FIDIC contracts Claims and disputes under international construction contracts. Claims and dispute resolution procedures under FIDIC contracts

Size: px
Start display at page:

Download "FIDIC contracts Claims and disputes under international construction contracts. Claims and dispute resolution procedures under FIDIC contracts"

Transcription

1 FIDIC contracts Claims and disputes under international construction contracts Istanbul 29 th March 2016 Claims and dispute resolution procedures under FIDIC contracts 1. Introduction I am very pleased to be able to present to you today. As you may have seen from the brochure, my experience extends over quite a few years and numerous international projects as well as using different forms of Contract In addition, I have been fortunate enough to be chosen as a Dispute Board Adjudicator under sundry FIDIC Contracts and also appointed as one of the FIDIC President s List of Dispute Adjudicators My presentation this afternoon will deal only with FIDIC forms of contract and procedures. There are presentations later by others covering ICC Dispute Board Rules, and I very much look forward to listening to those presenters. 2. What is a claim? 2.1 Under FIDIC and most other construction contracts, a Claim is a contractual right. It applies equally to the Contractor and to the Employer. Not as I had recently, the Engineer trying to claim against the Contractor on behalf of the Employer. 2.2 Sub-Clause 20.1 sets out the procedure to be followed by the Contractor and the Engineer and begins by saying: If the Contractor considers himself to be entitled to any extension of the Time for Completion and/or any additional payment under any Clause off these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Engineer describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance 2.3 Thus, it seems evident that the Contractor may claim for an extension to the Time for Completion; he may claim for additional Costs, all of which I m sure you are familiar with. Of course, when making an application for an Interim Payment Certificate, he is also making a claim, but the procedure under Sub-Clause 20.1 does not apply, unless the application is, in the view of the Contractor, wrongfully certified by the Engineer. 2.4 He, the Contractor, might also claim for other issues such as the Engineer mal-administered the Contract; the Commencement Date set by the Engineer is totally different from that imparted at Tender Stage;

2 The Engineer has been told by the Employer not to do something (like issue a fair determination under Sub-Clause 3.5). 2.5 However, just because there is a claim made does not mean the claim is valid. The Engineer has to play his part in assessing the fully detailed particulars of the claim and respond with approval or disapproval and detailed comments on the principle of the claim. 2.6 The Employer, may also make a claim. The procedure to be followed is set out in Sub- Clause 2.5 and states: If the Employer consider himself to be entitled to any payment under any Clause of these Conditions or otherwise in connection with the Contract, and/or to any extension of the Defects Notification Period, the Employer or the Engineer shall give notice and particulars to the Contractor. However,... The notice shall be given as soon as practicable after the Employer became aware of the event or circumstances giving rise to the claim. The Engineer shall then proceed in accordance with Sub-Clause 3.5 to agree or determine 2.7 What about in connection with the Contract. Would such a matter as removal of the Contractor s Representative constitute such a claim? 3. Notices 3.1 Of course, as you will no doubt know, there are notice provisions scattered throughout the various sub-clauses and particularly in respect of notices to be given by the Contractor under Sub Clause 20.1 the infamous Time-Bar. 3.2 So, does Sub-Clause 20.1 really mean, that if a notice is later than 28 days, even by one day, that the Contractor is not entitled to an extension to the Time for Completion or to additional payment? 3.3 Many arguments of course as to what is the aware date. 3.4 What if any other notices are not given as required by Sub Clause 20.1? What if the fully detailed particulars are not provided within the prescribed time given in Sub-Clause No such Time Bar if the Employer fails to give Notice, even though in FIDIC MDB it says within 28 days of the aware date. However, it seems that as long as a notice to extend the Defects Notification Period is given before the expiry of the period at that time then there is no other default provision. 4. Particulars 4.1 So, what particulars are required under FIDIC?

3 4.2 Firstly, the Contractor s claim must be fully detailed and must be accompanied by full supporting particulars of the basis of the claim and of the extension and/or additional payment claimed. 4.3 Secondly, the claim should be supported by contemporaneous records. Contemporaneous means records made at, or very close, to the time of the event or circumstance giving rise to the claim. 4.4 Provision of further (and better) particulars. Should the Claimant be assisted by the Engineer or the DAB(DB) by asking for better particulars? 4.5 The Employer in making a claim only has to give particulars. Although the MDB Version does say they should give the Clause or other basis of the claim and include substantiation of the amount and/or extension to which the Employer considers himself entitled. In the instance of removal of the Contractor s Representative, what if there is no monetary or time compensation? 4.6 In the latter instance it seems to me the Engineer might need to be a brave man/woman to reject his/her Employer s claim if such details are missing. 5. What is a Dispute? 5.1 There are many descriptions and definitions of a Dispute. 5.2 FIDIC (in the Gold Book) states in Sub Clause Dispute means any situation where (a) one Party makes a claim against the other Party and (b) the other Party rejects the claim in whole or in part; and (c) the first Party does not acquiesce, provided however that a failure by the other Party to oppose or respond to the claim, in whole or in part, may constitute a rejection if, in the circumstances the DAB or arbitrator as the case may be, deem it reasonable for it to do so. A Dictionary definition: Any statement, complaint, request, allegation or claim, which has been rejected and the rejection is not acceptable to the person who made the original statement, complaint, request, allegation or claim. 5.3 How do Disputes arise? Poor/wrong strategy Poor Communications structure Oral/verbal instructions Misunderstanding of the terms and conditions

4 Parties become entrenched Parties do not speak to each other Contract avoidance Inability to pay Unrealistic time-scales Broken promises Poor Contract administration Non-resolution of claims And so on. 6. What is the FIDIC process for resolution? 6.1 Essentially, 5 stages of resolution available to the parties. 1) Agreement 2) Determination by the Engineer/Employer s Representative Sub Clause 3.5. It is very often forgotten (conveniently) that the parties MUST give effect to the Engineer s decision. 3) Decision by a Dispute Adjudication Board A binding decision to be complied with whether a notice of dissatisfaction is given or not. 4) Amicable Settlement 5) Arbitration Award Final and Binding. The Ultimate Step or is it? 7. The Appointment Process 7.1 I will refer only to the Standing Board situation such as in CONS (Red) or MDB (Pink) but am perfectly willing to answer questions on the P & DB (Yellow) and other Ad-Hoc types. 7.2 The Dispute (Adjudication) Board [Board] appointment process is set out in Sub-Clause 20.2, and is intended to be a consensual process. The Employer in the Tender documents sets out the composition of the Board of suitably qualified persons either one or three. The default number is three. 7.3 The Sub-Clause goes on to say that: If the Board is to comprise three persons then each Party shall nominate one member for the approval of the other Party. The Parties shall consult both these members and shall agree upon a third member, who shall be appointed to act as chairman. However, if a list of potential members is included in the Contract, the members shall be selected from those on the list

5 7.4 The appointment of a sole member is not dealt with explicitly, but it must be implied that the Parties must agree on who that one person is to be. Maybe, this is where a list of potential members willing and able to act as a sole Board, could be advantageous. However, it needs consideration prior to going to tender. 8. Do Dispute Boards work? Statistics 8.1 Although some ten years ago now, the DRBF conducted some research and reported in 2006 that: 98% of disputes referred to dispute boards concluded the matter Of the remaining 2% which were referred to arbitration/courts, at least half upheld the DB decision. Therefore, only 1% of disputes referred to a DB were overturned. 8.2 At a conference, about 4 years ago, in Australia it was confirmed that: No cases in Australia referred to a DB had been passed on to arbitration/litigation. 8.3 My own opinion is that: provided the Board (1 or 3 person) is properly considered and formed early enough, then it has a good prospect of success; if the parties want it to work it will work; success breeds success 8.4 To answer my own question - Do they work? I believe that, in the main, they do. 9. Advantages DB become part of the Team Provide Real Time value Provide a form of insurance Knowledge gained from experts Standing Boards have knowledge of the project from their regular site visits Prevent claims becoming disputes Decision on dispute given within 84 days Cheaper than arbitration/litigation They can provide opinions if requested by both parties Less formal proceedings Impartial and independent A dispute avoidance ethos. The decision is binding upon the parties for the time being and becomes final and binding if no Notice of Dissatisfaction within 28 days after receiving the decision

6 10. Disadvantages Generally, one of perception Why have another tier of dispute resolution we have the CA? Another project cost but can you afford not to have a Dispute Board? A poorly formed DB. 11. Suggestions 11.1 Provision for Succession Planning by inviting the parties to include graduates and the like to attend site visits and hearings should they arise 11.2 Maybe some means of removing the uncertainty of fees for example inserting in the Particular Conditions Maybe as a set percentage related to the Contract Amount DO YOU HAVE ANY SUGGESTIONS? THANK YOU Malcolm Kelly mkresolve@gmail.com or malcolm_k100@hotmail.com

COMPARISON TABLE OF DISPUTE BOARD RULES

COMPARISON TABLE OF DISPUTE BOARD RULES COMPARISON TABLE OF DISPUTE BOARD RULES Glossary: AAA American Arbitration Association CDB Combined Dispute Board DAB Dispute Adjudication Board DB Dispute Board DRBF Dispute Resolution Board Foundation

More information

Evolution of dispute resolution under the FIDIC Red Book. Bill Smith, Partner 10 May 2018

Evolution of dispute resolution under the FIDIC Red Book. Bill Smith, Partner 10 May 2018 Evolution of dispute resolution under the FIDIC Red Book Bill Smith, Partner 10 May 2018 Outline Disputes why a dispute resolution procedure is needed How the dispute resolution provisions in the FIDIC

More information

THE NEW ENGINEERING CONTRACT FOURTH EDITION (NEC4)

THE NEW ENGINEERING CONTRACT FOURTH EDITION (NEC4) THE NEW ENGINEERING CONTRACT FOURTH EDITION (NEC4) Author: Tsele Moloi THE NEW ENGINEERING CONTRACT FOURTH EDITION (NEC4): SOME INTERESTING DEVELOPMENTS The NEC suite of contracts have been updated and

More information

USING DISPUTES BOARDS THE ROMANIAN EXPERIENCE ON DISPUTE BOARDS

USING DISPUTES BOARDS THE ROMANIAN EXPERIENCE ON DISPUTE BOARDS Giovanni Di Folco USING DISPUTES BOARDS THE ROMANIAN EXPERIENCE ON DISPUTE BOARDS Other articles written by the same author: Enforcement of a DAB decision through an ICC partial award; (co-author Mark

More information

Arbitral tribunals; Decisions; Dispute adjudication boards; Enforcement; FIDIC forms of contract; Jurisdiction; Singapore

Arbitral tribunals; Decisions; Dispute adjudication boards; Enforcement; FIDIC forms of contract; Jurisdiction; Singapore An Excellent Decision From Singapore Which Should Enhance the Enforceability of Decisions of Dispute Adjudication Boards the Second Persero Case before the Court of Appeal Christopher R Seppälä * Arbitral

More information

The Gap in Sub-Clause 20.7 of The 1999 FIDIC Contracts for Major Works

The Gap in Sub-Clause 20.7 of The 1999 FIDIC Contracts for Major Works The Gap in Sub-Clause 20.7 of The 1999 FIDIC Contracts for Major Works by Nael G. Bunni, BSc, MSc, PhD, CEng, FICE, FIEI, FIStructE, FCIArb, FIAE, MConsEI. Chartered Engineer, Conciliator & Registered

More information

Chapter 10. A Note on Dispute Boards. Chapter 10

Chapter 10. A Note on Dispute Boards. Chapter 10 A Note on Dispute Boards Whilst this book is primarily concerned with the preparation and review of claims, it is also appropriate to consider what happens in situations where the parties cannot agree

More information

ADR in FIDIC Contracts and the Cyprus perspective

ADR in FIDIC Contracts and the Cyprus perspective ADR in FIDIC Contracts and the Cyprus perspective Alternative Dispute Resolution (ADR) in the Construction Industry: History Advantages and Disadvantages 1 Eur. Ing. Platonas Stylianou B.Eng. (Hons), MSc,

More information

DAAB and Dispute Resolution Under the 2017 FIDIC Forms of Contract

DAAB and Dispute Resolution Under the 2017 FIDIC Forms of Contract DAAB and Dispute Resolution Under the 2017 FIDIC Forms of Contract Eugenio Zoppis PhD Researcher, Centre for Construction Law and Dispute Resolution King s College, London Abstract This article has been

More information

FIDIC Dispute Adjudication Boards

FIDIC Dispute Adjudication Boards 1. Under the Pink Book, the Multilateral Development Banks version of the Red Book, if the parties have not jointly appointed the Dispute Board 21 days after the date stated in the Contract Data, and the

More information

FIDIC SUITE OF CONTRACTS 2017 NEW DISPUTE RESOLUTION REGIMES 21 March 2018

FIDIC SUITE OF CONTRACTS 2017 NEW DISPUTE RESOLUTION REGIMES 21 March 2018 FIDIC SUITE OF CONTRACTS 2017 NEW DISPUTE RESOLUTION REGIMES 21 March 2018 Paula Boast, Partner, Head of Construction Engineering & Projects Middle East 3 rd INTERNATIONAL ARBITRATION CONFERENCE ARBITRATION

More information

A DAB Decision between the Notice of Dissatisfaction and the Enforcement in ICC Arbitration

A DAB Decision between the Notice of Dissatisfaction and the Enforcement in ICC Arbitration A DAB Decision between the Notice of Dissatisfaction and the Enforcement in ICC Arbitration Oana Soimulescu Partner, Soimulescu & Soltan, Bucharest 1 I. Introduction A lot has been said about the issue

More information

REQUEST FOR ARBITRATION

REQUEST FOR ARBITRATION IN THE MATTER OF AN ARBITRATION UNDER THE RULES OF THE INTERNATIONAL COURT OF ARBITRATION OF THE INTERNATIONAL CHAMBER OF COMMERCE BETWEEN: [NAME OF CLAIMANT] (CLAIMANT) -AND- [NAME OF RESPONDENT] (RESPONDENT)

More information

AN OUNCE OF PREVENTION IS WORTH A POUND OF CURE - Benjamin Franklin. Gordon L. Jaynes 24 May 2018

AN OUNCE OF PREVENTION IS WORTH A POUND OF CURE - Benjamin Franklin. Gordon L. Jaynes 24 May 2018 AN OUNCE OF PREVENTION IS WORTH A POUND OF CURE - Benjamin Franklin Gordon L. Jaynes Glj4law@aol.com 24 May 2018 Inspired by the image of Mount Fuji, the slogan of this year s DRBF International Conference

More information

Statute of limitation in FIDIC contracts concluded in the public procurement procedures

Statute of limitation in FIDIC contracts concluded in the public procurement procedures NEW PERSPECTIVES IN IN CONSTRUCTION LAW Statute of limitation in FIDIC contracts concluded in the public procurement procedures Zaira Andra BAMBERGER Lawyer - SCA Margarit Florov and Partners Bucharest

More information

Below are standard clauses for use by parties who wish to set up and operate a dispute board under the Rules contained in this booklet.

Below are standard clauses for use by parties who wish to set up and operate a dispute board under the Rules contained in this booklet. STANDARD ICC DISPUTE BOARD CLAUSES 05 standard icc dispute board clauses Below are standard clauses for use by parties who wish to set up and operate a dispute board under the Rules contained in this booklet.

More information

LIMITATIONS AND CONSTRAINTS IMPOSED BY ROMANIAN LAW ON FIDIC CONDITIONS OF CONTRACT A CONTRACTOR S DILEMMA WHILE PERFORMING PUBLIC WORKS IN ROMANIA

LIMITATIONS AND CONSTRAINTS IMPOSED BY ROMANIAN LAW ON FIDIC CONDITIONS OF CONTRACT A CONTRACTOR S DILEMMA WHILE PERFORMING PUBLIC WORKS IN ROMANIA GIOVANNI DI FOLCO LIMITATIONS AND CONSTRAINTS IMPOSED BY ROMANIAN LAW ON FIDIC CONDITIONS OF CONTRACT A CONTRACTOR S DILEMMA WHILE PERFORMING PUBLIC WORKS IN ROMANIA Key aspects that Contractors, while

More information

An Engineer s / Dispute Adjudication Board s Decision Is Enforceable By An Arbitral Award

An Engineer s / Dispute Adjudication Board s Decision Is Enforceable By An Arbitral Award December 2009 Contrary to widespread belief, a binding but not final decision of an Engineer under the FIDIC Conditions is enforceable by an arbitral award, in appropriate circumstances. This has been

More information

THE ICC S NEW DISPUTE BOARD RULES. CARROLL S DORGAN Jones Day Paris

THE ICC S NEW DISPUTE BOARD RULES. CARROLL S DORGAN Jones Day Paris THE ICC S NEW DISPUTE BOARD RULES CARROLL S DORGAN Jones Day Paris This article has been reproduced with the permission of the publisher and originally appeared in Volume 22, Part 2 of The International

More information

Arbitration rules. International Chamber of Commerce. The world business organization

Arbitration rules. International Chamber of Commerce. The world business organization Arbitration and adr rules International Chamber of Commerce The world business organization International Chamber of Commerce (ICC) 38, Cours Albert 1er, 75008 Paris, France www.iccwbo.org ICC 2001, 2011

More information

Multi-Tier Dispute Resolution Clauses Definition and Examples

Multi-Tier Dispute Resolution Clauses Definition and Examples ! Multi-Tier Dispute Resolution Clauses Definition and Examples ASA Conference of September 15, 2017 Henry Peter Stefanie Pfisterer Overview of Bundle I. Examples of Multi-Tier Dispute Resolution Clauses...

More information

The legal justification for the enforcement of a binding DAB decision under the FIDIC 1999 Red Book

The legal justification for the enforcement of a binding DAB decision under the FIDIC 1999 Red Book The legal justification for the enforcement of a binding DAB decision under the FIDIC 1999 Red Book Taner Dedezade Corbett & Co International Construction Lawyers Ltd, London In a previous article, the

More information

Singapore Court Should Not Have Set Aside ICC Award Enforcing Dispute Adjudication Board Decision

Singapore Court Should Not Have Set Aside ICC Award Enforcing Dispute Adjudication Board Decision MEALEY S TM International Arbitration Report Singapore Court Should Not Have Set Aside ICC Award Enforcing Dispute Adjudication Board Decision by Chris Seppälä White & Case LLP Paris A commentary article

More information

Making an Effective and Persuasive Case to a Dispute Board

Making an Effective and Persuasive Case to a Dispute Board Making an Effective and Persuasive Case to a Dispute Board Simon Longley, Partner, HKA MAKING AN EFFECTIVE AND PERSUASIVE CASE TO A DISPUTE BOARD This paper is based on my involvement with some 100 referrals

More information

Dispute Resolution in Romania - Before and After Accession to the European Union

Dispute Resolution in Romania - Before and After Accession to the European Union International In-house Counsel Journal Vol. 2, No. 6, Winter 2009, 935 939 Dispute Resolution in Romania - Before and After Accession to the European Union ANDREEA CHIRITA Legal Counsel, Ministry of Economy

More information

ICC Rules of Conciliation and Arbitration 1975

ICC Rules of Conciliation and Arbitration 1975 ICC Rules of Conciliation and Arbitration 1975 (in force as from 1st June 1975) Optional Conciliation Article 1 (ADMINISTRATIVE COMMISSION FOR CONCILIATION. CONCILIATION COMMITTEES) 1. Any business dispute

More information

FOREIGN TRADE ARBITRATION LAW. Chapter I General provisions

FOREIGN TRADE ARBITRATION LAW. Chapter I General provisions Article 1. Purpose of the Law FOREIGN TRADE ARBITRATION LAW Chapter I General provisions The purpose of this Law is to regulate relations pertaining to arbitral proceedings of suits brought by a citizen

More information

FIDIC Conditions of Contract for Construction

FIDIC Conditions of Contract for Construction FIDIC Conditions of Contract for Construction 1 1 General Provisions 2 1 1.1 Definitions 1.1.1 The Contract Contract means the Contract Agreement, the Letter of Acceptance, the Letter of Tender, these

More information

NOTICE OF ARBITRATION

NOTICE OF ARBITRATION IN THE MATTER OF AN ARBITRATION UNDER THE HONK KONG INTERNATIONAL ARBITRATION CENTRE ADMINISTERED ARBITRATION RULES BETWEEN: [NAME OF CLAIMANT] (CLAIMANT) -AND- [NAME OF RESPONDENT] (RESPONDENT) NOTICE

More information

ARBITRATION RULES MEDIATION RULES

ARBITRATION RULES MEDIATION RULES ARBITRATION RULES MEDIATION RULES International Chamber of Commerce (ICC) 33-43 avenue du Président Wilson 75116 Paris, France www.iccwbo.org Copyright 2011, 2013 International Chamber of Commerce (ICC)

More information

Annual Review of English Construction Law Developments. An international perspective

Annual Review of English Construction Law Developments. An international perspective Annual Review of English Construction Law Developments An international perspective June 2018 Contents 3 Introduction 5 The FIDIC 2017 Suite 15 Contract splitting in international construction projects

More information

The Construction Act of Ontario

The Construction Act of Ontario The Construction Act of Ontario What Does it Mean for Industry Stakeholders? Presented By BLG These materials are designed to provide information only and although prepared by professionals, do not constitute

More information

REQUEST FOR ARBITRATION

REQUEST FOR ARBITRATION IN THE MATTER OF AN ARBITRATION UNDER THE ARBITRATION RULES OF THE LONDON COURT OF INTERNATIONAL ARBITRATION BETWEEN: [NAME OF CLAIMANT] (CLAIMANT) -AND- [NAME OF RESPONDENT] (RESPONDENT) REQUEST FOR ARBITRATION

More information

NOTICE OF ARBITRATION

NOTICE OF ARBITRATION IN THE MATTER OF AN ARBITRATION UNDER THE ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE BETWEEN: [NAME OF CLAIMANT] (CLAIMANT) -AND- [NAME OF RESPONDENT] (RESPONDENT) NOTICE OF ARBITRATION

More information

1) ICC ADR proceedings are flexible and party-controlled to the greatest extent possible.

1) ICC ADR proceedings are flexible and party-controlled to the greatest extent possible. Guide to ICC ADR Contents Part 1: Introduction... 1 Characteristics of ICC ADR... 1 Overview of the Rules... 2 Part 2: Analysis of the ICC ADR Rules... 3 Preamble... 3 Article 1: Scope of the ICC ADR Rules...

More information

2012 ICC Rules 1998 ICC Rules. Article 1

2012 ICC Rules 1998 ICC Rules. Article 1 2012 ICC Rules 1998 ICC Rules Article 1 International Court of Arbitration 1 The International Court of Arbitration (the "Court") of the International Chamber of Commerce (the "ICC") is the independent

More information

Dispute Board Rules. in force as from 1 September Standard ICC Dispute Board Clauses. Model Dispute Board Member Agreement

Dispute Board Rules. in force as from 1 September Standard ICC Dispute Board Clauses. Model Dispute Board Member Agreement Dispute Board Rules in force as from September 004 with Standard ICC Dispute Board Clauses Model Dispute Board Member Agreement International Chamber of Commerce 8 cours Albert er 75008 Paris - France

More information

TENNIS AUSTRALIA DISCIPLINARY POLICY

TENNIS AUSTRALIA DISCIPLINARY POLICY TENNIS AUSTRALIA DISCIPLINARY POLICY Contents... 1 1. Application and Administration... 3 2. Categories of Offences... 4 3. Minor offences... 6 4. Serious offences... 7 5. Appeals procedures... 11 Notice

More information

IMechE Seminar Arbitration & Engineering

IMechE Seminar Arbitration & Engineering IMechE Seminar Arbitration & Engineering Presented by Man Sing Yeung FHKIS, FRICS, FCIArb Chartered Arbitrator Accredited Mediator/Adjudicator, Solicitor, Partner of Li & Partners Arbitration & Engineering

More information

RULES FOR EXPEDITED ARBITRATION. of the Finland Chamber of Commerce

RULES FOR EXPEDITED ARBITRATION. of the Finland Chamber of Commerce RULES FOR EXPEDITED ARBITRATION of the Finland Chamber of Commerce RULES FOR EXPEDITED ARBITRATION of the Finland Chamber of Commerce The English text prevails over other language versions. TABLE OF CONTENTS

More information

Security of payment under FIDIC contracts: more secure, for now

Security of payment under FIDIC contracts: more secure, for now INSIGHT Security of payment under FIDIC contracts: more secure, for now January 28, 2015 Written by Eugene Tan, Tia Starey and Rupert Coldwell The High Court of Singapore recently handed down an important

More information

11th. Edition The Baker McKenzie International Arbitration Yearbook. Turkey

11th. Edition The Baker McKenzie International Arbitration Yearbook. Turkey 11th Edition 2017-2018 The Baker McKenzie International Arbitration Yearbook Turkey 2018 Arbitration Yearbook Turkey Turkey Ismail G. Esin, 1 Ali Selim Demirel 2 and Yigitcan Bozoglu 3 A. Legislation and

More information

DRAFTING AND INTERPRETING GOVERNING LAW AND JURISDICTION CLAUSES A PRACTICAL GUIDE

DRAFTING AND INTERPRETING GOVERNING LAW AND JURISDICTION CLAUSES A PRACTICAL GUIDE DRAFTING AND INTERPRETING GOVERNING LAW AND JURISDICTION CLAUSES A PRACTICAL GUIDE 1. Introduction 2. Governing law a. Guide to governing law clauses b. Choosing a governing law 3. Jurisdiction a. Litigation

More information

New Expert Rules launched by the ICC

New Expert Rules launched by the ICC Colin Johnson, Head of International Arbitration in the Forensic team Grant Thornton UK LLP Barry Fletcher, Solicitor, and Dispute Resolution A division of Reed Elsevier (UK) Ltd. Registered office 1-3

More information

Arbitration Act 1996

Arbitration Act 1996 Arbitration Act 1996 An Act to restate and improve the law relating to arbitration pursuant to an arbitration agreement; to make other provision relating to arbitration and arbitration awards; and for

More information

CONSTRUCTION BRIEFING November 2016

CONSTRUCTION BRIEFING November 2016 CONSTRUCTION BRIEFING November 2016 New Pre-Action Protocol for Construction and Engineering Disputes launched The Second Edition of the Pre-Action Protocol for Construction and Engineering Disputes comes

More information

Arbitration Rules of the Court of International Commercial Arbitration of the Chamber of Commerce and Industry of Romania

Arbitration Rules of the Court of International Commercial Arbitration of the Chamber of Commerce and Industry of Romania Arbitration Rules of the Court of International Commercial Arbitration of the Chamber of Commerce and Industry of Romania adopted by the Board of the Court of International Commercial Arbitration in force

More information

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory Arbitration Act 1996 1996 CHAPTER 23 1 Part I Arbitration pursuant to an arbitration agreement Introductory 1. General principles. 2. Scope of application of provisions. 3. The seat of the arbitration.

More information

Reference to Clause 10 or to the Taking-Over Certificate is found in the following clauses:-

Reference to Clause 10 or to the Taking-Over Certificate is found in the following clauses:- Clause 10 Summary Clause 10 deals with the Taking-Over of the Works, Sections, or parts of the Works. Sub-Clause 10.1 deals with the Taking-Over of the Works and Sections. Taking-Over by the Employer happens

More information

IN THE HIGH COURT OF JUSTICE. Between MOOTILAL RAMHIT & SONS CONTRACTING LIMITED. And EDUCATIONAL FACILITIES COMPANY LIMITED

IN THE HIGH COURT OF JUSTICE. Between MOOTILAL RAMHIT & SONS CONTRACTING LIMITED. And EDUCATIONAL FACILITIES COMPANY LIMITED THE REPUBLIC OF TRINIDAD AND TOBAGO IN THE HIGH COURT OF JUSTICE Claim No. CV 2017-02302 Between MOOTILAL RAMHIT & SONS CONTRACTING LIMITED Claimant And EDUCATIONAL FACILITIES COMPANY LIMITED First Defendant

More information

Consolidated text PROJET DE LOI ENTITLED. The Arbitration (Guernsey) Law, 2016 * [CONSOLIDATED TEXT] NOTE

Consolidated text PROJET DE LOI ENTITLED. The Arbitration (Guernsey) Law, 2016 * [CONSOLIDATED TEXT] NOTE PROJET DE LOI ENTITLED The Arbitration (Guernsey) Law, 2016 * [CONSOLIDATED TEXT] NOTE This consolidated version of the enactment incorporates all amendments listed in the footnote below. It has been prepared

More information

What are the requirements for the South African construction industry to fully utilise adjudication?

What are the requirements for the South African construction industry to fully utilise adjudication? What are the requirements for the South African construction industry to fully utilise adjudication? Maiketso NC 1, Maritz MJ 2 1 Trans-Caledon Tunnel Authority (TCTA), Centurion 2 Department of Construction

More information

Investments, Life Insurance & Superannuation Terms of Reference

Investments, Life Insurance & Superannuation Terms of Reference Investments, Life Insurance & Superannuation Terms of Reference These Terms of Reference apply to those members of the Financial Ombudsman Service Limited who have been designated as having the Investments,

More information

VBN / VGB ARBITRATION BOARD

VBN / VGB ARBITRATION BOARD VBN / VGB ARBITRATION BOARD The Arbitration Board Preface In 1992, the Dutch Flower Auctions Association (Vereniging van Bloemenveilingen in Nederland, or VBN) and the Association of Wholesale Trade in

More information

ANNEX V PROCEDURAL RULES ON CONCILIATION AND ARBITRATION OF CONTRACTS FINANCED BY THE EUROPEAN DEVELOPMENT FUND (EDF)

ANNEX V PROCEDURAL RULES ON CONCILIATION AND ARBITRATION OF CONTRACTS FINANCED BY THE EUROPEAN DEVELOPMENT FUND (EDF) ANNEX V PROCEDURAL RULES ON CONCILIATION AND ARBITRATION OF CONTRACTS FINANCED BY THE EUROPEAN DEVELOPMENT FUND (EDF) I. INTRODUCTION Article 1 - Scope of application. Article 2 - Definitions. Article

More information

Decision of the Dispute Resolution Chamber

Decision of the Dispute Resolution Chamber Decision of the Dispute Resolution Chamber passed in Zurich, Switzerland, on 13 August 2015, in the following composition: Geoff Thompson (Engand), Chairman Mario Gallavotti (Italy), member Jon Newman

More information

White Young Green Consulting v Brooke House Sixth Form College [2007] APP.L.R. 05/22

White Young Green Consulting v Brooke House Sixth Form College [2007] APP.L.R. 05/22 JUDGMENT : Mr Justice Ramsey : TCC. 22 nd May 2007 Introduction 1. This is an application for leave to appeal under s.69(3) of the Arbitration Act 1996. The arbitration concerns the appointment of the

More information

PAM NORTHERN CHAPTER

PAM NORTHERN CHAPTER PAM NORTHERN CHAPTER SATURDAY, 27 FEBRUARY 2016 DELAY AND DISRUPTION IN CONSTRUCTION CONTRACTS BY LIM HOCK SIANG MESSRS PRESGRAVE & MATTHEWS STANDARD CHARTERED BANK CHAMBERS, 2 LEBUH PANTAI, 10300 PENANG,

More information

Commencing an (ICC) Arbitration

Commencing an (ICC) Arbitration Commencing an (ICC) Arbitration by Rajendra Navaratnam Partner, Azman Davidson & Co. Member, ICC Malaysia Arbitration Committee Introduction Focus on ICC Arbitration Institutional Arbitration ICC Secretariat

More information

Industrial Relations Amendment (Public Sector Conditions of Employment) Act 2011 No 13

Industrial Relations Amendment (Public Sector Conditions of Employment) Act 2011 No 13 New South Wales Industrial Relations Amendment (Public Sector Conditions of Employment) Contents Page 1 Name of Act 2 2 Commencement 2 Schedule 1 Amendment of Industrial Relations Act 1996 No 17 3 New

More information

PART 8 ARBITRATION REGULATIONS CONTENTS

PART 8 ARBITRATION REGULATIONS CONTENTS PART 8 ARBITRATION REGULATIONS * CONTENTS Section Page 1 Definitions and Interpretations 8-1 2 Commencement 8-2 3 Appointment of Tribunal 8-3 4 Procedure 8-5 5 Notices and Communications 8-5 6 Submission

More information

ARBITRATION & CONCILIATION ACT AND MEDIATION

ARBITRATION & CONCILIATION ACT AND MEDIATION ARBITRATION & CONCILIATION ACT AND MEDIATION The established courts are too remote, too legalistic, too expensive and too supine and slow. INTRODUCTION Pawan Agarwal Chartered Accountant Indian legal system

More information

Let s take a peek at. - Emanuele Lancellotti - Executive Director

Let s take a peek at. - Emanuele Lancellotti - Executive Director Techno Engineering & Associates further consolidates its leading position with the appointment of Mr. Emanuele Lancellotti as Executive Director p. 1 Early enforcement of binding but not final DAB decisions

More information

SKI RACING AUSTRALIA (SRA) SELECTION POLICY 2016/2017

SKI RACING AUSTRALIA (SRA) SELECTION POLICY 2016/2017 SKI RACING AUSTRALIA (SRA) SELECTION POLICY 2016/2017 1. PHILOSOPHY The objective of the SRA Selection Policy (Policy) is to achieve the best possible Australian representative water ski racing team. The

More information

QUEENSLAND INDUSTRIAL RELATIONS COMMISSION

QUEENSLAND INDUSTRIAL RELATIONS COMMISSION QUEENSLAND INDUSTRIAL RELATIONS COMMISSION CITATION: PARTIES: State of Queensland (Department of Community Safety - Queensland Ambulance Service) v United Voice, Industrial Union of Employees, Queensland

More information

Financiers' Certifier Direct Deed

Financiers' Certifier Direct Deed RFP Version Stage One - East West Link [ ] State [ ] Financiers' Certifier Contents 1. Defined terms & interpretation... 1 1.1 Project Agreement definitions... 1 1.2 Defined terms... 1 1.3 Interpretation...

More information

Index. Volume 21 (2005) 21 BCL

Index. Volume 21 (2005) 21 BCL Index Abandoned claims judgment on, principally concerned with costs, 12-13, 33-44 whether cost reduction appropriate because of, 125 Access to the premises AS 4917-2003, 9-10 Acts Interpretation Act 1954

More information

LABOUR ARBITRATION RULES

LABOUR ARBITRATION RULES THE INSTITUTE of ARBITRATORS & MEDIATORS AUSTRALIA ACN 008 520 045 ARBITRATORS MEDIATORS CONCILIATORS LABOUR ARBITRATION RULES Preamble The preferred method of resolving a dispute between an employer and

More information

Enforceability of Multi-Tiered Dispute Resolution Clauses

Enforceability of Multi-Tiered Dispute Resolution Clauses KluwerArbitration Search term "enforceability of multitiered" Document information Author Didem Kayali (IAI profile) Publication Journal of International Arbitration Bibliographic reference Didem Kayali,

More information

ENGLAND GOLF DISCIPLINARY AND APPEAL REGULATIONS (Including appeals from Clubs and Counties)

ENGLAND GOLF DISCIPLINARY AND APPEAL REGULATIONS (Including appeals from Clubs and Counties) ENGLAND GOLF DISCIPLINARY AND APPEAL REGULATIONS (Including appeals from Clubs and Counties) 1 INTRODUCTION 1.1 These disciplinary regulations (the Regulations ) are made pursuant to the powers of England

More information

Arbitration from a UAE Legal Perspective

Arbitration from a UAE Legal Perspective Arbitration from a UAE Legal Perspective By Tony Maalouli Dubai's property and construction market is booming as world class projects are being launched by innovative property developers with the help

More information

Pakistan Stock Exchange Limited (formerly: Karachi Stock Exchange Limited) RULE BOOK

Pakistan Stock Exchange Limited (formerly: Karachi Stock Exchange Limited) RULE BOOK Pakistan Stock Exchange Limited (formerly: Karachi Stock Exchange Limited) RULE BOOK Chapter 18: INVESTORS CLAIMS, BROKERS DISPUTES AND ARBITRATION REGULATIONS 18.2. DISPUTES TO BE REFERRED TO ARBITRATION:

More information

Commercial Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex Commercial Disputes)

Commercial Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex Commercial Disputes) Commercial Arbitration Rules and Mediation Procedures (Including Procedures for Large, Complex Commercial Disputes) Rules Amended and Effective October 1, 2013 Fee Schedule Amended and Effective June 1,

More information

Palestinian Legislative Council Proposed Arbitration Law

Palestinian Legislative Council Proposed Arbitration Law Case Western Reserve Journal of International Law Volume 32 Issue 2 2000 Palestinian Legislative Council Proposed Arbitration Law Palestine Legislative Council Follow this and additional works at: http://scholarlycommons.law.case.edu/jil

More information

Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland

Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland (Royaume-Uni - Royaume-Uni de Grande-Bretagne et d'irlande du Nord) ARBITRATION ACT 1996 1996 CHAPTER 23 An Act to

More information

Model letters for use by the Contractor

Model letters for use by the Contractor 178 Appendices Model letters for use by the Contractor Letter to the Engineer c.c. Employer ML 1.3 Sub - Clause 1.3 Communications We confirm the agreement made between us on (date) in respect of site

More information

CONSTRUCTION BULLETIN. Welcome to the September edition of our Construction Bulletin. Construction. September

CONSTRUCTION BULLETIN. Welcome to the September edition of our Construction Bulletin. Construction. September Construction September CONSTRUCTION 2015 BULLETIN Welcome to the September edition of our Construction Bulletin. In this edition we cover a broad range of contractual and legal issues relevant to the construction

More information

DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY Introductory Provisions. Article (1) Definitions

DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY Introductory Provisions. Article (1) Definitions DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY 2011 Introductory Provisions Article (1) Definitions 1.1 The following words and phrases shall have the meaning assigned thereto unless

More information

Resolution Institute. Policy on the Accreditation and Register of Adjudicators

Resolution Institute. Policy on the Accreditation and Register of Adjudicators Resolution Institute Policy on the Accreditation and Register of Adjudicators 1 Resolution Institute Policy on the Accreditation and Register of Adjudicators Introduction Resolution Institute is the membership

More information

CORRIGENDUM No 1 WORKS TENDER DOSSIER

CORRIGENDUM No 1 WORKS TENDER DOSSIER CORRIGENDUM No 1 WORKS TENDER DOSSIER 1 In the Volume 1 - Instructions to Tenderes launched 24/11/2009, Section 2 Form 2.2. Appendix to Tender, pgs 39 and 40 two rows were added, relating to the Advance

More information

Decision of the Dispute Resolution Chamber

Decision of the Dispute Resolution Chamber Decision of the Dispute Resolution Chamber passed in Zurich, Switzerland, on 21 November 2006, in the following composition: Slim Aloulou (Tunisia), Chairman Paulo Amoretty Souza (Brazil), member Ivan

More information

Decision of the Dispute Resolution Chamber

Decision of the Dispute Resolution Chamber Decision of the Dispute Resolution Chamber passed in Zurich, Switzerland, on 2 November 2007, in the following composition: ALOULOU Slim (Tunisia), Chairman DIDULICA John (Australia), member MOVILLA Gerardo

More information

Mind the Gap: Analysis of Cases and Principles Concerning the Ability of ICC Arbitral Tribunals to Enforce Binding DAB Decisions

Mind the Gap: Analysis of Cases and Principles Concerning the Ability of ICC Arbitral Tribunals to Enforce Binding DAB Decisions Analysis of Cases and Principles Concerning the Ability of ICC Arbitral Tribunals to Enforce Binding DAB Decisions under the 1999 FIDIC Conditions of Contract 145 Mind the Gap: Analysis of Cases and Principles

More information

ANSWER TO THE REQUEST FOR ARBITRATION [NOTE: OR ANSWER TO THE REQUEST FOR ARBITRATION AND COUNTERCLAIMS, IF

ANSWER TO THE REQUEST FOR ARBITRATION [NOTE: OR ANSWER TO THE REQUEST FOR ARBITRATION AND COUNTERCLAIMS, IF ARBITRATION NO. [INSERT CASE NUMBER AS PROVIDED BY THE ICC SECRETARIAT ] IN THE MATTER OF AN ARBITRATION UNDER THE RULES OF THE INTERNATIONAL COURT OF ARBITRATION OF THE INTERNATIONAL CHAMBER OF COMMERCE

More information

Contract Disputes Act of 1978 (Federal Acquisition Regulation - Subpart 33.2)

Contract Disputes Act of 1978 (Federal Acquisition Regulation - Subpart 33.2) Appendix 1 - Contract Disputes Act of 1978/FAR 33.2 Contract Disputes Act of 1978 (Federal Acquisition Regulation - Subpart 33.2) This appendix contains the complete SUBPART 33.2-DISPUTES AND APPEALS of

More information

CONDITIONS OF APPOINTMENT

CONDITIONS OF APPOINTMENT CONDITIONS OF APPOINTMENT CONDITIONS OF APPOINTMENT 1 The Landscape Consultant s Authority and Obligations Duty of Care 1.1 The Landscape Consultant has exercised and shall continue to exercise reasonable

More information

Arunga Park Speedway Association Incorporated Constitution 2018

Arunga Park Speedway Association Incorporated Constitution 2018 Arunga Park Speedway Association Incorporated Constitution 2018 Part 1 Preliminary 1. Name The name of the incorporated association ("the Association") is Arunga Park Speedway Association Incorporated

More information

THE LMAA SMALL CLAIMS PROCEDURE

THE LMAA SMALL CLAIMS PROCEDURE THE LONDON MARITIME ARBITRATORS ASSOCIATION THE LMAA SMALL CLAIMS PROCEDURE and COMMENTARY (Revised 1st January 2006) 1. INTRODUCTION THE LMAA SMALL CLAIMS PROCEDURE These provisions shall be known as

More information

CHAPTER 4 THE ARBITRATION AND CONCILIATION ACT. Arrangement of Sections.

CHAPTER 4 THE ARBITRATION AND CONCILIATION ACT. Arrangement of Sections. CHAPTER 4 THE ARBITRATION AND CONCILIATION ACT. Arrangement of Sections. Section 1. Application. 2. Interpretation. PART I PRELIMINARY. PART II ARBITRATION. 3. Form of arbitration agreement. 4. Waiver

More information

Gafta No.125. Copyright THE GRAIN AND FEED TRADE ASSOCIATION

Gafta No.125. Copyright THE GRAIN AND FEED TRADE ASSOCIATION Effective for contracts dated from 1 st January 2006 Gafta No.125 Copyright THE GRAIN AND FEED TRADE ASSOCIATION ARBITRATION RULES GAFTA HOUSE 6 CHAPEL PLACE RIVINGTON STREET LONDON EC2A 3SH Tel: +44 20

More information

Elements of a Civil Claim

Elements of a Civil Claim Elements of a Civil Claim This presentation provides an overview of the elements of a civil claim, with particular reference to construction claims, and looks at each dispute resolution option in the context

More information

RULES OF ARBITRATION

RULES OF ARBITRATION RULES OF ARBITRATION IN FORCE AS FROM 1 NOVEMBER 2016 Palais Brongniart, 16 place de la Bourse, 75002 Paris, France www.delosdr.org. secretariat@delosdr.org MODEL CLAUSES... 2 SEAT AND LANGUAGES S CHEDULES

More information

MOMBASA PORT AREA ROAD DEVELOPMENT PROJECT BIDDING DOCUMENTS FOR THE CONSTRUCTION OF MWACHE JUNCTION TSUNZA MTEZA SECTION (PACKAGE 2)

MOMBASA PORT AREA ROAD DEVELOPMENT PROJECT BIDDING DOCUMENTS FOR THE CONSTRUCTION OF MWACHE JUNCTION TSUNZA MTEZA SECTION (PACKAGE 2) FINAL MOMBASA PORT AREA ROAD DEVELOPMENT PROJECT BIDDING DOCUMENTS FOR THE CONSTRUCTION OF MWACHE JUNCTION TSUNZA MTEZA SECTION (PACKAGE 2) ICB No.:KeNHA/1519/2017 VOLUME 3 SECTION VII: General Conditions

More information

The new Arbitration (Guernsey) Law, a guide to the key provisions

The new Arbitration (Guernsey) Law, a guide to the key provisions JERSEY GUERNSEY LONDON BVI SINGAPORE GUERNSEY BRIEFING May 2017 The new Arbitration (Guernsey) Law, 2016 - a guide to the key provisions Historically, parties in Guernsey have been reluctant to use arbitration

More information

RESPONSE TO REVIEW OF THE CONSTRUCTION CONTRACTS (SECURITY OF PAYMENTS) ACT (NT): ISSUES PAPER OCTOBER 2017

RESPONSE TO REVIEW OF THE CONSTRUCTION CONTRACTS (SECURITY OF PAYMENTS) ACT (NT): ISSUES PAPER OCTOBER 2017 HIA Submission to the Department of Attorney-General & Justice RESPONSE TO REVIEW OF THE CONSTRUCTION CONTRACTS (SECURITY OF PAYMENTS) ACT (NT): ISSUES PAPER OCTOBER 2017 28 November 2017 1. EXECUTIVE

More information

LAW ON THE INTERNATIONAL COMMERCIAL ARBITRATION BULGARIA. Chapter I GENERAL PROVISIONS

LAW ON THE INTERNATIONAL COMMERCIAL ARBITRATION BULGARIA. Chapter I GENERAL PROVISIONS LAW ON THE INTERNATIONAL COMMERCIAL ARBITRATION BULGARIA Prom. SG 60/1988, Amend. SG 93/1993, Amend. SG 59/1998, Amend. SG 38/2001, Amend. SG 46/2002 Chapter I GENERAL PROVISIONS Art. 1. (1) (amend. SG

More information

STANDARD MATERIAL TRANSFER AGREEMENT*

STANDARD MATERIAL TRANSFER AGREEMENT* STANDARD MATERIAL TRANSFER AGREEMENT* PREAMBLE WHEREAS The International Treaty on Plant Genetic Resources for Food and Agriculture (hereinafter referred to as the Treaty ) 1 was adopted by the Thirty-first

More information

Design and Construct Contract - Standard User Funding Agreement

Design and Construct Contract - Standard User Funding Agreement QCA Draft 8 September 2014 Aurizon Network Pty Ltd [insert Trustee] Design and Construct Contract - Standard User Funding Agreement (amended form of AS 4902-2000) Ref: QRPA15047 9101397 11391098/5 L\313599357.2

More information

Financiers' Certifier Direct Deed

Financiers' Certifier Direct Deed Document for Release Execution Version Stage One - East West Link The Minister for Roads on behalf of the Crown in right of the State of Victoria State Aquenta Consulting Pty Ltd Financiers' Certifier

More information

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013)

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) 1. Scope of Application and Interpretation 1.1 Where parties have agreed to refer their disputes

More information