Editorial. Contents. September edition 4. Keith Lonsdale

Size: px
Start display at page:

Download "Editorial. Contents. September edition 4. Keith Lonsdale"

Transcription

1 Building brief September edition 4 Contents Editorial Adjudication and professional negligence claims: a case to answer p2 A leap of faith? Good faith in UK & UAE construction contracts p3 Agency: when is there a binding contract between parties p4 Pirelli - still good construction law p5 Contractual limitation periods p5 Building a swimming pool in Spain does not necessarily mean a headache p7 Welcome to the latest edition of Building brief. This edition has a distinctly international flavour with articles from our Dubai office and Spanish associates (for those still dreaming of their summer holidays). Suzanne Weight's article on Abbott and Another v Will Gannon & Smith Ltd is a wonderful example of the law biting back just when you thought the position was clear (to the extent that it will forever be the case when the words 'tort' and 'limitation' appear in the same sentence). Just to re-cap on history, in Pirelli General Cable Works Ltd v Oscar Faber and Partners the House of Lords decided that a building owner's cause of action against a consulting engineer for negligent design accrued, for limitation purposes, when physical damage to the building first occurred. The situation where latent damage had occurred was 'repaired' by virtue of Section 14A of the Limitation Act (three years from 'date of knowledge') so, presumably, that was the end of Pirelli? As Suzanne explains Pirelli lives on. On the subject of confusion, the eagle eyed will have noticed an article from Paul Taylor in our Dubai office. The author is Paul D Taylor and not Paul J Taylor, our former national senior partner and new consultant. I can assure you that this has been the cause of confusion on a Pirelli type scale! Building Brief is published by the marketing department of Berrymans Lace Mawer (Castle Chambers, 43 Castle Street, Liverpool L2 9SU) on behalf of the partnership. Printed in England by Patersons Printing Ltd. Berrymans Lace Mawer 2006 Keith Lonsdale Partner, BLM London

2 Adjudication and professional negligence claims: a case to answer It is an often made observation that adjudication has become used for disputes for which it was never contemplated by Sir Michael Latham when he drafted his final report in 1994, noting: There should be no restrictions on the issues capable of being referred to the adjudicator, conciliator or mediator. The drafters of the legislation took him at his word and duly translated the recommendation into the Housing Grants, Construction and Regeneration Act (the Act). This has resulted in adjudications of considerable complexity, including claims of professional negligence which have lasted many months at considerable and irrecoverable costs to both parties. When Sir Michael Latham originally made his recommendations he envisaged that arbitrators would be acting as adjudicators: If the proposed system of adjudication works properly many current arbitrators will be making decisions during the course of the project but in the role of adjudicators. The problem is that arbitrators have had little exposure or training in professional negligence claims, which almost invariably (except in international contracts) are heard by the courts. In London & Amsterdam Properties v Waterman Judge Wilcox remarked: On this issue (that of an expert report concluding that the defendants were not negligent) it is strongly arguably that the adjudicator failed to properly address the issue of professional negligence, he did not do so in his reasons. Other common law jurisdictions, notably New Zealand and certain Australian States, as well as Singapore, have implemented in one form or another many of Sir Michael's recommendations, especially those on payment and pay when paid clauses. Interestingly New South Wales has chosen to limit adjudication to disputes about payment of either fees or stage payments, relegating allegations of defects in workmanship or design to a defence rather than them being claims in their own right. The DTI in its review initiated in 2004 Improving Payment Practises in the Construction Industry has not sought as part of its remit to restrict the scope or use of adjudication, rather the contrary. A consultation at the DTI on 1 June 2006 was principally concerned to diminish the potential challenges to an enforceable adjudication decision and to streamline the payment provisions. Professional negligence claims can and will continue to be pursued in adjudication, despite some very trenchant criticism from the judiciary. Lady Paton in Gillies Ramsey Diamond v PJW Enterprises Limited said: Whilst therefore it may on one view seem startling that a professional person acting as an adjudicator should be invited to rule within 28 days on the important and often difficult and often delicate question as to whether a fellow professional has failed in his or her duty to such an extent that there has been professional negligence, the exceptional and summary adjudication procedure permits this very result. There are two fundamental objections to the use of adjudication for claims of professional negligence:! That the brevity of the procedure (which of course is its principal attraction) is insufficient for a proper examination of such issues.! That the majority of adjudicators are unversed in professional negligence claims and what is required to prove them. There is some anecdotal evidence to suggest that those making claims of professional negligence are coming to realise that the adjudication timetable and procedure, and the nil cost recovery under it, make it an unattractive option. As to the second concern, BLM has sought to address this. Advanced training for adjudicators is now being run on behalf of the four principal appointing bodies (RICS, RIBA, ICE and the Chartered Institute of Arbitrators). BLM has contributed a module on professional negligence and the proof the evidence required to make a finding of negligence at the first of such courses run in autumn It apparently provoked food for thought. Robert Stevenson Partner, BLM London page 2 Berrymans Lace Mawer

3 A leap of faith? Good faith in UK & UAE construction contracts In Dubai, United Arab Emirates (UAE), some things never change: it will be hot again tomorrow, sand will always somehow get into the car again, and contractors will use the traditional enquiry/tender procurement route for all construction work. Or so we all thought. The heat and sand remain. However, a change may be in the air. Phrases such as 'partnering', 'co-operation' and 'alliancing' are being whispered in the boardrooms of Dubai's construction industry. So is this simply the UAE following English legal concepts, or could the UK learn something from the UAE? Other than the weather, the fundamental difference between the UAE and the UK (and a point all those seeking to do business in this part of the Middle East need to be aware of) is the nature of their respective legal systems. English law is based on 'common law' and relies on case law created by the courts to set its rights, rules and precedents. Dubai's law is based on 'civil law', a written code which sets out the overriding rules of the game from the outset. Both countries have a history of competitive tendering and traditional procurement procedures for construction work. However, the UAE Civil Law at Article 246(1) states that: The contract must be performed in accordance with its contents and in a manner consistent with the requirements of good faith. At the other end of the scale, for years English Law has debated the 'good faith' issue and never formally recognised the concept (save in insurance contracts where the relationship is based on an absolute duty of good faith/full disclosure). In the UK, some standard form construction contracts have even sought to encapsulate the concept of good faith or something akin to it:! The ECC/NEC New Engineering Contract requires a ' spirit of mutual trust and co-operation' and proffers its own bespoke Partnering Option X12 arrangements.! The PPC2000 Partnering Contract requires a ' spirit of trust fairness and mutual co-operation.! The Be Collaborative Contract requires a ' co-operative manner in good faith and in a spirit of mutual trust and respect'. The English courts even came close to recognising the rather nebulous concept of good faith in the well-known case of Birse Construction Ltd v St David Limited (1999) BLR4 when HHJ Humphrey Lloyd QC took into consideration conduct and attitudes to be a non-binding partnering charter between two parties. All very laudible yet still the concept of good faith is not an enshrined rule or doctrine of English law. Some may say that this is hardly surprising in an industry in which the chief protagonists have for many years been at loggerheads in countless construction claims, arbitrations and adjudications against each other. The fact that the concept and duty of good faith is already enshrined in its Civil Code, might just give the UAE a distinct advantage if partnering agreements become prevalent in Dubai. UAE law might in fact be able to lead the way for others in recognising, embracing and enforcing the meaning and effect of good faith in construction contracts and providing guidance to others on how it should be approached. Until then, certainly in the UK, concluding that any conduct or action of one party to a construction contract amounts to an enforceable breach of good faith, will still very much mean taking a leap of faith. Paul D Taylor Senior construction solicitor, BLM Dubai Berrymans Lace Mawer page 3

4 terms of the contract, the quantity surveyor had reverted to the employer for confirmation and this evidenced their authority). It was also argued that the contract sent to the contractor was not sent as a 'draft' or 'subject to contract' and the quantity surveyor did not say that the contract would be referred to the employer for approval. What defeated the claim was that it was not the conduct of the employer which had led to the contractor's belief that the quantity surveyor had authority to enter into the contract, but the conduct of the quantity surveyor. Judge Kirkham decided that: 1 There is a significant difference between negotiating the terms of a contract and actually entering into one. 2 The employer's silence, in not saying that the quantity surveyor's authority was limited, did not amount to a representation of authority. Agency: when is there a binding contract between parties? In the case of GPN Limited (in receivership) v O2 (UK) Limited [2004] the court had to decide whether an employer's (O2's) quantity surveyors (McCreadies) had ostensible or apparent authority to bind the employer to a contract with the contractor (GPN Limited). The works were the construction of approximately 1900 sites to allow for 3G technology. The employer sent the contractor a letter of intent. Terms of the contract were subsequently negotiated by the quantity surveyor and the contractor. The quantity surveyor agreed terms without always referring back to the employer, and finally sent the contractor the 15 th version of the contract, requesting that it be signed. The following month the contractor went into administrative receivership. In a subsequent adjudication the adjudicator decided that there was a contract between the parties and made an award for the contractor. In the enforcement proceedings the employer maintained that there was no contract because the quantity surveyor only had authority to discuss schedules of rates, to draft contract documents and to negotiate terms. 3 That the quantity surveyor had to refer back to the employer on some negotiated elements was evidence that there was a limit on the quantity surveyor's authority. 4 The contractor's evidence that agents are commonly used to negotiate and enter into contracts was unconvincing. 5 The signed letter of intent referred to the parties agreeing terms and to formal execution of the contract so did not aid the contractor. 6 Although the contract itself referred to the quantity surveyor as the employer's agent, this was a mere 'bootstrap argument' (self-supporting) and in itself, not sufficient. Comment There were 14 previous drafts of the contract, some of which presumably contained the agency clause and some presumably read by the employer. The terms of the contract were correctly agreed by someone with authority to agree them. The contractor may feel hard-done-by. Parties to a contract clearly need to be extremely careful that the other party gives the final approval of the contract, or they may find themselves protected only by the emperor's new bootstraps. The contractor argued that agents are often used to negotiate and enter into contracts and they had not been informed that the quantity surveyor's authority was restricted to negotiation. Charles Ingmire Solicitor, BLM London The contractor claimed that employees of the employer had led them to believe by their conduct that the quantity surveyor had ostensible authority to act on their behalf (although, for some page 4 Berrymans Lace Mawer

5 Pirelli - still good construction law In Pirelli General Cable Works Ltd v Oscar Faber and Partners (1983), the House of Lords decided that a building owner's cause of action against a consulting engineer for negligent design accrues, for limitation purposes, when physical damage to the building first occurs. The 2005 case of Abbott and Another v Will Gannon & Smith Ltd asked the Court of Appeal (CA) to decide whether Pirelli is still good law. At first instance, the district judge had heard limitation as a preliminary issue, and held that Pirelli applied. The defendant appealed this decision. In May 1995, Mr Abbott, the owner of a hotel in Torquay, retained the defendant consulting engineer to design work to remedy structural defects in a large bay window of the hotel. Remedial work was carried out according to the engineer's design and completed by a local builder in March In late 1999, the claimant first noticed that the lintel over the bay window had moved and cracked the surrounding structure. The claimant arranged for further remedial work to be carried out which cost approximately 20,000. Proceedings were not issued in both contract and tort until September made the following interesting points: 1 He made the distinction that, if the claimant discovers the defect before the damage occurs he has a claim for economic loss (as long as there is a special relationship ie between the builder or designer and the claimant) (Murphy)). However, if the claimant does not discover the defect before damage occurs, the cause of action will accrue at the date the physical damage first occurs (Pirelli). 2 He held that even if Pirelli is not good law and if the claimant's cause of action accrued at the time it suffered economic loss, in Abbott such loss would only occur when it manifested itself in some way which would affect the value of the building, measured either by cost of repairs or by depreciation in the market value. The CA therefore rejected the defendant's arguments and, even if based on the decision in Murphy, the claimant in Abbott would have made the claim in time, as the loss which affected the value of the building occurred in late 1999 when the cracks first appeared. Although Pirelli is still good law, I suspect that there will be further cases as LJ Tuckey raised the possibility of there being more than one cause of action for limitation purposes. Guidance from the House of Lords will be required. The parties agreed that the contract claim was time barred, as more than six years had elapsed since the contract was entered into in The claim in tort was time barred if the cause of action accrued more than six years before the issue of the claim, and the cause of action would not accrue until damage had occurred. In Abbott, the Latent Damages Act did not help the claimant, as this only extends the limitation period for a further three years from the claimant's date of knowledge, and the claimant discovered the damage in late The claimant relied on the decision in Pirelli. Damage first occurred in late 1999, so the claimant would have six years from 1999 to issue a claim. The defendant relied on the decision in Murphy v Brentwood DC (1991). This was a later decision by the House of Lords, which is inconsistent with Pirelli, in that Murphy decided that the cause of action accrues when the building owner suffers economic loss, and this occurs when work carried out according to the negligent design has been completed, leaving the owner with a defective building in need of remedial work. The CA judge, in Abbott, decided that Murphy had not expressly or impliedly overruled the decision in Pirelli. Therefore, the cause of action accrued at the date of physical damage, which was late 1999, and therefore the limitation period extended until late Lord Justice Tuckey, who gave the main CA judgment in Abbott, Suzanne Weight Solicitor, BLM London Contractual limitation periods Periods of limitation have been the subject of English Statues for at least 500 years. The concept is often the subject of criticism. Only recently a rape victim's case against her assailant, lottery winner Lorworth Hoare, was struck out for being brought more than six years after the event. Why have limitation periods? The combined judicial pronouncements have been distilled to:! Long dormant claims have more cruelty than justice in them.! A defendant might have lost the evidence to disprove a stale claim.! Persons with good causes of action should pursue them with reasonable diligence. None of these would appear to apply to the example above, but as the Law Commission has commented 'It will never be possible to achieve complete fairness between the parties'. Berrymans Lace Mawer page 5

6 The Limitation Act 1980 is the principal but not the only statute on limitations. It provides a basic six year period for claims in contract, from the date of breach; and in tort from the date injury is suffered or reasonably discoverable. The most recent Law Commission Report (No 270) on limitation considers these periods to be too long and recommends shortening them to three years (the same period as for personal injury claims). The report also recommends parties agreeing their own limitation periods, leading to the prospect of even longer periods of liability than the current 12 years for contracts executed as deeds. Arguments about limitation provide much grist to the legal mill. Two recent Court of Appeal (CA) cases, Henry Boot Construction Limited v Alstrom Combined Cycles and Birse Construction Limited v McCormick (UK) Limited illustrate this well. The Henry Boot contract incorporated the ICE Standard Form, 6 th Edition. Alstrom argued (successfully before the arbitrator judge) that on a true interpretation of the contract, sums included in the final certificate by the engineer were in fact statute barred, as the relevant causes of action had arisen when the work itself had been done (or at least when an interim certificate in respect of that work had or should have been issued) and these were more than six years before the commencement of the arbitration. After a lengthy analysis of the contract their Lordships concluded that interim valuations, or their non-payment, are not the breach from which the limitation period was to run, rather it is the revision of those interim sums as part of the final certificate which constitutes the starting point. contractor to make a claim which was to be either accepted or rejected in fairly short order by the employer. The judge at first instance and the CA took the accrual of any cause of action to be the date of submission of the claim, plus three to four weeks. As with many of these contractual claims, the calculation of when the limitation period starts to run will be a question of construing the contract. The answer for other forms of contract, for example the JCT Standard Form will be different as there is a contractual machinery for the positive ascertainment by the architect/ supervising officer, in accordance with a post completion timetable, of sums due to the contractor, the contractor nominally providing information for this ascertainment to be undertaken. All this can lead to considerable uncertainty as to just when a contractor's claim becomes statute barred. This is to be contrasted with the position in certain standard professional appointments such as those published by the ACE and RIBA, where there is a provision limiting the bringing of any action, in contract or in tort, to six/twelve years following practical completion. This type of provision was first included in collateral warranties, and interestingly a similar provision does not appear in the new BPF Consultancy Form, except in the appendices which are the equivalent of collateral warranties. A similar provision in building contracts would serve to concentrate both parties' minds on an end date. It would also avoid the possibility of a tort claim being pursued just because the contractual limitation period has expired. Henry Boot did not succeed on every count. The CA ruled that claims for interest on claims that sums should have been included in interim certificates, became statute barred six years after that right accrued. This ruling may have an important impact on financing charges which can form a significant part of a contractor's claim (in this particular case Henry Boot was claiming in excess of 13 million in compound interest). Much of a claim for financing charges is based on unpaid loss and expense, which should have been certified and paid during the course of the works, the delay in payment extends the contractor's borrowing, hence the financing charges. If the eventual arbitration/limitation is commenced more than six/twelve years after the date when the loss and expense should have been certified, then at least part of the financing charges may be statute barred. Drafters of all construction contracts are going to have to turn their minds to limitation periods if the Law Commission proposals are enacted, three years will be too short but for the simplest contracts. There is however, a simple step that can be taken now, to make the position of limitation a little clearer. Robert Stevenson Partner, BLM London In Birse Construction v McCormack the issue of limitation concerned the date of the accrual of the cause of action. Birse's claim was for additional site establishment costs and was initially made on 14 November Proceedings were on 23 May The contract was not in the standard form and provided for the page 6 Berrymans Lace Mawer

7 Building a swimming pool in Spain does not necessarily mean a headache Many Europeans enjoy the long, sunny days of the Eastern Spanish coast and have decided to own apartments and bungalows, with enough room for a swimming pool to make their holiday extra special. However, few owners of these mini-paradises are aware of the actions, rights and resources that the EU and Spanish law offers them when the construction or maintenance of a swimming pool could cause serious headaches and considerable expenses. A swimming pool, as with any other building work in Spain, must be built by a properly authorised builder, who must offer the customer not only the guarantee for the building work for defects, where this guarantee is extended to 10 years (article 1591 of the Civil Code) but also a guarantee over the products used to build the swimming pool such as insulating panels, spotlights, ladders, water purifiers and even the rolls of interior covering material of the swimming pool. This guarantee must last for no less than two years (Law 23/2003 implements EC Directive. 44/1999 of the Plmt And Cncl). upon in the contract other conditions that may be demanded in good faith and for the building practices and uses must also be fulfilled (article 1258 Spanish Civil Code). Nowadays, many builders offer their customers 'key in hand' contracts, under which the builder is obliged, on the customer's behalf to obtain all the authorisations and licences, be they regional, municipal or from other organisations as might be the supplying companies (water, electricity, etc) as well as the necessary permits for the sewerage and water treatment if required. When the builder offers the customer this type of contract, he usually demands an advance amount varying between 30% and 50% of the total cost of the work. On this point, the customer may always request the builder to accredit the amounts received as insurance in case the job is unfinished for any reason attributable to the builder (ie builder's insolvency, demise of the work's foreman, etc). Before signing the job's approval certificate the customer must demand (and of course the builder must offer) the details of the builder's civil liability insurance with coverage over the damages that faulty installation or construction could cause to the property (the customer), or to the construction and finally the damages that could be caused to third parties and their properties. This must last for a time period of no less than the guarantee period (two years) and even in the case of the action deadline for damages caused by a faulty product incorporated (three years for the action and in all cases, 10 years) Law 22/1994 implements EEC Directive 85/374 of the Cncl. There is nothing new about the fact that in most cases the builders operating along the coast practice 'blanket' agreements, therefore there will be no important differences in their prices and competition is severely restricted, if it exists at all. However, it is undeniable that the quality of the finished work forms the final true point of competition between the different builders operating in the same geographical area. Theoretically, the quality of the work is standardised in accordance with the Building Regulations issued by the competent Autonomous Region (local governments) in terms of the location of the work. Under this heading the details about the excavation of the land, building of the walls or swimming pool basin along with the details about the concrete and its components and additives intervene, and are established in detail by the Autonomous Region's regulations. However, there is no regulation about the perfection of the finished work and the detail of its components. The customer will always be protected by the Civil Code that states that, as well as the points agreed In the case of house building, the Law 57/1968 obliges the builders to guarantee or insure the amounts handed over on account by the future owners. In Spain there is no specific regulation that applies a similar requirement to builders of edifices not to be used as dwellings. (For example: silos, tanks, stables, etc). When ordering the building of a swimming pool, the guarantees that the builder must accredit to the customer about the amounts handed over on account must be negotiated in the contract. Finally, when the day arrives for the handing over of the completed work with all its details - lighting, water filtering, water maintenance, substance tipping vessels, pumps, electrical boards, etc the customer must personally check the operation of each piece of equipment and product used in the work and obtain copies or originals of the invoices issued by the manufacturers to the builder for the products used in the work, Berrymans Lace Mawer page 7

8 in order to be able to bring the relevant actions before the courts in the case of malfunction or damages derived from malfunction. 'Inspectorate' inspection companies are not frequently used in Spain. These companies in turn certify that the jobs and works have been completed in accordance with the contract and their termination is acceptable in accordance with the acceptance standards. However, in those cases where knowledge of the language is insufficient or the chance of inspecting the development of the work is not possible as the customer lives in another place, it is advisable to seek out the collaboration of a works inspection company which in turn will offer an additional guarantee with the corresponding civil liability insurance. The Spanish courts are slowly extending the idea that the construction of swimming pools, despite being a job perceived by some as of minor importance, is subject to Construction Law, resulting in each person being responsible for the faults or damages in or caused by the work being bound by law jointly and severally before the owner (Articles 9, 10, 11 and successive ones. Construction Arrangement Act Law 38/1999). Likewise, the owners who privately order the building of a swimming pool using a 'key in hand' contract are legally consumers and therefore they are protected by the Consumer and User Defence Act (Law 26/1984) that they can invoke before the courts as well as the Guarantees in the Sale of Consumer Goods Act (Law 23/ implementing EEC Directive 1999/94 of the Plmt & Cncl ) for the products incorporated in the work. If, in the end, the work has been correctly performed and the customer accepts it, there is nothing more for us to do, except wish him a happy holidays. Fernando Beteta Estudio Internacional Abogados, Madrid Events calendar 2006/07 BLM has a very comprehensive programme of events each year offering in depth coverage of key specialist areas. This year highlights include: BLM Claims Review and 11 October Manchester (5 October at New Century House) and London (11 October at One Great George Street) Each full day will feature BLM specialists and expert external speakers covering topics such as EL, PL, costs, quantum, motor, policy development, claims trends, fraud, ADR/mediation and health and safety. Construction Law Seminar Bristol (2 November at IoD Hub) Southampton (January 2007 date and venue tbc) Other events BLM is involved in and is sponsoring a number of seminars run by Post Magazine over the next few months including Management briefing 'Fraud' - 27 September, Claims Club Annual Conference - 11 October, and Management Briefing 'Environmental Claims' 7 December. For full details of our full and half-day seminar programme, please contact: Linda Coppell, Berrymans Lace Mawer, Castle Chambers, 43 Castle Street, Liverpool L2 9SU. T e linda.coppell@blm-law.com DX LIVERPOOL 1 or visit All details are correct at the time of printing and can be subject to change. If you have any questions about the services that BLM can provide, please contact one of the following: Birmingham Leeds Liverpool London Manchester Southampton Stockton-on-Tees Dubai 63 Temple Row Park Row House Castle Chambers Salisbury House King s House Carlton House Innovation House Suite 701 Birmingham Park Row 43 Castle Street London Wall 42 King Street West Carlton Place Yarm Road Al Khaleej Centre B2 5LS Leeds Liverpool London Manchester Southampton Stockton-on-Tees PO Box LS1 5JF L2 9SU EC2M 5QN M3 2NU SO15 2DZ TS18 3TN Dubai, UAE T T T T T T T T +971(0) F F F F F F F F +971(0) DX BIRMINGHAM 1 DX LEEDS 1 DX LIVERPOOL 1 DX FINSBURY SQ DX MANCHESTER 1 DX SOUTHAMPTON DX STOCKTON 8 Disclaimer This document does not present a complete or comprehensive statement of the law, nor does it constitute legal advice. It is intended only to highlight issues that may be of interest to clients of Berrymans Lace Mawer. Specialist legal advice should always be sought in any particular case. 0906_608 page 8 Berrymans Lace Mawer

Examining the current law relating to limitation and causes of action (tortious and contractual) within a construction context

Examining the current law relating to limitation and causes of action (tortious and contractual) within a construction context Examining the current law relating to limitation and causes of action (tortious and contractual) within a construction context Received (in revised form): 11th September, 2005 Sarah Wilson is an associate

More information

The Contractor s building defects liability in England and Wales

The Contractor s building defects liability in England and Wales The Contractor s building defects liability in England and Wales We discuss in this paper in what circumstances can a contractor be found liable for defects discovered by the building occupier several

More information

NEW TEMPLE CHAMBERS. Commercial, Chancery and Construction Barristers CONSTRUCTION LAW AND DISPUTE RESOLUTION BARRISTERS

NEW TEMPLE CHAMBERS.   Commercial, Chancery and Construction Barristers CONSTRUCTION LAW AND DISPUTE RESOLUTION BARRISTERS NEW TEMPLE CHAMBERS Commercial, Chancery and Construction Barristers CONSTRUCTION LAW AND DISPUTE RESOLUTION BARRISTERS www.newtemplechambers.com 0207 203 8468 Contents 3 About Us Instructing Chambers

More information

Adjudication Lifecycle

Adjudication Lifecycle DAC Beachcroft Expertise Pre-Action Is there a construction contact? Is it subject to the Housing Grants Construction and regeneration Act 1996 (the Act )? Is the dispute ready to be referred to adjudication?

More information

Edmund Neuberger PRACTICE CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE. Call Date 2008 //

Edmund Neuberger PRACTICE CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE. Call Date 2008 // CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE PROFESSIONAL NEGLIGENCE ENERGY INFORMATION TECHNOLOGY AND TELECOMMUNICATIONS Edmund Neuberger Call Date 2008 // eneuberger@atkinchambers.com PRACTICE Edmund

More information

Enterprise Managed Services Ltd v East Midland Contracting Ltd [2007] Adj.L.R. 03/27

Enterprise Managed Services Ltd v East Midland Contracting Ltd [2007] Adj.L.R. 03/27 JUDGEMENT : HHJ STEPHEN DAVIES. Manchester District Registry, TCC, 27 th March 2008 A. Introduction 1. On 11 December 2007 the claimant issued these proceedings, in which it seeks to reverse the decision

More information

Version 3.0 December Self-Lay Agreement. for services connecting to our existing network. Scheme Location Reference Date

Version 3.0 December Self-Lay Agreement. for services connecting to our existing network. Scheme Location Reference Date Version 3.0 December 2017 Self-Lay Agreement for services connecting to our existing network Scheme Location Reference Date THIS AGREEMENT is made the day of 20 (note this date to be completed by Thames

More information

IMPROVING PAYMENT PRACTICES IN THE CONSTRUCTION INDUSTRY

IMPROVING PAYMENT PRACTICES IN THE CONSTRUCTION INDUSTRY IMPROVING PAYMENT PRACTICES IN THE CONSTRUCTION INDUSTRY Report of the DTI s post-consultation event held in London on 14th February 2006 On Valentine s Day 2006, the Right Honourable Alun Michael MP compared

More information

RECENT DEVELOPMENTS CONCERNING THE LIABILITY OF BUILDING PROFESSIONALS IN NSW

RECENT DEVELOPMENTS CONCERNING THE LIABILITY OF BUILDING PROFESSIONALS IN NSW RECENT DEVELOPMENTS CONCERNING THE LIABILITY OF BUILDING PROFESSIONALS IN NSW Paper given by Brian Walton to the Annual Conference of the Australian Institute of Building Surveyors 21 22 July 2014 Introduction

More information

David Johnson PRACTICE CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE INTERNATIONAL ARBITRATION. Call Date: 2010 //

David Johnson PRACTICE CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE INTERNATIONAL ARBITRATION. Call Date: 2010 // David Johnson Call Date: 2010 // djohnson@atkinchambers.com CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE PROFESSIONAL NEGLIGENCE JURISDICTION DISPUTES AND CONFLICT OF LAWS GENERAL COMMERCIAL PRACTICE David

More information

Adjudication. Information note. Adjudication

Adjudication. Information note. Adjudication Information note In July 1994 Sir Michael Latham published his report Constructing the Team. In the report were recommendations concerning adjudication. Following these recommendations, provisions for

More information

Pre-Action Protocol for Professional Negligence

Pre-Action Protocol for Professional Negligence Page 1 of 7 Pre-Action Protocol for Professional Negligence PROFESSIONAL NEGLIGENCE PRE-ACTION PROTOCOL THIS PROTOCOL MERGES THE TWO PROTOCOLS PREVIOUSLY PRODUCED BY THE SOLICITORS INDEMNITY FUND (SIF)

More information

OLIVIA WAIYEE LEE Appellant. WHANGAREI DISTRICT COUNCIL Respondent. Winkelmann, Simon France and Woolford JJ

OLIVIA WAIYEE LEE Appellant. WHANGAREI DISTRICT COUNCIL Respondent. Winkelmann, Simon France and Woolford JJ IN THE COURT OF APPEAL OF NEW ZEALAND CA656/2015 [2016] NZCA 258 BETWEEN AND OLIVIA WAIYEE LEE Appellant WHANGAREI DISTRICT COUNCIL Respondent Hearing: 4 May 2016 Court: Counsel: Judgment: Winkelmann,

More information

IN THE HIGH COURT OF JUSTICE CHARLES SAYERS SHERRY SAYERS. and WILLIAM FRANCOIS CLARA FRANCOIS

IN THE HIGH COURT OF JUSTICE CHARLES SAYERS SHERRY SAYERS. and WILLIAM FRANCOIS CLARA FRANCOIS SAINT LUCIA IN THE HIGH COURT OF JUSTICE SUIT NO.: 1061 of 1996 BETWEEN CHARLES SAYERS SHERRY SAYERS and WILLIAM FRANCOIS CLARA FRANCOIS Plaintiffs Defendants Appearances Mr. W. Hinkson for the Plaintiffs

More information

Before: MR JUSTICE AKENHEAD Between: BECK INTERIORS LIMITED - and - UK FLOORING CONTRACTORS LIMITED

Before: MR JUSTICE AKENHEAD Between: BECK INTERIORS LIMITED - and - UK FLOORING CONTRACTORS LIMITED Neutral Citation Number: [2012] EWHC 1808 (TCC) Case No: HT-12-176 IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION TECHNOLOGY AND CONSTRUCTION COURT Before: MR JUSTICE AKENHEAD - - - - - - - - - -

More information

Alternative Dispute Resolution (ADR) In Chapter 36 of his Final Report Jackson LJ wrote:

Alternative Dispute Resolution (ADR) In Chapter 36 of his Final Report Jackson LJ wrote: Alternative Dispute Resolution (ADR) In Chapter 36 of his Final Report Jackson LJ wrote: 4.2 I recommend that: (i) There should be a serious campaign (a) to ensure that all litigation lawyers and judges

More information

Arbitration Act 1996

Arbitration Act 1996 Arbitration Act 1996 An Act to restate and improve the law relating to arbitration pursuant to an arbitration agreement; to make other provision relating to arbitration and arbitration awards; and for

More information

White Young Green Consulting v Brooke House Sixth Form College [2007] APP.L.R. 05/22

White Young Green Consulting v Brooke House Sixth Form College [2007] APP.L.R. 05/22 JUDGMENT : Mr Justice Ramsey : TCC. 22 nd May 2007 Introduction 1. This is an application for leave to appeal under s.69(3) of the Arbitration Act 1996. The arbitration concerns the appointment of the

More information

A GUIDE TO SERVING ON A STRATA COMMITTEE

A GUIDE TO SERVING ON A STRATA COMMITTEE A GUIDE TO SERVING ON A STRATA COMMITTEE 2 CONTENTS A GUIDE TO SERVING ON A STRATA COMMITTEE 3 The Decision Making Powers of a Strata Committee Restrictions to the Decision Making Powers of The Committee

More information

GUIDE TO ARBITRATION

GUIDE TO ARBITRATION GUIDE TO ARBITRATION Arbitrators and Mediators Institute of New Zealand Inc. Level 3, Hallenstein House, 276-278 Lambton Quay P O Box 1477, Wellington, New Zealand Tel: 64 4 4999 384 Fax: 64 4 4999 387

More information

Unit 5 : ADJUDICATION

Unit 5 : ADJUDICATION Unit 5 : ADJUDICATION WHAT IS ADJUDICATION? Adjudication is a quick and inexpensive process in which an independent third party makes binding decisions on construction contract disputes. The adjudicator

More information

The Pre-Action Protocol for Resolution of Package Travel Claims is approved by the Master of the Rolls as Head of Civil Justice.

The Pre-Action Protocol for Resolution of Package Travel Claims is approved by the Master of the Rolls as Head of Civil Justice. The Pre-Action Protocol for Resolution of Package Travel Claims is approved by the Master of the Rolls as Head of Civil Justice. The Right Honourable Sir Terence Etherton Master of the Rolls and Head of

More information

Index. Volume 21 (2005) 21 BCL

Index. Volume 21 (2005) 21 BCL Index Abandoned claims judgment on, principally concerned with costs, 12-13, 33-44 whether cost reduction appropriate because of, 125 Access to the premises AS 4917-2003, 9-10 Acts Interpretation Act 1954

More information

Declan Redmond T: +44 (0) E:

Declan Redmond T: +44 (0) E: Keating Chambers 15 Essex Street London WC2R 3AA T +44 (0)20 7544 2600 F +44 (0)20 7544 2700 keatingchambers.com DX: LDE 1045 Call: 2008 pbury@keatingchambers.com Areas of practice Clerks' Details Construction

More information

Construction & Engineering News

Construction & Engineering News Construction & Engineering News Spring 2010 When will the Court pierce the adjudicator s veil? - Geoffrey Osborne Limited v Atkins Rail Limited [2009] (TCC) Enforcing the Oracle SG South Ltd v Swan Yard

More information

Mott MacDonald Ltd v London & Regional Properties Ltd [2007] Adj.L.R. 05/23

Mott MacDonald Ltd v London & Regional Properties Ltd [2007] Adj.L.R. 05/23 JUDGMENT : HHJ Anthony Thornton QC. TCC. 23 rd May 2007 1. Introduction 1. The claimant, Mott MacDonald Ltd ( MM ) is a specialist engineering multi-disciplinary consultancy providing services to the construction

More information

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory Arbitration Act 1996 1996 CHAPTER 23 1 Part I Arbitration pursuant to an arbitration agreement Introductory 1. General principles. 2. Scope of application of provisions. 3. The seat of the arbitration.

More information

TERMS AND CONDITIONS. BACKGROUND: These Terms and Conditions shall apply to the provision of cleaning services by Cambridge Doms to clients.

TERMS AND CONDITIONS. BACKGROUND: These Terms and Conditions shall apply to the provision of cleaning services by Cambridge Doms to clients. Page 1 of 13 TERMS AND CONDITIONS BACKGROUND: These Terms and Conditions shall apply to the provision of cleaning services by Doms to clients. 1. Definitions and Interpretation 1.1 In these Terms and Conditions,

More information

CONSTRUCTION BRIEFING November 2016

CONSTRUCTION BRIEFING November 2016 CONSTRUCTION BRIEFING November 2016 New Pre-Action Protocol for Construction and Engineering Disputes launched The Second Edition of the Pre-Action Protocol for Construction and Engineering Disputes comes

More information

AUCKLAND DISTRICT LAW SOCIETY INC. JAMIE WAUGH- BARRISTER TERMS OF ENGAGEMENT

AUCKLAND DISTRICT LAW SOCIETY INC. JAMIE WAUGH- BARRISTER TERMS OF ENGAGEMENT AUCKLAND DISTRICT LAW SOCIETY INC. JAMIE WAUGH- BARRISTER TERMS OF ENGAGEMENT IMPORTANT INFORMATION FOR INSTRUCTING SOLICITORS AND CLIENTS Currently, with limited exceptions, as a barrister I am required

More information

THE NEW PRE-ACTION PROTOCOL FOR CONSTRUCTION AND ENGINEERING DISPUTES

THE NEW PRE-ACTION PROTOCOL FOR CONSTRUCTION AND ENGINEERING DISPUTES BRIEFING THE NEW PRE-ACTION PROTOCOL FOR CONSTRUCTION AND ENGINEERING DISPUTES JANUARY 2017 PRE-ACTION PROTOCOL REMAINS COMPULSORY BUT PROCEDURE HAS BEEN SCALED BACK COSTS CONSEQUENCES WILL BE IMPOSED

More information

SPAFORM CONSUMER WARRANTY 2006 YOUR STATUTORY RIGHTS ARE NOT AFFECTED BY THIS WARRANTY.

SPAFORM CONSUMER WARRANTY 2006 YOUR STATUTORY RIGHTS ARE NOT AFFECTED BY THIS WARRANTY. SPAFORM CONSUMER WARRANTY 2006 YOUR STATUTORY RIGHTS ARE NOT AFFECTED BY THIS WARRANTY. 1. DEFINITIONS In this warranty: "Authorised Dealer" means either Spaform or a dealer approved by Spaform, a list

More information

Introduction Agreement

Introduction Agreement Introduction Agreement between Spigo Malta Ltd. and Introducer Table of Contents 1.Interpretation...3 2.Introductions...4 3.Anti-bribery compliance...5 4.Commission and payment...6 5.Obligations of Spigo...8

More information

RSR LIMITED TERMS AND CONDITIONS OF SUPPLY (GOODS AND SERVICES)

RSR LIMITED TERMS AND CONDITIONS OF SUPPLY (GOODS AND SERVICES) RSR LIMITED TERMS AND CONDITIONS OF SUPPLY (GOODS AND SERVICES) 1. DEFINITIONS In these Conditions: Business Day means a day other than a Saturday, Sunday or public holiday in England when banks in London

More information

The new Arbitration (Guernsey) Law, a guide to the key provisions

The new Arbitration (Guernsey) Law, a guide to the key provisions JERSEY GUERNSEY LONDON BVI SINGAPORE GUERNSEY BRIEFING May 2017 The new Arbitration (Guernsey) Law, 2016 - a guide to the key provisions Historically, parties in Guernsey have been reluctant to use arbitration

More information

Technical claims brief. Monthly update May 2011

Technical claims brief. Monthly update May 2011 Technical claims brief Monthly update May 2011 Contents Technical claims brief Monthly update May 2011 News 1 Association of Personal Injury Lawyers initiates judicial review of discount rate 1 Ministry

More information

B. Warranty for Latent Defects Reported After the First Ninety Days But Prior to Expiration Date

B. Warranty for Latent Defects Reported After the First Ninety Days But Prior to Expiration Date LIMITED WARRANTY AGREEMENT This limited warranty agreement (this Agreement ) is extended by D3 Design/Build LLC (the Builder ), whose address is PO Box 21144, Seattle, WA 98111, to the original buyer(s)

More information

The NEW Pre-Action Protocol for Construction and Engineering Disputes. Simon Tolson

The NEW Pre-Action Protocol for Construction and Engineering Disputes. Simon Tolson The NEW Pre-Action Protocol for Construction and Engineering Disputes Simon Tolson Introduction - A bit of background on the Protocol The Pre-Action Protocol for Construction and Engineering Disputes (the

More information

Shalson v DF Keane Ltd [2003] Adj.LR. 02/21

Shalson v DF Keane Ltd [2003] Adj.LR. 02/21 JUDGMENT : Mr Justice Blackburne. Ch. Div. 21 st February 2003. 1. This is an appeal against orders made by Chief Registrar James on 28 November 2002, dismissing two applications by Peter Shalson to set

More information

DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY Introductory Provisions. Article (1) Definitions

DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY Introductory Provisions. Article (1) Definitions DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY 2011 Introductory Provisions Article (1) Definitions 1.1 The following words and phrases shall have the meaning assigned thereto unless

More information

Building and Construction Industry Security of Payment Act 1999 No 46

Building and Construction Industry Security of Payment Act 1999 No 46 Building and Construction Industry Security of Payment Act 1999 No 46 Current version for 27 June 2017 to date (accessed 15 November 2017 at 14:57) Status information New South Wales Status information

More information

Ahmad Al-Naimi (t/a Buildmaster Construction Services) v. Islamic Press Agency Inc [2000] APP.L.R. 01/28

Ahmad Al-Naimi (t/a Buildmaster Construction Services) v. Islamic Press Agency Inc [2000] APP.L.R. 01/28 CA on Appeal from High Court of Justice TCC (HHJ Bowsher QC) before Waller LJ; Chadwick LJ. 28 th January 2000. JUDGMENT : Lord Justice Waller: 1. This is an appeal from the decision of His Honour Judge

More information

Elements of a Civil Claim

Elements of a Civil Claim Elements of a Civil Claim This presentation provides an overview of the elements of a civil claim, with particular reference to construction claims, and looks at each dispute resolution option in the context

More information

Independent Arbitration Service for Customers Service Rules Cavity Insulation Guarantee Agency (CIGA)

Independent Arbitration Service for Customers Service Rules Cavity Insulation Guarantee Agency (CIGA) Independent Arbitration Service for Customers Service Rules Cavity Insulation Guarantee Agency (CIGA) These Rules apply to applications forms received by Centre for Effective Dispute Resolution (CEDR)

More information

Skanska Rashleigh Weatherfoil Ltd v Somerfield Stores Ltd [2006] ABC.L.R. 11/22

Skanska Rashleigh Weatherfoil Ltd v Somerfield Stores Ltd [2006] ABC.L.R. 11/22 CA on appeal from QBD (Mr Justice Ramsey) before Neuberger LJ; Richards LJ; Leveson LJ. 22 nd November 2006 LORD JUSTICE NEUBERGER: 1. This is an appeal from the decision of Ramsey J on the preliminary

More information

PRIVATE INTERNATIONAL LAW : CONFLICT OF LAWS

PRIVATE INTERNATIONAL LAW : CONFLICT OF LAWS Arbitration under the Arbitration Act 1996 Aim: To provide a clear outline of the principal issues relating to the legally binding resolution of conflict of laws disputes via arbitration under the Arbitration

More information

SUPPLY AGREEMENT TERMS AND CONDITIONS OF PURCHASE (INFLIGHT SERVICES) SELLER IS ADVISED TO READ THESE TERMS & CONDITIONS CAREFULLY

SUPPLY AGREEMENT TERMS AND CONDITIONS OF PURCHASE (INFLIGHT SERVICES) SELLER IS ADVISED TO READ THESE TERMS & CONDITIONS CAREFULLY SUPPLY AGREEMENT TERMS AND CONDITIONS OF PURCHASE (INFLIGHT SERVICES) SELLER IS ADVISED TO READ THESE TERMS & CONDITIONS CAREFULLY THIS SUPPLY AGREEMENT (the Agreement ) is made on the applicable dates

More information

Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland

Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland (Royaume-Uni - Royaume-Uni de Grande-Bretagne et d'irlande du Nord) ARBITRATION ACT 1996 1996 CHAPTER 23 An Act to

More information

BUILDING SERVICES CORPORATION ACT 1989 Na 147

BUILDING SERVICES CORPORATION ACT 1989 Na 147 BUILDING SERVICES CORPORATION ACT 1989 Na 147 NEW SOUTH WALES 1. Short title 2. Commencement 3. Definitions TABLE OF PROVISIONS PART 1 - PRELIMINARY PART 2 - REGULATION OF RESIDENTIAL BUILDING WORK AND

More information

The material in this paper is based upon the law of England and Wales.

The material in this paper is based upon the law of England and Wales. DESIGN LIABILITY: REASONABLE SKILL AND CARE OR FITNESS FOR PURPOSE May 2016 ADAM ROBB The material in this paper is based upon the law of England and Wales. This material is only intended to provoke and

More information

CONDITIONS OF APPOINTMENT

CONDITIONS OF APPOINTMENT CONDITIONS OF APPOINTMENT CONDITIONS OF APPOINTMENT 1 The Landscape Consultant s Authority and Obligations Duty of Care 1.1 The Landscape Consultant has exercised and shall continue to exercise reasonable

More information

Projects Disputes in Australia: Recent Cases

Projects Disputes in Australia: Recent Cases WHITE PAPER June 2017 Projects Disputes in Australia: Recent Cases The High Court of Australia and courts in other Australian States have recently ruled on matters of significant importance to the country

More information

GUIDANCE FOR ADJUDICATORS

GUIDANCE FOR ADJUDICATORS CONSTRUCTION UMBRELLA BODIES ADJUDICATION TASK GROUP JULY 2002 GUIDANCE FOR ADJUDICATORS Guidance for adjudicators in adjudications conducted under Part II of the Housing Grants, Construction and Regeneration

More information

New Zealand Institute of Chartered Accountants RULES OF THE NEW ZEALAND INSTITUTE OF CHARTERED ACCOUNTANTS EFFECTIVE 26 JUNE 2017 CONTENTS

New Zealand Institute of Chartered Accountants RULES OF THE NEW ZEALAND INSTITUTE OF CHARTERED ACCOUNTANTS EFFECTIVE 26 JUNE 2017 CONTENTS New Zealand Institute of Chartered Accountants RULES OF THE NEW ZEALAND INSTITUTE OF CHARTERED ACCOUNTANTS EFFECTIVE 26 JUNE 2017 CONTENTS Rule no Page no 1. INTERPRETATION...1 2. FUNCTIONS...2 3. MEMBERSHIP...3

More information

SCOPE AND EXTENT OF ENGINEERS LEGAL RESPONSIBILITIES FOR DEFECTS AND CONSTRUCTION ACTIVITIES ON SITE

SCOPE AND EXTENT OF ENGINEERS LEGAL RESPONSIBILITIES FOR DEFECTS AND CONSTRUCTION ACTIVITIES ON SITE IES-MOM Seminar on "Moving Beyond Nicoll Highway Incident" SCOPE AND EXTENT OF ENGINEERS LEGAL RESPONSIBILITIES FOR DEFECTS AND CONSTRUCTION ACTIVITIES ON SITE presented by MONICA NEO Advocate & Solicitor

More information

MIB Untraced Drivers Agreement

MIB Untraced Drivers Agreement MIB Untraced Drivers Agreement THIS AGREEMENT is made on the 28 th February 2017 between the SECRETARY OF STATE FOR TRANSPORT ( the Secretary of State ) and the MOTOR INSURERS BUREAU ( MIB ), whose registered

More information

USERS GUIDE TO ADJUDICATION

USERS GUIDE TO ADJUDICATION USERS GUIDE TO ADJUDICATION CONSTRUCTION UMBRELLA BODIES ADJUDICATION TASK GROUP APRIL 2003 USERS GUIDE TO ADJUDICATION A guide for participants in adjudications conducted under Part II of the Housing

More information

Cuthbert v Gair (t/a The Bowes Manor Equestrian Centre) [2008] APP.L.R. 09/03

Cuthbert v Gair (t/a The Bowes Manor Equestrian Centre) [2008] APP.L.R. 09/03 JUDGMENT : Master Haworth : Costs Court. 3 rd September 2008 1. This is an appeal pursuant to CPR Rule 47.20 from a decision of Costs Officer Martin in relation to a detailed assessment which took place

More information

CEDR Arbitration Procedure for Surveying Disputes

CEDR Arbitration Procedure for Surveying Disputes CENTRE for EFFECTIVE DISPUTE RESOLUTION www.cedr.com CEDR Arbitration Procedure for Surveying Disputes 70 Fleet Street, London EC4Y 1EU Tel: +44 (0)20 7536 6060 Fax: +44 (0)20 7536 6001 email: adr@cedr.com

More information

Birse Construction Ltd. v McCormick (U.K.) Ltd [2004] ABC.L.R. 12/09

Birse Construction Ltd. v McCormick (U.K.) Ltd [2004] ABC.L.R. 12/09 JUDGMENT : HIS HONOUR JUDGE PETER COULSON Q.C: TCC. 9 th December 2004. [1] INTRODUCTION 1. Pursuant to a Claim Form issued on 23 rd May 2003, Birse Construction Limited ("Birse") sought the sum of 810,165

More information

9/13/2013 gerard o sullivan Mulcahy McDonagh & Partners 1

9/13/2013 gerard o sullivan Mulcahy McDonagh & Partners 1 STATUTORY IMPLIED PAYMENT TERMS AND STATUTORY ADJUDCIATION THE CONSTRUCTION CONTRACTS ACT Number 34 of 2013 SEPTEMBER 2013 Gerry O Sullivan FSCSI FRICS FCIArb 9/13/2013 gerard o sullivan Mulcahy McDonagh

More information

International Conditions of Sale for Customers not Resident in Germany

International Conditions of Sale for Customers not Resident in Germany I. Application of the International Conditions of Sale 1. These International Conditions of Sale apply to all customers of Dr. Günther Kast GmbH & Co. Technische Gewebe Spezial-Fasererzeugnisse KG - hereinafter

More information

Limitations Act 2002: A huge reform of existing law

Limitations Act 2002: A huge reform of existing law Limitations Act 2002: A huge reform of existing law by Graeme Mew Gowling Lafleur Henderson LLP On December 9, 2002, the Ontario legislature passed Bill 213 - the Justice Statute Law Amendment Act - by

More information

FINAL DETERMINATION Adjudicator: P A McConnell

FINAL DETERMINATION Adjudicator: P A McConnell IN THE WEATHERTIGHT HOMES TRIBUNAL TRI-2012-100-000058 [2013] NZWHT AUCKLAND 12 BETWEEN AND AND AND AND ENGELA SOUTH TRUSTEE LIMITED Claimant AUCKLAND COUNCIL First Respondent R J NEALE LIMITED Second

More information

PART I ARBITRATION - CHAPTER I

PART I ARBITRATION - CHAPTER I INDIAN BARE ACTS THE ARBITRATION AND CONCILIATION ACT, 1996 No.26 of 1996 [16th August, 1996] An Act to consolidate and amend the law relating to domestic arbitration, international commercial arbitration

More information

BIG ISLAND CONSTRUCTION (HONG KONG) LTD v ABDOOLALLY EBRAHIM & CO (HONG KONG) LTD - [1994] 3 HKC 518

BIG ISLAND CONSTRUCTION (HONG KONG) LTD v ABDOOLALLY EBRAHIM & CO (HONG KONG) LTD - [1994] 3 HKC 518 1 BIG ISLAND CONSTRUCTION (HONG KONG) LTD v ABDOOLALLY EBRAHIM & CO (HONG KONG) LTD - [1994] 3 HKC 518 HIGH COURT KAPLAN J ACTION NO 11313 OF 1993 28 July 1994 Civil Procedure -- Summary judgment -- Lack

More information

JCLI Scottish Landscape Maintenance Works Agreement April 2017 (JCLI SLMWA )

JCLI Scottish Landscape Maintenance Works Agreement April 2017 (JCLI SLMWA ) JCLI Scottish Landscape Maintenance Works Agreement April 2017 (JCLI SLMWA 2017-04) for use with the JCLI Landscape Maintenance Works Contract 2017 (JCLI LMWC 2017) JCLI Scottish Landscape Maintenance

More information

TRADING TERMS OF KLINGER LTD

TRADING TERMS OF KLINGER LTD 1. INTERPRETATION 1.1 In these terms of trade: (1) Business Day means a day other than Saturday, Sunday or a public holiday in the place in which a document is received or an act is done, as may be applicable;

More information

Guide: An Introduction to Litigation

Guide: An Introduction to Litigation Guide: An Introduction to Litigation Matthew Purcell, Head of Dispute Resolution Saunders Law Solicitors The aim of this guide This guide is designed to provide an outline of how to resolve a commercial

More information

RESPONSE TO REVIEW OF THE CONSTRUCTION CONTRACTS (SECURITY OF PAYMENTS) ACT (NT): ISSUES PAPER OCTOBER 2017

RESPONSE TO REVIEW OF THE CONSTRUCTION CONTRACTS (SECURITY OF PAYMENTS) ACT (NT): ISSUES PAPER OCTOBER 2017 HIA Submission to the Department of Attorney-General & Justice RESPONSE TO REVIEW OF THE CONSTRUCTION CONTRACTS (SECURITY OF PAYMENTS) ACT (NT): ISSUES PAPER OCTOBER 2017 28 November 2017 1. EXECUTIVE

More information

ADJUDICATION REPORTING CENTRE

ADJUDICATION REPORTING CENTRE ADJUDICATION REPORTING CENTRE RESEARCH ANALYSIS OF THE PROGRESS OF ADJUDICATION BASED ON RETURNED QUESTIONNAIRES FROM ADJUDICATOR NOMINATING BODIES (ANBs) AND ON QUESTIONNAIRES RETURNED BY ADJUDICATORS

More information

Fisyon Trade General Business / Delivery and Payment Conditions

Fisyon Trade General Business / Delivery and Payment Conditions Fisyon Trade General Business / Delivery and Payment Conditions 1 General 1.1 These General Terms and Conditions of Sale shall apply to all of our business relationships with our customers. These Conditions

More information

Did You Blow the Statute of Limitations?

Did You Blow the Statute of Limitations? Did You Blow the Statute of Limitations? The Effect of Title 7 on a Community Association s Right to Sue for Construction Defects Tyler P. Berding, Esq. It s 1998. The plumbing in your association s 5-year

More information

Website Disclaimer. by SEQ Legal

Website Disclaimer. by SEQ Legal Website Disclaimer by SEQ Legal Website disclaimer 1 (1) Introduction This disclaimer governs your use of our website; by using our website, you accept this disclaimer in full. 2 If you disagree with any

More information

LLOYD'S STANDARD FORM OF SALVAGE AGREEMENT LLOYD'S STANDARD SALVAGE AND ARBITRATION CLAUSES

LLOYD'S STANDARD FORM OF SALVAGE AGREEMENT LLOYD'S STANDARD SALVAGE AND ARBITRATION CLAUSES LLOYD'S STANDARD FORM OF SALVAGE AGREEMENT (Approved and Published by the Council of Lloyd's) LLOYD'S STANDARD SALVAGE AND ARBITRATION CLAUSES 1 Introduction 1.1 These clauses ( the LSSA Clauses ) or any

More information

THE BUILDING CONTROL AMENDMENT REGULATIONS. Martin Waldron BL

THE BUILDING CONTROL AMENDMENT REGULATIONS. Martin Waldron BL MARTIN WALDRON BL FCIArb MSCSI MRICS Accredited Adjudicator & Mediator Law Library The Four Courts Dublin 7 +353(1)8177865 +353(86)2395167 www.waldron.ie martin@waldron.ie THE BUILDING CONTROL AMENDMENT

More information

Evidence in International Arbitration. Expert Evidence / Expert Determination Clause. 莫世傑 / Danny Mok CILTHK 9 April 2017

Evidence in International Arbitration. Expert Evidence / Expert Determination Clause. 莫世傑 / Danny Mok CILTHK 9 April 2017 Evidence in International Arbitration / Expert Determination Clause 莫世傑 / Danny Mok CILTHK 9 April 2017 1 Why necessary Finding of facts is the duty of the judge / arbitrator, but he or she should not

More information

Evolution of dispute resolution under the FIDIC Red Book. Bill Smith, Partner 10 May 2018

Evolution of dispute resolution under the FIDIC Red Book. Bill Smith, Partner 10 May 2018 Evolution of dispute resolution under the FIDIC Red Book Bill Smith, Partner 10 May 2018 Outline Disputes why a dispute resolution procedure is needed How the dispute resolution provisions in the FIDIC

More information

STANDARD CFA TERMS AND CONDITIONS FOR PERSONAL INJURY CASES TREATED AS ANNEXED TO THE CONDITIONAL FEE AGREEMENT BETWEEN SOLICITOR AND COUNSEL

STANDARD CFA TERMS AND CONDITIONS FOR PERSONAL INJURY CASES TREATED AS ANNEXED TO THE CONDITIONAL FEE AGREEMENT BETWEEN SOLICITOR AND COUNSEL STANDARD CFA TERMS AND CONDITIONS FOR PERSONAL INJURY CASES TREATED AS ANNEXED TO THE CONDITIONAL FEE AGREEMENT BETWEEN SOLICITOR AND COUNSEL FOR USE AFTER 31 JANUARY 2013 PLEASE NOTE: THESE TERMS WILL

More information

THE CHARTERED INSTITUTE OF LEGAL EXECUTIVES RIGHTS OF AUDIENCE QUALIFICATION SCHEME

THE CHARTERED INSTITUTE OF LEGAL EXECUTIVES RIGHTS OF AUDIENCE QUALIFICATION SCHEME THE CHARTERED INSTITUTE OF LEGAL EXECUTIVES RIGHTS OF AUDIENCE QUALIFICATION SCHEME GUIDELINES FOR APPLICANTS COMPLETING AN APPLICATION FOR A CERTICATE OF ELIGIBILITY INTRODUCTION These guidance notes

More information

1.2. This book covers the three Agreements published by JBCC (see 2.1 below) and the MBSA 2014 Domestic Subcontract Agreement.

1.2. This book covers the three Agreements published by JBCC (see 2.1 below) and the MBSA 2014 Domestic Subcontract Agreement. JBCC March 2014 AGREEMENTS 1 2 3 4 5 6 7 Text books available concerning JBCC 2014 General - Contract Documents issued by JBCC Synopsis of important changes JBCC PBA 2007 2014 Contract Data Tender process

More information

OEM Supply Agreement

OEM Supply Agreement OEM Supply Agreement PAAMA Agrico Pvt. Ltd. OEM Supply Agreement between PAAMA Agrico Pvt Ltd & (here in after referred to as the SUPPLIER) Preamble PAPL has approached THE SUPPLIER for the supply of products

More information

The Labour Relations Agency Arbitration Scheme. Guide to the Scheme

The Labour Relations Agency Arbitration Scheme. Guide to the Scheme The Labour Relations Agency Arbitration Scheme Guide to the Scheme Labour Relations Agency The Labour Relations Agency is an independent, publicly funded organisation. Our job is to promote good employment

More information

Adjudication Claim Dated [insert date]

Adjudication Claim Dated [insert date] Under the Construction Contracts Act 2002 IN THE MATTER of an Adjudication BETWEEN ABC CONSTRUCTION LTD Claimant AND JOHN DOE Respondent [AND JANE DOE] [Owner] (only relevant to an adjudication brought

More information

TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES

TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES THE CUSTOMER'S ATTENTION IS PARTICULARLY DRAWN TO THE PROVISIONS OF CLAUSE 8 (LIMITATION OF LIABILITY). 1. Interpretation The following definitions and rules

More information

PUBLIC ACCESS: HOW TO GIVE A DIRECT INSTRUCTION TO A BARRISTER

PUBLIC ACCESS: HOW TO GIVE A DIRECT INSTRUCTION TO A BARRISTER 7 PUBLIC ACCESS: HOW TO GIVE A DIRECT INSTRUCTION TO A BARRISTER This document is published by Practical Law and can be found at: uk.practicallaw.com/w-010-6430 Get more information on Practical Law and

More information

International Conditions of Sale for Customers not Resident in Germany

International Conditions of Sale for Customers not Resident in Germany International Conditions of Sale for Customers not Resident in Germany I. Application of the International Conditions of Sale 1. These International Conditions of Sale apply to all customers of Feldhaus

More information

Myths of Brexit. Speech at Brexit Conference in Hong Kong. The Right Honourable Lord Justice Hamblen. 2 December 2017

Myths of Brexit. Speech at Brexit Conference in Hong Kong. The Right Honourable Lord Justice Hamblen. 2 December 2017 Myths of Brexit Speech at Brexit Conference in Hong Kong The Right Honourable Lord Justice Hamblen 2 December 2017 This was a Conference organised by the Hong Kong Department of Justice entitled: Impact

More information

Combar/CLLS Guidance note on the Agreement for the Supply of Services by a Barrister in a Commercial Case

Combar/CLLS Guidance note on the Agreement for the Supply of Services by a Barrister in a Commercial Case Combar/CLLS Guidance note on the Agreement for the Supply of Services by a Barrister in a Commercial Case Introduction... 2 Background... 2 Entering into an agreement incorporating the Terms... 3 The Services...

More information

Professional Services Agreement (short form)

Professional Services Agreement (short form) Professional Services Agreement (short form) Contract Details Item No Item Details 1 Project [#insert name of project and description] 2 JCU Name: James Cook University Address: 1 James Cook Drive, Townsville,

More information

Arbitration Agreement

Arbitration Agreement Arbitration Agreement (Domestic & International Arbitrations) Written By S. Ravi Shankar Advocate on Record Supreme Court of India Senior Partner - Law Senate Law Firm National President - Arbitration

More information

Building and Construction Industry Security of Payment Act 1999

Building and Construction Industry Security of Payment Act 1999 Building and Construction Industry Security of Payment Act 1999 Reprint history: Reprint No 1 30 September 2003 Long Title An Act with respect to payments for construction work carried out, and related

More information

The SIAC Arbitration Rules 2016: A detailed look at the new rules 1 August 2016

The SIAC Arbitration Rules 2016: A detailed look at the new rules 1 August 2016 The SIAC Arbitration Rules 2016: A detailed look at the new rules 1 August 2016 The SIAC Arbitration Rules 2016 (the 2016 Rules) came into force on 1 August 2016 and apply to all arbitrations commenced

More information

Alister Holden & Murray Bridge as Trustees of the Estate of Bruce Morris Claimants. Peter Hanns trading as Hanns Builders & Joiners First Respondent

Alister Holden & Murray Bridge as Trustees of the Estate of Bruce Morris Claimants. Peter Hanns trading as Hanns Builders & Joiners First Respondent WEATHERTIGHT HOMES TRIBUNAL CLAIM NO: TRI-2008-101-109 BETWEEN AND AND AND AND AND AND AND Alister Holden & Murray Bridge as Trustees of the Estate of Bruce Morris Claimants Vivienne Smitheram & Bernard

More information

TERMS AND CONDITIONS OF SALES

TERMS AND CONDITIONS OF SALES 1. Acceptance No Contract, Order or information (literature, drawings etc.) provided to or by the Purchaser shall be binding on Infra Green Ltd unless confirmed in the Infra Green Ltd Order Confirmation.

More information

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS ICON DRILLING ABN 75 067 226 484 PURCHASE ORDER TERMS & CONDITIONS Acceptance of this offer is subject to the terms and conditions of this Agreement. Acceptance of materials, work or services, payment

More information

Serco Limited Purchase Order Terms and Conditions (the "PO Terms")

Serco Limited Purchase Order Terms and Conditions (the PO Terms) 1. Definitions and Interpretation For the purpose of these Conditions: 1.1 "Affiliate" means any entity that directly or indirectly through one or more intermediaries, controls or is under the control

More information

CHAPTER 4 THE ARBITRATION AND CONCILIATION ACT. Arrangement of Sections.

CHAPTER 4 THE ARBITRATION AND CONCILIATION ACT. Arrangement of Sections. CHAPTER 4 THE ARBITRATION AND CONCILIATION ACT. Arrangement of Sections. Section 1. Application. 2. Interpretation. PART I PRELIMINARY. PART II ARBITRATION. 3. Form of arbitration agreement. 4. Waiver

More information

Conditions of Contract for Purchase of Goods and Services

Conditions of Contract for Purchase of Goods and Services Conditions of Contract for Purchase of Goods and Services DOCUMENT GOVERNANCE Policy Owner Head of Procurement Effective date 1 March 2017 This policy will be reviewed every six months. CONTENTS 1. DEFINITIONS

More information

In the field of construction, Felicity has experience of bespoke and standard form contracts and is familiar with the JCT and NEC forms.

In the field of construction, Felicity has experience of bespoke and standard form contracts and is familiar with the JCT and NEC forms. CONSTRUCTION, ENGINEERING AND INFRASTRUCTURE PROFESSIONAL NEGLIGENCE ADJUDICATION INFORMATION TECHNOLOGY AND TELECOMMUNICATIONS GUARANTEES AND INDEMNITIES GENERAL COMMERCIAL Felicity Dynes Call Date 2010

More information