1 Livelihood Restoration in Practice: Key Challenges and Opportunities BRITISH MUSEUM, LONDON, NOVEMBER 9, 2016 Shaza Zeinelabdin, Senior Social Dev t Specialist Larissa Luy, Principal E&S Specialist

2 IFC RESETTLEMENT HANDBOOK Update the existing IFC Resettlement Handbook (2002) Provide practical guidance on implementation of PS 5 Expand scope to include emerging issues e.g. fragile and post conflict situations, large scale urban displacement Provide practical tools, approaches, examples and case studies

3 DILEMMAS What constitutes success: How do we assure ourselves that the livelihood Program has met its objectives? Government is handling resettlement & compensation and our client has no leverage: what do we expect them to do? How do we close the gap between national regulations and where there are material gaps regarding the IFC PS 5? What should you do in case the government is or has already completed the resettlement If resettlement happened a few years before our client was provided the land, do they need to do anything?

4 LIVELIHOOD RESTORATION: DEFINING SUCCESS Improvement or restoration of livelihoods is the objective of most international resettlement standards, but - No established paradigm for how we measure progress with restoring livelihoods - Clarity on how livelihoods should be defined Newmont Ahafo mine, Ghana RAP Completion Audit - 6 years after physical relocation: Living standards significantly improved 75% of households had access to land/ well developed crops livelihoods restored or close to being restored 25% had not reached point of secure livelihood illness, drug dependency, bad luck with land, fire, drought, lack of finance, etc.

5 WORKING WITH GOVERNMENT MANAGED RESETTLEMENT PROGRAMS How do we achieve objectives of our standards? The business case for client: why it pays off to get involved? The business case for the Government: why it pays off to work with the private sector Partnering with government and strengthening capacity

6 PARTNERING WITH GOVERNMENT Private sector sponsors usually cannot sustain livelihood programs indefinitely Government capacity needs to be developed for longer term sustainability (e.g. vulnerable peoples support; agricultural extension, SME support etc.) CNOOC Shell Petrochemical Project, Daya Bay, PR China - Jointly led, government executed resettlement - Project Sponsor provided: - Construction and operations employment - Skills training and paid work experience - Mentored formation of village construction companies - Government provided: - Provided transitional support, industrial land - Registered those needing employment - Provided bidding opportunities for village companies

7 USE LIVELIHOOD RESTORATION PROGRAM DELIVERY PARTNERS Most Private Sector sponsors have no expertise in livelihood restoration Emerging model is to partner with development NGOs, Consultants, Buyers to design/implement multi-faceted programs BTC pipeline - Sponsor was oil and gas operator, not a livelihood specialist - Used umbrella NGOs as Project Managers, - Local NGO, Institutions and Consultant partners to deliver programs - All programs/sub-programs based on logical frameworks - Performance based evaluation

8 CUT-OFF DATES Validity of census and asset surveys ~ 2 years how do you manage a cut-off when the use-by date of census/asset surveys has expired? Problems where project is delayed and moratorium restricts affected peoples rights to develop for a protracted period compensable? Managing customary/ancestral claims over land - the claimants live elsewhere (e.g. PNG post clan/tribal conflict) not present at the cut-off? Examples LNG Project, West Africa - cut-off date and restriction on new development announced project never proceeded Petrochemical project, China affected villagers subjected to a cut-off and restriction on new development for 12 years, before the Project finally proceeded

9 COMPREHENSIVE LIVELIHOOD BASELINE STUDIES Often insufficient data is collected to fully understand or describe pre-resettlement livelihoods Failure to account for full suite of livelihood resources that communities or households utilize (esp. in subsistence settings) losses are significantly undervalued Linear project in Sub-Saharan Africa - poor data, difficult to reconstruct livelihoods retrospectively (e.g. women s coastal gathering overlooked by baseline) Mozambique Gas Development Project comprehensive agriculture, foraging, fisheries, coastal gathering, small trading studies including value chain analysis and gender disaggregation

10 DESIGN MULTIPLE PROGRAMS - NOT ALL WILL SUCCEED Livelihood restoration is an imprecise art Good practice requires multiple programs don t put all your eggs in one basket Sufficient dialogue upfront with sponsors to help them understand livelihood implications Livelihood support durations years

11 DURATION OF LIVELIHOOD PROGRAMS How long do livelihood programs need to be maintained? Sponsor perception is often that livelihood support need only be short duration/ is easy to execute To effect changes in traditional agricultural practices/adopt new methods takes time (trials, demonstration, adoption, assistance in overcoming problems) Tenke Fungurume Mining, DRC - Agricultural intensification with introduction of irrigation, fertilizers: 7-8 yrs. BTC Pipeline: 3 yrs. to restore production levels on good soils; >10 yrs. on alpine grazing land CNOOC-Shell Petrochemical Project - Rural to urban resettlement: 6-8 yrs.

12 LEGACIES Bottom line Did past displacement result in unmitigated adverse impacts, diminished wellbeing, and/or grievances which may place the client social license to operate at risk? Key questions When did it occur, why, by whom, what process was followed, residual impacts/ grievances? Risk Analysis No significant residual impacts / displacement was minor: no further action required. Document the historic process Residual impacts identified: gap analysis + supplemental actions required, esp. if recent (3-5 yrs.) or with ongoing mitigation

13 MONITORING & ADAPTIVE MANAGEMENT Monitoring is often an afterthought not integral part of program design Designing/ implementing livelihood restoration programs is an imprecise science programs often need mid-term adjustment to improve effectiveness External factors (political, economic, natural disasters) can change the project context, necessitating mid-program adjustments Major Private Sector Projects (BTC Pipeline, Newmont Ahafo Gold, Chad Cameroon, Tangguh LNG, PNG LNG) - Internal Monitoring by Sponsor s resettlement team - External Monitoring by Independent Environmental and Social Consultant - Completion Audit by independent third party unremoved from the Project (livelihood/resettlement completion) - (Others: Government EIA monitoring, NGO Monitoring, High Level IAP)

14 Strictly Confidential Mizuho s Experience with implementing Livelihood Restoration Plans Sustainable Development Office Global Project Finance Department

15 CASE 1 Project located in Asia Involving large scale land acquisition and loss of income of affected communities Project affected communities include mainly farmers. Land owners given cash compensation as there was no land available in the areas close by Livelihood Restoration Plan (LRP) was prepared for affected communities, however it had some fundamental issues: The project company did not identify a cut off date, the census was done much later and was based on village records and not undertaken specifically by the project company As a result, the number of people to benefit from the project kept increasing through out the due diligence process, no identification of number of women, aged or vulnerable households The project company submitted a LRP which was just an extension of their CSR activities, in which all the project villagers could participate and it did not prioritize project affected farmers who lost their source livelihood due to land acquisition. These CSR activities were working well but the activities were mainly attended by women and were only sufficient to supplement income and not replace income from farming that had been lost The LRP mentioned that project company will focus on providing alternative livelihood and jobs creation, but little information was provided on what type of jobs will be identified Monitoring and reporting process was not identified to measure the success/failure.

16 CASE 2 Project located in Asia Involving land acquisition and loss of income of affected communities Project affected communities include - land owners, tenant farmers and daily farmers (who rent the land from the land owners for farming and harvesting) Initially, project company was to only provide compensation to the land owners and ask land owners to compensate the tenant farmers and daily farmers accordingly. In order to be in line with the requirements of IFC PS5 they agreed to consider tenant farmers and daily farmers as project affected communities. The tenant farmers and daily farmers were compensated with livelihood allowance each month (the allowance was determined based on consultation and agreed by all the affected parties). This monetary compensation was provided to the farmers until the tenant farmers could harvest the replacement land and daily farmer find another job. Project company found a replacement land for the tenant farmers, which the project company is going to lease from an agricultural company and provide it to the tenant farmers to cultivate. Eventually, the plan was to hand it over to a local NGO to manage the land. However, as a result of perceptions of inequality within the communities, the village head started collecting a certain percentage of the compensation to distribute to the rest of the village. The affected farmers were disappointed that they did not receive the amount which was agreed upon but there was little client could do to change this situation!

17 OTHER EMERGING ISSUES Legacy resettlement (usually government managed) Forced eviction vs legal eviction Buffers should have been resettled, but weren t Land donation acceptable in private sector resettlement? Staged resettlement (e.g. for large mines) where there is incremental loss of productive land with each expansion Civil society (Oxfam, Human Rights Watch): -Addressing cost of access to services post resettlement -Raised challenges of engagement/consultation in repressive countries -Incidence of reprisals against people making complaints -Challenges of customary law vs national/ statutory law -Predatory loan schemes targeting resettlement beneficiaries Clearer guidance on gender considerations in resettlement projects Expanding concept of marginalized groups LGTBs Refugees/ IDPs Climate change induced resettlement Fragile States special considerations Indigenous People & how IFC PS 5 is applied

18 THANK YOU!

EBRD Performance Requirement 5

EBRD Performance Requirement 5 EBRD Performance Requirement 5 Land Acquisition, Involuntary Resettlement and Economic Displacement Introduction 1. Involuntary resettlement refers both to physical displacement (relocation or loss of

More information

IAIA Special Symposium Resettlement and Livelihoods October Ted Pollett

IAIA Special Symposium Resettlement and Livelihoods October Ted Pollett IAIA Special Symposium Resettlement and Livelihoods 21 22 October 2014 Ted Pollett WHAT PLETHORA OF STANDARDS, GUIDELINES AND FRAMEWORKS? GOVERNMENT POLICIES, LEGISLATION AND REGULATIONS (NATIONAL, REGIONAL,

More information

Performance Standard 5 Land Acquisition and Involuntary Resettlement

Performance Standard 5 Land Acquisition and Involuntary Resettlement Introduction Performance Standard 5 1. Involuntary resettlement refers both to physical displacement (relocation or loss of shelter) and to economic displacement (loss of assets or access to assets that

More information

Guidance Note 5 Land Acquisition and Involuntary Resettlement

Guidance Note 5 Land Acquisition and Involuntary Resettlement This Guidance Note 5 corresponds to Performance Standard 5. Please also refer to the Performance Standards 1-4 and 6-8 as well as the corresponding Guidance Notes for additional information. Bibliographical

More information

RP297. Resettlement and Rehabilitation (R&R) Entitlement Framework

RP297. Resettlement and Rehabilitation (R&R) Entitlement Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized FINAL REPORT Resettlement and Rehabilitation (R&R) Entitlement Framework RP297 Under

More information

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea

The Resettlement Policy Framework for the Smallholder Agriculture Development Project. Papua New Guinea Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Resettlement Policy Framework for the Smallholder Agriculture Development Project

More information

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B.

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B. Module 8 - Involuntary Resettlement- Policy Principles & Requirements (World bank OP 4.12 and 4.12 Annex A) Key principles and objectives of an involuntary Resettlement Policy Resettlement planning instruments

More information

SECOND DRAFT FOR CONSULTATION JULY Environmental and Social Standard 5 Land Acquisition, Restrictions on Land Use and Involuntary Resettlement

SECOND DRAFT FOR CONSULTATION JULY Environmental and Social Standard 5 Land Acquisition, Restrictions on Land Use and Involuntary Resettlement This document should be read in conjunction with the proposed World Bank Policy to understand the proposed responsibilities of the World Bank (in the Policy) and the Borrowing Country (in the Standards).

More information

Tenke Fungurume Mining An affiliate of Freeport-McMoRan Copper & Gold

Tenke Fungurume Mining An affiliate of Freeport-McMoRan Copper & Gold Tenke Fungurume Mining An affiliate of Freeport-McMoRan Copper & Gold Tenke Fungurume Mining (TFM), an affiliate of Freeport-McMoRan Copper & Gold, is the largest private foreign investment in the DRC,

More information

Involuntary Resettlement - Overview. Transport Forum Washington, D.C. March 30, 2007

Involuntary Resettlement - Overview. Transport Forum Washington, D.C. March 30, 2007 Involuntary Resettlement - Overview Transport Forum Washington, D.C. March 30, 2007 OP 4.12 - Triggers Trigger: acquisition of land which displaces people physically and / or economically. Policy applies

More information

Resettlement and Impact Assessment points of intersection

Resettlement and Impact Assessment points of intersection Resettlement and Impact Assessment points of intersection IAIA Webinar December 15 th, 2016 Liz Wall Shared Resources Contents The basic principles of resettlement Intersections with impact assessment:

More information

THE WORLD BANK OPERATIONAL MANUAL OP 4.12 December Involuntary Resettlement. Policy Objectives

THE WORLD BANK OPERATIONAL MANUAL OP 4.12 December Involuntary Resettlement. Policy Objectives Page 1 of 9 Involuntary Resettlement 1. Bank 1 experience indicates that involuntary resettlement under development projects, if unmitigated, often gives rise to severe economic, social, and environmental

More information

Human Rights and Business Fact Sheet

Human Rights and Business Fact Sheet Sector-Wide Impact Assessment Human Rights and Business Fact Sheet Housing, Land Acquisition and Resettlement This factsheet was compiled for the use of the Myanmar Centre for Responsible Business (MCRB)

More information

THE CHALLENGES AND LEGAL IMPLICATIONS OF SECURING THE OCCUPATION OF LAND REQUIRED FOR PROJECTS IN WEST AFRICA

THE CHALLENGES AND LEGAL IMPLICATIONS OF SECURING THE OCCUPATION OF LAND REQUIRED FOR PROJECTS IN WEST AFRICA THE CHALLENGES AND LEGAL IMPLICATIONS OF SECURING THE OCCUPATION OF LAND REQUIRED FOR PROJECTS IN WEST AFRICA 28 OCTOBER 2014 Nicolas Heurzeau, Of Counsel, +33 1 53 57 78 55, nicolas.heurzeau@hsf.com OUTLINE

More information

Rights to land, fisheries and forests and Human Rights

Rights to land, fisheries and forests and Human Rights Fold-out User Guide to the analysis of governance, situations of human rights violations and the role of stakeholders in relation to land tenure, fisheries and forests, based on the Guidelines The Tenure

More information

Securing Free, Prior & Informed Consent to Resettlement. First Quantum s Cobre Panama Project

Securing Free, Prior & Informed Consent to Resettlement. First Quantum s Cobre Panama Project Securing Free, Prior & Informed Consent to Resettlement First Quantum s Cobre Panama Project International Seminar on Resettlement Medellin, Colombia; November 7, 2013 Overview 1. Introduction 2. Project

More information

Work plan of Independent Agency and Implementation of IFC Performance Standards. Green Goal Ltd., 17 February 2014

Work plan of Independent Agency and Implementation of IFC Performance Standards. Green Goal Ltd., 17 February 2014 Work plan of Independent Agency and Implementation of IFC Performance Standards Green Goal Ltd., 17 February 2014 Content IFC performance standards Legal grounds of Cambodia Resettlement planning process

More information

THE WORLD BANK OPERATIONAL MANUAL. Indigenous Peoples

THE WORLD BANK OPERATIONAL MANUAL. Indigenous Peoples THE WORLD BANK OPERATIONAL MANUAL Indigenous Peoples (Draft OP 4.10, March 09, 2000) INTRODUCTION. 1. The Bank's policy 1 towards indigenous peoples contributes to its wider objectives of poverty reduction

More information

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005 Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity Prime Minister s Office No 192/PM Date: 7 July, 2005 DECREE on the Compensation and Resettlement of the Development Project

More information

Mining Toolkit. In-Migration

Mining Toolkit. In-Migration Tool Child Rights and Mining Toolkit Children are the most vulnerable stakeholders regarding mining impacts, including the effects of project-related in-migration. As dependents of migrant mine workers,

More information

Helpdesk Research Report: Policies on Displacement and Resettlement

Helpdesk Research Report: Policies on Displacement and Resettlement Helpdesk Research Report: Policies on Displacement and Resettlement 23.09.2011 Query: Identify key donor and NGO approaches to preventing or limiting the impact of developmentinduced displacement and resettlement.

More information

Indonesia: Enhanced Water Security Investment Project

Indonesia: Enhanced Water Security Investment Project Initial Poverty and Social Analysis March 2018 Indonesia: Enhanced Water Security Investment Project This document is being disclosed to the public in accordance with ADB s Public Communications Policy

More information

Papua New Guinea LNG Project

Papua New Guinea LNG Project Esso Highlands Limited Papua New Guinea LNG Project Land Access, Resettlement and Livelihood Restoration Management Plan - Production PGGP-EH-OPZZZ-000004-006 LNG Project Page 2 of 35 CONTENTS 1.0 INTRODUCTION...

More information

SUMMARY EQUIVALENCE ASSESSMENT BY POLICY PRINCIPLE AND KEY ELEMENTS

SUMMARY EQUIVALENCE ASSESSMENT BY POLICY PRINCIPLE AND KEY ELEMENTS SUMMARY EQUIVALENCE ASSESSMENT BY POLICY PRINCIPLE AND KEY ELEMENTS ENVIRONMENTAL SAFEGUARDS Objectives To ensure the environmental soundness and sustainability of projects and to support the integration

More information

Introduction. - RSPO Standards and FPIC - Cross reference of other criteria - P&C review and FPIC implementation 5/11/2012

Introduction. - RSPO Standards and FPIC - Cross reference of other criteria - P&C review and FPIC implementation 5/11/2012 Institutionalisation of Respect for Free, Prior and Informed Consent (Towards RSPO implementation and verification working for forest, lands and livelihoods of indigenous peoples and local communities)

More information

REPORT 2014/052 INTERNAL AUDIT DIVISION

REPORT 2014/052 INTERNAL AUDIT DIVISION INTERNAL AUDIT DIVISION REPORT 2014/052 Audit of the operations of the Regional Office in South Africa for the Office of the United Nations High Commissioner for Refugees Overall results relating to the

More information

Guidance Note 5 Land Acquisition and Involuntary Resettlement

Guidance Note 5 Land Acquisition and Involuntary Resettlement This Guidance Note 5 corresponds to Performance Standard 5. Please also refer to the Performance Standards 1-4 and 6-8 as well as their corresponding Guidance Notes for additional information. Bibliographical

More information

SYMBION POWER LAKE KIVU LTD.

SYMBION POWER LAKE KIVU LTD. SYMBION POWER LAKE KIVU LTD. DRAFT Abbreviated Relocation Action Plan and Livelihoods Restoration Plan Final October 2018 [11.4.3.3] [10669-20181009-ESIA Abbreviated RAP_final_signed.pdf] [Page 1 of 52]

More information

Daniel Owen (World Bank) with Jay Wagner; Susan Dowse; Murray Jones; Marla Orenstein (Plexus Energy)

Daniel Owen (World Bank) with Jay Wagner; Susan Dowse; Murray Jones; Marla Orenstein (Plexus Energy) Managing Social Impacts of Labour Influx IAIA18 Conference Proceedings Environmental Justice in Societies in Transition 38 th Annual Conference of the International Association for Impact Assessment 16-19

More information

Workshop: Human Rights and Development-Induced Displacement Concept Note

Workshop: Human Rights and Development-Induced Displacement Concept Note Workshop: Human Rights and Development-Induced Displacement Concept Note Project to Support Social Movements and Grassroots Groups Challenging Forced Displacement ESCR-Net is coordinating a multi-year

More information

CONCEPT PAPER: SUSTAINABLE SHELTER SOLUTIONS Internally Displaced Persons in Somalia

CONCEPT PAPER: SUSTAINABLE SHELTER SOLUTIONS Internally Displaced Persons in Somalia CONCEPT PAPER: SUSTAINABLE SHELTER SOLUTIONS Internally Displaced Persons in Somalia SHELTER CLUSTER STRATEGIC OBJECTIVES 2013-2015 There are an estimated 1.1 million IDPs in Somalia. The needs of different

More information

LIVELIHOOD RESTORATION IN URBANISING ENVIRONMENTS ANGELA REEMAN, REEMAN CONSULTING PTY LTD

LIVELIHOOD RESTORATION IN URBANISING ENVIRONMENTS ANGELA REEMAN, REEMAN CONSULTING PTY LTD IAIA Special Symposium, Resettlement & Livelihoods Manila, Philippines, 20-22 February 2017 LIVELIHOOD RESTORATION IN URBANISING ENVIRONMENTS ANGELA REEMAN, PTY LTD ASIA AND URBANIZATION Source: Asian

More information

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the RESETTLEMENT FRAMEWORK Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the Secondary Education Modernization Project II in Sri Lanka Ministry of Education

More information

Annex 2: Does the Xayaburi resettlement comply with Lao law?

Annex 2: Does the Xayaburi resettlement comply with Lao law? Annex 2: Does the Xayaburi resettlement comply with Lao law? The Xayaburi project s resettlement scheme has not complied with Lao laws and policies on involuntary resettlement and compensation. As the

More information

Understanding Vulnerability and Property Rights

Understanding Vulnerability and Property Rights Understanding Vulnerability and Property Rights Presenter: Kirk Talbott Property Rights and Resource Governance Issues and Best Practices October, 2011 Objectives 1. Define vulnerability in the context

More information

CENTER STAGING GRASSROOTS WOMEN S LEADERSHIP IN SECURING SUSTAINABLE, INCLUSIVE URBANIZATION

CENTER STAGING GRASSROOTS WOMEN S LEADERSHIP IN SECURING SUSTAINABLE, INCLUSIVE URBANIZATION CENTER STAGING GRASSROOTS WOMEN S LEADERSHIP IN SECURING SUSTAINABLE, INCLUSIVE URBANIZATION THE HUAIROU COMMISSION NETWORK: TWO DECADES OF CONTRIBUTIONS TO POLICY- MAKING AND DEVELOPMENT INITIATIVES TO

More information

Managing Social Risks and Impacts in Geothermal Projects Turkey Geothermal Development Project

Managing Social Risks and Impacts in Geothermal Projects Turkey Geothermal Development Project BURCU ERGIN SOCIAL SAFEGUARDS SPECIALIST WORLD BANK RSM LAUNCH WORKSHOP IZMIR, 5 JULY 2018 Managing Social Risks and Impacts in Geothermal Projects Turkey Geothermal Development Project Why is it critical

More information

MINISTRY OF COMMERCE, TRADE AND INDUSTRY

MINISTRY OF COMMERCE, TRADE AND INDUSTRY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Republic of Zambia SFG2542 MINISTRY OF COMMERCE, TRADE AND INDUSTRY Project ID: No. P156492

More information

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 26: Resettlement Policy Framework PGGP-EH-SPENV

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 26: Resettlement Policy Framework PGGP-EH-SPENV Esso Highlands Limited Papua New Guinea LNG Project Environmental and Social Management Plan Appendix 26: PGGP-EH-SPENV-000018-030 LNG Project Page i of iv CONTENTS 1.0 PURPOSE OF THE RESETTLEMENT POLICY

More information

Rights to land and territory

Rights to land and territory Defending the Commons, Territories and the Right to Food and Water 1 Rights to land and territory Sofia Monsalve Photo by Ray Leyesa A new wave of dispossession The lack of adequate and secure access to

More information

Climate Change & Migration: Some Results and Policy Implications from MENA

Climate Change & Migration: Some Results and Policy Implications from MENA Climate Change & Migration: Some Results and Policy Implications from MENA Outline 1. An abridged history of climate induced migration 2. Investigating CIM in MENA 3. Some results and policy considerations

More information

Study on Impact and Costs of Forced Displacement. February 17, Social Development Department The World Bank

Study on Impact and Costs of Forced Displacement. February 17, Social Development Department The World Bank Study on Impact and Costs of Forced Displacement February 17, 2011 Social Development The World Bank Presentation outline Forced Displacement: The Development Challenge The World Bank Program on Forced

More information

Gender Equality and Development

Gender Equality and Development Overview Gender Equality and Development Welcome to Topic 3 of the e-module on Gender and Energy. We have already discussed how increased access to electricity improves men s and women s lives. Topic Three

More information

Guidance Note UNDP Social and Environmental Standards. Standard 5: Displacement and Resettlement

Guidance Note UNDP Social and Environmental Standards. Standard 5: Displacement and Resettlement Guidance Note UNDP Social and Environmental Standards Standard 5: Displacement and Resettlement December 2016 UNDP Guidance Notes on the Social and Environmental Standards (SES) This Guidance Note is part

More information

Activist Guide to Sinohydro s International Corporation Limited s Environmental and Social Policy Commitments

Activist Guide to Sinohydro s International Corporation Limited s Environmental and Social Policy Commitments Activist Guide to Sinohydro s International Corporation Limited s Environmental and Social Policy Commitments Sinohydro, a Chinese government-owned enterprise, is the world s largest dam builder. By its

More information

Chapter 5. Development and displacement: hidden losers from a forgotten agenda

Chapter 5. Development and displacement: hidden losers from a forgotten agenda Chapter 5 Development and displacement: hidden losers from a forgotten agenda There is a well-developed international humanitarian system to respond to people displaced by conflict and disaster, but millions

More information

HLP GUIDANCE NOTE ON RELOCATION FOR SHELTER PARTNERS March Beyond shelter, the social and economic challenges of relocation

HLP GUIDANCE NOTE ON RELOCATION FOR SHELTER PARTNERS March Beyond shelter, the social and economic challenges of relocation HLP GUIDANCE NOTE ON RELOCATION FOR SHELTER PARTNERS March 2014 This Advisory Note provides guidance to Shelter Cluster Partners on national and international standards related to relocation as well as

More information

Compensation for Land Acquisition: The Movement and Emerging Social Order

Compensation for Land Acquisition: The Movement and Emerging Social Order Compensation for Land Acquisition: The Movement and Emerging Social Order Dr. Abstract Sociologists use the term social movements to refer to organized collective activities to bring about or resist fundamental

More information

THE UNHCR NGO RESETTLEMENT DEPLOYMENT SCHEME. Overview and Follow-up

THE UNHCR NGO RESETTLEMENT DEPLOYMENT SCHEME. Overview and Follow-up ANNUAL TRIPARTITE CONSULTATIONS ON RESETTLEMENT Geneva, 20-21 June 2001 THE UNHCR NGO RESETTLEMENT DEPLOYMENT SCHEME Overview and Follow-up Background 1. The UNHCR - NGO deployment scheme for refugee resettlement

More information

POLICY SEA: CONCEPTUAL MODEL AND OPERATIONAL GUIDANCE FOR APPLYING STRATEGIC ENVIRONMENTAL ASSESSMENT IN SECTOR REFORM EXECUTIVE SUMMARY

POLICY SEA: CONCEPTUAL MODEL AND OPERATIONAL GUIDANCE FOR APPLYING STRATEGIC ENVIRONMENTAL ASSESSMENT IN SECTOR REFORM EXECUTIVE SUMMARY POLICY SEA: CONCEPTUAL MODEL AND OPERATIONAL GUIDANCE FOR APPLYING STRATEGIC ENVIRONMENTAL ASSESSMENT IN SECTOR REFORM EXECUTIVE SUMMARY June 2010 The World Bank Sustainable Development Network Environment

More information

UNDP UNHCR Transitional Solutions Initiative (TSI) Joint Programme

UNDP UNHCR Transitional Solutions Initiative (TSI) Joint Programme UNITED NATIONS DEVELOPMENT PROGRAMME UNITED NATIONS HIGH COMMISSIONER FOR REFUGEES UNDP UNHCR Transitional Solutions Initiative (TSI) Joint Programme DEVELOPMENT PARTNER BRIEF, NOVEMBER 2013 CONTEXT During

More information

FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT

FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT DRAFT COMPARATIVE ANALYSIS OF NEPAL s LEGAL FRAMEWORK FOR LAND ACQUISTION AND INVOLUNTARY RESETTLEMENT AND THE ASIAN DEVELOPMENT BANK SAFEGUARD FOR INVOLUNTARY RESETTLMENT Note: The following is based

More information

International Conference o n. Social Protection. in contexts of. Fragility & Forced Displacement. Brussels September, 2017.

International Conference o n. Social Protection. in contexts of. Fragility & Forced Displacement. Brussels September, 2017. International Conference o n Social Protection in contexts of Fragility & Forced Displacement Brussels 28-29 September, 2017 Outcome Document P a g e 2 1. BACKGROUND: In the past few years the international

More information

Housing, Land & Property in Humanitarian Emergencies

Housing, Land & Property in Humanitarian Emergencies Housing, Land & Property in Humanitarian Emergencies Skovskolen, 24 September 2013 Szilard Fricska Coordinator Global HLP Area of Responsibility International Legal & Policy Framework UDHR (Art 25) Right

More information

THE HILL TRIBES OF NORTHERN THAILAND: DEVELOPMENT IN CONFLICT WITH HUMAN RIGHTS - REPORT OF A VISIT IN SEPTEMBER 1996

THE HILL TRIBES OF NORTHERN THAILAND: DEVELOPMENT IN CONFLICT WITH HUMAN RIGHTS - REPORT OF A VISIT IN SEPTEMBER 1996 THE HILL TRIBES OF NORTHERN THAILAND: DEVELOPMENT IN CONFLICT WITH HUMAN RIGHTS - REPORT OF A VISIT IN SEPTEMBER 1996 Contents Summary A background Perceptions, prejudice and policy Cards and identity

More information

Project Information Document (PID)

Project Information Document (PID) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name: Region: Project Information Document (PID) Sri Lanka: Puttalam Housing

More information

Japan s Actions Towards Gender Mainstreaming with Human Security in Its Official Development Assistance

Japan s Actions Towards Gender Mainstreaming with Human Security in Its Official Development Assistance Japan s Actions Towards Gender Mainstreaming with Human Security in Its Official Development Assistance March, 2008 Global Issues Cooperation Division International Cooperation Bureau Ministry of Foreign

More information

BANQUE AFRICAINE DE DEVELOPPEMENT

BANQUE AFRICAINE DE DEVELOPPEMENT BANQUE AFRICAINE DE DEVELOPPEMENT Publication autorisée Publication autorisée KENYA: PROPOSAL FOR AN EMERGENCY HUMANITARIAN ASSISTANCE TO POPULATION AFFECTED BY DROUGHT AND FAMINE* LIST OF ACRONYMS AND

More information

REPORT 2016/063 INTERNAL AUDIT DIVISION. Audit of the operations in Nepal for the Office of the United Nations High Commissioner for Refugees

REPORT 2016/063 INTERNAL AUDIT DIVISION. Audit of the operations in Nepal for the Office of the United Nations High Commissioner for Refugees INTERNAL AUDIT DIVISION REPORT 2016/063 Audit of the operations in Nepal for the Office of the United Nations High Commissioner for Refugees Overall results relating to the effective management of the

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: VIE 34055 TECHNICAL ASSISTANCE TO THE SOCIALIST REPUBLIC OF VIET NAM FOR ENHANCING THE RESETTLEMENT LEGAL FRAMEWORK AND INSTITUTIONAL CAPACITY September 2001 CURRENCY EQUIVALENTS

More information

Agriculture Bill [AS AMENDED IN PUBLIC BILL COMMITTEE] CONTENTS PART 1

Agriculture Bill [AS AMENDED IN PUBLIC BILL COMMITTEE] CONTENTS PART 1 [AS AMENDED IN PUBLIC BILL COMMITTEE] CONTENTS PART 1 NEW FINANCIAL ASSISTANCE POWERS 1 Secretary of State s powers to give financial assistance 2 Financial assistance: forms, conditions, delegation and

More information

INTERNAL AUDIT DIVISION REPORT 2017/149

INTERNAL AUDIT DIVISION REPORT 2017/149 INTERNAL AUDIT DIVISION REPORT 2017/149 Audit of the regional operations for South Caucasus in Georgia for the Office of the United Nations High Commissioner for Refugees There was a need to address control

More information

AN EMERGENCY FOR WHOM?

AN EMERGENCY FOR WHOM? OXFAM BRIEFING NOTE SUMMARY NOVEMBER 2017 Ibrahim, from Gambia in Agadez, Niger. Credit: Pablo Tosco/Oxfam AN EMERGENCY FOR WHOM? The EU Emergency Trust Fund for Africa migratory routes and development

More information

Finland s Development Policy Results Report 2018 Summary

Finland s Development Policy Results Report 2018 Summary Finland s Development Policy Results Report 2018 Summary The development policy and cooperation of Finland generate results The Development Policy Results Report 2018 presents results of Finland s development

More information

FAO MIGRATION FRAMEWORK IN BRIEF

FAO MIGRATION FRAMEWORK IN BRIEF FAO MIGRATION FRAMEWORK IN BRIEF MIGRATION AS A CHOICE AND AN OPPORTUNITY FOR RURAL DEVELOPMENT Migration can be an engine of economic growth and innovation, and it can greatly contribute to sustainable

More information

Which sub- Saharan African countries are attracting the most interest?

Which sub- Saharan African countries are attracting the most interest? FAQs on Indian Agriculture Investments in Ethiopia The Oakland Institute, February 2013 Why has the recent surge of foreign land acquisitions and leases been dubbed a global land grab? Since the food price

More information

UNHCR AND THE 2030 AGENDA - SUSTAINABLE DEVELOPMENT GOALS

UNHCR AND THE 2030 AGENDA - SUSTAINABLE DEVELOPMENT GOALS UNHCR AND THE 2030 AGENDA - SUSTAINABLE DEVELOPMENT GOALS 2030 Agenda PRELIMINARY GUIDANCE NOTE This preliminary guidance note provides basic information about the Agenda 2030 and on UNHCR s approach to

More information

STAKEHOLDER ENGAGEMENT IN PLANNING AND IMPLEMENTATION OF RESETTLEMENT AND LIVELIHOOD RESTORATION

STAKEHOLDER ENGAGEMENT IN PLANNING AND IMPLEMENTATION OF RESETTLEMENT AND LIVELIHOOD RESTORATION STAKEHOLDER ENGAGEMENT IN PLANNING AND IMPLEMENTATION OF RESETTLEMENT AND LIVELIHOOD RESTORATION Lead writer: Afandi Anwar Muhammad Foundation Co-writer: Aldi Muhammad Alizar IAP2 Indonesia For: IAIA event

More information

MALAWI TESTIMONIES. By getting this assistance, I was able to feed my family properly. Estor Elliott

MALAWI TESTIMONIES. By getting this assistance, I was able to feed my family properly. Estor Elliott By getting this assistance, I was able to feed my family properly. Estor Elliott TESTIMONIES "It was fair to receive this additional support because SCT cash amounts are very small and meant for survival.

More information

Lake Turkana Wind Power Project - Kenya Resettlement Policy Framework

Lake Turkana Wind Power Project - Kenya Resettlement Policy Framework Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Lake Turkana Wind Power Project - Kenya Resettlement Policy Framework November 2011 Prepared

More information

Under-five chronic malnutrition rate is critical (43%) and acute malnutrition rate is high (9%) with some areas above the critical thresholds.

Under-five chronic malnutrition rate is critical (43%) and acute malnutrition rate is high (9%) with some areas above the critical thresholds. May 2014 Fighting Hunger Worldwide Democratic Republic of Congo: is economic recovery benefiting the vulnerable? Special Focus DRC DRC Economic growth has been moderately high in DRC over the last decade,

More information

Sri Lanka. Pakistan Myanmar Various Refugees

Sri Lanka. Pakistan Myanmar Various Refugees Sri Lanka The end of the 26-year conflict between Government forces and the separatist Liberation Tigers of Tamil Eelam in May 2009 changed the operational environment in Sri Lanka. The massive displacement

More information

Background. Types of migration

Background. Types of migration www.unhabitat.org 01 Background Fishman64 / Shutterstock.com Types of migration Movement patterns (circular; rural-urban; chain) Decision making (voluntary/involuntary) Migrant categories: Rural-urban

More information

Evaluating Integrated Conservation & Development at Bwindi Impenetrable National Park, Uganda. Julia Baker 29 th November 2012 Oxford Brookes

Evaluating Integrated Conservation & Development at Bwindi Impenetrable National Park, Uganda. Julia Baker 29 th November 2012 Oxford Brookes Evaluating Integrated Conservation & Development at Bwindi Impenetrable National Park, Uganda Julia Baker 29 th November 2012 Oxford Brookes Conservation Policy Priorities for managing protected areas

More information

RP1 93 RESETTLEMENT POLICY FRAMEWORK MINISTRY OF EDUCATION, YOUTH AND SPORTS (MEYS) REPUBLIC OF GHANA. (EdSeP) Public Disclosure Authorized

RP1 93 RESETTLEMENT POLICY FRAMEWORK MINISTRY OF EDUCATION, YOUTH AND SPORTS (MEYS) REPUBLIC OF GHANA. (EdSeP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized January 5, 20041/5/2004 2:44 PM EDUCATION SECTOR PROJECT MINISTRY OF EDUCATION, YOUTH

More information

Insert Mali/Sahel specific picture. Mali and the Sahel First Quarterly Operational Briefing. Presentation to the WFP Executive Board

Insert Mali/Sahel specific picture. Mali and the Sahel First Quarterly Operational Briefing. Presentation to the WFP Executive Board Insert Mali/Sahel specific picture Mali and the Sahel 2015 First Quarterly Operational Briefing Presentation to the WFP Executive Board WFP Auditorium 27 January 2015 SITUATIONAL UPDATE Humanitarian Situation

More information

India: Delhi Meerut Regional Rapid Transit System Project

India: Delhi Meerut Regional Rapid Transit System Project Initial Poverty and Social Analysis October 2018 India: Delhi Meerut Regional Rapid Transit System Project This document is being disclosed to the public in accordance with ADB s Public Communications

More information

Internally displaced personsreturntotheir homes in the Swat Valley, Pakistan, in a Government-organized return programme.

Internally displaced personsreturntotheir homes in the Swat Valley, Pakistan, in a Government-organized return programme. Internally displaced personsreturntotheir homes in the Swat Valley, Pakistan, in a Government-organized return programme. 58 UNHCR Global Appeal 2011 Update Finding Durable Solutions UNHCR / H. CAUX The

More information

Written contribution of FIAN Nepal to the Universal Periodic Review of Nepal - The Situation of the Right to Food and Nutrition in Nepal

Written contribution of FIAN Nepal to the Universal Periodic Review of Nepal - The Situation of the Right to Food and Nutrition in Nepal Written contribution of FIAN Nepal to the Universal Periodic Review of Nepal - The Situation of the Right to Food and Nutrition in Nepal 1. Introduction Submitted 23 of March 2015 1. This information is

More information

Managing Social Impacts of Labour Influx

Managing Social Impacts of Labour Influx Managing Social Impacts of Labour Influx This paper summarizes the results of a recent global portfolio review focused on the social impacts of labor influx commissioned by the World Bank and carried out

More information

Resettlement and Income Restoration in Thilawa SEZ

Resettlement and Income Restoration in Thilawa SEZ Resettlement and Income Restoration in Thilawa SEZ Lessons from the first & second phases and emerging good practices Thilawa SEZ Management Committee (TSMC) Yangon Region Government (YRG) 20 February

More information

IOM DEMOCRATIC REPUBLIC OF CONGO IOM s Early Recovery and Resilience Programme in North Kivu

IOM DEMOCRATIC REPUBLIC OF CONGO IOM s Early Recovery and Resilience Programme in North Kivu IOM DEMOCRATIC REPUBLIC OF CONGO IOM s Early Recovery and Resilience Programme in North Kivu SITUATION REPORT UPDATE 13 May 2015 Community-field of Kibumba for Agriculture Re-launching to support transition

More information

WOMEN AND GIRLS IN EMERGENCIES

WOMEN AND GIRLS IN EMERGENCIES WOMEN AND GIRLS IN EMERGENCIES SUMMARY Women and Girls in Emergencies Gender equality receives increasing attention following the adoption of the UN Sustainable Development Goals (SDGs). Issues of gender

More information

PLAAS LARGE-SCALE LAND ACQUISITIONS, DISPLACEMENT AND RESETTLEMENT IN ZAMBIA POLICY BRIEF 41 KEY ISSUES 1. BACKGROUND

PLAAS LARGE-SCALE LAND ACQUISITIONS, DISPLACEMENT AND RESETTLEMENT IN ZAMBIA POLICY BRIEF 41 KEY ISSUES 1. BACKGROUND PLAAS Institute for Poverty, Land and Agrarian Studies Faculty of Economic and Management Sciences POLICY BRIEF 41 Jessica Chu, Kathleen Young and Dimuna Phiri, Zambia Land Alliance www.plaas.org.za Email:

More information

Modern Slavery Statement 2017

Modern Slavery Statement 2017 Modern Slavery Statement 2017 This statement has been published in accordance with the Modern Slavery Act 2015. It sets out the steps taken by Fresnillo plc ( Fresnillo or the Company ) to prevent any

More information

Government of Sierra Leone Bumbuna Hydroelectric Environmental and Social Management Project Updated Resettlement Action Plan August 2010

Government of Sierra Leone Bumbuna Hydroelectric Environmental and Social Management Project Updated Resettlement Action Plan August 2010 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Government of Sierra Leone Bumbuna Hydroelectric Environmental and Social Management

More information

Achim Steiner, UNDP Administrator and Chair UN Development Group, remarks on The Sustainable Development Goals: Building a better future in Myanmar

Achim Steiner, UNDP Administrator and Chair UN Development Group, remarks on The Sustainable Development Goals: Building a better future in Myanmar Achim Steiner, UNDP Administrator and Chair UN Development Group, remarks on The Sustainable Development Goals: Building a better future in Myanmar Yangon University, Myanmar 2:00pm, August 7, 2017 [Suggested

More information

Why has the recent surge of foreign land acquisitions and leases been dubbed a global land grab?

Why has the recent surge of foreign land acquisitions and leases been dubbed a global land grab? FAQs on Indian Agriculture Investments in Ethiopia The Oakland Institute, February 2013 Why has the recent surge of foreign land acquisitions and leases been dubbed a global land grab? Since the food price

More information

LIVESTOCK WASTE MANAGEMENT IN EAST ASIA

LIVESTOCK WASTE MANAGEMENT IN EAST ASIA LIVESTOCK WASTE MANAGEMENT IN EAST ASIA Project preparation under the PDF-B grant IPP133 v 1 STRATEGY AND GUIDELINES FOR ETHNIC MINORITY DEVELOPMENT PLAN IN GUANGDONG PROVINCE Public Disclosure Authorized

More information

Reduce and Address Displacement

Reduce and Address Displacement Reduce and Address Displacement Analytical Paper on WHS Self-Reporting on Agenda for Humanity Transformation 3A Executive Summary: This paper was prepared by: 1 One year after the World Humanitarian Summit,

More information

Ensuring inclusion, resilience and sustainability in the implementation of the SDGs. Joan Carling, Indigenous Peoples Major Group

Ensuring inclusion, resilience and sustainability in the implementation of the SDGs. Joan Carling, Indigenous Peoples Major Group Ensuring inclusion, resilience and sustainability in the implementation of the SDGs Joan Carling, Indigenous Peoples Major Group CONTEXT Ensuring inclusion, Resilience and sustainability are necessary

More information

Indigenous Peoples' Declaration on Extractive Industries. Indigenous Peoples Declaration on Extractive Industries

Indigenous Peoples' Declaration on Extractive Industries. Indigenous Peoples Declaration on Extractive Industries Preamble: Indigenous Peoples Declaration on Extractive Industries Our futures as indigenous peoples are threatened in many ways by developments in the extractive industries. Our ancestral lands- the tundra,

More information

People s Republic of China: Jilin Yanji Low-Carbon Climate-Resilient Urban Development Project

People s Republic of China: Jilin Yanji Low-Carbon Climate-Resilient Urban Development Project Initial Poverty and Social Analysis May 2018 People s Republic of China: Jilin Yanji Low-Carbon Climate-Resilient Urban Development Project This document is being disclosed to the public in accordance

More information

INTERNAL AUDIT DIVISION REPORT 2016/183

INTERNAL AUDIT DIVISION REPORT 2016/183 INTERNAL AUDIT DIVISION REPORT 2016/183 Audit of the Regional Representation for West Africa for the Office of the United Nations High Commissioner for Refugees The Regional Representation needed to fulfil

More information

Food Security in Protracted Crises: What can be done?

Food Security in Protracted Crises: What can be done? For too long, we simply equated a food security problem with a food gap, and a food gap with a food aid response. 1 When emergency situations continue for years or decades, achieving food security becomes

More information

REPORT 2016/100 INTERNAL AUDIT DIVISION. Audit of the operations in Niger for the Office of the United Nations High Commissioner for Refugees

REPORT 2016/100 INTERNAL AUDIT DIVISION. Audit of the operations in Niger for the Office of the United Nations High Commissioner for Refugees INTERNAL AUDIT DIVISION REPORT 2016/100 Audit of the operations in Niger for the Office of the United Nations High Commissioner for Refugees Overall results relating to the effective management of the

More information

WIDER KNOWLEDGE AND AGENDA 2030 CHALLENGES

WIDER KNOWLEDGE AND AGENDA 2030 CHALLENGES Presentation to the Finnish Development Policy Committee WIDER KNOWLEDGE AND AGENDA 2030 CHALLENGES Finn Tarp, Director, UNU-WIDER Rachel Gisselquist, Research Fellow, UNU-WIDER Smriti Sharma, Research

More information

Joint submission to the United Nations Convention on Climate Change (UNFCCC) On National Adaptation Plans (NAPs)

Joint submission to the United Nations Convention on Climate Change (UNFCCC) On National Adaptation Plans (NAPs) Joint submission to the United Nations Convention on Climate Change (UNFCCC) On National Adaptation Plans (NAPs) The International Organization for Migration (IOM) The United Nations High Commissioner

More information

Government Led Resettlement : Experiences in Zambia Challenges and Lessons Learned

Government Led Resettlement : Experiences in Zambia Challenges and Lessons Learned Government Led Resettlement : Experiences in Zambia Challenges and Lessons Learned Presentation to Resettlement & Livelihoods Symposium held from 20-24 October 2014 in Kruger National Park, South Africa.

More information

SESSION #8 DUE DILIGENCE

SESSION #8 DUE DILIGENCE SESSION #8 DUE DILIGENCE Presented by Monkey Forest Consulting OBJECTIVE AND OUTLINE The aim of this module is to share our experiences in due diligence and interactively discuss some key considerations.

More information