1 UK: Engineering, Procurement & Construction Briefing May 2013 Contents Introduction 01 Liquidated damages vs penalty 01 causes a clear cut dichotomy? Varying the construction methods 03 to catch up how do you value that variation? Ambiguity and/or consistency on 05 different contractual documents and the application of the order of precedence clause How is using reasonable 06 endeavours to complete different from exercising diligence? Contacts 08 Guarding against contractor delay an update from recent case law Introduction Delay, liquidated damages and extension of time are some of the most common issues for any construction project. Not only are they likely to be the focus of negotiations when parties seek to conclude a construction contract, but they are frequently the major causes of disputes between the parties. Such disputes often emerge from a variety of consequential or concurrent events or causes not necessarily attributable to time management failures. This briefing note provides an overview of four recent cases in which the Courts looked at the following areas of construction law, each of which relates, either directly or indirectly, to the issue of contractor delay: liquidated damages for delay; variations (to omit certain works); ambiguity and/or inconsistency between contractual documents and the application of the order of precedence clause; and using reasonable endeavours to complete vs exercising diligence. Liquidated damages vs penalty clauses a clear cut dichotomy? The enforceability of any liquidated damages clause has traditionally rested on whether the amount of liquidated damages agreed at the time the contract is entered into represents the partiesʹ genuine pre estimate of loss which may be suffered in the future due to the relevant breach. If not, the clause could be viewed as a penalty clause and hence unenforceable under English law. In the relatively recent case of Cavendish Square Holdings v El Makdessi [2012] EWHC 3582, however, the Court confirmed and adopted a more flexible modern approach that attempts to determine the commercial justifications for the provision rather than the traditional approach of classifying and limiting the analysis to a genuine pre estimate of loss. wfw.com
2 02 UK: ENGINEERING, PROCUREMENT AND CONSTRUCTION BRIEFING What happened in Cavendish? In Cavendish, a dispute arose after the sale of a majority shareholding in an advertising and marketing communications company. In order to reflect the significant value placed on the ongoing involvement of the seller (as a minority shareholder and director) in the business after the sale, the relevant agreement included certain restrictive covenants which applied whilst the seller remained involved in the business and for a period thereafter. If the restrictive covenants were breached, the purchaser: (i) would be released from its obligation to pay the seller the last two instalments of the consideration; and (ii) could purchase from the seller his remaining minority stake in the company at net asset value (i.e. at an undervalue). One of the issues in question was whether these provisions were penal and hence unenforceable. Cavendish is just part of a growing body of case law that suggests that the strict classification of liquidated damages as either a penalty or a genuine pre estimate of loss is no longer applied. 1 Although on the very specific facts of the case, the provision releasing the buyer from the last two instalments of consideration was held to be a penalty on the ground of double counting, since the buyer s loss was reduced by the company having already received damages for breach of fiduciary duty from the seller. The Court enforced the provision subject to credit being given to the damages already paid to the company. What did the Court decide? In arriving at the conclusion that the provisions on their own were not penalty clauses, 1 the Court considered that one effect of such provisions was to adjust the consideration on the basis of substantial loss of goodwill, which was neither extravagant nor oppressive. Further, the right to buy out the seller s stake also served the commercial purpose of decoupling the defaulting shareholder (i.e. the seller) from the company in the event of breach. Accordingly, the relevant provisions did not have the purpose of deterring breach. The Court s decision referred to previous decisions which pointed to the focus on commercial justification in determining whether a clause is penal or not, rather than the need to ascertain whether there was a genuine pre estimate of loss. At paragraph 53 of his judgment, Mr. Justice Burton summarised the position as follows: the reality is that, in the modern approach to the concept of penalty discussed above, there is no longer the need for the dichotomy between liquidated damages and genuine pre estimate of loss, and so the relevant questions seem to me to be simply: i. Was there a commercial justification? ii. Was the provision extravagant or oppressive? iii. Was the predominant purpose of the provision to deter breach? iv. If relevant, was the provision negotiated on a level playing field? The legal trend in analysing liquidated damages clause Although Cavendish is not a construction and engineering case, it is likely that this judgment may affect how practitioners of this field negotiate, draft and analyse liquidated damages clauses in construction contracts. In fact, from the judgment of Mr. Justice Burton, Cavendish is just part of a growing body of case law that suggests that the strict classification of liquidated damages as either a penalty or a genuine pre estimate of loss is no longer a necessary or sole test. For example, in the shipbuilding case of Azimut Benetti SpA (Benetti Division) v Darrell Marcus Healey [2010] EWHC 2234, the Court upheld a liquidated damages clause despite the fact that the level of damages provided for was clearly not a genuine pre estimate of the claimantʹs losses. Such a clause was held to be commercially justifiable on the basis that its dominant purpose was not to deter breach. Our thoughts Despite the judicial trend of moving away from the concept of a genuine pre estimate of loss, is it likely that we will see any practical differences when dealing with liquidated damages clauses? Perhaps not, or at least not immediately. Many recently concluded construction contracts still contain an express reference to both parties acknowledging that the pre agreed liquidated damages payable are a genuine pre estimate of the loss. The
3 UK: ENGINEERING, PROCUREMENT AND CONSTRUCTION BRIEFING 03 prudent approach, in our view, is still to calculate one s entitlement to liquidated damages on this basis. After all, if the amount of liquidated damages is calculated to reflect one s genuine expectation of loss, it would be strong evidence of commercial justification for the clause, and such clause would neither be extravagant or oppressive. In summary, whilst the modern approach may discourage defaulting contractors from seeking to avoid a liquidated damages clause by arguing that it is penal and hence unenforceable, employers should, wherever possible, structure such a clause to reflect the likely losses that they may suffer in the event of breach. If a figure for liquidated damages cannot be readily determined by reference to a pre estimate of the likely losses, employers will then need to think carefully what the commercial justification for the provision is, and, not the least, ensure that there is no double recovery. Varying the construction methods to catch up how do you value that variation? Most construction contracts, whether bespoke or based on standard forms, provide for the employer s right to issue variations to vary the works during the course of a project. These may include, for example, the carrying out of additional works, employing different construction methods or materials and/or not carrying out certain works. In the context of contractor delay, especially where such a delay has not yet happened but is inevitable due to the circumstances, we have sometimes seen employers issuing variations to either vary or omit the affected works in order to avoid or mitigate the (potential) contractor delay. Variations hence can be a useful time and cost management tool. Whilst the construction contract will typically contain valuation provisions setting out how any resulting adjustment to the contract price is to be calculated, disputes can often arise when the parties are unable to agree on how such valuation provisions should be applied. This was the case in MT Hojgaard A/S v (1) E.ON Climate & Renewables UK Robin Rigg East Limited and (2) E.ON Climate & Renewables UK Robin Rigg West Limited [2013] EWHC 967. Whilst the construction contract will typically contain valuation provisions setting out how any resulting adjustment to the contract price is to be calculated, disputes can often arise when the parties are unable to agree on how such valuation provisions should be applied... What happened in Robin Rigg? In Robin Rigg, the contractor was engaged by the employer to design, manufacture, deliver, install and commission foundations for 60 wind turbine generators and two substations in the Solway Firth. Amongst other obligations, the contractor was to charter a barge for the installation of the foundations. When it was subsequently discovered that the contractor s barge was technically inadequate and would also take significantly longer than anticipated to install those foundations, the employer (through the engineer) issued a series of variations whereby the employer would (at its own cost) charter a replacement vessel to carry out the installation works. A dispute arose as to how much should be deducted from the contract price to reflect the fact that the contractor s barge was not used to carry out the installation works. The contractor argued that since the high level breakdown of the contract price reflected the cost of installing the foundations using the contractor s barge, the deduction should be based on such amount subject to some minor adjustments; whereas the employer contended that the deduction should be calculated by reference to the time the contractor s barge would have taken to carry out the works (had it done so) and multiplying that with an applicable rate. The difference between each party s position was up to approximately 44 million. What did the Court decide? Mr. Justice Stuart Smith agreed with the contractor s interpretation that the deduction should be based on the amount included in the breakdown of contract price for the Watson, Farley & Williams May 2013
4 04 UK: ENGINEERING, PROCUREMENT AND CONSTRUCTION BRIEFING chartering of the contractor s barge, and pointed out that words or phrases in a contract should be interpreted in the context of the contract as a whole. In line with this principle, it held that the inclusion of the breakdown meant that the contract recognised that the contract price represented the sum of the costs of the various elements of the works; accordingly, if the contractor carried out part of the works, it would be entitled to that element of the contract price, but if not, the amount accorded to those works should be deducted. Windfall gain for the contractor? What about the fact that the contractor avoided having to pay significant liquidated damages but for the employer s variations? In response to this, Mr. Justice Stuart Smith stated that:...the contractual mechanism for dealing with delay was the application of liquidated damages no reason why the additional delay which would have been incurred should be reflected in an adjustment to the Contract Price, particularly when the delay has in fact been avoided...the contractual mechanism for dealing with delay was the application of liquidated damages If the [variations] had not been issued, the delay may have been even greater, in which case the remedies provided by the Contract would have been applicable... That being so, there seems to be no reason why the issuing of the [variations] should have the result that the additional delay which would have been incurred had [the contractor] continued to work with the [original barge] should be reflected in an adjustment to the Contract Price, particularly when the delay has in fact been avoided It is correct that the effect of the [variations], on [the contractor s] interpretation, was to relieve it of the financial consequences that it might have incurred in future if it had been required to complete the contract using the [original barge]; but this is not a transfer of risk as such and is not objectionable since the purpose of the [variations] was to avoid the consequences of further delays attributable to the [original barge], which was for the benefit of both parties. The real transfer of risk arose because [the employer] elected to hire the [replacement vessel] itself without putting in place any mechanism that would transfer the cost of hire to [the contractor]. Lesson learnt The facts in Robin Rigg were arguably unusual in that the employer had agreed to pay for the cost of the replacement vessel even though the original contract sum reflected that it should have been borne by the contractor. Nevertheless, it clearly illustrated that where an employer decides to omit part of the works in order to avoid or mitigate a contractor delay, the valuation of that variation or omission, unless expressly provided for in the contract or agreed upfront between the parties, would be what the contractor has allowed for in the contract price originally for that part of the omitted work, rather than what the contractor would have incurred had the delay not been avoided/mitigated. In other words, by issuing the variation to avoid or minimise the contractor delay, the employer could not claim for what is effectively compensation for delay under the guise of adjustment of contract price due to such a variation. Our thoughts Aside from the need for an employer faced with a (potential) contractor delay to pay particular attention to its contractual options and their consequences, Robin Rigg also highlights the importance of clear and unambiguous contractual drafting in avoiding disputes, especially in the context of how adjustments to the contract price are to be determined. In particular, it would be wise to consider the following:
5 UK: ENGINEERING, PROCUREMENT AND CONSTRUCTION BRIEFING 05 The contract should set out in detail how and in what circumstances any adjustments to the contract price are to be calculated; worked examples may be useful where alternatives are applicable. Obvious as it may be, the parties should seek to agree any adjustments to the contract price (or failing that, the formulae for determining the adjustment) before a variation is issued and/or carried out. If adjustments to the contract price are to be calculated by reference to what is reasonable, the parties should seek to define, as far as possible, the criteria to be used to determine what is reasonable (for example what percentage of cost should treated as profit, if any). It may be useful to include a fast track mechanism, such as expert determination, for resolving disputes on valuation or other specific areas prone to disagreement between the parties. Last but not least, the parties should always follow the variation procedure set out in the contract, including the issuing of variation notices and orders. Ambiguity and/or inconsistency on different contractual documents and the application of the order of precedence clause Those working in the construction industry will be familiar with the concept that a construction contract typically consists of a whole range of legal and technical documents, such as the general and specific legal terms and conditions, the various appendices and annexures to such conditions, the technical specifications and drawings, etc. As no single document constitutes a construction contract, it is almost standard (and certainly common for most industry standard forms) to contain a priority of documents or order of precedence clause that clarifies which documents make up the construction contract and specifies their order of precedence in the event of conflict. Having an order of precedence clause, however, does not always provide the certainty the parties might have expected. In respect of delay and liquidated damages provisions, it is not uncommon for the concept of completion (i.e. the stage in the progress of the works that the contractor is to achieve by a pre agreed date beyond which liquidated damages would be payable) to be mentioned or defined in two or more contractual documents (for example, in the legal document setting out the particular conditions and in the technical document setting out the specifics of the project including the programme). The key, as illustrated by the case of RWE Npower Renewables Ltd v J N Bentley Ltd [2013] EWHC 978, is to ensure that all references or definitions of completion (or any equivalent concepts) are entirely consistent with each other. Having an order of precedence clause, however, does not always provide the certainty the parties might have expected when including such a clause in the contract. What happened in RWE? In RWE, the parties have fallen out in relation to various delays to the completion of the project and a dispute arose between the parties as to whether material ambiguity exists between the definitions of section 2 completion referred to in the various documents constituting the construction contract. Although the Court recognised that there were undoubtedly differences between the wording in the two documents in question (one requiring completion, including testing, of the intake, penstock pipeline to allow Hydro Plant to be installed and the other requiring completion, including testing, of the intakes, penstock pipelines to be completed to allow the hydro Watson, Farley & Williams May 2013
6 06 UK: ENGINEERING, PROCUREMENT AND CONSTRUCTION BRIEFING plant to be tested and commissioned [emphasis added]), it held that there was no material ambiguity between the two documents in question. Accordingly, the application of the order of precedence clause was held not to be necessary because the Court could interpret apparently discrepant items by construing the contract as a whole. Parties to a construction contract will frequently include an order of precedence clause with the intention of providing greater level of certainty... However the circumstances under which such a clause may be applied is not always clear cut 2 Note that a successful appeal was brought against this decision in Telford Homes (Creekside) Ltd v Ampurius New Homes Holdings Ltd [2013] EWCA Civ 577. The points of appeal, however, were concerned with whether the trial judge was correct in holding that there was a repudiatory breach by the property developer (which entitled the investor to terminate the contract). The issue of whether the developer breached both or only one of the obligations to use reasonable endeavours to complete and to carry out the works diligently was not in dispute in the appeal. Accordingly, the outcome of the appeal did not affect the discussions below. In arriving at this conclusion, the Court provided the following guidance in determining whether the order of precedence clause should be engaged or not: What one cannot and should not do is to carry out an initial contractual construction exercise on each of the material contract documents on any given topic and then, so to speak, compare the results of that exercise to see if there is ambiguity If it is possible to identify a clear and sensible commercial interpretation from reviewing all the contract documents which does not produce an ambiguity, that interpretation is likely to be the right one; in those circumstances, one does not need the order of precedence to resolve an ambiguity which does not actually on a proper construction arise at all. In support of its view, the Court pointed out that the order of precedence clause expressly provided that all the documents were ʺdeemed to form and be read and construed as part of this Agreementʺ. Accordingly, this meant that the contract should simply be construed in the usual way by reference to all the documents forming part of the contract and it is only if there is an ambiguity or discrepancy between two or more documents that one then needs to have regard to the express order of precedence. Our thoughts Parties to a construction contract will frequently include an order of precedence clause with the intention of providing greater level of certainty on which document should prevail in the case of a clash between two or more contractual documents. However, it is clear from RWE that the interpretation and application of such a clause will depend on its context. In fact, the judgment itself is contrary to (or arguably a successful appeal from) the decision made previously by the adjudicator in relation to the parties dispute, who considered that one interpretation should have precedence over the other (in line with the order of precedence clause). RWE is just one of the many cases which illustrate that clear and consistent drafting could have made all the difference, especially when drafting for important concepts such as completion, and a failure to do so can prove fatal to an employer s claim for liquidated damages. How is ʺusing reasonable endeavours to completeʺ different from ʺexercising diligenceʺ? In the last of the four cases, we consider the obligations on a contractor to carry out the works diligently and to exercise all reasonable endeavours to ensure the works are completed without delay. Neither phrase is uncommon in a construction contract. But do they mean essentially the same thing in practice, such that if the contractor satisfies one obligation, he will necessarily have satisfied the other? These were some of the questions considered in Morris Homes (West Midlands) Ltd v (1) Antony Paul Keay and (2) Jeffrey David Keay [2013] EWHC 932 which reflected the previous trial decision in Ampurius New Homes Holdings Ltd v Telford Homes (Creekside) Ltd [2012] EWHC 1820 on these specific questions. 2 What happened in Morris Homes? The claimant, Morris Homes, entered into a contract with the defendants whereby Morris Homes, amongst other obligations, was to diligently carry out the Works (the diligence obligation ), and to exercise all reasonable endeavours to ensure that the Works are completed as
7 UK: ENGINEERING, PROCUREMENT AND CONSTRUCTION BRIEFING 07 soon as reasonably practicable (the reasonable endeavours obligation ). Owing to financial crisis, Morris Homes subsequently unilaterally suspended the construction works. In an arbitration brought by the defendants against it, Morris Homes argued that it would have risked commercial suicide by continuing with the works, and that the reasonable endeavours obligation did not oblige it to risk financial ruin by continuing with the works. Morris Homes further submitted that, if it had satisfied the reasonable endeavours obligation, it would also have satisfied the diligence obligation. What the Court decided Both the arbitrator and the Court (in an appeal brought by Morris Homes against the arbitrator s decision) rejected Morris Homes arguments. First, the Court explained that a provision requiring a contractor to carry out works diligently relates to the way in which the works are carried out (for example, the construction methods and materials used) and the time and order in which the works are carried out. Second, the Court agreed that an obligation to carry out works diligently differs from a reasonable endeavours obligation, in that a contractor may satisfy a reasonable endeavours obligation by, as in Morris Homes, suspending the works in order to ensure that it has sufficient capital to eventually complete the works, but breach an obligation to carry out works diligently by, for example, failing to programme the works properly. What about the obligation to have funding to complete? The Court s decision therefore reinforced the previous trial decision in Ampurius, the judgment of which also covered the following in respect of the issue of having adequate funding in place to complete a contract by a certain time: 3 I do not think a ʹreasonable endeavoursʹ clause as regards the time of completion in a construction contract can extend to endeavours to have sufficient money to perform the contract [O]n an objective reading the qualification of ʺreasonable endeavoursʺ, as opposed to an absolute obligation to complete, is designed to cover matters that directly relate to the physical conduct of the works, thereby providing an excuse for delay in such circumstances as inclement weather or a shortage of materials for which the Defendant was not responsible. The clause does not, in my view, extend to matters antecedent or extraneous to the carrying out of the work, such as having the financial resources to do the work at all. In other words, if a contractor runs out of materials to complete for reasons beyond his control, this in itself might not be a breach of the reasonable endeavours obligation; however, if the contractor runs out of money to complete (which may well be for reasons beyond his control), he would be in breach of the reasonable endeavours obligation. Our thoughts Morris Homes is a useful reminder that, when drafting and negotiating obligations concerning the carrying out and completion of construction works, the concepts of using reasonable endeavours to complete and carrying the works out diligently do serve different purposes and are not to be assumed to be interchangeable. An event of contractor s delay (in absence of any justifiable reasons) may amount to a breach of one but not necessarily both obligations. That issue aside, when faced with a significant contractor delay, the most pertinent questions for an employer are likely to be, what options are available to it and what the legal and practical consequences are for each option. These questions will not only require establishing what obligations have been breached, but also an assessment of the seriousness and other circumstances of such breach. An employer would be well advised to take appropriate professional advice before responding (or even terminating the contractual relationship) too quickly....a contractor may satisfy a reasonable endeavours obligation by suspending the works in order to ensure that it has sufficient capital to eventually complete the works, but breach an obligation to carry out works diligently by failing to programme the works properly. 3 As mentioned in footnote 2 on the previous page, the developer successfully appealed against the trial judgeʹs decision that there was a repudiatory breach (due to the developerʹs delay). However, the Court of Appeal decision did not affect the trial judgeʹs statement below. Watson, Farley & Williams May 2013
8 08 UK: ENGINEERING, PROCUREMENT AND CONSTRUCTION BRIEFING Contacts Should you wish to discuss any of the matters raised in this briefing, please speak with a member of our team below, or your regular contact at Watson, Farley & Williams. Martin Lucas Partner mlucas@wfw.com Mark Lawson Partner mlawson@wfw.com Pauline Page ppage@wfw.com Jon Thursby jthursby@wfw.com Freddie Phillips fphillips@wfw.com Charlotte Corble ccorble@wfw.com James Dow jdow@wfw.com All references to Watson, Farley & Williams and the firm in this publication mean Watson, Farley & Williams LLP and/or its affiliated undertakings. Any reference to a partner means a member of Watson, Farley & Williams LLP, or a member of or partner in an affiliated undertaking of either of them, or an employee or consultant with equivalent standing and qualification. This publication is produced by Watson, Farley & Williams. It provides a summary of the legal issues, but is not intended to give specific legal advice. The situation described may not apply to your circumstances. If you require advice or have questions or comments on its subject, please speak to your usual contact at Watson, Farley & Williams. This publication constitutes attorney advertising. Watson, Farley & Williams LON KW KW 29/05/2013 wfw.com
THE INTERPRETATION OF EXCLUSION CLAUSES
BRIEFING THE INTERPRETATION OF EXCLUSION CLAUSES MAY 2016 LITERAL AND NATURAL MEANING IS OF PRIMARY IMPORTANCE COMMERCIALITY MAY BE CONSIDERED THE COURT MAY ALSO CONSIDER APPLICATION OF THE CONTRA PROFERENTEM
More informationLunch & Learn Liquidated Damages Best Practice Alistair Maughan 10 February 2014 Morrison & Foerster (UK) LLP
Lunch & Learn Liquidated Damages Best Practice Alistair Maughan 10 February 2014 Morrison & Foerster (UK) LLP 2013 Morrison & Foerster (UK) LLP All Rights Reserved mofo.com Lunch & Learn 2 nd Monday of
More informationThe Commencement Date was 1/1/14 and the Time for Completion was 18 months.
Scenario for Edinburgh Working Weekend WorldTech is a multinational IT corporation. It entered into a contract with ConstructIT for the construction of a key next-generation datacentre facility in North
More informationThe material in this paper is based upon the law of England and Wales.
DESIGN LIABILITY: REASONABLE SKILL AND CARE OR FITNESS FOR PURPOSE May 2016 ADAM ROBB The material in this paper is based upon the law of England and Wales. This material is only intended to provoke and
More informationPAY NOW, ARBITRATE LATER?
BRIEFING PAY NOW, ARBITRATE LATER? OCTOBER 2018 ENGLISH HIGH COURT HOLDS THAT ONLY MATTERS THAT GO DIRECTLY TO ENFORCEABILITY OF ADJUDICATOR S DECISION WILL FALL WITHIN ARBITRATION AGREEMENT EXCEPTION
More informationDispute Resolution Briefing
Dispute Resolution Briefing August 2014 Contents How enforceable is an obligation to negotiate? Introduction 01 The issue 01 The background facts 02 The decision 03 Conclusion 04 Contacts 05 Introduction
More informationDANGERS OF NOT OBSERVING THE LCIA ARBITRATION RULES
BRIEFING DANGERS OF NOT OBSERVING THE LCIA ARBITRATION RULES MARCH 2018 ENGLISH HIGH COURT FINDS REQUEST FOR ARBITRATION FOR DISPUTES UNDER TWO SEPARATE CONTRACTS INVALID ALSO GIVES USEFUL GUIDANCE ON
More informationFINAL SUPPLY CHAIN SOLUTION LTD TERMS AND CONDITIONS FOR THE SUPPLY OF LOGISTICS SERVICES
SUPPLY CHAIN SOLUTION LTD TERMS AND CONDITIONS FOR THE SUPPLY OF LOGISTICS SERVICES Supply Chain Solution Ltd is not a common carrier and only accepts goods for carriage and/or storage on that condition
More informationContract Law Highlights of 2015
Lunch & Learn Christmas Special 264856 Contract Law Highlights of 2015 14 December 2015 Alistair Maughan, Sue McLean, Sarah Wells, Mercedes Samavi 2014 Morrison & Foerster (UK) LLP All Rights Reserved
More informationCITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY -
CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY - Background I practice in the building and construction industry as a mediator and conciliator, assisting contracted parties in
More informationSTANDARD TERMS AND CONDITIONS FOR SUPPLY OF GOODS AND SERVICES FROM PREMIER PRODUCE SCOTLAND LTD.
STANDARD TERMS AND CONDITIONS FOR SUPPLY OF GOODS AND SERVICES FROM PREMIER PRODUCE SCOTLAND LTD. Table of Contents 1. DEFINITIONS... 1 2. GENERAL... 1 3. PRICE AND PAYMENT... 2 4. SPECIFICATION OF THE
More informationDesign Life Warranties and Fitness for Purpose in Construction Contracts: the Position in Australia and England
May 2016 Practice Group: Real Estate Design Life Warranties and Fitness for Purpose in Construction Contracts: the Position in Australia and England By Sandra Steele, Belinda Montgomery and Julia Kingston
More informationEnforceability of take-or-pay provisions in English law contracts resolved
Journal of Energy & Natural Resources Law, 2016 http://dx.doi.org/10.1080/02646811.2016.1164554 Enforceability of take-or-pay provisions in English law contracts resolved Ben Holland is a partner in the
More informationCOURT OF APPEAL CONFIRMS PAYMENT OF HIRE UNDER TIME CHARTERPARTIES IS NOT A CONDITION
BRIEFING COURT OF APPEAL CONFIRMS PAYMENT OF HIRE UNDER TIME CHARTERPARTIES IS NOT A CONDITION DECEMBER 2016 THE OBLIGATION TO PAY HIRE PUNCTUALLY AND IN ADVANCE IS AN INNOMINATE TERM RATHER THAN A CONDITION
More informationCompany Policies CHEMIDOSE LIMITED. Chemical dosing specialists
Company Policies CHEMIDOSE LIMITED Chemical dosing specialists Unit 1 Centre 2000 St.Michael s Road Sittingbourne Kent ME10 3DZ Tel:01795 425169 www.chemidose.co.uk Chemidose Policies, Terms and Conditions
More informationBRIEFING NIL BY MOUTH? EXCLUDING ORAL VARIATION OF CONTRACTS MAY 2018
BRIEFING NIL BY MOUTH? EXCLUDING ORAL VARIATION OF CONTRACTS MAY 2018 THE UK SUPREME COURT HAS OVERTURNED THE DECISION OF THE COURT OF APPEAL, AND DETERMINED THAT NO ORAL MODIFICATION CLAUSES ARE EFFECTIVE
More informationTime and Construction Contracts
Time and Construction Contracts Extensions of Time and the Prevention Principle By Nathan Abbott Introduction The purpose of this paper is to expose and consider the Prevention Principle from a practical
More informationIntroduction Agreement
Introduction Agreement between Spigo Malta Ltd. and Introducer Table of Contents 1.Interpretation...3 2.Introductions...4 3.Anti-bribery compliance...5 4.Commission and payment...6 5.Obligations of Spigo...8
More informationPenalty Clauses: What is left? Jonathan Owen
Penalty Clauses: What is left? Jonathan Owen The history of the issue 1. Every undergraduate law student has had to grapple with the common law rule against penalty clauses in contracts, in the sense of
More informationMINOR SERVICES AGREEMENT FORM
Agreement Title: Agreement for Agreement Date: Contractor: Address: This Agreement is comprised of: (i) (ii) (iii) (iv) the Minor Services Schedule 1 Special Conditions; Schedule 2 Terms and Conditions;
More informationCARGO CHARTER GENERAL TERMS AND CONDITIONS
CARGO CHARTER GENERAL TERMS AND CONDITIONS 1. DEFINITIONS 1.1. In these Cargo Charter Terms and Conditions capitalised words and expressions have the meanings set out for them below: Cargo Charter Summary
More informationConstruction & Engineering News
Construction & Engineering News Spring 2010 When will the Court pierce the adjudicator s veil? - Geoffrey Osborne Limited v Atkins Rail Limited [2009] (TCC) Enforcing the Oracle SG South Ltd v Swan Yard
More informationRecent Developments in English Contract Law
September 2011 Recent Developments in English Contract Law BY GARRETT HAYES, ROSS MCNAUGHTON & GEORGE WESTON This Stay Current focuses on four significant recent cases in England which may have implications
More informationArbitration 187 This Arbitration was governed by the International Arbitration Act 1974 (Cth). Contract type - GTA FOB Contract No.
Arbitration 187 This Arbitration was governed by the International Arbitration Act 1974 (Cth). Contract type - GTA FOB Contract No. 1 Date of Issue: January 2014 Claimant: & Respondent: Export FOB seller
More informationBusiness Name: Trading Address: Post Code: Nature of Business: How long established: Company Reg. No: Credit limit requested:
BELGRADE INSULATIONS LTD Unit T, Gildersome Spur Industrial Estate Stone Pits Lane, Leeds, West Yorkshire LS27 7JZ Tel: 0113 252 6524 Fax: 0113 253 6540 E-mail: credit.control@belgradeinsulations.com APPLICATION
More informationBANGKOK TO MONTREAL GOING ALL THE WAY? DEVIATION OR DIRECT? MARCH 2015
BRIEFING BANGKOK TO MONTREAL GOING ALL THE WAY? DEVIATION OR DIRECT? MARCH 2015 THAILAND S NEW INTERNATIONAL AIR TRANSPORT ACT WILL COME INTO FORCE ON 16 MAY 2015. THE LAW IS INTENDED TO GIVE EFFECT TO
More informationTERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES
TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES THE CUSTOMER'S ATTENTION IS PARTICULARLY DRAWN TO THE PROVISIONS OF CLAUSE 8 (LIMITATION OF LIABILITY). 1. Interpretation The following definitions and rules
More informationSTANDARD TERMS AND CONDITIONS FOR SUPPLY OF GOODS AND SERVICES. React Computer Partnership Ltd
STANDARD TERMS AND CONDITIONS FOR SUPPLY OF GOODS AND SERVICES OF React Computer Partnership Ltd 1 DEFINITIONS In this document the following words shall have the following meanings: 1.1 "Agreement" means
More informationExamining the current law relating to limitation and causes of action (tortious and contractual) within a construction context
Examining the current law relating to limitation and causes of action (tortious and contractual) within a construction context Received (in revised form): 11th September, 2005 Sarah Wilson is an associate
More informationRe Calibre Solicitors Ltd (in administration) Justice Capital Ltd v Murphy and another (Administrators of Calibre Solicitors Ltd)
Page 1 Judgments Re Calibre Solicitors Ltd (in administration) Justice Capital Ltd v Murphy and another (Administrators of Calibre Solicitors Ltd) [2014] Lexis Citation 259 Chancery Division, Companies
More informationDirectors Duties Handbook
Introduction This handbook has been prepared for directors of private limited companies to provide them with a summary of their duties under the Companies Act 2006 (2006 Act). This guide should not be
More informationTERMS OF REFERENCE. Issued Date: 3 January 2011
TERMS OF REFERENCE Issued Date: 3 January 2011 Last Revised Date: 21 March 2017 List of Revisions Revision No. Revision Date Effective Date Revision 1 23 November 2015 1 December 2015 Revision 2 21 March
More informationTerms and Conditions of Sale
Terms and Conditions of Sale 1. Interpretation 1.1 Van Hessen shall mean Van Hessen UK Casings Ltd and its subsidiaries and the words we, us and our shall have the same meaning. 1.2 Goods shall mean the
More informationDirectors' Duties in Guernsey
Directors' Duties in Guernsey March 2018 1. OVERVIEW 1.1 This note provides a brief synopsis of the common law duties owed by directors of companies ("companies") incorporated in the Island of Guernsey
More informationDeed of Company Arrangement
Deed of Company Arrangement Matthew James Donnelly Deed Administrator David Mark Hodgson Deed Administrator Riverline Enterprises Pty Ltd ACN 112 906 144 (Administrators Appointed) trading as Matera Construction
More informationAA4 submission to the Economic Regulation Authority No. 2: Western Power s proposed standard electricity transfer access contract 8 December 2017
AA4 submission to the Economic Regulation Authority No. 2: Western Power s proposed standard electricity transfer access contract 8 December 2017 DMS# 15104172 Page 1 of 24 Contents A. EXECUTIVE SUMMARY...
More informationGrand Court Approval Of Proceedings Brought By Companies In Liquidation, Litigation Funding Agreements And Contingency Fee Arrangements
28 April 2014 page 1/5 Grand Court Approval Of Proceedings Brought By Companies In Liquidation, Litigation Funding Agreements And Contingency Fee Arrangements In an unreported judgment in ICP Strategic
More informationTERMS AND CONDITIONS
This Contract comprises the Sales Confirmation overleaf and these terms and conditions to the exclusion of all other terms and conditions (including any terms or conditions which Buyer purports to apply
More informationBefore: JUSTICE ANDREW BAKER (In Private) - and - ANONYMISATION APPLIES
If this Transcript is to be reported or published, there is a requirement to ensure that no reporting restriction will be breached. This is particularly important in relation to any case involving a sexual
More informationSection 112 of the HGCR Act is set out below, with the amendments which will be introduced under the LDEDC Act shown in bold:
SUSPENSION OF WORK By Peter Sheridan Introduction The remedy of suspension of work for non-payment or late payment is likely to be of increased interest as the credit crunch and the recession continue
More information1 terms & conditions STAL5/6 AEF.AS
'Literature' means catalogues, pamphlets, price lists and advertising literature provided by us and includes materials on our website. CRYOGENETICS LTD TERMS AND CONDITIONS FOR EQUINE SEMEN STORAGE AND
More informationCMS Commercial Law Group Guide. Distribution and Agency Agreements
CMS Commercial Law Group Guide Distribution and Agency Agreements February 2014 Whilst many aspects of the distribution relationship will be similar when distributing within the EU there are important
More informationRSR LIMITED TERMS AND CONDITIONS OF SUPPLY (GOODS AND SERVICES)
RSR LIMITED TERMS AND CONDITIONS OF SUPPLY (GOODS AND SERVICES) 1. DEFINITIONS In these Conditions: Business Day means a day other than a Saturday, Sunday or public holiday in England when banks in London
More informationATM ACCESS AUSTRALIA LIMITED ATM ACCESS CODE
Effective 1 January 2011 Version 003 ATM ACCESS AUSTRALIA LIMITED ABN 52 130 571 103 A Company limited by Guarantee ATM ACCESS CODE Commencement Date: 3 March 2009 Copyright 2009 ATM Access Australia Limited
More informationAUCKLAND DISTRICT LAW SOCIETY INC. JAMIE WAUGH- BARRISTER TERMS OF ENGAGEMENT
AUCKLAND DISTRICT LAW SOCIETY INC. JAMIE WAUGH- BARRISTER TERMS OF ENGAGEMENT IMPORTANT INFORMATION FOR INSTRUCTING SOLICITORS AND CLIENTS Currently, with limited exceptions, as a barrister I am required
More informationJUDGMENT REPUBLIC OF TRINIDAD AND TOBAGO IN THE HIGH COURT OF JUSTICE CV BETWEEN D. C. DEVELOPERS LIMITED. Claimant AND
REPUBLIC OF TRINIDAD AND TOBAGO IN THE HIGH COURT OF JUSTICE CV2006-02313 BETWEEN D. C. DEVELOPERS LIMITED AND Claimant MANAGEMENT AND CONSTRUCTION CONSULTANTS LIMITED Defendant Before The Honourable Mr.
More informationIMPROVING PAYMENT PRACTICES IN THE CONSTRUCTION INDUSTRY
IMPROVING PAYMENT PRACTICES IN THE CONSTRUCTION INDUSTRY Report of the DTI s post-consultation event held in London on 14th February 2006 On Valentine s Day 2006, the Right Honourable Alun Michael MP compared
More informationPenalty Clauses under Brazilian Law: Is there a common ground with the criteria set forth by Cavendish Square v. Makdessi?
Penalty Clauses under Brazilian Law: Is there a common ground with the criteria set forth by Cavendish Square v. Makdessi? Thiago Moreira Caio Lucas Gabra 1. Introduction Although extensively debated by
More informationDelays. Dr. Mohammad S. El-Mashaleh. Delays
Delays 1 Delays A delay is the time during which some part of the construction project has been extended or not performed due to an unanticipated (or anticipated) circumstance May be caused by any of the
More informationLFMI MEDIA SERVICES LIMITED T/A RUE POINT MEDIA
Dated: September 2017 LFMI MEDIA SERVICES LIMITED T/A RUE POINT MEDIA TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES 1. INTERPRETATION 1.1 THE FOLLOWING DEFINITIONS AND RULES OF INTERPRETATION APPLY IN
More informationTYPES OF MONETARY DAMAGES
TYPES OF MONETARY DAMAGES A breach of contract entitles the non-breaching party to sue for money damages, including: Compensatory Damages: Damages that compensate the non-breaching party for the injuries
More informationUK: Dispute Resolution Briefing
UK: Dispute Resolution Briefing September 2014 Contents A more efficient process 01 Emergency arbitrators 02 Party representation and conduct 03 Governing law 04 Conclusion 04 Contacts 05 Everything changes:
More informationSTANDARD CFA TERMS AND CONDITIONS FOR PERSONAL INJURY CASES TREATED AS ANNEXED TO THE CONDITIONAL FEE AGREEMENT BETWEEN SOLICITOR AND COUNSEL
STANDARD CFA TERMS AND CONDITIONS FOR PERSONAL INJURY CASES TREATED AS ANNEXED TO THE CONDITIONAL FEE AGREEMENT BETWEEN SOLICITOR AND COUNSEL FOR USE AFTER 31 JANUARY 2013 PLEASE NOTE: THESE TERMS WILL
More information(2) (Company Number ) whose correspondence address is at
THIS AGREEMENT is made the 1 BETWEEN (1) BMS Solutions Limited (Company Number6213 700) whose correspondence address is at Regus House, Victory Way, Admirals Park, Dartford, Kent. ( BMS ) (2) (Company
More informationBRIEFING JANUARY 2016
BRIEFING C L E A R E R S K I E S A H E A D : T H E C O U R T O F A P P E A L R E V I E W S T H E E X T E N T O F A M O R T G A G E E S D U T I E S O N S A L E O F A D I S T R E S S E D A S S E T JANUARY
More informationCARBON LINK LTD T/A CPL ACTIVATED CARBONS: CONDITIONS OF SALE
CARBON LINK LTD T/A CPL ACTIVATED CARBONS: CONDITIONS OF SALE 1. GENERAL In these conditions the company means Carbon Link Ltd, trading as CPL Activated Carbons and the customer means the person or company
More information1.2. This book covers the three Agreements published by JBCC (see 2.1 below) and the MBSA 2014 Domestic Subcontract Agreement.
JBCC March 2014 AGREEMENTS 1 2 3 4 5 6 7 Text books available concerning JBCC 2014 General - Contract Documents issued by JBCC Synopsis of important changes JBCC PBA 2007 2014 Contract Data Tender process
More informationTrustmark Licence Agreement
Trustmark Licence Agreement This Agreement is dated as of the Commencement Date Between: (1) Retail Excellence, having its principal place of business at 1 Barrack Street, Ennis, County Clare ("we", "us",
More informationILM Customer Handbook (for ILM Centres and Providers)
ILM Customer Handbook (for ILM Centres and Providers) The essential information you need to work with ILM (incorporating terms, conditions, policies and guidance) Version 4 April 2018 Your Contract with
More informationCommunity Dental Services
Community Dental Services Contents of this chapter: 1. Background to contracting for community dental services 2. How the NHS Act provides for different types of dental contracts 3. General dental services
More informationOil & Gas JOA Defaults: Enforcing Forfeiture Clauses after the Cavendish Square Decision
Oil & Gas JOA Defaults: Enforcing Forfeiture Clauses after the Cavendish Square Decision February 2016 The continuing decline in oil & gas prices has led to increasing numbers of defaults under oil & gas
More informationWhat You Should Know About General Agreements of Indemnity and Why You Should Know It
What You Should Know About General Agreements of Indemnity and Why You Should Know It Summary When a contractor (for purposes of this discussion, contractor includes subcontractor) first seeks surety credit,
More informationGetting ready for Ontario s new Construction Act. Understanding the key changes and how to prepare for them. Howard Krupat
Getting ready for Ontario s new Construction Act Understanding the key changes and how to prepare for them Howard Krupat Getting ready for Ontario s new Construction Act Understanding the key changes and
More informationIN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV BAVERSTOCK DEVELOPMENTS LIMITED Plaintiff
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV 2009-404-004917 BETWEEN AND BAVERSTOCK DEVELOPMENTS LIMITED Plaintiff HOUSING NEW ZEALAND LIMITED Defendant Hearing: 19 November 2009 Appearances:
More informationConditions Precedent to Recovery of Loss and Expense Claims
Conditions Precedent to Recovery of Loss and Expense Claims Dated 07 January 2011 Author Robert Dalton (Head of Construction and Dispute Resolution NW for Blake Newport) Introduction There is a growing
More informationSCHEDULE 10 LENDERS REMEDIES AGREEMENT
SCHEDULE 10 LENDERS REMEDIES AGREEMENT for the Saskatchewan Joint-Use Schools Project # 2 HER MAJESTY THE QUEEN IN RIGHT OF THE PROVINCE OF SASKATCHEWAN COMPUTERSHARE TRUST COMPANY OF CANADA, AS INDENTURE
More informationGENERAL TERMS AND CONDITIONS FOR THE SUPPLY OF GOODS AND SERVICES
GENERAL TERMS AND CONDITIONS FOR THE SUPPLY OF GOODS AND SERVICES 1 Interpretation 1.1 Definitions. In these Conditions, the following definitions apply: Business Day means a day (other than a Saturday,
More informationA LITIGATOR S GUIDE TO DAMAGES January 17, 2017 CONTRACT DAMAGES. *With special thanks to Lesley Campbell, Student-at-Law OVERVIEW
A LITIGATOR S GUIDE TO DAMAGES January 17, 2017 CONTRACT DAMAGES Harvin D. Pitch / Jennifer J. Lake *With special thanks to Lesley Campbell, Student-at-Law OVERVIEW 1. Specific Performance & Mitigation
More informationMutual Indemnity and Hold Harmless Deed
Mutual Indemnity and Hold Harmless Deed THIS DEED is made the...day of... 20... WHEREAS A. Each of the Signatories may perform Services. B. The Signatories wish to enter into this Deed to create between
More informationBusiness Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business.
Geldbach UK Ltd The customer's attention is drawn in particular to the provisions of clause 9. 1. INTERPRETATION 1.1 Definitions. In these Conditions, the following definitions apply: Business Day: a day
More informationTERMS AND CONDITIONS OF SALES
1. Acceptance No Contract, Order or information (literature, drawings etc.) provided to or by the Purchaser shall be binding on Infra Green Ltd unless confirmed in the Infra Green Ltd Order Confirmation.
More information(THIS FORM HAS 7 PAGES AND MUST BE COMPLETED IN FULL)
PRIME INDUSTRIAL PRODUCTS PTY LTD ACN 131 559 772 69 CRAIGIE STREET, PO BOX 5003 BUNBURY WESTERN AUSTRALIA 6230 PHONE: 08 9780 1111 FAX: 08 9726 0399 EMAIL: admin@primesupplies.com.au 30 DAY CREDIT ACCOUNT
More informationSTANDARD TERMS AND CONDITIONS FOR THE PURCHASE OF GOODS. 1. Application
STANDARD TERMS AND CONDITIONS FOR THE PURCHASE OF GOODS 1. Application The Buyer orders and the Supplier, by accepting the Order, agrees that it will supply the Goods specified and subject to these Conditions
More informationLiability: A conclusion for exclusion?
Liability: A conclusion for exclusion? Nick Lees explains key cases on exclusion clauses and offers some practical advice Walker Morris LLP 0 SHARES The ability to pre-emptively exclude or limit future
More informationPARADISE TIMBERS PTY LTD APPLICATION FOR COMMERCIAL CREDIT
PARADISE TIMBERS PTY LTD ABN 41 010 596 353 P O Box 3230 HELENSVALE TOWN CENTRE QLD 4212 128 Millaroo Drive GAVEN QLD 4211 Accounts: accounts@paradise-timbers.com.au Sales: sales@paradise-timbers.com.au
More informationFOR USE AFTER 1 NOVEMBER
APIL / PIBA 6 STANDARD TERMS AND CONDITIONS POSTED ON THE APIL AND PIBA WEBSITES AND TREATED AS ANNEXED TO THE CONDITIONAL FEE AGREEMENT BETWEEN SOLICITOR AND COUNSEL FOR USE AFTER 1 NOVEMBER 2005 INDEX
More informationConsidering Contract Termination Under English Common Law
Portfolio Media. Inc. 111 West 19 th Street, 5th Floor New York, NY 10011 www.law360.com Phone: +1 646 783 7100 Fax: +1 646 783 7161 customerservice@law360.com Considering Contract Termination Under English
More informationLumiere London Limited Terms & Conditions
Lumiere London Limited Terms & Conditions Date: 07/09/2016 Lumiere London Limited - Terms & Conditions 1. INTERPRETATION 1.1 Definitions. In these Terms & Conditions, the following definitions apply: Business
More informationTRADING TERMS OF KLINGER LTD
1. INTERPRETATION 1.1 In these terms of trade: (1) Business Day means a day other than Saturday, Sunday or a public holiday in the place in which a document is received or an act is done, as may be applicable;
More informationWassenaar v. Towne Hotel 111 Wis. 2d 518, 331 N.W.2d 357 (1983)
Wassenaar v. Towne Hotel 111 Wis. 2d 518, 331 N.W.2d 357 (1983) This court granted the employee's petition for review limiting the issue on review to whether the clause in the employment contract stipulating
More informationCOMMUNITY INFRASTRUCTURE LEVY. Scott Lyness. Landmark Chambers 1
COMMUNITY INFRASTRUCTURE LEVY Scott Lyness Landmark Chambers 1 Introduction: what is the Community Infrastructure Levy (CIL)? 1. CIL is a tax on development introduced by the Planning Act 2008 to fund
More informationSTANDARD TERMS AND CONDITIONS FOR THE SUPPLY OF GOODS AND SERVICES
. DEFINITIONS: In this document the following words shall have the following meanings: 1.1 "Agreement" means these Terms and Conditions; 1.2 "Customer" means the organisation or person who purchases goods
More informationGuidance Notes to the Master Securities Forward Transaction Agreement December 2012 Version
Guidance Notes to the Master Securities Forward Transaction Agreement December 2012 Version The Securities Industry and Financial Markets Association (the Association ) has prepared a revised version of
More informationSUPREME COURT OF QUEENSLAND
SUPREME COURT OF QUEENSLAND CITATION: PARTIES: David & Gai Spankie & Northern Investment Holdings Pty Limited v James Trowse Constructions Pty Limited & Ors [2010] QSC 29 DAVID & GAI SPANKIE & NORTHERN
More informationWebsite Disclaimer. by SEQ Legal
Website Disclaimer by SEQ Legal Website disclaimer 1 (1) Introduction This disclaimer governs your use of our website; by using our website, you accept this disclaimer in full. 2 If you disagree with any
More informationSKRINE BREACH OF CONTRACT: TERMINATION AND OTHER OPTIONS. 10 December LEE SHIH ADVOCATES & SOLICITORS
SKRINE ADVOCATES & SOLICITORS BREACH OF CONTRACT: TERMINATION AND OTHER OPTIONS 10 December 2013 - LEE SHIH 1 SUMMARY OF PART TWO Issues to consider when deciding to terminate Contractual or common law
More informationEXAMINATION OF GOVERNANCE FOR COLLECTIVE INVESTMENT SCHEMES
EXAMINATION OF GOVERNANCE FOR COLLECTIVE INVESTMENT SCHEMES PART II Independence Criteria, Empowerment Conditions and Functions to be performed by the Independent Oversight Entities FINAL REPORT A Report
More informationincorporate, or which are implied by trade, custom, practice or course of dealing.
CUSTOMER TERMS AND CONDITIONS 1. INTERPRETATION 1.1 Definitions. Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business. Conditions: the terms
More informationDEFENCES TO ENFORCEMENT OF FOREIGN JUDGMENTS AND AWARDS IN ENGLAND
DEFENCES TO ENFORCEMENT OF FOREIGN JUDGMENTS AND AWARDS IN ENGLAND 1. Sovereign immunity as a defence to enforcement of foreign judgments and awards in England. Overview Sovereign immunity derives from
More informationGUARANTEE AND INDEMNITY
(1) INSPIRED ASSET MANAGEMENT limited (2) MORE GROUP CAPITAL SERVICES LIMITED DATED 2018 GUARANTEE AND INDEMNITY Salisbury House London Wall London EC2M PS Tel: 020 738 9271 Fax: 020 728 72 Ref: CBA/AC/GRM1.1
More informationA Summary of Construction Cases in 2012
A Summary of Construction Cases in 2012 Formation of Contract Specialist Insulation Limited v Pro-Duct (Fife) Limited Each party proceeds on the basis that their standard form of contract regulates the
More informationAccenture Purchase Order Terms and Conditions. Accenture shall mean Accenture Japan Ltd or an Affiliate Company as defined below.
Accenture Purchase Order Terms and Conditions Accenture shall mean Accenture Japan Ltd or an Affiliate Company as defined below. Affiliate Company shall mean any Accenture entity, whether incorporated
More informationDischarge of Contract Performance, Breach, Frustration Introduction
Discharge of Contract Performance, Breach, Frustration Introduction Discharge of a valid contract involves the process under which the primary (performance) obligations come to an end. Discharge by breach
More informationTERMS OF TRADING AGREEMENT
Incorporating KAILIS BROS Pty Ltd (ACN 008 723 000), NATIONAL FISHERIES Pty Ltd (ACN 009 412 382), TRILOR Pty Ltd (ACN 008 877 290) and CENVILL PTY LTD (ACN 009 013 843). Operating Address: 23 CATALANO
More informationPersonal Information has been redacted from this document under Section 40 of the Freedom of Information (FOI) Act.
FREEDOM OF INFORMATION REDACTION SHEET SUMMERHILL ACADEMY SUPPLEMENTAL AGREEMENT Exemptions in full n/a Partial exemptions Personal Information has been redacted from this document under Section 40 of
More information1. Corporation. and. 2. Licensee. Background
Mobile Hydrant Standpipe Licence Agreement This Hydrant Standpipe Licence Agreement is made on the date that the Licensee submits the Application to the Corporation and is between the following parties:
More informationPurchase Agreement TERMS AND CONDITIONS PRICES PAYMENT AND PAYMENT TERMS. Bright Ideas. Better Solutions. Benchmark is Branch Automation.
Purchase Agreement The following terms and conditions shall apply to the sale of goods or products ( goods or products ) associated with your invoice: TERMS AND CONDITIONS The obligations and rights of
More informationMarch 2016 INVESTOR TERMS OF SERVICE
March 2016 INVESTOR TERMS OF SERVICE This Agreement is between you and Financial Pulse Limited and sets out the terms on which Financial Pulse offers you access to and use of certain services via the online
More informationAPPLICATION FOR COMMERCIAL CREDIT ACCOUNT TRADING TERMS AND CONDITIONS
APPLICATION FOR COMMERCIAL CREDIT ACCOUNT TRADING TERMS AND CONDITIONS These Trading Terms and Conditions are to be read and understood prior to the execution of the Application for Commercial Credit Account.
More informationNOTICES, TIME BARS AND PROPORTIONALITY
NOTICES, TIME BARS AND PROPORTIONALITY A talk by Sir Rupert Jackson to the Hong Kong Society of Construction Law on 21 st September 2018 CONTENTS 1. Introduction 2. Notice provisions 3. A conundrum 4.
More information