1 SOCIAL SAFEGUARD DUE DILIGENCE REPORT Social Safeguard Due Diligence Report for proposed Additional Road Sections (Sindh Provincial Road Improvement Project SPRIP) (September 2018) PAK: Sindh Provincial Road Improvement Project (SPRIP) Prepared by Project Management Unit (PMU), Works and Services Department (WSD), Government of Sindh (GOS) for the Asian Development Bank.

2 (i) (ii) NOTES The fiscal year (FY) of the Government of the Islamic Republic of Pakistan and its agencies ends on 30 June. In this report, "$" refers to US dollars. This Social Safeguard Due Diligence Report for 3 proposed additional road sections is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

3 Clients: Asian Development Bank Works & Services Department Government of Sindh SOCIAL SAFEGUARD DUE DILIGENCE REPORT FOR THE CONSTRUCTION OF A NEW BRIDGE AT CHAINAGE UNDER ICB-04 SEPTEMBER 2018 SINDH PROVINCIALROAD IMPROVEMENT PROJECT (SPRIP) Loan No PAK/Contract No. SPRIP CS1 This consultant s report does not necessarily reflect the view of ADB or the Government concerned and ADB and the Government cannot be held liable for its contents.

4 SOCIAL SAFEGUARDS DUE DILIGENCE REPORT FOR THE CONSTRUCTION OF A NEW BRIDGE AT ICB-04 CHAINAGE SEPTEMBER 2018 MEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 2 of 11

5 TABLE OF CONTENTS SR NO DESCRIPTION 1 INTRODUCTION 5 Background 5 2 METHODOLOGY 7 3 FINDINGS 7 4 TRAFFIC DIVERSION PLAN 7 5 IMPACT ON INDIGENOUS PEOPLE 8 6 STAKEHOLDER CONSULTATIONS 8 Type of Participants (Stakeholders) 9 Future Consultation and Participation 10 7 GRIEVANCE REDRESS PROCESS 10 PAGE NO 8 CONCLUSIONS AND RECOMMENDATIONS 11

6 LIST OF ABBREVIATIONS ADB SPRIP FGD WSD GOS IR LAR GRC APs IP MPR NGO PIU ROW RD SPS ToR UTM RP VOC SC DP L/S Asian Development Bank Sindh Provincial Road Improvement Project focus group discussion Works and Services Department Government of Sindh involuntary resettlement land acquisition and resettlement plan grievances redress committee affected persons indigenous people monthly progress report non-governmental organization project implementation unit right of way reduced distance Safeguard Policy Statement terms of reference universal transverse mercator resettlement plan vehicle operating cost supervision consultants displaced persons left side Page 4 of 11 SMEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 4 of 11

7 1. INTRODUCTION Background 1. The Government of Sindh (GOS), with assistance from the Asian Development Bank (ADB) is rehabilitating six major provincial roads in Sindh covering 328 km of the provincial highway network. These six roads include: (i) Thull to Kandhkot, (ii)sheranpur to Ratodero, (iii) Khyber to Sanghar, (iv)sanghar to Mirpurkhas, (v) Tando Muhammad Khan to Badin, and (vi) Digri to Naukot. 2. The Project Rehabilitation works were limited to the existing right of way (ROW), which is 110 feet wide. Adjustments in the design were made to avoid impacting encroaching structures in the ROW as provided in the approved Social Safeguards Due Diligence Report prepared in May 2017 and are monitored by the Resettlement Specialist hired under the Project Management Consultants (PMC) for the project. Implementation of civil works in these 6 road packages is ongoing and is expected to be completed before January Asian Development Bank (ADB) has approved variation order No. 2 for construction of a new bridge at Subproject-4 Sanghar-Mirpurkhas subproject. The new bridge would have width of 9.5 meters with approach slabs of 3 meters each on both sides and 60 meters length. Drawing of new bridge attached as figure-1. Figure 1 Drawing of New Bridge ICB A social safeguard due diligence report has been prepared to assess if the construction of a new bridge will have involuntary resettlement (IR) risks that need to be addressed either through design adjustments, or compensated if cannot be avoided, Page 5 of 11 SMEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 5 of 11

8 following the ADB Safeguards Policy Statement (2009) and the loan covenants of the Project. Page 6 of 11 SMEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 6 of 11

9 2. METHODOLOGY 5. A survey was conducted in September 2018 by PMC Resettlement Specialist following professionals conducted field visit. i. Mr. Saeed uz Zafar Resettlement Specialist, PMC ii. Mr. Bhura Lal Resident Engineer ICB # 04 iii. Mr. Israr Ali iv. Mr. Shahnawaz Magsi Surveyor, PMC Surveyor, PMC 6. During the field survey, the team visited the bridge site and the diversion road to identify any social and resettlement impacts which may be caused by the construction of new bridge and selected diversion road. Consultation meetings were held with local people and notables for providing them information regarding construction of new bridge and selected diversion road. Local community was also consulted regarding social and likely resettlement impacts of the diversion road in compliance of ADB Safeguard Policy FINDINGS Involuntary Resettlement Impact Assessment No Land acquisition is required for construction of the new bridge as itis to be constructed on existing alignment. No residential, commercial and religious importance structure was located at bridge site within ROW. 4. TRAFFIC DIVERSION PLAN 7. For uninterrupted flow various types of long route and local commuter traffic a diversion plan has been formulated by utilization of existing 14.5 Km length starting from Chainage42+00 and meets the project road at chainage Available width of diversion road is found 5.5 meters 2 lane road which is sufficient for movement of heavy trucks and passenger buses traffic without causing any traffic congestion. Diversion plan has been prepared by conducting preliminary involuntarily resettlement impact assessment survey along the populated areas located along the road and conducting consultation meetings and interviews with local communities. A detailed description of Diversion plan is described hereunder: Diversion road passes through following4 villages and there was one hotel was located atchange Team found no resettlement impacts on the whole stretch of the diversion road as shown in Table-1. Diversion road Sindhri Dilber Khan Meharis owned by Works Services department Govt. of Sindh which has been selected for diverting traffic for a limited period of time i.e, about 04 months. Page 7 of 11 SMEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 7 of 11

10 Table-1: Preliminary Involuntary Resettlement Impact Assessment Sr. # Chainage Name of village Besham Brohi Nako Stop Dilber khan Mehar Kerio Shakh Hakeem Hotel Remarks 4 katcha shops were located on both sides of diversion road (figure-2). Shops were found located at sufficient distance from the road Shops were found located at sufficient distance from the road Shops were found located at sufficient distance from the road (figure-3). Hotel is located at sufficient distance from the road Figure 2 Shops located at the edge of diversion road at Besham Brohi Bazar Chainage Figure 3 Shops located at sufficient distance from the diversion road at Nako Stop chainage IMPACT ON INDIGENOUS PEOPLE 8. The main castes located in the project area are Junejo, Syed, Soomro. Team observed that almost 90% are Kacha houses and remaining 10% are semi pacca houses scarcely located. The predominant language is Sindhi. None of these people may be considered as IP as defined in ADB SPS (2009). 6. STAKEHOLDERCONSULTATIONS 9. Consultations were made with the stakeholders and general public by the survey team. Consultative meeting was held to learn about the views and concerns of the public on the proposed construction of new bridge. In order to enhance the Project acceptability for the general public on social considerations. The main objectives of the consultation were to: Introduce the project Page 8 of 11 SMEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 8 of 11

11 Sharing full information with the stakeholders about the expected impact on the socioeconomic environment of the project corridor. Information was shared with them regarding formulation of diversion plan to safeguard social and resettlement issues in compliance of ADB Safeguard policy Ensure transparency in all activities related to social mitigation and resettlement matters. Receive feedback from stakeholders on their concerns regarding the project s input and mitigation measures suggested by them. Gather information regarding stakeholders' views about the project; TYPE OF PARTICIPANTS (STAKEHOLDERS) 10. Stakeholders who were consulted include shopkeepers, and notables of the area s such as shopkeepers, gov t employees and road users such as truck and bus drivers. 11. Consultation sessions were made with local community in September A list of consultations and participants is given in Table-2 In addition to these, official consultations were held with WSD officials and PMC to make the plan better and organized. Table-2: Consultations with Local People & Notables Serial NO. Date Location/ Venue Name of Main Participants Results of Consultations Besham Brohi Nasurallah S/O 1 11-Sept Ghulam Ali Besham Brohi Muhammad Sadiq S/O 11-Sept Muhammad Yousaf 3 11-Sept Besham Brohi GulMunir S/O Ghulab 4 11-Sept Sept Sept Sept Besham Brohi Muqadar Ali S/O Fizal Ahmed Besham Brohi Yousaf S/O Ismial Keerio Shakh MuhramKeerio S/O Ghulam Haider Keerio Shakh PirBux S/O NabiBux Keerio Shakh Allah Warayo S/O 8 11-Sept Bashir Warayo 9 11-Sept Keerio Shakh Samano S/O Haji Jagan Sept Keerio Shakh Ghulam Haider S/O Ghulam Qadir The business of the shopkeeper would not be affected due to movement of diverted traffic. Safe and free mobility of locals especially women and children as well as safety measures to be taken during construction activities. Proper arrangements should be made for smooth and un interrupted flow of traffic passing through the road during the construction of the project works. Page 9 of 11 SMEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 9 of 11

12 Serial NO. Date Location/ Venue Name of Main Participants Results of Consultations Sept Sept Hakim Lashari Stop Hakim Lashari Stop Rattan Kumar S/O GordanLal Naroo S/O Rana Due to long route and local commuter, Tea star and food hotel business will be increased Sept Sept Sept Hakim Lashari Stop Hakim LashariStop Hakim Lashari Stop Jodhu S/O Dhano Lakhana S/O Alan Muhammad Anwar S/O Haji WaheedBux Speed breakers should be constructed in the built up area. Traffic signals must be installed at various points Figure 4 Consultation meeting with local shopkeepers at Besham Brohi at Chainage Figure 5 Interview with shopkeepers at Keerio Shakh at Chainage Future Consultation and Participation 12. Resettlement Specialist accompanied by PMU & Supervision Consultant staff will hold meetings with the local communities during construction and implementation stages so as to reduce potential damage to the properties of the of community reduce traffic accident possibilities. 7. GRIEVANCE REDRESS PROCESS 13. A grievance redress mechanism is already working under Deputy Director (Safeguards Quality Control), PMU for social monitoring of existing 6 roads for this purpose a Resettlement specialist has been hired through PMC. Page 10 of 11 SMEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 10 of 11

13 8. CONCLUSIONS AND RECOMMENDATIONS 14. This Due Diligence Report evaluates IR impacts due to construction of Bridge at ICB-04 Chainage Due to construction activities no impact has been found because a good diversion motorable 2-lane road is already available which is owned by Works & Services Department and sufficient ROW of irrigation Channel and Highways Department is also available. Hence, it is assessed that safe mobility of the local communities, particularly women and children and their livestock will not be hindered by the diverted traffic during construction of new bridge. To ensure this, the following are recommended. Proper safety measures like traffic signs to be erected at interval of 100m. Warning signs like reduced speed will be erected. These cautioning signs must be placed commencing at least 1 km before the start of populated area. Proper care should be undertaken by the contractor to avoid accidental damage to the shop, residential houses and religious or community structures due to movement of heavy traffic. To avoid inconvenience to the locals due to noise, smoke and fugitive dust caused by movement of diverted traffic, the contractor should frequently sprinkle water on diversion road. In case of accidentally damaged/affected private structures (houses), compensation should be assessed and compensated promptly Page 11 of 11 SMEC International Pty Ltd, 4 th Floor, ICCI Building, Mauve Area G-8/1, Islamabad Page 11 of 11

PAK: Sindh Provincial Road Improvement Project (SPRIP)

PAK: Sindh Provincial Road Improvement Project (SPRIP) RESETTLEMENT DUE DILIGENCE REPORT Resettlement Due Diligence Report for proposed Additional Road Sections (Sindh Provincial Road Improvement Project SPRIP) (September 2018) PAK: Sindh Provincial Road Improvement

More information

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project

Internal Monitoring Report. PAK: Loan 2299: Lower Bari Doab Canal Improvement Project Internal Monitoring Report 37231-023 March 2016 PAK: Loan 2299: Lower Bari Doab Canal Improvement Project This social monitoring report is a document of the borrower. The views expressed herein do not

More information

IND: Uttarakhand Emergency Assistance Project

IND: Uttarakhand Emergency Assistance Project Resettlement Planning Document Project Number: 47229-001 May 2016 IND: Uttarakhand Emergency Assistance Project Sub Project : DDR for Roads of Dehradun District Submitted by Uttarakhand Emergency Assistance

More information

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II

Social Safeguards Monitoring Report. CAM: Rural Roads Improvement Project II Social Safeguards Monitoring Report Full Report November 2018 CAM: Rural Roads Improvement Project II Prepared by the Ministry of Rural Development for the Kingdom of Cambodia and the Asian Development

More information

MON: Urban Development Sector Project Bulgan Subproject

MON: Urban Development Sector Project Bulgan Subproject Resettlement Completion Report Annual Report 24 December 2012 MON: Urban Development Sector Project Bulgan Subproject Prepared by Purevsuren Dorjnamjil, Resettlement Specialist, Project Management Unit

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Quang Binh Province Prepared by the Ministry of

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Nghe An Province Prepared by the Ministry of Education

More information

MLD - Kulhudhuffushi Harbor Expansion Project

MLD - Kulhudhuffushi Harbor Expansion Project Kulhudhuffushi Harbor Expansion Project (RRP MLD 36111-013) Due Diligence Report on Involuntary Resettlement and Indigenous Peoples March 2016 MLD - Kulhudhuffushi Harbor Expansion Project Prepared by

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Ha Tinh Province Prepared by the Ministry of Education

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Soc Trang Province Prepared by the Ministry of

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Thua Thien Hue Province Prepared by the Ministry

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Binh Thuan Province Prepared by the Ministry of

More information

Land Acquisition and Resettlement Due Diligence Report

Land Acquisition and Resettlement Due Diligence Report Land Acquisition and Resettlement Due Diligence Report Document stage: Draft for consultation Project Number: 48434 Loan and/or Grant Number(s): {LXXXX; GXXXX; TAXXXX} March 2016 India: Visakhapatnam-Chennai

More information

Due Diligence Report on Social Safeguards

Due Diligence Report on Social Safeguards 1 Due Diligence Report on Social Safeguards Loan 3264-PAK: Flood Emergency Reconstruction and Resilience Project (FERRP) AJK s Component Due Diligence Report on Social Safeguards May 2016 Prepared by:

More information

IND: Uttarakhand Emergency Assistance Project

IND: Uttarakhand Emergency Assistance Project Resettlement Planning Document Project Number: 47229-001 July 2016 IND: Uttarakhand Emergency Assistance Project Sub Project : Supplementary Due Diligence Report (social) internal roads of Dehradun district

More information

Semi-annual Social Safeguards Monitoring Report (January to June 2012)

Semi-annual Social Safeguards Monitoring Report (January to June 2012) Semi-annual Social Safeguards Monitoring Report (January to June 2012) Armenia: Sustainable Urban Development Investment Program Tranche 1 Project Number: 42417 Loan Number: L2752 Prepared: July 2013 Prepared

More information

PAK: Loan 2299: Lower Bari Doab Canal Improvement Project

PAK: Loan 2299: Lower Bari Doab Canal Improvement Project External Social Monitoring Report 37231-023 September 2015 PAK: Loan 2299: Lower Bari Doab Canal Improvement Project This social monitoring report is a document of the borrower. The views expressed herein

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Bac Lieu Province Prepared by the Ministry of Education

More information

Resettlement Plan. IND: Bihar State Highways II Project. March Siwan-Siswan Subproject (SH-89)

Resettlement Plan. IND: Bihar State Highways II Project. March Siwan-Siswan Subproject (SH-89) Resettlement Plan March 2012 IND: Bihar State Highways II Project Siwan-Siswan Subproject (SH-89) Prepared by Bihar State Road Development Corporation, Government of Bihar for the Asian Development Bank.

More information

Land Acquisition and Resettlement Framework. PAK: Khyber Pakhtunkhwa Provincial Roads Improvement Project

Land Acquisition and Resettlement Framework. PAK: Khyber Pakhtunkhwa Provincial Roads Improvement Project Land Acquisition and Resettlement Framework Document Stage: Draft September 2017 PAK: Khyber Pakhtunkhwa Provincial Roads Improvement Project Prepared by Khyber Pakhtunkhwa Highways Authority, Communications

More information

PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project

PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project Resettlement Plan November 2017 PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project (Reach-2 Package 2) Firdous Cinema to Aman Chowk Prepared by the Planning and Development Department, Government

More information

TIM G-0180: Road Network Development Sector Project Contract Packages R1 Liquica - Maubara Road Contract Packages R2 Karimbala Atabae Road

TIM G-0180: Road Network Development Sector Project Contract Packages R1 Liquica - Maubara Road Contract Packages R2 Karimbala Atabae Road Social Safeguards Final Report May 2016 TIM G-0180: Road Network Development Sector Project Contract Packages R1 Liquica - Maubara Road Contract Packages R2 Karimbala Atabae Road Prepared by Ministry of

More information

India: Delhi Meerut Regional Rapid Transit System Project

India: Delhi Meerut Regional Rapid Transit System Project Initial Poverty and Social Analysis October 2018 India: Delhi Meerut Regional Rapid Transit System Project This document is being disclosed to the public in accordance with ADB s Public Communications

More information

PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project Reach 3: Aman Chowk to Hayatabad

PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project Reach 3: Aman Chowk to Hayatabad Resettlement Plan October 2017 PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project Reach 3: Aman Chowk to Hayatabad Prepared by the Planning and Development Department, Government of Khyber Pakhtunkhwa

More information

PAK: Additional Financing for Khyber Pakhtunkhwa Provincial Roads Improvement Project

PAK: Additional Financing for Khyber Pakhtunkhwa Provincial Roads Improvement Project Additional Financing for Khyber Pakhtunkhwa Provincial Roads Improvement Project (RRP PAK 47360-003) Resettlement Plan August 2018 PAK: Additional Financing for Khyber Pakhtunkhwa Provincial Roads Improvement

More information

PAK: MFF II Power Transmission Enhancement Program (PTEIP II)

PAK: MFF II Power Transmission Enhancement Program (PTEIP II) Social Document stage: Draft 16 May, 2017 PAK: 48078-002 MFF II Power Transmission Enhancement Program (PTEIP II) Social Due Diligence Review of Upgradation/ Extension of NTDC s Telecommunication & SCADA

More information

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the

RESETTLEMENT FRAMEWORK. Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors. on the RESETTLEMENT FRAMEWORK Supplementary Appendix to the Report and Recommendation of the President to the Board of Directors on the Secondary Education Modernization Project II in Sri Lanka Ministry of Education

More information

IND: Chhattisgarh State Road Sector Project

IND: Chhattisgarh State Road Sector Project Resettlement Plan August 2012 IND: Chhattisgarh State Road Sector Project Nandghat Gidhoury Road Section Subproject Prepared by Public Works Department, Government of Chhattisgarh for the Asian Development

More information

IND: Mumbai Metro Rail Systems Project

IND: Mumbai Metro Rail Systems Project Social Due Diligence Report October 2018 IND: Mumbai Metro Rail Systems Project Prepared by Mumbai Metropolitan Region Development Authority, Government of India for the Asian Development Bank. ABBREVIATION

More information

IND: Chhattisgarh State Road Sector Project

IND: Chhattisgarh State Road Sector Project Resettlement Plan November 2012 IND: Chhattisgarh State Road Sector Project Dhamdha Khairagarh Road Subproject Prepared by Public Works Department, Government of Chhattisgarh for the Asian Development

More information

TAJ: CAREC Corridors 3 and 5 Enhancement Project. Rehabilitation of 88 km Vose - Khovaling subnetwork

TAJ: CAREC Corridors 3 and 5 Enhancement Project. Rehabilitation of 88 km Vose - Khovaling subnetwork Safeguards Document June 2016 Due Diligence Report TAJ: CAREC Corridors 3 and 5 Enhancement Project Rehabilitation of 88 km Vose - Khovaling subnetwork connecting road. Assessment of Compliance with the

More information

India: Jammu & Kashmir Urban Sector Development Project

India: Jammu & Kashmir Urban Sector Development Project Resettlement Planning Document Full Resettlement Plan- Improvements to B.C Road from Shakuntala Crossing to Children s Hospital Including pedestrian subway Document Stage: Final Project Number: 41116 October

More information

Technical Assistance Consultant s Report. TA 7566-REG: Strengthening and Use of Country Safeguard Systems

Technical Assistance Consultant s Report. TA 7566-REG: Strengthening and Use of Country Safeguard Systems Technical Assistance Consultant s Report Project Number: 44140 Date: April 2014 TA 7566-REG: Strengthening and Use of Country Safeguard Systems Subproject: Supporting and Strengthening National-Level Capacity

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: VIE 34055 TECHNICAL ASSISTANCE TO THE SOCIALIST REPUBLIC OF VIET NAM FOR ENHANCING THE RESETTLEMENT LEGAL FRAMEWORK AND INSTITUTIONAL CAPACITY September 2001 CURRENCY EQUIVALENTS

More information

IND: Railway Sector Investment Program

IND: Railway Sector Investment Program Resettlement Framework Document Stage: Final March 2011 IND: Railway Sector Investment Program Prepared by Ministry of Railways for the Asian Development Bank. CURRENCY EQUIVALENTS (as of 16 March 2011)

More information

IND: Bihar State Highways II Project Additional Financing

IND: Bihar State Highways II Project Additional Financing Resettlement Plan November 2011 IND: Bihar State Highways II Project Additional Financing Roonisaidpur Bhiswa Subproject (SH-87) Prepared by Bihar State Road Development Corporation, Government of Bihar

More information

India: Uttarakhand State Road Investment Program

India: Uttarakhand State Road Investment Program Resettlement Planning Document Resettlement Plan for Kirti Nagar New Tehri Road Subproject Document Stage: Final Project Number: 38255 May 2008 India: Uttarakhand State Road Investment Program Prepared

More information

AFG: MFF Water Resources Development Investment Program- Tranche 1, Nangarhar Valley Development Authority Grant No: 0167 AFG

AFG: MFF Water Resources Development Investment Program- Tranche 1, Nangarhar Valley Development Authority Grant No: 0167 AFG Social Monitoring Report Semiannual Report February 2015 AFG: MFF Water Resources Development Investment Program- Tranche 1, Nangarhar Valley Development Authority 42091 Grant No: 0167 AFG Project Implementation

More information

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT

SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT SUMMARY RESETTLEMENT PLAN OF WATER SUPPLY AND SOLID WASTE MANAGEMENT TRANCHE-2 SUB PROJECT OF GANGTOK UNDER ADB ASSISTED NERCCDIP PROJECT A. Introduction and Subprojects Components 1. Tranche 2 of the

More information

Revised Resettlement Plan Tibar-Gleno Road

Revised Resettlement Plan Tibar-Gleno Road REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS INFRA-ESTRUTURAS ROAD NETWORK UPGRADING PROJECT February 2012 Democratic Republic of Timor-Leste REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS

More information

Resettlement Plan. February Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank.

Resettlement Plan. February Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank. Resettlement Plan February 2012 IND: Jammu & Kashmir Urban Sector Development Investment Programme (JKUSDIP) Rehabilitation and Channelization of Storm Water Drains at Channi Himmat in Jammu City Prepared

More information

Final Monitoring Report to the Board of Directors. on the. Implementation of Remedial Actions. for the

Final Monitoring Report to the Board of Directors. on the. Implementation of Remedial Actions. for the Final Monitoring Report to the Board of Directors on the Implementation of Remedial Actions for the Integrated Citarum Water Resources Management Investment Program Project 1 in the Republic of Indonesia

More information

Resettlement Plan. October Prepared by the Government of Jammu and Kashmir, Economic Reconstruction Agency for the Asian Development Bank.

Resettlement Plan. October Prepared by the Government of Jammu and Kashmir, Economic Reconstruction Agency for the Asian Development Bank. Resettlement Plan October 2013 IND: Jammu and Kashmir Urban Sector Development Investment Program (JKUSDIP) - Construction of Mechanized Automated Multi Level Parking Facility at Super Bazaar, Jammu (Tranche

More information

Resettlement Plan. October Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank.

Resettlement Plan. October Prepared by the Government of Jammu & Kashmir, Economic Reconstruction Agency for the Asian Development Bank. Resettlement Plan October 2013 IND: Jammu & Kashmir Urban Sector Development Investment Programme (JKUSDIP) Construction of Storm Water Drains in the Adjoining Areas of NH Bypass (Rawalpora Chowk Chanapora

More information

Earthquake Emergency Assistance Project

Earthquake Emergency Assistance Project Government of Nepal Ministry of Federal Affairs and Local Development Central Level Project Implementation Unit Earthquake Emergency Assistance Project (ADB Loan 3260-NEP) Section IV: Gender Equality and

More information

Resettlement Plan Dili-Tibar-Liquica Road

Resettlement Plan Dili-Tibar-Liquica Road REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS INFRA-ESTRUTURAS ROAD NETWORK UPGRADING SECTOR PROJECT November 2011 REPUBLICA DEMOCRATICA DE TIMOR LESTE MINISTERIO DAS INFRA-ESTRUTURAS ROAD NETWORK

More information

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B.

A. Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs. B. Module 8 - Involuntary Resettlement- Policy Principles & Requirements (World bank OP 4.12 and 4.12 Annex A) Key principles and objectives of an involuntary Resettlement Policy Resettlement planning instruments

More information

Indonesia: Enhanced Water Security Investment Project

Indonesia: Enhanced Water Security Investment Project Initial Poverty and Social Analysis March 2018 Indonesia: Enhanced Water Security Investment Project This document is being disclosed to the public in accordance with ADB s Public Communications Policy

More information

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing

Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing Indigenous People Planning Document Due Diligence Report Loan Number: 2796 and Grant Number: 0267 NEP October 2013 Nepal: Decentralized Rural Infrastructure and Livelihood Project- Additional Financing

More information

PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project Reach 1: Chamkani Mor to Firdous Cinema

PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project Reach 1: Chamkani Mor to Firdous Cinema Resettlement Plan October 2017 PAK: Peshawar Sustainable Bus Rapid Transit Corridor Project Reach 1: Chamkani Mor to Firdous Cinema Prepared by the Planning and Development Department, Government of Khyber

More information

BAN: Railway Sector Investment Program

BAN: Railway Sector Investment Program Resettlement Planning Document Resettlement Framework Document Stage: Final Project Number: 32234 June 2006 BAN: Railway Sector Investment Program Prepared by Bangladesh Railway, Dhaka, Bangladesh The

More information

BAN: Railway Sector Investment Program

BAN: Railway Sector Investment Program Resettlement Due Diligence Report February 2016 BAN: Railway Sector Investment Program Sub Project 1: Tongi-Bhairab Bazar Double Line Project (TBDLP) Sub Project 2: Rehabilitation of Yards and Extension

More information

JBIC ODA Loan Project Mid-Term Review

JBIC ODA Loan Project Mid-Term Review JBIC ODA Loan Project Mid-Term Review Project Title: Thailand: Second Mekong International Bridge Construction Project (L/A No. T GMS-1) [Loan Outline] Thailand Loan Amount/Contract Approved Amount/Disbursed

More information

BAN: South Asia Subregional Economic Cooperation Dhaka-Northwest Corridor Road Project, Phase 2

BAN: South Asia Subregional Economic Cooperation Dhaka-Northwest Corridor Road Project, Phase 2 Resettlement Due Diligence Report May 2017 BAN: South Asia Subregional Economic Cooperation Dhaka-Northwest Corridor Road Project, Phase 2 Prepared by the Roads and Highways Department, Government of the

More information

PROJECT RATIONALE. The new road and tunnel will open up the area to tourists coming south from Russia and north from Tblisi.

PROJECT RATIONALE. The new road and tunnel will open up the area to tourists coming south from Russia and north from Tblisi. PROJECT RATIONALE 1. Status of Existing Road Why is construction of the Kvesheti-Kobi road necessary? The existing 35-km road connecting Kvesheti and Kobi is unsafe and does not conform to international

More information

SRI: Additional Financing for National Highway Sector Project

SRI: Additional Financing for National Highway Sector Project Resettlement Plan May 2011 Document Stage: Draft SRI: Additional Financing for National Highway Sector Project Hikkaduwa Baddegama Section of Hikkaduwa Baddegama Nilhena Road (B153) Prepared by Road Development

More information

Involuntary Resettlement Due Diligence Report

Involuntary Resettlement Due Diligence Report Involuntary Resettlement Due Diligence Report # Report May 2016 VIE: Second Lower Secondary Education for the Most Disadvantaged Areas Project (LSEMDAP2) Cao Bang Province Prepared by the Ministry of Education

More information

MYA: Maubin-Phyapon Road Rehabilitation Project

MYA: Maubin-Phyapon Road Rehabilitation Project Social Monitoring Report Semi-Annual Report (July-December 2016) January 2018 MYA: Maubin-Phyapon Road Rehabilitation Project Prepared by SMEC International Pty. Ltd. In Joint Venture with Oriental Consultants

More information

Resettlement and Indigenous Peoples Plan. IND: North Eastern State Roads Investment Program

Resettlement and Indigenous Peoples Plan. IND: North Eastern State Roads Investment Program Resettlement and Indigenous Peoples Plan February 2013 IND: North Eastern State Roads Investment Program Udaipur Melaghar Subproject (TR02) Prepared by Ministry of Development of North Eastern Region for

More information

IND: Infrastructure Development Investment Program for Tourism - Tranche 3

IND: Infrastructure Development Investment Program for Tourism - Tranche 3 Resettlement Planning Document Project Number: 40648-034 March 2016 IND: Infrastructure Development Investment Program for Tourism - Tranche 3 Sub Project : Conservation and Adaptive Reuse of Town Hall,

More information

Bangladesh: Urban Public and Environmental Health Sector Development Program

Bangladesh: Urban Public and Environmental Health Sector Development Program Resettlement Planning Document Draft Resettlement Framework Document Stage: Draft for Consultation Project Number: 39305 May 2009 Bangladesh: Urban Public and Environmental Health Sector Development Program

More information

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project

Indigenous Peoples Development Planning Document. VIE: Calamity Damage Rehabilitation Project Indigenous Peoples Development Planning Document Indigenous Peoples Development Framework Document Stage: Final Project Number: 40282 September 2006 VIE: Calamity Damage Rehabilitation Project The summary

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project RESETTLEMENT DUE DILIGENCE REPORT Project Number: 46391-001 January 2018 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Ho Chi Minh City Power Corporation, Electricity

More information

Updated Land Acquisition and Compensation Plan. LAO: Additional Financing of Water Supply and Sanitation Sector Project (Xamneau Subproject)

Updated Land Acquisition and Compensation Plan. LAO: Additional Financing of Water Supply and Sanitation Sector Project (Xamneau Subproject) Updated Land Acquisition and Compensation Plan April 2018 LAO: Additional Financing of Water Supply and Sanitation Sector Project (Xamneau Subproject) Part 2 Prepared by the Department of Water Supply,

More information

SRI: Local Government Enhancement Project

SRI: Local Government Enhancement Project Appendix 13 Resettlement Framework Dec 2011 SRI: Local Government Enhancement Project CURRENCY EQUIVALENTS (as of 27 June 2011) Currency Unit = Sri Lankan Rupee/s (SLR/Rs) Rs1.00 = $0.0091 $1.0 = Rs 109.8700

More information

Garma-Nele-Bogal Subproject, Solukhumbu Chainage: (O )

Garma-Nele-Bogal Subproject, Solukhumbu Chainage: (O ) Government of Nepal Ministry of Federal Affairs and Local Development Central Level Project Implementation Unit Earthquake Emergency Assistance Project Lalitpur, Nepal (ADB Loan 3260-NEP) Gender Equality

More information

Annex 2: Does the Xayaburi resettlement comply with Lao law?

Annex 2: Does the Xayaburi resettlement comply with Lao law? Annex 2: Does the Xayaburi resettlement comply with Lao law? The Xayaburi project s resettlement scheme has not complied with Lao laws and policies on involuntary resettlement and compensation. As the

More information

India: Madhya Pradesh Urban Services Improvement Project (MPUSIP)

India: Madhya Pradesh Urban Services Improvement Project (MPUSIP) Resettlement Planning Document Resettlement Framework Document Stage: Draft for Consultation Project Number: 42486 June 2016 India: Madhya Pradesh Urban Services Improvement Project (MPUSIP) The resettlement

More information

Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Mannar Subprojects

Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Mannar Subprojects Resettlement Implementation Plan Project Number: 37381-013 September 2012 Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Mannar Subprojects Prepared by SMEC Consultants for Dry Zone Urban

More information

Social Safeguards Monitoring Report. TIM L-2857/2858: Road Network Upgrading Project Contract Packages R4 Tibar - Gleno Road

Social Safeguards Monitoring Report. TIM L-2857/2858: Road Network Upgrading Project Contract Packages R4 Tibar - Gleno Road March 2015 TIM L-2857/2858: Contract Packages R4 Prepared by for the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent

More information

Indigenous Peoples Planning Framework. India: Assam Power Sector Investment Program

Indigenous Peoples Planning Framework. India: Assam Power Sector Investment Program Indigenous Peoples Planning Framework Document Stage: Draft for Consultation Project Number: 47101 (IND) September 2013 India: Assam Power Sector Investment Program Prepared by Assam Power Generation Corporation

More information

Ethnic Minorities Development Framework. PRC: Guangxi Regional Cooperation and Integration Promotion Investment Program

Ethnic Minorities Development Framework. PRC: Guangxi Regional Cooperation and Integration Promotion Investment Program Ethnic Minorities Development Framework Project Number: 50050-002 September 2016 PRC: Guangxi Regional Cooperation and Integration Promotion Investment Program Prepared by the Government of the People

More information

IND: Railway Sector Investment Program Tranche 3

IND: Railway Sector Investment Program Tranche 3 Resettlement Due Diligence Report September 2017 IND: Railway Sector Investment Program Tranche 3 Prepared by the Ministry of Railways for the Republic of India and the Asian Development Bank. CURRENCY

More information

IND: Second Jharkhand State Road Project

IND: Second Jharkhand State Road Project Resettlement Plan March 2015 IND: Second Jharkhand State Road Project Dumka Hansdiha Road Prepared by State Highways Authority of Jharkhand (SHAJ), Government of India for the Asian Development Bank. ADB

More information

ASIAN DEVELOPMENT BANK JFPR: AFG 36553

ASIAN DEVELOPMENT BANK JFPR: AFG 36553 ASIAN DEVELOPMENT BANK JFPR: AFG 36553 PROPOSED GRANT ASSISTANCE (Financed by the Japan Fund for Poverty Reduction) TO AFGHANISTAN FOR SUPPORTING THE ROAD EMPLOYMENT PROJECT FOR SETTLEMENT AND INTEGRATION

More information

Donated for a Cause: Land Transfers in DRILP

Donated for a Cause: Land Transfers in DRILP Overview The Decentralized Rural Infrastructure and Livelihood Project (DRILP) has been successful in bringing much needed road and community infrastructure to Nepal's hill and mountain districts. An additional

More information

IND: Uttarakhand State Roads Investment Program (Project 3)

IND: Uttarakhand State Roads Investment Program (Project 3) Resettlement Plan November 2011 IND: Uttarakhand State Roads Investment Program (Project 3) Pauri Bend Magnesite Factory Road Subproject Prepared by Public Works Department, Government of Uttarakhand for

More information

Public Disclosure Authorized SFG3015 V1. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

Public Disclosure Authorized SFG3015 V1. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized Public Disclosure Authorized SFG3015 V1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Resettlement Policy Framework Karachi Neighborhood Improvement Project February,

More information

MATARBARI PORT ACCESS ROAD DEVELOPMENT PROJECT

MATARBARI PORT ACCESS ROAD DEVELOPMENT PROJECT Government of the People s Republic of Bangladesh Ministry of Road Transport and Bridges Roads and Highways Department Land Acquisition and Resettlement Action Plan Submitted by: November 2018 BETS Consulting

More information

SRI: Southern Road Connectivity Project

SRI: Southern Road Connectivity Project Resettlement Plan January 2016 SRI: Southern Road Connectivity Project Kesbewa to Pokunuwita Section of Pamankada Horana (B084) Road Prepared by Ministry of University Education & Highways, Government

More information

TRIBAL DEVELOPMENT PLAN

TRIBAL DEVELOPMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Rehabilitation, Upgradation and Strengthening of Nuapada-Bango Munda Section of NH-217

More information

2862/63/64-BAN (SF): Greater Dhaka Sustainable Urban Transport Project

2862/63/64-BAN (SF): Greater Dhaka Sustainable Urban Transport Project Social Monitoring Report Project No. 42169-013 Semestral Report December 2016 2862/63/64-BAN (SF): Greater Dhaka Sustainable Urban Transport Project Prepared by Roads and Highways Department (RHD) for

More information

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005

Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity. Prime Minister s Office Date: 7 July, 2005 Lao People s Democratic Republic Peace Independence Democracy Unity Prosperity Prime Minister s Office No 192/PM Date: 7 July, 2005 DECREE on the Compensation and Resettlement of the Development Project

More information

SUMMARY POVERTY REDUCTION AND SOCIAL STRATEGY

SUMMARY POVERTY REDUCTION AND SOCIAL STRATEGY Greater Mekong Subregion Tourism Infrastructure for Inclusive Growth Project (RRP CAM46293) SUMMARY POVERTY REDUCTION AND SOCIAL STRATEGY Country: Cambodia Project Title: Greater Mekong Subregion Tourism

More information

BANK MANAGEMENT RESPONSE TO REQUEST FOR INSPECTION PANEL REVIEW OF THE INDIA MUMBAI URBAN TRANSPORT PROJECT (IBRD LOAN

BANK MANAGEMENT RESPONSE TO REQUEST FOR INSPECTION PANEL REVIEW OF THE INDIA MUMBAI URBAN TRANSPORT PROJECT (IBRD LOAN BANK MANAGEMENT RESPONSE TO REQUEST FOR INSPECTION PANEL REVIEW OF THE INDIA MUMBAI URBAN TRANSPORT PROJECT (IBRD LOAN No. 4665-IN; IDA CREDIT No. 3662-IN) Management has reviewed the Request for Inspection

More information

BASIC SOCIAL ASSESSMENT REPORT FOR THE N11, SECTION 13, MOKOPANE

BASIC SOCIAL ASSESSMENT REPORT FOR THE N11, SECTION 13, MOKOPANE E02.JNB.000973 BASIC SOCIAL ASSESSMENT REPORT FOR THE N11, SECTION 13, MOKOPANE 15 August 2012 SANRAL Tel: +27 (0) 11 7986000 Email: kimm@ssi.co.za Building No 5, Country Club Estate, 21 Woodlands Drive,

More information

PNG: Bridge Replacement for Improved Rural Access Sector Project

PNG: Bridge Replacement for Improved Rural Access Sector Project Resettlement Plan June 2011 PNG: Bridge Replacement for Improved Rural Access Sector Project Prepared by the Department of Works of the Government of Papua New Guinea for the Asian Development Bank. Resettlement

More information

IND: Infrastructure Development Investment Program for Tourism - Tranche 3

IND: Infrastructure Development Investment Program for Tourism - Tranche 3 Resettlement Planning Document Project Number: 40648-034 March 2016 IND: Infrastructure Development Investment Program for Tourism - Tranche 3 Sub Project : Eco Tourism Development at Ropar and Harike

More information

Resettlement Framework. BHU: Urban Infrastructure Project. October Prepared by the Royal Government of Bhutan for the Asian Development Bank.

Resettlement Framework. BHU: Urban Infrastructure Project. October Prepared by the Royal Government of Bhutan for the Asian Development Bank. Resettlement Framework October 2011 BHU: Urban Infrastructure Project Prepared by the Royal Government of Bhutan for the Asian Development Bank. CURRENCY EQUIVALENTS (as of 5 October 2011) Currency unit

More information

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION

VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION VOLUME 4 CHAPTER 1 PROJECT DESCRIPTION Table of Content Volume 4 Chapter 1: Project Description 1 PROJECT DESCRIPTION...1 1.1 THE NT2 PROJECT...1 1.2 THE NEED FOR RESETTLEMENT AND DEVELOPMENT...1 1.3 THE

More information

Ex-Post Evaluation of Japanese ODA Loan Project Pak Kret Bridge and Connecting Road Construction Project

Ex-Post Evaluation of Japanese ODA Loan Project Pak Kret Bridge and Connecting Road Construction Project Kingdom of Thailand Ex-Post Evaluation of Japanese ODA Loan Project Pak Kret Bridge and Connecting Road Construction Project 1. Project Description Yasuhiro Kawabata, Sanshu Engineering Consultant Location

More information

IND: Second Jharkhand State Road Project

IND: Second Jharkhand State Road Project Resettlement Plan March 2015 IND: Second Jharkhand State Road Project Khunti - Tamar Road Prepared by State Highways Authority of Jharkhand (SHAJ), Government of India for the Asian Development Bank. ADB

More information

BAN: City Region Development Project for Shakhari Bazaar Urban Renewal Subproject

BAN: City Region Development Project for Shakhari Bazaar Urban Renewal Subproject Resettlement Plan Document Stage: Draft for Consultation Project Number: 39298 July 2010 BAN: City Region Development Project for Shakhari Bazaar Urban Renewal Subproject Prepared By: Local Government

More information

Summary of the Indigenous Peoples' Consultation with the Asian Development Bank, November 27 th 2007

Summary of the Indigenous Peoples' Consultation with the Asian Development Bank, November 27 th 2007 Summary of the Indigenous Peoples' Consultation with the Asian Development Bank, November 27 th 2007 This document is an overview of the discussions of the indigenous peoples' consultation held in Manila

More information

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang)

VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Resettlement Plan August 2011 VIE: Comprehensive Socioeconomic Urban Development Project Viet Tri, Hung Yen, and Dong Dang (Dong Dang) Prepared by the Lang Son Provincial People s Committee for the Asian

More information

People s Republic of China: Jilin Yanji Low-Carbon Climate-Resilient Urban Development Project

People s Republic of China: Jilin Yanji Low-Carbon Climate-Resilient Urban Development Project Initial Poverty and Social Analysis May 2018 People s Republic of China: Jilin Yanji Low-Carbon Climate-Resilient Urban Development Project This document is being disclosed to the public in accordance

More information

SRI: Local Government Enhancement Project

SRI: Local Government Enhancement Project Draft Resettlement Framework July 2011 SRI: Local Government Enhancement Project Prepared by the Ministry of Local Government and Provincial Councils for the Asian Development Bank. CURRENCY EQUIVALENTS

More information

EBRD Performance Requirement 5

EBRD Performance Requirement 5 EBRD Performance Requirement 5 Land Acquisition, Involuntary Resettlement and Economic Displacement Introduction 1. Involuntary resettlement refers both to physical displacement (relocation or loss of

More information

SRI: Integrated Road Investment Program

SRI: Integrated Road Investment Program Resettlement Due Diligence Report April 2017 SRI: Integrated Road Investment Program Improvement, Rehabilitation and Maintenance of Maradankadawala - Habarana section of Maradankadawela - Habarana Tirikkondiadimadu

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: PIDC3287 Project Name Greater

More information