 2LL Date: 02/04/2014

More information

TEAM NO. 7. Memorandum for the Claimant (CLAIMANT) (RESPONDENT) THE FIFTEENTH ANNUAL INTERNATIONAL MARITIME LAW ARBITRATION MOOT

TEAM NO. 7. Memorandum for the Claimant (CLAIMANT) (RESPONDENT) THE FIFTEENTH ANNUAL INTERNATIONAL MARITIME LAW ARBITRATION MOOT THE FIFTEENTH ANNUAL INTERNATIONAL MARITIME LAW ARBITRATION MOOT Memorandum for the Claimant On Behalf of: Reliable Holdings, Inc. (CLAIMANT) Against: Super Charters, Inc. (RESPONDENT) FARAH NABILA RAOUL

More information

SALE OF GOODS (VIENNA CONVENTION) ACT 1986 No. 119

SALE OF GOODS (VIENNA CONVENTION) ACT 1986 No. 119 SALE OF GOODS (VIENNA CONVENTION) ACT 1986 No. 119 NEW SOUTH WALES TABLE OF PROVISIONS 1. Short title 2. Commencement 3. Interpretation 4. Act binds Crown 5. Convention to have the force of law 6. Convention

More information

THE BALTIC STRAIT FOOD FOR THOUGHT IN RELATION TO CARGO CLAIMS

THE BALTIC STRAIT FOOD FOR THOUGHT IN RELATION TO CARGO CLAIMS MARCH 2018 SHIPPING THE BALTIC STRAIT FOOD FOR THOUGHT IN RELATION TO CARGO CLAIMS 1. Sevylor Shipping and Trading Corp v Altfadul Company for Food, Fruits and Livestock and Siat The recent Judgment in

More information

JUDGMENT. By: MR JUSTICE ADREW SMITH. Between: Ramburs Inc. and. Agrifert SA

JUDGMENT. By: MR JUSTICE ADREW SMITH. Between: Ramburs Inc. and. Agrifert SA JUDGMENT By: MR JUSTICE ADREW SMITH Between: Ramburs Inc and Agrifert SA Mr Justice Andrew Smith: 1. The question for determination is whether the defendants, Agrifert SA, the buyers under a FOB contract

More information

A GUIDE TO TERMINATION OF LONG TERM CONTRACTS IN THE ENERGY SECTOR KEY POINTS AND RECENT DEVELOPMENTS

A GUIDE TO TERMINATION OF LONG TERM CONTRACTS IN THE ENERGY SECTOR KEY POINTS AND RECENT DEVELOPMENTS A GUIDE TO TERMINATION OF LONG TERM CONTRACTS IN THE ENERGY SECTOR KEY POINTS AND RECENT DEVELOPMENTS By Dan Jewell (Senior Associate), Elinor Thomas (Legal Director), Simon Collier (Senior Associate)

More information

MEMORANDUM for CLAIMANT

MEMORANDUM for CLAIMANT INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014 Hong Kong MEMORANDUM for CLAIMANT MAASTRICHT UNIVERSITY ON BEHALF OF CLAIMANT Reliable Holdings Inc. AGAINST RESPONDENT Super Charters Inc.

More information

THE ASTRA. Kuwait Rocks Co v AMN Bulk Carriers Inc [2013] EWHC 865 (Comm) 2. Isabella Shipowner SA v Shajang Shipping Co Ltd [2012] EWHC 1077 (Comm)

THE ASTRA. Kuwait Rocks Co v AMN Bulk Carriers Inc [2013] EWHC 865 (Comm) 2. Isabella Shipowner SA v Shajang Shipping Co Ltd [2012] EWHC 1077 (Comm) THE ASTRA Except for anyone living as a hermit over the last year, the Judgment of Flaux J in The Astra 1 will be well known. In a lengthy, careful and reasoned analysis he concluded that the obligation

More information

Repudiation, anticipatory breach and conditions in a contract for services

Repudiation, anticipatory breach and conditions in a contract for services Brodies The Legal 500 & The In-House Lawyer Legal Briefing Public Sector The Legal 500 Rose Marie O Donnell, Associate rosemarie.odonnell@brodies.com Repudiation, anticipatory breach and conditions in

More information

BEFORE: HIS HONOUR JUDGE MACKIE QC (Sitting as a Judge of the Queen s Bench Division) TIDEBROOK MARITIME CORPORATION. -and- VITOL SA OF GENEVA

BEFORE: HIS HONOUR JUDGE MACKIE QC (Sitting as a Judge of the Queen s Bench Division) TIDEBROOK MARITIME CORPORATION. -and- VITOL SA OF GENEVA Neutral Citation Number: [2005] EWHC 2582 (Comm) IN THE HIGH COURT OF JUSTICE QUEEN S BENCH DIVISION COMMERCIAL COURT CLAIM NO: 2005 FOLIO 189 Hearing 21 st October 2005 BEFORE: HIS HONOUR JUDGE MACKIE

More information

International Conditions of Sale for Customers not Resident in Germany

International Conditions of Sale for Customers not Resident in Germany International Conditions of Sale for Customers not Resident in Germany I. Application of the International Conditions of Sale 1. These International Conditions of Sale apply to all customers of Feldhaus

More information

1. Scope of Application (Chapter 2) / Freedom of Contract (Validity of Contractual terms) (Chapter 16)

1. Scope of Application (Chapter 2) / Freedom of Contract (Validity of Contractual terms) (Chapter 16) ROTTERDAM RULES KEY PROVISIONS 1. Scope of Application (Chapter 2) / Freedom of Contract (Validity of Contractual terms) (Chapter 16) Essentially the scope of the Convention extends to contracts of carriage

More information

United Nations Convention On Contracts For The International Sale Of Goods, 1980 (CISG) United Nations (UN)

United Nations Convention On Contracts For The International Sale Of Goods, 1980 (CISG) United Nations (UN) United Nations Convention On Contracts For The International Sale Of Goods, 1980 (CISG) United Nations (UN) Copyright 1980 United Nations (UN) ii Contents Contents PART I - Sphere of Application and General

More information

Article 1. In this Convention the following words are employed with the meanings set out below:

Article 1. In this Convention the following words are employed with the meanings set out below: International Convention for the unification of certain rules of law relating to bills of lading and protocol of signature as amended by the 1968 and the 1979 Protocols Article 1. In this Convention the

More information

THE BUILDING CONTROL AMENDMENT REGULATIONS. Martin Waldron BL

THE BUILDING CONTROL AMENDMENT REGULATIONS. Martin Waldron BL MARTIN WALDRON BL FCIArb MSCSI MRICS Accredited Adjudicator & Mediator Law Library The Four Courts Dublin 7 +353(1)8177865 +353(86)2395167 www.waldron.ie martin@waldron.ie THE BUILDING CONTROL AMENDMENT

More information

Glencore Grain Ltd. v Goldbeam Shipping Inc. [2002] EWHC 27 (Commercial)

Glencore Grain Ltd. v Goldbeam Shipping Inc. [2002] EWHC 27 (Commercial) JUDGMENT : Mr Justice Moore-Bick: Commercial Court. 25 th January 2002 1. On 24 th November 1997 Glencore Shipping Ltd ( Glencore ) entered into a contract of affreightment with Goldbeam Shipping Inc.

More information

Cuthbert v Gair (t/a The Bowes Manor Equestrian Centre) [2008] APP.L.R. 09/03

Cuthbert v Gair (t/a The Bowes Manor Equestrian Centre) [2008] APP.L.R. 09/03 JUDGMENT : Master Haworth : Costs Court. 3 rd September 2008 1. This is an appeal pursuant to CPR Rule 47.20 from a decision of Costs Officer Martin in relation to a detailed assessment which took place

More information

Client Update August 2009

Client Update August 2009 Highlights Introduction...1 Brief Facts...1 Issue...2 Ruling Of The Court...2 Concluding Words...7 When Is An Innocent Party Entitled To Terminate A Contract? Introduction It is often not difficult deciding

More information

RIGHTS TO TERMINATE A COMMERCIAL CONTRACT SUCCESSFUL USE AND LIABILITY FOR MISUSE. David Thomas QC and Matthew Finn Keating Chambers.

RIGHTS TO TERMINATE A COMMERCIAL CONTRACT SUCCESSFUL USE AND LIABILITY FOR MISUSE. David Thomas QC and Matthew Finn Keating Chambers. RIGHTS TO TERMINATE A COMMERCIAL CONTRACT SUCCESSFUL USE AND LIABILITY FOR MISUSE David Thomas QC and Matthew Finn Keating Chambers 18 January 2018 INTRODUCTION It is often the case that one party to a

More information

INTERNATIONAL CONVENTION ON SALVAGE, 1989

INTERNATIONAL CONVENTION ON SALVAGE, 1989 INTERNATIONAL CONVENTION ON SALVAGE, 1989 Whole document THE STATES PARTIES TO THE PRESENT CONVENTION, RECOGNIZING the desirability of determining by agreement uniform international rules regarding salvage

More information

General Terms and Conditions of Sale and Delivery of ECKART GmbH

General Terms and Conditions of Sale and Delivery of ECKART GmbH General Terms and Conditions of Sale and Delivery of ECKART GmbH (September 2010) 1. GENERAL 1.1 These General Terms and Conditions of Sale and Delivery (hereinafter called General Sales and Delivery Conditions

More information

International Conditions of Sale for Customers not Resident in Germany

International Conditions of Sale for Customers not Resident in Germany I. Application of the International Conditions of Sale 1. These International Conditions of Sale apply to all customers of Dr. Günther Kast GmbH & Co. Technische Gewebe Spezial-Fasererzeugnisse KG - hereinafter

More information

DAMAGES FOR LATE DELIVERY UNDER TIME CHARTERS: CERTAINTY AT LAST?

DAMAGES FOR LATE DELIVERY UNDER TIME CHARTERS: CERTAINTY AT LAST? DAMAGES FOR LATE DELIVERY UNDER TIME CHARTERS: CERTAINTY AT LAST? Gary Richard Coveney * Introduction In Transfield Shipping Inc v Mercator Shipping Inc (Transfield), 1 the House of Lords examined the

More information

TREATY SERIES 1999 Nº 1. International Convention on Salvage

TREATY SERIES 1999 Nº 1. International Convention on Salvage TREATY SERIES 1999 Nº 1 International Convention on Salvage Done at London on 28 April 1989 Signed on behalf of Ireland on 26 June 1990 Ireland s Instrument of Ratification deposited with the Secretary-General

More information

GENERAL COMMERCIAL TERMS AND CONDITIONS FOR PURCHASE OF GOODS AND SERVICES

GENERAL COMMERCIAL TERMS AND CONDITIONS FOR PURCHASE OF GOODS AND SERVICES GENERAL COMMERCIAL TERMS AND CONDITIONS FOR PURCHASE OF GOODS AND SERVICES Definitions "Supplier" "Purchaser" "Goods" "Contract" shall mean the company contracting to supply the goods and/or perform works

More information

LIMITATION OF LIABILITY BY ACCOUNTANTS

LIMITATION OF LIABILITY BY ACCOUNTANTS LIMITATION OF LIABILITY BY ACCOUNTANTS Introduction 1. Traditionally, a central plank of an accountant s corporate work has been carrying out the audit. However, over the years the profession s role has

More information

Maritime & Commercial on i-law

Maritime & Commercial on i-law i-law.com Business intelligence Maritime & Commercial on i-law August 2017 highlights the best of i-law.com Contents Written by experts in shipping, trade, contracts and commercial law, Maritime & Commercial

More information

Before : MR JUSTICE ROBIN KNOWLES CBE Between : SEATRADE GROUP N.V. - and -

Before : MR JUSTICE ROBIN KNOWLES CBE Between : SEATRADE GROUP N.V. - and - Neutral Citation Number:[2018] EWHC 654 (Comm) Case No: CL-2017-000196 IN THE HIGH COURT OF JUSTICE THE BUSINESS AND PROPERTY COURTS OF ENGLAND & WALES COMMERCIAL COURT (QBD) Before : MR JUSTICE ROBIN

More information

CONTRACT FOR UNITED KINGDOM AND IRELAND GRAIN FOB TERMS

CONTRACT FOR UNITED KINGDOM AND IRELAND GRAIN FOB TERMS Effective 1 st September 2018 Contract No.79A Copyright THE GRAIN AND FEED TRADE ASSOCIATION CONTRACT FOR UNITED KINGDOM AND IRELAND GRAIN FOB TERMS *delete/specify as applicable Date... 1 2 3 4 5 6 7

More information

FIFTEENTH ANNUAL INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014

FIFTEENTH ANNUAL INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014 FIFTEENTH ANNUAL INTERNATIONAL MARITIME LAW ARBITRATION MOOT COMPETITION 2014 IN THE MATTER OF AN ARBITRATION HELD AT HONG KONG MEMORANDUM FOR THE RESPONDENT IN THE FIRST REFERENCE AND CLAIMANT IN THE

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS This Contract comprises the Sales Confirmation overleaf and these terms and conditions to the exclusion of all other terms and conditions (including any terms or conditions which Buyer purports to apply

More information

Shipping and International Trade News Bulletin

Shipping and International Trade News Bulletin Shipping and International Trade News Bulletin The Supreme Court Decision in THE GLOBAL SANTOSH: defining responsibility for vicarious contractual performance The Supreme Court handed down its decision

More information

Sabah Shipyard (Pakistan) Ltd v Government of the Islamic Republic of Pakistan

Sabah Shipyard (Pakistan) Ltd v Government of the Islamic Republic of Pakistan 184 SINGAPORE LAW REPORTS (REISSUE) [2004] 3 SLR(R) Sabah Shipyard (Pakistan) Ltd v Government of the Islamic Republic of Pakistan [2004] SGHC 109 High Court Originating Motion No 31 of 2003 Judith Prakash

More information

GENERAL RULES ABOUT COSTS

GENERAL RULES ABOUT COSTS PRACTICE DIRECTION PART 44 DIRECTIONS RELATING TO PART 44 GENERAL RULES ABOUT COSTS SECTION 7 SOLICITOR S DUTY TO NOTIFY CLIENT: RULE 44.2 7.1 For the purposes of rule 44.2 client includes a party for

More information

Contract No.64. Copyright THE GRAIN AND FEED TRADE ASSOCIATION GENERAL CONTRACT FOR GRAIN IN BULK FOB TERMS SELLERS... INTERVENING AS BROKERS...

Contract No.64. Copyright THE GRAIN AND FEED TRADE ASSOCIATION GENERAL CONTRACT FOR GRAIN IN BULK FOB TERMS SELLERS... INTERVENING AS BROKERS... Effective 1 st September 2018 Contract No.64 Copyright THE GRAIN AND FEED TRADE ASSOCIATION GENERAL CONTRACT FOR GRAIN IN BULK FOB TERMS * delete/specify as applicable Date... 1 2 3 4 5 6 7 8 9 10 11 12

More information

CONTRACT FOR THE DELIVERY OF GOODS BY INLAND WATERWAYS CENTRAL AND EASTERN EUROPE IN BULK FOB TERMS

CONTRACT FOR THE DELIVERY OF GOODS BY INLAND WATERWAYS CENTRAL AND EASTERN EUROPE IN BULK FOB TERMS Effective 1 st March 2016 Contract No.47 Copyright THE GRAIN AND FEED TRADE ASSOCIATION CONTRACT FOR THE DELIVERY OF GOODS BY INLAND WATERWAYS CENTRAL AND EASTERN EUROPE IN BULK FOB TERMS *delete/specify

More information

IN THE HIGH COURT OF JUSTICE GARY LEGGE AND MAUREEN LEGGE. Between CHRIS RAMSAWACK AND WESTERN SHIP AND RIG SUPPLIES LIMITED

IN THE HIGH COURT OF JUSTICE GARY LEGGE AND MAUREEN LEGGE. Between CHRIS RAMSAWACK AND WESTERN SHIP AND RIG SUPPLIES LIMITED THE REPUBLIC OF TRINIDAD AND TOBAGO CV No. 2013-00249 IN THE HIGH COURT OF JUSTICE GARY LEGGE 1 st Claimant AND MAUREEN LEGGE 2 nd Claimant Between CHRIS RAMSAWACK 1 st Defendant AND WESTERN SHIP AND RIG

More information

ICC/CMI Rules International Maritime Arbitration Organization in force as from 1 January 1978

ICC/CMI Rules International Maritime Arbitration Organization in force as from 1 January 1978 ICC/CMI Rules International Maritime Arbitration Organization in force as from January 978 Article The International Chamber of Commerce (ICC) and the Comité Maritime International (CMI) have jointly decided,

More information

Fisyon Trade General Business / Delivery and Payment Conditions

Fisyon Trade General Business / Delivery and Payment Conditions Fisyon Trade General Business / Delivery and Payment Conditions 1 General 1.1 These General Terms and Conditions of Sale shall apply to all of our business relationships with our customers. These Conditions

More information

Actions in rem and contemporary problems in the Far East

Actions in rem and contemporary problems in the Far East Actions in rem and contemporary problems in the Far East Peter K S Kwang* An examination ofthe implementation of the 1952 Convention on the Arrest of Sea-Going Ships by certain Far East Countries. I. THE

More information

IN THE SUPREME COURT OF BELIZE, A.D IN THE MATTER of Section 11, 12, 13 of the Arbitration Act, Chapter 125 of the Laws of Belize AND

IN THE SUPREME COURT OF BELIZE, A.D IN THE MATTER of Section 11, 12, 13 of the Arbitration Act, Chapter 125 of the Laws of Belize AND IN THE SUPREME COURT OF BELIZE, A.D. 2009 CLAIM NO. 169 of 2011 CLAIM NO. 293 of 2011 IN THE MATTER of Section 11, 12, 13 of the Arbitration Act, Chapter 125 of the Laws of Belize AND IN THE MATTER of

More information

Topics this week. Part A Classification of Contract Terms. Part B Performance, Breach & Right of Termination

Topics this week. Part A Classification of Contract Terms. Part B Performance, Breach & Right of Termination Topics this week So far we have looked at contract formation and how terms are incorporated into the contract. We have also looked at how to interpret the meaning of contract terms and whether extrinsic

More information

IN THE HIGH COURT OF JUSTICE INTEGRAL PETROLEUM SA AND MELARS GROUP LIMITED EAST-WEST LOGISTICS LLP AND MELARS GROUP LIMITED

IN THE HIGH COURT OF JUSTICE INTEGRAL PETROLEUM SA AND MELARS GROUP LIMITED EAST-WEST LOGISTICS LLP AND MELARS GROUP LIMITED IN THE EASTERN CARIBBEAN SUPREME COURT TERRITORY OF THE VIRGIN ISLANDS COMMERCIAL DIVISION IN THE HIGH COURT OF JUSTICE Claim No. BVIHC (COM) 0087 OF 2015 INTEGRAL PETROLEUM SA Claimant/Respondent AND

More information

1. What are the current challenges to enforcement of multi-tiered dispute resolution clauses?

1. What are the current challenges to enforcement of multi-tiered dispute resolution clauses? England Simon Hart RPC London Simon.Hart@rpc.co.uk Law firm bio 1. What are the current challenges to enforcement of multi-tiered dispute resolution clauses? There are two key challenges a party may face

More information

APPLICATION FOR COMMERCIAL CREDIT ACCOUNT TRADING TERMS AND CONDITIONS

APPLICATION FOR COMMERCIAL CREDIT ACCOUNT TRADING TERMS AND CONDITIONS APPLICATION FOR COMMERCIAL CREDIT ACCOUNT TRADING TERMS AND CONDITIONS These Trading Terms and Conditions are to be read and understood prior to the execution of the Application for Commercial Credit Account.

More information

AEROPOST TRINIDAD LIMITED PETER EDWARDS AND VINCY AVIATION SERVICES CARIBBEAN FREIGHT & COURIERS LTD. 2008: November, 17th November, 18th DECISION

AEROPOST TRINIDAD LIMITED PETER EDWARDS AND VINCY AVIATION SERVICES CARIBBEAN FREIGHT & COURIERS LTD. 2008: November, 17th November, 18th DECISION THE EASTERN CARIBBEAN SUPREME COURT IN THE HIGH COURT OF JUSTICE SAINT VINCENT AND THE GRENADINES HIGH COURT CIVIL CLAIM NO: 368/2008 BETWEEN: AEROPOST TRINIDAD LIMITED PETER EDWARDS 1st applicant 2nd

More information

A breach of contract occurs where a party does not comply with one or more of the terms of contract, express or implied.

A breach of contract occurs where a party does not comply with one or more of the terms of contract, express or implied. CITY UNIVERSITY OF HONG KONG Breach and Remedy Refer to Richards, P. Law of Contract Chapters 16-18 Uff, J. Construction Law 9 th Edition Chapter 9 BREACH OF CONTRACT A breach of contract occurs where

More information

Articles. Pathetically Pathological a Stumble Through the Maze of Dispute Resolution Clauses. Melanie Willems The Arbiter Winter 2015

Articles. Pathetically Pathological a Stumble Through the Maze of Dispute Resolution Clauses. Melanie Willems The Arbiter Winter 2015 Pathetically Pathological a Stumble Through the Maze of Dispute Resolution Clauses Melanie Willems The Arbiter Winter 2015 Arbitration is intended to be a more efficient and commercial alternative to litigating

More information

Examining the current law relating to limitation and causes of action (tortious and contractual) within a construction context

Examining the current law relating to limitation and causes of action (tortious and contractual) within a construction context Examining the current law relating to limitation and causes of action (tortious and contractual) within a construction context Received (in revised form): 11th September, 2005 Sarah Wilson is an associate

More information

TERMS AND CONDITIONS OF SALES

TERMS AND CONDITIONS OF SALES 1. Acceptance No Contract, Order or information (literature, drawings etc.) provided to or by the Purchaser shall be binding on Infra Green Ltd unless confirmed in the Infra Green Ltd Order Confirmation.

More information

NUBALTWOOD. Download sample copy. NUBALTWOOD C/P revised

NUBALTWOOD. Download sample copy. NUBALTWOOD C/P revised NUBALTWOOD Download sample copy NUBALTWOOD C/P revised The first NUBALTWOOD was issued by the Chamber of Shipping of the United Kingdom in 1951 after negotiations with the Timber Trade Federation of the

More information

Contract No.81. Copyright THE GRAIN AND FEED TRADE ASSOCIATION GENERAL CONTRACT CIF/CIFFO/C&F/C&FFO TERMS. *delete/specify as applicable SELLERS...

Contract No.81. Copyright THE GRAIN AND FEED TRADE ASSOCIATION GENERAL CONTRACT CIF/CIFFO/C&F/C&FFO TERMS. *delete/specify as applicable SELLERS... Effective 1 st March 2016 Contract No.81 Copyright THE GRAIN AND FEED TRADE ASSOCIATION GENERAL CONTRACT CIF/CIFFO/C&F/C&FFO TERMS *delete/specify as applicable Date... 1 2 3 4 5 6 7 8 9 10 11 12 13 14

More information

The clause (ACAS Form COT-3) provided:

The clause (ACAS Form COT-3) provided: THE CONSTRUCTION OF COMPROMISE AGREEMENTS The leading case is Bank of Credit and Commerce International SAI v Ali [2001] UKHL 8; [2002] 1 AC 251. It was also an extreme case where the majority of the House

More information

General Terms and Conditions of MMG (March 2018) 1. Scope of Application

General Terms and Conditions of MMG (March 2018) 1. Scope of Application General Terms and Conditions of MMG (March 2018) 1. Scope of Application (1) All contractual relationships between MMG Aluminium AG, headquartered in Mayen, Germany, hereinafter referred to as MMG and

More information

STANDARD TERMS & CONDITONS

STANDARD TERMS & CONDITONS STANDARD TERMS & CONDITONS VERSION I DTD 01 APRIL 2017 WaterFront Maritime Services DMCC Dubai, UAE STANDARD TERMS AND CONDITIONS OF WATERFRONT MARITIME SERVICES DMCC, DUBAI Waterfront Maritime Services

More information

Principles of European Contract Law

Principles of European Contract Law Article 1:101: Application of the Principles Principles of European Contract Law CHAPTER 1: GENERAL PROVISIONS Section 1: Scope of the Principles (1) These Principles are intended to be applied as general

More information

Contract No.119 Copyright THE GRAIN AND FEED TRADE ASSOCIATION

Contract No.119 Copyright THE GRAIN AND FEED TRADE ASSOCIATION Effective 1 st March 2016 Contract No.119 Copyright THE GRAIN AND FEED TRADE ASSOCIATION GENERAL CONTRACT FOR FEEDINGSTUFFS IN BAGS OR BULK FOB TERMS * delete/specify as applicable Date... 1 2 3 4 5 6

More information

RECENT CASES: CONTRACT CONTRACT. Effect of rescission of contract on exception clauses

RECENT CASES: CONTRACT CONTRACT. Effect of rescission of contract on exception clauses RECENT CASES: CONTRACT CONTRACT Effect of rescission of contract on exception clauses In Suisse Atlantique Socie'te' D'Armement Maritime S.A. v. N. V. Rotterdamsche Kolen Centralel, the respondents agreed

More information

International Conditions of Sale for Customers not Resident in Germany

International Conditions of Sale for Customers not Resident in Germany International Conditions of Sale for Customers not Resident in Germany I. Application of the International Conditions of Sale 1. These International Conditions of Sale apply to all customers of HAWITA

More information

Gafta No.125. Copyright THE GRAIN AND FEED TRADE ASSOCIATION

Gafta No.125. Copyright THE GRAIN AND FEED TRADE ASSOCIATION Effective for contracts dated from 1 st January 2006 Gafta No.125 Copyright THE GRAIN AND FEED TRADE ASSOCIATION ARBITRATION RULES GAFTA HOUSE 6 CHAPEL PLACE RIVINGTON STREET LONDON EC2A 3SH Tel: +44 20

More information

SALE OF BULBS: BUYERS CONDITIONS TABLE OF CONTENTS

SALE OF BULBS: BUYERS CONDITIONS TABLE OF CONTENTS SALE OF BULBS: BUYERS CONDITIONS TABLE OF CONTENTS 1. INTERPRETATION... 1 2. CONDITIONS OF PURCHASE... 2 3. AGENT S STATUS... 2 4. BASIS OF CONTRACT... 2 5. DELIVERY, TITLE AND RISK... 2 6. PRICE AND PAYMENT...

More information

NC General Statutes - Chapter 62 Article 10 1

NC General Statutes - Chapter 62 Article 10 1 Article 10. Transportation in General. 62-200. Duty to transport household goods within a reasonable time. (a) It shall be unlawful for any common carrier of household goods doing business in this State

More information

Enforceability of take-or-pay provisions in English law contracts resolved

Enforceability of take-or-pay provisions in English law contracts resolved Journal of Energy & Natural Resources Law, 2016 http://dx.doi.org/10.1080/02646811.2016.1164554 Enforceability of take-or-pay provisions in English law contracts resolved Ben Holland is a partner in the

More information

BIG ISLAND CONSTRUCTION (HONG KONG) LTD v ABDOOLALLY EBRAHIM & CO (HONG KONG) LTD - [1994] 3 HKC 518

BIG ISLAND CONSTRUCTION (HONG KONG) LTD v ABDOOLALLY EBRAHIM & CO (HONG KONG) LTD - [1994] 3 HKC 518 1 BIG ISLAND CONSTRUCTION (HONG KONG) LTD v ABDOOLALLY EBRAHIM & CO (HONG KONG) LTD - [1994] 3 HKC 518 HIGH COURT KAPLAN J ACTION NO 11313 OF 1993 28 July 1994 Civil Procedure -- Summary judgment -- Lack

More information

Standard Terms and Conditions for Sales and Deliveries of SPECTRO Analytical Instruments GmbH (SPECTRO)

Standard Terms and Conditions for Sales and Deliveries of SPECTRO Analytical Instruments GmbH (SPECTRO) Standard Terms and Conditions for Sales and Deliveries of SPECTRO Analytical Instruments GmbH (SPECTRO) 1 Exclusive Applicability To the extent not otherwise expressly agreed in the individual case overall

More information

B e f o r e: LORD JUSTICE LEWISON LORD JUSTICE FLOYD

B e f o r e: LORD JUSTICE LEWISON LORD JUSTICE FLOYD A2/2014/1626 Neutral Citation Number: [2015] EWCA Civ 984 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE MANCHESTER DISTRICT REGISTRY QUEEN'S BENCH DIVISION (HIS HONOUR JUDGE ARMITAGE QC) Royal

More information

MEMORANDUM FOR RELIABLE HOLDINGS INC.

MEMORANDUM FOR RELIABLE HOLDINGS INC. 15 TH ANNUAL INTERNATIONAL MARITIME LAW ARBITRATION MOOT, 2014 NATIONAL LAW SCHOOL OF INDIA UNIVERSITY TEAM NO. 18 MEMORANDUM FOR RELIABLE HOLDINGS INC. ON BEHALF OF RELIABLE HOLDINGS INC. CLAIMANTS AGAINST

More information

The Australian position

The Australian position A comparative analysis of how courts in different countries deal with Jurisdiction and Arbitration Clauses in Bills of Lading and Other Sea Carriage Documents. The Australian position Professor Sarah C

More information

Contract No.23. Copyright THE GRAIN AND FEED TRADE ASSOCIATION CONTRACT FOR PULSES FOR HUMAN CONSUMPTION IN BULK OR BAGS FOB TERMS

Contract No.23. Copyright THE GRAIN AND FEED TRADE ASSOCIATION CONTRACT FOR PULSES FOR HUMAN CONSUMPTION IN BULK OR BAGS FOB TERMS Effective 07 th September 2017 Contract No.23 Copyright THE GRAIN AND FEED TRADE ASSOCIATION CONTRACT FOR PULSES FOR HUMAN CONSUMPTION IN BULK OR BAGS FOB TERMS * delete/specify as applicable Date... 1

More information

Contract No.49. Copyright THE GRAIN AND FEED TRADE ASSOCIATION

Contract No.49. Copyright THE GRAIN AND FEED TRADE ASSOCIATION Effective 1 st April 2012 Contract No.49 Copyright THE GRAIN AND FEED TRADE ASSOCIATION CONTRACT FOR THE DELIVERY OF GOODS CENTRAL AND EASTERN EUROPE IN BULK OR BAGS FOB TERMS *delete/specify as applicable

More information

INSTITUTE OF CHARTERED SHIPBROKERS LEGAL PRINCIPLES IN SHIPPING BUSINESS

INSTITUTE OF CHARTERED SHIPBROKERS LEGAL PRINCIPLES IN SHIPPING BUSINESS INSTITUTE OF CHARTERED SHIPBROKERS APRIL 2009 EXAMINATIONS MONDAY 20 APRIL AFTERNOON LEGAL PRINCIPLES IN SHIPPING BUSINESS Time allowed Three hours Answer any FIVE questions All questions carry equal marks

More information

LLOYD'S STANDARD FORM OF SALVAGE AGREEMENT LLOYD'S STANDARD SALVAGE AND ARBITRATION CLAUSES

LLOYD'S STANDARD FORM OF SALVAGE AGREEMENT LLOYD'S STANDARD SALVAGE AND ARBITRATION CLAUSES LLOYD'S STANDARD FORM OF SALVAGE AGREEMENT (Approved and Published by the Council of Lloyd's) LLOYD'S STANDARD SALVAGE AND ARBITRATION CLAUSES 1 Introduction 1.1 These clauses ( the LSSA Clauses ) or any

More information