Fisher, Stephen J v Sunho Construction Pte Ltd

Size: px
Start display at page:

Download "Fisher, Stephen J v Sunho Construction Pte Ltd"

Transcription

1 This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher s duty in compliance with the law, for publication in LawNet and/or the Singapore Law Reports. Fisher, Stephen J v Sunho Construction Pte Ltd [2018] SGHC 76 High Court Originating Summons No 388 of 2017 Kannan Ramesh J 8; 18 August; 8, 15 September; 27 November 2017 Arbitration recourse against award setting aside 29 March 2018 Kannan Ramesh J: Introduction 1 The plaintiff applied by Originating Summons ( OS ) No 278 of 2017 ( OS 278 ) for leave to appeal to the court on questions of law arising out of an arbitral award ( the Award ), under s 49 of the Arbitration Act (Cap 10, 2002 Rev Ed) ( the Act ). The plaintiff also applied by OS No 388 of 2017 ( OS 388 ) for the Award to be set aside for breach of natural justice and on the basis that it was contrary to public policy, under s 48(1) of the Act. Having heard the parties submissions, I dismissed both OS 278 and OS 388. The plaintiff has appealed against my decision in OS 388. As no appeal has been filed against my decision in OS 278, I say nothing further on that application save for the observation below (see [44]). I now give the reasons for my decision in OS 388.

2 Facts The parties 2 The plaintiff Stephen J Fisher is the owner of a property along Ocean Drive, Sentosa ( the Property ). He purchased the Property intending to develop it for his matrimonial home. 3 The defendant Sunho Construction Pte Ltd is a Singapore incorporated company that carried on the business of providing construction services. Background to the dispute 4 The facts of the dispute referred to arbitration were strongly contested by both sides. For present purposes, a broad account of the background facts to set the context for the issues raised by the plaintiff in OS 388 would suffice. 5 By a contract dated 14 July 2006 ( the Contract ), the plaintiff engaged the defendant as main contractor to build a house for the sum of $1,980,000. Under the Contract, GUZ Architects was appointed as the architect for the project ( the Architect ) while Barton Associates Pte Ltd was appointed as the Quantity Surveyor ( the Quantity Surveyor ). The Contract incorporated the Singapore Institute of Architects Articles and Conditions of Building Contract ( the SIA Conditions ). 6 As things turned out, there was substantial delay in the completion of the project. The scheduled completion date was 1 December By April 2008, the project had not been completed. In a bid to expedite the completion of the project, the plaintiff appointed Mr Chow Chee Meng ( Mr Chow ) to help facilitate completion of the project. It would appear that Mr Chow assisted from June 2008 to August

3 7 On 2 June 2008, the Architect issued a delay certificate under the Contract declaring that the defendant was in default for not having completed the works by the scheduled completion date. 8 Subsequently, on 26 June 2008, the defendant submitted extension of time claims ( EOT Claims ) to the Architect amounting to 287 days. On 11 May 2009, the Architect allowed the EOT Claims in part to the extent of 60 days (see [11] below]. The EOT Claims that were allowed and the other EOT Claims were the subject of dispute in the arbitration. For present purposes, it suffices to note that the plaintiff was of the view that the defendant was in delay due to severe financial difficulties whereas the defendant contended that it had met with numerous delaying events that entitled it to extensions of time under the Contract. 9 Mr Chow subsequently returned to the project in December 2008 upon the execution of a Memorandum of Understanding ( MOU ) between the parties. A copy of the MOU was placed before me and was of some relevance given that the remuneration of Mr Chow was another issue considered in the Award. It was relevant to note the MOU did not state that the defendant would pay Mr Chow any remuneration or bear any of his fees for his services. Instead, it merely set out the understanding between the parties that the role of Mr Chow (and his company Oneness Engineering Pte Ltd) was that of a facilitator to expedite the completion of the project. The MOU also delegated authority as regards certain aspects of the project to Oneness Engineering Pte Ltd. 10 The Temporary Occupation Permit ( TOP ) for the project was obtained on 27 February 2009 and the completion certificate for the project was issued by the Architect on 31 March

4 11 On 11 May 2009, on the basis of the EOT Claims that were submitted on 26 June 2008, the Architect revised his earlier delay certificate, certifying that the defendant was entitled to an extension of time of 60 days ( the Allowed EOT ). The completion date for the project was revised to 16 February This date formed the basis for the plaintiff s computation of the liquidated damages that the defendant was liable to the plaintiff for under the Contract. 12 On 17 May 2013, the Architect finalised the accounts and issued the final certificate in which he certified that a sum of $71, was due and payable to the defendant. Procedural history 13 On 3 February 2015, the defendant commenced arbitral proceedings against the plaintiff. This was pursuant to cl 37(1) of the Contract which incorporated the SIA Conditions. Clause 37(1) of the Contract provided as follows: Any dispute between the Employer and the Contractor as to any matter arising under or out of or in connection with this Contract or under or out of or in connection with the carrying out of the Works and whether in contract or tort, or as to any direction or instruction or certificate of the Architect or as to the contents of or granting or refusal of or reasons for any such direction, instruction or certificate shall be referred to the arbitration and the final decision of a person to be agreed by the parties, or failing agreement within 28 days of either party giving written notice requiring arbitration to the other, a person to be appointed on the written request of either party by or on behalf of the President or Vice-President for the time being of the S.I.A. or, failing such appointment within 28 days of receipt of such written request, together with such information or particulars of the dispute as may be requested in writing by the President or Vice-President for the time being of the S.I.A., such persons as may be appointed by the Courts. The arbitration proceedings shall be conducted in accordance with the Arbitration Rules of S.I.A. for the time being in force 4

5 which Rules are deemed to be incorporated by references to this clause. 14 On 18 March 2015, upon application by both the plaintiff and the defendant, the President of the Singapore Institute of Architects appointed an arbitrator to hear the matter ( the Arbitrator ). The Arbitrator was a quantity surveyor by training and profession. 15 The defendant claimed the sum of $500, in the arbitration. Amongst other things, the defendant claimed for a refund of liquidated damages wrongfully charged by the plaintiff to the defendant and set-off against the sums certified as due to the defendant. The defendant contended that it was entitled to an extension of time beyond the Allowed EOT, with the completion date consequently being adjusted to a later date and the quantum of liquidated damages payable by the defendant being correspondingly reduced. The defendant therefore argued that the excess liquidated damages which had been charged ought to be refunded. 16 The plaintiff counterclaimed that the defendant had breached the Contract or, in the alternative, a duty of care owed to the plaintiff. The plaintiff claimed the sum of $1,770, which included, among other things, liquidated damages allegedly owing to him for delay in completion of the project and the cost of rectification of defects, such as those that related to the construction of the swimming pool. It should be noted that the plaintiff claimed liquidated damages for 409 days commencing from the day after the Contract completion date of 1 December 2007 until the completion date for the works under the Contract, which was 31 December The plaintiff contended that the defendant was not entitled to any of the EOT Claims, including the Allowed EOT (see above at [11]). In this regard, the plaintiff further contended that the defendant had failed to satisfy two conditions precedent before an EOT Claim 5

6 might be allowed. These were contained in cll 23(1) and (2) of the Contract. They provided as follows: 23.(1) The Contract Period and the Date for Completion may be extended and recalculated, subject to compliance by the [defendant] with the requirements of the next following subclause, by such further periods and until such further dates as may reasonably reflect any delay in completion which, notwithstanding due diligence and the taking of all reasonable steps by the [defendant] to avoid or reduce the same, has been caused by [a delaying event]. 23.(2) It shall be a condition precedent to an extension of time by the Architect under any provision of this Contract including the present clause (unless the Architect has already informed the [defendant] of his willingness to grant an extension of time) that the [defendant] shall within 28 days notify the Architect in writing of any event or direction or instruction which he considers entitles him to an extension of time, together with a sufficient explanation of the reasons why delay to completion will result [emphasis added] 17 Before the Arbitrator, the plaintiff contended that cl 23(1) of the Contract provided for a condition precedent, ie, that the defendant had to take all reasonable steps to avoid such delay before making an EOT Claim in respect of the delaying event ( the First Condition Precedent ). The plaintiff further contended that cl 23(2) of the Contract provided for a second condition precedent, ie, that the defendant had to notify the Architect of any delaying event within 28 days of its occurrence ( the Second Condition Precedent ). The plaintiff submitted that the First Condition Precedent was not satisfied as the delay was caused by the defendant s own conduct and that the Second Condition Precedent was not satisfied as it had failed to give the requisite notice within 28 days. 18 In the alternative, the plaintiff contended that the defendant had breached three implied terms ( the Implied Terms ) of the Contract or had 6

7 wrongfully repudiated the Contract by reason of the breach of the Implied Terms. The Implied Terms were: (a) That the defendant possessed the necessary knowledge, skills, care, work force and financial ability to undertake the Contract and to complete the works under the Contract by 1 December (b) That the materials supplied and workforce employed by the defendant would be of good workmanship and quality. (c) That the defendant would cooperate with the plaintiff and the Architect at all times and not in any way hinder or prevent the carrying out of the contract works and its completion by the completion date of 1 December The arbitration was conducted over several tranches in 2016, and involved 28 days of hearing. Both the defendant s representative and the plaintiff testified, called witnesses and made submissions. The parties positions were crystallised in comprehensive pleadings. 20 On 15 February 2017, the Arbitrator issued the Award ordering the plaintiff to pay to the defendant $278, and interest. Specifically, the Arbitrator had made the following orders which were relevant to OS 388: (a) The sum of $71, set out in the final certificate was to be paid to the defendant (see above at [12]). (b) The defendant was entitled to 297 days of extension of time. Consequently, liquidated damages for delay in completion of the project amounting to $118,800 was to be refunded to the defendant. 7

8 (c) Mr Chow s remuneration of $15,000 for his services from December 2008 to February 2009 was to be paid by the plaintiff. As the plaintiff had deducted that amount from the sum payable to the defendant under the Contract, the Arbitrator ordered the plaintiff to refund that amount to the defendant. (d) The defendant was entitled to variation costs in the sum of $10,224 for audio cabling works in relation to an audio cabling system and $16,950 for providing pre-insulated refrigerant piping for the airconditioning refrigerant piping. (e) In relation to the counterclaim, the plaintiff was entitled to $24,000 as rectification costs for defects in the swimming pool. 21 Dissatisfied with the outcome of the arbitral proceedings, the plaintiff commenced OS 388 to set aside the Award. The parties cases 22 The plaintiff made two broad submissions: (a) The Arbitrator had breached the rules of natural justice under s 48(1)(a)(vii) of the Act. In this regard, the plaintiff submitted that the rules of natural justice had been breached in three distinct ways: (i) First, the Arbitrator had failed to consider the plaintiff s submissions on crucial issues in the dispute ( the Issues ). The plaintiff identified no less than ten issues in his affidavit filed in support of OS

9 (ii) Second, the Arbitrator had deprived the plaintiff of his right to be heard in relation to the cost of rectification of the defects in the swimming pool. (iii) Third, the Arbitrator had failed to exclude false and fraudulent evidence adduced by the defendant in the arbitration. Specifically, this was in relation to 58 photographs ( the Photographs ) which the plaintiff claimed the defendant falsely held out as Photographs of the Property and which were allegedly relied upon by the Arbitrator. (b) The Award was contrary to public policy under s 48(1)(b)(ii) of the Act. Specifically, it was argued that enforcement of the Award would be an affront to the basic notions of morality and justice due to the numerous and severe errors of law with grave repercussions to the construction industry. 23 The defendant denied that there was breach of natural justice. Specifically, in relation to the three allegations that the plaintiff made, the defendant made the following submissions: (a) First, there was no evidence of any failure by the Arbitrator to consider any of the Issues. (b) Second, the Arbitrator had not deprived the parties of the right to be heard in relation to the rectification costs for the defects in the swimming pool. Instead, he had exercised his power to assess the rectification costs correctly. 9

10 (c) Third, there was no breach of the rules of natural justice in relation to the Photographs. Specifically, there was no evidence that the Photographs had in fact been relied upon by the Arbitrator. 24 The defendant also submitted that the circumstances alleged by the plaintiff did not amount to a contravention of public policy. Issues to be determined 25 Accordingly, there were two broad issues I had to consider, namely: (a) (b) Whether the Arbitrator breached the rules of natural justice; and Whether the Award was contrary to public policy. I address these issues in turn. Natural justice 26 The plaintiff submitted that the Arbitrator breached the rules of natural justice in three ways. The plaintiff made several points which I shall examine in turn. Failure to consider material issues 27 I shall first consider the applicable legal principles relating to the setting aside of an arbitral award due to the failure of an arbitrator to consider material issues. I shall then address the Issues raised by the plaintiff. The applicable legal principles 28 The starting point is the Act. The Award was the result of a domestic arbitration and therefore the Act is the relevant statutory regime. Section 10

11 48(1)(a)(vii) of the Act enables the Court to set aside an award for breach of the rules of natural justice. It provides as follows: Court may set aside award 48. (1) An award may be set aside by the Court (a) if the party who applies to the Court to set aside the award proves to the satisfaction of the Court that (vii) a breach of the rules of natural justice occurred in connection with the making of the award by which the rights of any party have been prejudiced; or 29 It is settled law that in determining the scope of s 48(1)(a)(vii), regard may be had to cases involving the setting aside of international arbitral awards under s 24(b) of the International Arbitration Act (Cap 143A, 2002 Rev Ed) ( the IAA ). As a starting point, it is evident that the two provisions are identically drafted and should therefore be given a similar interpretation. The Court of Appeal in Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte Ltd [2007] 3 SLR(R) 86 ( Soh Beng Tee ) explained that this was because Parliament intended that the Act should largely mirror the IAA and international practices reflected in the [UNCITRAL Model Law on International Commercial Arbitration] (see Soh Beng Tee at [61]). As such, the Court of Appeal concluded that the same approach towards natural justice ought to be adopted for both international and domestic arbitrations in Singapore (see Soh Beng Tee at [62]). 30 It is also clear from the Court of Appeal decision in Soh Beng Tee, approving the decision in John Holland Pty Ltd v Toyo Engineering Corp (Japan) [2001] 1 SLR(R) 443, that a party seeking to set aside an arbitral award for breach of the rules of natural justice must first identify the rule of natural 11

12 justice that was allegedly breached (at [29]). This approach was also endorsed more recently by the Court of Appeal in AKN and another v ALC and others and other appeals [2015] 3 SLR 488 ( AKN ) (at [48]). As will be seen below (at [56]), it is only after this first stage that the Court will proceed to consider whether there was a causal nexus between the breach and the arbitral award, and whether the breach prejudiced the aggrieved party s rights (see AKN at [48]). 31 In this regard, the rule of natural justice that the plaintiff alleged had been breached was the omission on the part of the Arbitrator to consider the Issues which, it was said, were raised in the pleadings and addressed in the submissions of the plaintiff. As mentioned above (at [22(a)]), there were 10 Issues in total. 32 The legal principles in relation to such an argument are clear. It is settled law that the inference that an arbitrator failed to consider an issue may only be drawn if it was clear and virtually inescapable (see AKN at [46]). In determining whether such an inference may be drawn, the Court of Appeal highlighted the distinction between, on the one hand, an arbitral tribunal s decision to reject an argument whether implicitly or otherwise, whether rightly or wrongly and whether or not as a result of a failure to appreciate the merits of the argument and, on the other hand, the tribunal s failure to consider the argument (see AKN at [47]). Only the latter would amount to a breach of natural justice. In this regard, the inference should not be drawn if the facts were consistent with the arbitrator having (1) misunderstood a party s case, (2) been mistaken as to the law or (3) chosen not to deal with a point because he thought it unnecessary (even if this was due to a misunderstanding of a party s case). It is clear that the inference ought not to be drawn lightly. 12

13 33 Another useful principle may be gleaned from the decision of Chan Seng Onn J in TMM Division Maritima SA de CV v Pacific Richfield Marine Pte Ltd [2013] 4 SLR 972 ( TMM Division ). In TMM Division, the plaintiff submitted that the arbitrator had not tried to understand its arguments. However, as Chan J noted, the submission properly understood was essentially to force the Arbitrator to accept and not just consider or comprehend its argument (see TMM Division at [94]). Chan J thus rejected the submission, and observed that no party has a right to expect the arbitral tribunal to accept its arguments, regardless of how strong and credible it perceives its own arguments to be (see TMM Division at [94]). This was endorsed by the Court of Appeal in AKN at [47]. Chan J went on to explain that natural justice only protects the right to be heard. It does not function as a guarantee that the tribunal will fully comprehend the submissions made or that the tribunal will accept those submissions (see TMM Division at [96]). There is good reason for this. Accepting the submission that was made in TMM Division would be to allow a backdoor review of the merits of the arbitrator s conclusions, disguised as a challenge on the ground of breach of natural justice. 34 However, that is not to say that a party may never succeed in showing that an arbitrator failed to consider an issue. One instance in which an award was set aside because of the arbitrator s failure to consider an issue arose in Front Row Investment Holdings (Singapore) Pte Ltd v Daimler South East Asia Pte Ltd [2010] SGHC 80 ( Front Row ). In Front Row, the arbitrator had expressly stated in the award that the defendant to the arbitration had ceased to rely on a number of points pleaded (see Front Row at [14]). Before the High Court, the defendant sought to set aside that portion of the award and argued that the arbitrator had reached his decision under the mistaken impression that it had abandoned its arguments on those points. The High Court agreed and held that the arbitrator had failed to accord the defendant natural justice (see Front 13

14 Row at [46]). The Court of Appeal in AKN affirmed Front Row, but emphasised that the facts there were unique as there was no real dispute that the arbitrator had in fact failed to consider the party s pleaded representations. In my judgment, Front Row was an example of how high the threshold as set out in AKN really was. It must be a clear and virtually inescapable inference that the arbitrator had failed to consider the issue. Evidently, it is not frequent that such a situation will present itself. Application to the facts 35 Before I consider the Issues, I note as a preliminary observation that despite identifying ten Issues in his affidavit in support of OS 388, the plaintiff, in his submissions, in fact referred to thirteen Issues. The defendant objected to the plaintiff s reliance on the three further Issues, ie, Issues 11 to 13. Upon consideration of Issues 11 to 13, I was satisfied that they were distinct from Issues 1 to 10 and were unsupported by the plaintiff s affidavit in OS 388. I therefore did not consider Issues 11 to The Issues were as follows: [Issue] 1: that there are the following implied terms in the contract: i. That the Claimant [Sunho] possessed the necessary knowledge, skills, care, work force and financial ability to undertake the whole contract and to complete the Works as contracted on 1 December ii. That the material supplied and workforce employed by Sunho will be of good workmanship and quality iii. That Sunho will cooperate with me & the Architect at all times and not in any way hinder or prevent the carrying out of the works and its completion on the scheduled & contracted completion date of 1 December [Issue] 2. Sunho, by reason of its failure to comply with the express and/or implied terms of the Contract and proceed with 14

15 due diligence, has caused inordinate delay and therefore it has wrongfully repudiated the contract and is in breach of contract. [Issue] 3: Sunho, by failing to proceed with the works in a workmanlike or professional manner with proper materials, has caused inordinate delay and was in dominant delay, thereby breaching its duty of care owed to me and causing me loss and damages [Issue] 4: Sunho, by failing to comply with Clause 23(1) of the Contract and failing to proceed with the works with due diligence and the taking of all reasonable steps by the Contractor to avoid or reduce delays, are not entitled to any extension of time. [Issue] 5: In the context of Clause 23(2), an EOT claim that does not contain a sufficient explanation of the reasons why delay to completion will result (including, for instance, specific details on how a potential delay will affect the progress of the works, the specific number of days claimed, or even how the number of days claimed was calculated) does not constitute a valid EOT claim and therefore Sunho is not entitled to EOT for such claims. [Issue] 6: The Architect s change in roofing material had no time implication or impact on the progress of the works. This is because Sunho was, as at the end of April 2008, not ready to commence installation of the roofing material because they had yet to complete the roof structure, even though the roofing material had already arrived earlier in the same month. Given that the roof was not even ready to receive the roofing material when the roofing material arrived, the change in roofing material or delay in its arrival could not have any time implication or impact on the progress of the works and therefore Sunho is not entitled to EOT for the change in roofing material. [Issue] 7: Chow s evidence that he had worked for Sunho pursuant to the MOU and for that reason he had addressed his invoice to Sunho for his salary for his services from December 2008 to February 2009 [Issue] 8: Sunho, by failing to comply with Clause 1(5) of the Contract and dispute or claim extra payment for a direction by the Architect within 28 days of receipt of the direction, is conclusively deemed to have undertaken to comply with the direction without an increase in the Contract Sum or any additional payment or compensation, and are not entitled to claim variation costs (under Variation Order 17) for supplying labour to install the cabling for the audio system. [Issue] 9: My evidence and the Architect and QS evidence that the three of us, together with the M&E consultant had, at the 15

16 negotiations, insisted on pre-insulated refrigerant piping to be provided and Sunho had accepted the same. [Issue] 10: Pursuant to Clause 37(3)(f) of the SIA Conditions, the Learned Arbitrator does not have the power to grant any EOT to Sunho where Sunho had failed to comply with the requirements of Clause 23(2). 37 The plaintiff made the following submissions: (a) On Issue 1, there was an absence of any evaluation or conclusion on whether the defendant was in breach or in wrongful repudiation of the Contract. In addition, despite the Arbitrator accepting that the defendant was in delay, he failed to grant the plaintiff the declaration that he sought, ie, that the defendant was in breach or in wrongful repudiation of the Contract. (b) On Issues 2 to 6, despite the plaintiff having made extensive submissions on these Issues, they were not addressed in the Award. (c) On Issue 7, the Arbitrator must have omitted to consider the evidence of Mr Chow because, if he had, the natural conclusion would have been that the defendant was not entitled to claim for the sum of $15,000 that was deducted by the plaintiff for Mr Chow s salary as it was the defendant which was liable for the same. The plaintiff also raised the further point in his skeletal submissions that the defendant had not pleaded the claim for the refund of the $15,000 that was deducted by the plaintiff for Mr Chow s remuneration. (d) On Issues 8 to 10, that there was no consideration or assessment of these Issues in the Award. 38 I first address Issues 2 to 6 and 8 to 10. The plaintiff s submissions broadly adopted the approach that the Arbitrator failed to consider these Issues 16

17 since (a) the Award did not expressly state the Arbitrator s findings regarding each of these Issues, and (b) if the Arbitrator had considered them, he would have reached different conclusions. Evidently, such an argument was insufficient to lead to a clear and virtually inescapable inference, as required by AKN, that the Arbitrator had failed to consider each of these Issues. In fact, the argument was simply a variant of the argument that Chan J in TMM Division had rejected, ie, the plaintiff s argument here amounted simply to an assertion that these Issues must not have been considered because, if they had, the Arbitrator would have found in the plaintiff s favour as the conclusion was plainly correct. As highlighted above (at [33]), such an argument was untenable as it effectively required the Arbitrator to accept, and not just consider, the plaintiff s submissions on these Issues. The submission that there was a failure to consider Issues 2 to 6 and 8 to 10 was therefore a non-starter as the plaintiff was unable to establish that the Arbitrator had in fact omitted to consider these Issues. 39 In any event, it was clear that the Arbitrator had, in the course of the Award, considered and decided Issues 2 to 6 and 8 to 10. In this regard, I did not find that there was a clear and virtually inescapable inference that the Arbitrator had omitted to consider these Issues. As mentioned above (see above at [32]), it had to be borne in mind that so long as it appeared that the Arbitrator had dealt with each of these Issues implicitly, it could not be said that he had not considered it. I deal with these Issues as follows: (a) On Issue 2 (ie, that the defendant had caused inordinate delay by failing to comply with the Implied Terms and thereby wrongfully repudiated and breached the contract), the Arbitrator expressly noted in the Award that both parties chose to affirm the Contract leading to the Completion of the Project. This would suggest that the Arbitrator did 17

18 consider the question of repudiatory breach. Indeed, it seemed correct to conclude that the Arbitrator, having granted a significant extension of time, took the view that the defendant had not caused inordinate delay. It could not therefore be said that there was an inescapable inference that the Arbitrator had failed to consider Issue 2. The more likely inference was therefore that the Arbitrator had considered Issue 2 but decided it against the plaintiff. (b) On Issue 3 (ie, that the defendant had caused inordinate delay by failing to proceed with the works in a workmanlike manner and thereby breached its duty of care to the plaintiff), the same analysis with regard to Issue 2 would apply. The fact that the Arbitrator granted the defendant significant EOT claims again suggested that the Arbitrator took the view that the defendant had not caused inordinate delay. In this regard, the more likely inference was therefore that the Arbitrator had considered Issue 3 but decided against the plaintiff. (c) On Issues 4 and 5 (ie, that the defendant was not entitled to any extension of time as it had failed to comply with the First and Second Conditions Precedent), the fact that the Arbitrator allowed some of the defendant s EOT Claims alone would create the equally probable inference that the Arbitrator had considered these Issues but decided them against the plaintiff. In fact, the Award went further. The Arbitrator expressly rejected one EOT Claim made by the defendant on the basis that the defendant had failed to submit notice as required under Clause 23(2) within 28 days. This was a clear indication that the Arbitrator had considered the Second Condition Precedent for each EOT Claim in coming to his decision that the defendant was entitled to the EOT Claims granted but nevertheless had decided against the plaintiff on these 18

19 Issues. In my view, it stood to reason that the Arbitrator had also considered the First Condition Precedent but decided that it did not assist the plaintiff. (d) On Issue 6 (concerning the impact of the Architect s decision to change the roofing material on the progress of works), it seemed evident that the Arbitrator did find against the plaintiff. Specifically, the Award directly considered the defendant s EOT Claim in respect of the change of roofing material. The Arbitrator noted the evidence of the Architect that he was aware that the change of roofing material would delay the project completion. He also observed that the decision to change the roofing material was taken at a very late stage of the project. Consequently, this change delayed the architectural finishing works to the 2nd storey and upset the sequence of works. Taking these findings in totality, the inference must be that the Arbitrator considered but rejected the plaintiff s submissions on Issue 6. (e) On Issue 8 (ie, that the defendant was deemed to have undertaken to comply with the Architect s direction in relation to the audio cabling system without any additional payment by not raising a dispute under cl 1(5) of the Contract), it is true that the Award made no specific mention of cl 1(5) of the Contract. However, this alone did not give rise to the inescapable inference that the Arbitrator had failed to consider Issue 8. It was evident that the Arbitrator decided that the defendant was entitled to variation costs in respect of the audio cabling system. This would suggest that he was of the view that cl 1(5) of the Contract was not relevant or had been satisfied. Even if he was wrong in his conclusion, that did not give rise to a breach of natural justice. Again, this gave rise 19

20 to the equally probable inference that the Arbitrator had considered but simply disagreed with the plaintiff on Issue 8. (f) On Issue 9 (ie, that there was evidence to show that the defendant had accepted that pre-insulated refrigerant piping was within the original scope of works), the Award indicated that the Arbitrator had considered this Issue and decided against the plaintiff. The Award stated that the defendant had qualified during the tender stage that pre-insulated refrigerant piping would be at additional costs and that the evidence showed that this qualification had not been withdrawn during the negotiation stages. This was contrary to what the plaintiff contended the evidence showed. I did not consider that the failure of the Arbitrator to mention and deal specifically with the evidence of the plaintiff, the Architect and the Quantity Surveyor in the Award on this point showed that he had failed to consider their evidence. The equally likely, if not more likely, inference was that the Arbitrator had considered their evidence but disagreed with the plaintiff as to its weight or effect. (g) On Issue 10 (ie, that, pursuant to cl 37(3)(f) of the Contract, the Arbitrator did not have the power to grant any EOT Claims as the defendant had failed to comply with the Second Condition Precedent), a similar analysis as stated above in [39(c)] applied. It is true that under cl 37(3)(f) of the Contract, the Arbitrator had no power to grant extensions of time where the defendant failed to comply with the Second Condition Precedent. However, this simply begged the question as to whether the defendant had indeed failed to comply with the Second Condition Precedent. As stated above (at [39(c)]), there was an indication in the Award that the Arbitrator had considered the Second Condition Precedent. In fact, he had specifically refused one EOT Claim on the 20

21 basis that the Second Condition Precedent was not fulfilled. His decision to grant the remaining EOT Claims therefore suggested that he had disagreed with the plaintiff that the defendant had failed to comply with the Second Condition Precedent on those EOT Claims. It followed therefore that the Arbitrator did not find that cl 37(3)(f) of the Contract prevented him from granting the remaining EOT Claims. In this regard, the likely inference was that the Arbitrator had considered Issue 10 but simply decided it against the plaintiff. 40 As regards Issue 1 (ie, that there were the Implied Terms in the Contract), the argument at first glance appeared to be on a different footing from those made in respect of Issues 2 to 6 and 8 to 10. However, on closer scrutiny, this was not the case. Insofar as the argument was predicated on the Arbitrator not granting the declaration sought by the plaintiff, namely that the defendant was in breach or wrongful repudiation of the Contract (see above at [37(a)]), this was simply another way of saying that the Arbitrator ought to have found in the plaintiff s favour on Issue 1. This argument could therefore be dismissed for the same reasons as stated above (at [33] and [38]). In any event, it was evident from the Award that the Arbitrator had decided against granting the declaration. In fact, the Award expressly stated that both parties had chosen to affirm the Contract throughout and leading up to the completion of the project. I did not think that a further statement expressly stating that the declaration sought by the plaintiff was not granted was necessary; it was obvious from the fact that the Arbitrator had taken the view that the parties had affirmed the Contract. Any declaration that the defendant was in repudiatory breach of the Contract was not only unnecessary but also incorrect. 41 I would also make some observations on Issue 7 (ie, that Mr Chow s evidence that he had worked for the defendant pursuant to the MOU and 21

22 therefore addressed the invoice for his salary to the defendant was not considered). The plaintiff s first submission in relation to Issue 7, that it was not considered because, if it had been considered, the Arbitrator would have come to another conclusion, was essentially another variant of the argument raised in respect of Issues 2 to 6 and 8 to 10. In this regard, that argument might be dismissed for the same reasons (see above at [38]). 42 In any event, I was of the view that the Arbitrator had considered Mr Chow s evidence on Issue 7. The plaintiff relied on Mr Chow s evidence that he had been re-engaged as an employee. Specifically, Mr Chow had given evidence that he understood the MOU to mean that the defendant would pay his remuneration, and that this was evidenced by the submission of his invoice to the defendant in December By contrast, the defendant s position in the arbitration was that Mr Chow was engaged by the plaintiff as his representative. The crucial point was that the Arbitrator found that Mr Chow had not been re-engaged as an employee. Specifically, the Award stated that in August 2008, Mr Chow left the employ of the [defendant] and came back as a facilitator in December 2008 to February 2009 under the [MOU] [emphasis added]. It went on to state, in express terms, that Mr Chow was an independent party and was not under the employment of the [defendant] [emphasis added]. In this regard, the more probable inference was that the Arbitrator had considered Mr Chow s evidence on this matter and how it measured up against the defendant s position, and rejected the plaintiff s submission as to the weight to be attributed to or the effect of Mr Chow s evidence. 43 The second submission that the plaintiff made was that the defendant had not pleaded the claim for a refund of the $15,000, being Mr Chow s alleged remuneration, that was deducted by the plaintiff. The Arbitrator had ordered the sum to be refunded to the defendant. Two remarks are apposite here. 22

23 (a) The plaintiff did not depose that (part of) the Award was in breach of natural justice because the Arbitrator had awarded the defendant a sum that it did not plead for. The only complaint in relation to Issue 7 was that the Arbitrator had failed to consider Mr Chow s evidence. That was therefore the only point that I could consider in relation to Issue 7. In any event, counsel for the defendant noted that the question of whether Mr Chow was employed by the defendant, on which the Arbitrator found for the defendant and ordered refund of the $15,000 to the latter, was put into issue by the plaintiff in his pleadings in the Arbitration. There was therefore no prejudice. (b) Nonetheless, I acknowledge that the question remained whether the Award dealt with a point that fell outside the scope of the submission to arbitration, given that the plaintiff did not specifically claim for the $15,000 sum. I believed that the question could be satisfactorily answered in the defendant s favour in the following manner. If in resisting the defendant s claim in the arbitration, the plaintiff had put into issue, which he did, his entitlement to set-off Mr Chow s remuneration represented by the $15,000 against monies payable by him to the defendant under the Contract, it seemed correct that a determination of the point against the plaintiff ought to result in the defendant being entitled to a refund as the set-off by the plaintiff was incorrectly made. Even if it was incorrect to analyse the question in this manner, the critical point was that the plaintiff did not seek to set aside (this part of) the Award on this basis. OS 388 was brought on the grounds of breach of natural justice and public policy alone. There was therefore no basis for me to set aside this part of the Award on the ground that the Arbitrator had exceeded his jurisdiction in awarding the sum of $15,

24 44 Assessing the plaintiff s submissions in the round, it seemed apparent to me that the crux of the plaintiff s complaints was that the Arbitrator s findings were incorrect, and not that the Arbitrator had failed to consider the plaintiff s pleadings and submissions. The plaintiff was, in gist, seeking to appeal against the Arbitrator s findings by disguising it as a failure to consider the Issues. However, there was no (general) right of appeal against the merits of an arbitral award and a party could not circumvent this principle by bringing a backdoor appeal in the guise of an argument on natural justice. If the plaintiff had intended to challenge the merits of the arbitral award, the proper course would have been for him to appeal my decision in OS 278, which was his application for leave to appeal to the Court on certain questions of law. That would have given him the opportunity, provided the conditions in s 49(5) of the Act were fulfilled, to have the correctness of the Arbitrator s decisions on those questions of law examined by the Court. However, the plaintiff elected not to do so, presumably out of recognition of the difficulties with his application in OS For these reasons, I held that the plaintiff did not establish that the Arbitrator failed to consider the Issues. Hence, the allegation of breach of natural justice failed. Deprivation of right to be heard 46 The plaintiff s second submission in relation to breach of natural justice was that the Arbitrator had deprived him of his right to be heard in awarding him $24,000 as the costs of rectifying the swimming pool. The plaintiff made two points. First, that the Arbitrator departed from the expert evidence adduced by both parties in unilaterally assessing the costs of rectification without affording the plaintiff an opportunity to address the conclusion that the Arbitrator had arrived at. Second, that the Arbitrator did not consider the 24

25 evidence of the plaintiff s expert witness on the structural integrity of the swimming pool. 47 I did not accept the second contention. It was premised on the following statements in the Award: There were no evidence produced during the hearing to support that the structural integrity of the swimming pool was a problem. There is no necessity to demolish and re-construct the whole pool structure as suggested by the [plaintiff s expert] since the structural integrity of the pool was not in question. [emphasis added] 48 I did not think that it could be inferred from these statements that the Arbitrator had not considered the plaintiff s expert evidence. It seemed a stretch for the plaintiff to assert, based on the less than tight language used in the Award, that the Arbitrator had failed to consider the evidence of the plaintiff s expert whom he had heard and whose expert report was before him. It seemed more likely and fairer to the Arbitrator to conclude that he had considered the evidence, but had rejected it on the basis that it was not satisfactory. 49 In respect of the first contention, I accepted that the Arbitrator appeared to have departed from the evidence of the expert witnesses of both parties. It appeared that the Arbitrator found the area to be reinstated was 24m 2. This was not an area submitted by either party. It was plain from the Award that the Arbitrator made this finding after considering the evidence of Mr How Yong Meng ( Mr How ) adduced in the arbitration as the plaintiff s witness. Mr How s report was commissioned by the plaintiff and he provided the report on the defects in the swimming pool. Multiple references to Mr How s testimony at the hearing were made throughout paragraph 5.4 of the Award. Mr How was 25

26 an Assistant Manager at Setsco Services Pte Ltd which had been engaged by the Quantity Surveyor to carry out a survey of the defects in the swimming pool. In terms of the relevant rate, it seemed that the Arbitrator awarded $24,000 by applying a rate of $1,000/m 2. The defendant submitted that this rate was based on the evidence of its expert, who allegedly opined that $6,000 should be awarded on the basis of works to 6m 2 of the pool s surface area giving a per square metre rate of $1,000. Having reviewed the defendant s expert report, I did not accept this submission. The defendant s expert opined that it was only necessary to perform works covering approximately 0.7m 2, not 6m 2. The Arbitrator also appeared to have accounted for the cost of hacking works in assessing the cost of the rectification works; yet the defendant s expert opined that there was no need for such works. Thus, it was clear that the $1,000/m 2 rate was not based on the defendant s expert s evidence. 50 The Arbitrator therefore seemed to have made his own assessment of the area and rate in quantifying the cost of rectification of the defects in the swimming pool. However, I did not consider that this was a breach of natural justice that warranted the setting aside of the Award for two reasons. 51 First, each party had the opportunity to adduce evidence on the issue of the rectification costs for the defects in the swimming pool and to make submissions on this point. Each party also had the opportunity of responding to the evidence and submissions presented by the opposing party. The facts here were distinguishable from those in Permasteelisa Pacific Holdings Ltd v Hyundai Engineering & Construction Co Ltd [2005] 2 SLR(R) 270 ( Permasteelisa ), where the arbitrator had adopted a method of apportioning liquidated damages that was only advanced in one party s reply submissions and was not put forward in the course of the proceedings (see Permasteelisa at [42]). The other party was therefore not given an opportunity to challenge that 26

27 new method of computation. The breach of natural justice in Permasteelisa consisted in the arbitrator s failure to grant the opposing party an opportunity to respond to the plaintiff s submission, which the arbitrator had adopted. In contrast, in this case, there was no allegation by the plaintiff that it did not have the opportunity to challenge or respond to the evidence or submissions made by the defendant at the arbitration in relation to this issue. Instead, the Arbitrator had not accepted either party s position on the rectification costs. He had adopted a middle ground in assessing the rectification costs. The question was therefore whether, by so doing, the Arbitrator was within the holding in Permasteelisa. I did not think so. 52 Second, it is settled law that a court should not mechanically apply the rules of natural justice in arbitration such as to require that every conclusion that the arbitrator intends to make be put to or raised with the parties. Parties to an arbitration frequently appoint or accept the appointment of an expert in the relevant field as arbitrator for the purpose of relying on his or her expertise for a sound and swift judgment (see Soh Beng Tee at [63]). Indeed, an arbitrator is not bound to accept an either/or approach and is perfectly entitled to embrace a middle path (even without apprising the parties of his provisional thinking or analysis) (see Soh Beng Tee at [65(e)]). Here, the Arbitrator was an experienced professional architect. In my judgment, he was entitled to rely on his expertise in assessing the rectification costs. It was also unchallenged evidence that the Arbitrator had told the parties during the arbitration that he would be engaging a quantity surveyor to assist him in quantifying damages, and the parties had not objected to this (albeit it is not completely clear that the $1,000/m 2 rate was based on the evidence of the quantity surveyor). The parties were thus aware that the Arbitrator might undertake an independent assessment of the cost of rectification and did not object to this course of action. In my judgment, while the Arbitrator had adopted a middle path, he had given 27

28 parties the opportunity to object to him obtaining the independent assessment of the appointed quantity surveyor. Presumably, parties would also have had the opportunity to indicate if they had wished to respond to, or make submissions in relation to, the findings of the appointed quantity surveyor. As such, the Arbitrator did not fall foul of the standard required by Permasteelisa. In that light, I considered that the plaintiff s complaint that he did not have the opportunity to address the Arbitrator s assessment of costs of rectification was without force. 53 For all these reasons, I did not accept that the Arbitrator s award of $24,000 as the rectification costs for the swimming pool should be set aside for breach of natural justice. Failure to exclude allegedly fraudulent evidence 54 The plaintiff s third submission on breach of natural justice was that the Arbitrator had failed to exclude the Photographs that had been adduced by the defendant. The Photographs, it was argued, were fraudulently held out by the defendants as being photographs of the Property when they were not so. I did not accept this submission. 55 The plaintiff s complaint in relation to the Photographs was not so much that he had not been given the opportunity to address them, but that they had not been excluded. In the first place, it was not entirely clear that the Photographs were in fact included. Crucially, the Award did not refer to the Photographs at all which would suggest that the Arbitrator did not include or at the very least did not have regard to the Photographs. Nevertheless, I considered it important to note that the plaintiff had been given the opportunity to address the Photographs. It appeared that the first hint of the allegation that the Photographs were fraudulent, ie, not being of the Property, arose in the course 28

Zynergy Solar Projects & Services Pvt Ltd v Phoenix Solar Pte Ltd

Zynergy Solar Projects & Services Pvt Ltd v Phoenix Solar Pte Ltd This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher s duty in compliance with the law, for publication in LawNet and/or the Singapore

More information

CONTACT US. Background

CONTACT US. Background April 2015 Arbitration Singapore Court of Appeal espouses standards to be met when setting aside an arbitral award; reinforces Singapore s pro-arbitration policy CONTACT US In a judgment delivered on 31

More information

THE SINGAPORE APPROACH TO THE ADJOURNMENT OF PROCEEDINGS TO ENFORCE A FOREIGN ARBITRAL AWARD

THE SINGAPORE APPROACH TO THE ADJOURNMENT OF PROCEEDINGS TO ENFORCE A FOREIGN ARBITRAL AWARD Published on 6 September 2018 THE SINGAPORE APPROACH TO THE ADJOURNMENT OF PROCEEDINGS TO ENFORCE A FOREIGN ARBITRAL AWARD Margaret Joan LING LLB (National University of Singapore); Partner, Litigation

More information

Home Building Amendment Act 2014 No 24

Home Building Amendment Act 2014 No 24 New South Wales Home Building Amendment Act 2014 No 24 Contents Page 1 Name of Act 2 2 Commencement 2 3 Schedule 2 Amendment of NSW Self Insurance Corporation Act 2004 No 106 48 Schedule 3 Repeals 50 New

More information

Luzon Hydro Corp v Transfield Philippines Inc

Luzon Hydro Corp v Transfield Philippines Inc [2004] 4 SLR(R) SINGAPORE LAW REPORTS (REISSUE) 705 Luzon Hydro Corp v Transfield Philippines Inc [2004] SGHC 204 High Court Originating Motion No 27 of 2004 Judith Prakash J 19 July; 13 September 2004

More information

SPECIAL CONDITIONS OF CONTRACT (FOR USE WITH THE ACQS HKIA/HKIS STANDARD FORM OF BUILDING CONTRACT WITH QUANTITIES 2005 EDITION)

SPECIAL CONDITIONS OF CONTRACT (FOR USE WITH THE ACQS HKIA/HKIS STANDARD FORM OF BUILDING CONTRACT WITH QUANTITIES 2005 EDITION) (FOR USE WITH THE ACQS HKIA/HKIS STANDARD FORM OF BUILDING CONTRACT WITH QUANTITIES 2005 EDITION) Context General A. These Special Conditions of Contract are to be read in conjunction with the Conditions

More information

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013)

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) 1. Scope of Application and Interpretation 1.1 Where parties have agreed to refer their disputes

More information

JUDGMENT REPUBLIC OF TRINIDAD AND TOBAGO IN THE HIGH COURT OF JUSTICE CV BETWEEN D. C. DEVELOPERS LIMITED. Claimant AND

JUDGMENT REPUBLIC OF TRINIDAD AND TOBAGO IN THE HIGH COURT OF JUSTICE CV BETWEEN D. C. DEVELOPERS LIMITED. Claimant AND REPUBLIC OF TRINIDAD AND TOBAGO IN THE HIGH COURT OF JUSTICE CV2006-02313 BETWEEN D. C. DEVELOPERS LIMITED AND Claimant MANAGEMENT AND CONSTRUCTION CONSULTANTS LIMITED Defendant Before The Honourable Mr.

More information

DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY Introductory Provisions. Article (1) Definitions

DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY Introductory Provisions. Article (1) Definitions DUBAI INTERNATIONAL ARBITRATION CENTRE RULES 2007 AS OF 22 ND FEBRUARY 2011 Introductory Provisions Article (1) Definitions 1.1 The following words and phrases shall have the meaning assigned thereto unless

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: PARTIES: David & Gai Spankie & Northern Investment Holdings Pty Limited v James Trowse Constructions Pty Limited & Ors [2010] QSC 29 DAVID & GAI SPANKIE & NORTHERN

More information

SH Design & Build Pte Ltd v BD Cranetech Pte Ltd

SH Design & Build Pte Ltd v BD Cranetech Pte Ltd This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher s duty in compliance with the law, for publication in LawNet and/or the Singapore

More information

Consolidated text PROJET DE LOI ENTITLED. The Arbitration (Guernsey) Law, 2016 * [CONSOLIDATED TEXT] NOTE

Consolidated text PROJET DE LOI ENTITLED. The Arbitration (Guernsey) Law, 2016 * [CONSOLIDATED TEXT] NOTE PROJET DE LOI ENTITLED The Arbitration (Guernsey) Law, 2016 * [CONSOLIDATED TEXT] NOTE This consolidated version of the enactment incorporates all amendments listed in the footnote below. It has been prepared

More information

Legal Business. Overview Of Court Procedure. Memoranda on legal and business issues and concerns for multiple industry and business communities

Legal Business. Overview Of Court Procedure. Memoranda on legal and business issues and concerns for multiple industry and business communities Memoranda on legal and business issues and concerns for multiple industry and business communities Overview Of Court Procedure 1 Rajah & Tann 4 Battery Road #26-01 Bank of China Building Singapore 049908

More information

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) CONTENTS

ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE SIAC RULES (5 TH EDITION, 1 APRIL 2013) CONTENTS CONTENTS Rule 1 Scope of Application and Interpretation 1 Rule 2 Notice, Calculation of Periods of Time 3 Rule 3 Notice of Arbitration 4 Rule 4 Response to Notice of Arbitration 6 Rule 5 Expedited Procedure

More information

The new Arbitration (Guernsey) Law, a guide to the key provisions

The new Arbitration (Guernsey) Law, a guide to the key provisions JERSEY GUERNSEY LONDON BVI SINGAPORE GUERNSEY BRIEFING May 2017 The new Arbitration (Guernsey) Law, 2016 - a guide to the key provisions Historically, parties in Guernsey have been reluctant to use arbitration

More information

S P Chua Pte Ltd v Lee Kim Tah (Pte) Ltd

S P Chua Pte Ltd v Lee Kim Tah (Pte) Ltd [1993] 1 SLR(R) SINGAPORE LAW REPORTS (REISSUE) 793 S P Chua Pte Ltd v Lee Kim Tah (Pte) Ltd [1993] SGHC 104 High Court Suit No 1986 of 1991 Amarjeet Singh JC 10 May 1993 Arbitration Stay of court proceedings

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: Martinek Holdings Pty Ltd v Reed Construction (Qld) Pty Ltd [2009] QCA 329 PARTIES: MARTINEK HOLDINGS PTY LTD ACN 106 533 242 (applicant/appellant) v REED CONSTRUCTION

More information

Ron Clark June Downs. Melbourne Senior Member Lothian Small Claim Hearing

Ron Clark June Downs. Melbourne Senior Member Lothian Small Claim Hearing VICTORIAN CIVIL AND ADMINISTRATIVE TRIBUNAL CIVIL DIVISION DOMESTIC BUILDING LIST VCAT REFERENCE NO. D501/2011 CATCHWORDS Swimming pool contract, SPASA standard form, variations, prime cost items, provisional

More information

Dr. Nael Bunni, Chairman, Dispute Resolution Panel, Engineers Ireland, 22 Clyde Road, Ballsbridge, Dublin 4. December 2000.

Dr. Nael Bunni, Chairman, Dispute Resolution Panel, Engineers Ireland, 22 Clyde Road, Ballsbridge, Dublin 4. December 2000. Preamble This Arbitration Procedure has been prepared by Engineers Ireland principally for use with the Engineers Ireland Conditions of Contract for arbitrations conducted under the Arbitration Acts 1954

More information

THE INTERNATIONAL ARBITRATION ACT OF SINGAPORE

THE INTERNATIONAL ARBITRATION ACT OF SINGAPORE THE INTERNATIONAL ARBITRATION ACT OF SINGAPORE The laws governing private commercial arbitration in Singapore are divided into domestic and international regimes. There is a third regime that deals with

More information

Arbitration Act 1996

Arbitration Act 1996 Arbitration Act 1996 An Act to restate and improve the law relating to arbitration pursuant to an arbitration agreement; to make other provision relating to arbitration and arbitration awards; and for

More information

SMALL CLAIMS COURT ACT

SMALL CLAIMS COURT ACT LAWS OF KENYA SMALL CLAIMS COURT ACT NO. 2 OF 2016 Published by the National Council for Law Reporting with the Authority of the Attorney-General www.kenyalaw.org Small Claims Court No. 2 of 2016 Section

More information

Rules for the Conduct of an administered Arbitration

Rules for the Conduct of an administered Arbitration Rules for the Conduct of an administered Arbitration EXPLANATORY STATEMENT 1.1 These Rules govern disputes which are international in character, and are referred by the parties to AFSA INTERNATIONAL for

More information

BIG ISLAND CONSTRUCTION (HONG KONG) LTD v ABDOOLALLY EBRAHIM & CO (HONG KONG) LTD - [1994] 3 HKC 518

BIG ISLAND CONSTRUCTION (HONG KONG) LTD v ABDOOLALLY EBRAHIM & CO (HONG KONG) LTD - [1994] 3 HKC 518 1 BIG ISLAND CONSTRUCTION (HONG KONG) LTD v ABDOOLALLY EBRAHIM & CO (HONG KONG) LTD - [1994] 3 HKC 518 HIGH COURT KAPLAN J ACTION NO 11313 OF 1993 28 July 1994 Civil Procedure -- Summary judgment -- Lack

More information

Before: JUSTICE ANDREW BAKER (In Private) - and - ANONYMISATION APPLIES

Before: JUSTICE ANDREW BAKER (In Private) - and - ANONYMISATION APPLIES If this Transcript is to be reported or published, there is a requirement to ensure that no reporting restriction will be breached. This is particularly important in relation to any case involving a sexual

More information

Issues raised from Adjudication Determinations. The Security of Payment (SOP) Act came into effect on 1 April 2005.

Issues raised from Adjudication Determinations. The Security of Payment (SOP) Act came into effect on 1 April 2005. Security Of Payment Issues raised from Adjudication Determinations Edwin Lee Partner, Rajah & Tann 2 August 2007 1 Presentation Overview The Security of Payment (SOP) Act came into effect on 1 April 2005.

More information

FIJI ISLANDS HIGH COURT ACT (CHAPTER 13) HIGH COURT (AMENDMENT) RULES 1998

FIJI ISLANDS HIGH COURT ACT (CHAPTER 13) HIGH COURT (AMENDMENT) RULES 1998 FIJI ISLANDS HIGH COURT ACT (CHAPTER 13) HIGH COURT (AMENDMENT) RULES 1998 IN exercise of the powers conferred upon me by Section 25 of the High Court Act, I hereby make the following Rules: Citation 1.

More information

THE LONDON BAR ARBITRATION SCHEME. Administered by The London Common Law and Commercial Bar Association

THE LONDON BAR ARBITRATION SCHEME. Administered by The London Common Law and Commercial Bar Association THE LONDON BAR ARBITRATION SCHEME Administered by The London Common Law and Commercial Bar Association 2004 EDITION Correspondence to be addressed to Melissa Wood Administrator, LCLCBA Hardwicke Hardwicke

More information

THE STATUTES OF THE REPUBLIC OF SINGAPORE ARBITRATION ACT (CHAPTER 10)

THE STATUTES OF THE REPUBLIC OF SINGAPORE ARBITRATION ACT (CHAPTER 10) THE STATUTES OF THE REPUBLIC OF SINGAPORE ARBITRATION ACT (CHAPTER 10) (Original Enactment: Act 37 of 2001) REVISED EDITION 2002 (31st July 2002) Prepared and Published by THE LAW REVISION COMMISSION UNDER

More information

10th Anniversary Edition The Baker McKenzie International Arbitration Yearbook. Singapore

10th Anniversary Edition The Baker McKenzie International Arbitration Yearbook. Singapore 10th Anniversary Edition 2016-2017 The Baker McKenzie International Arbitration Yearbook Singapore 2017 Arbitration Yearbook Singapore Singapore Chan Leng Sun, S.C. 1 and Tan Weiyi 2 A. Legislation and

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: Gemini Nominees Pty Ltd v Queensland Property Partners Pty Ltd ATF The Keith Batt Family Trust [2007] QSC 20 PARTIES: GEMINI NOMINEES PTY LTD (ACN 011 020 536) (plaintiff)

More information

DISPUTE RESOLUTION RULES

DISPUTE RESOLUTION RULES DISPUTE RESOLUTION RULES First Issued: March 1998 Amended: November 1999 Amended: July 2000 Amended: September 2001 Amended: September 2003 Amended: October 2004 Amended: May 2005 Amended: September 2005

More information

7:12 PREVIOUS CHAPTER

7:12 PREVIOUS CHAPTER TITLE 7 Chapter 7:12 TITLE 7 PREVIOUS CHAPTER SMALL CLAIMS COURTS ACT Acts 20/1992, 8/1996, 22/2001, 14/2002; S.I. s 134/1996, 136/1996, 158/2000 ARRANGEMENT OF SECTIONS PART I PRELIMINARY Section 1. Short

More information

Econ Piling Pte Ltd and another (both formerly trading as Econ-NCC Joint Venture) v Shanghai Tunnel Engineering Co Ltd

Econ Piling Pte Ltd and another (both formerly trading as Econ-NCC Joint Venture) v Shanghai Tunnel Engineering Co Ltd 246 SINGAPORE LAW REPORTS [2011] 1 SLR Econ Piling Pte Ltd and another (both formerly trading as Econ-NCC Joint Venture) v Shanghai Tunnel Engineering Co Ltd [2010] SGHC 253 High Court Originating Summons

More information

THE LABOUR COURT OF SOUTH AFRICA, JOHANNESBURG JUDGMENT. MICHAEL KAWALYA-KAGWA Applicant

THE LABOUR COURT OF SOUTH AFRICA, JOHANNESBURG JUDGMENT. MICHAEL KAWALYA-KAGWA Applicant THE LABOUR COURT OF SOUTH AFRICA, JOHANNESBURG JUDGMENT Not reportable Case no: J 2406/16 In the matter between: MICHAEL KAWALYA-KAGWA Applicant and DEVELOPMENT BANK OF SOUTHERN AFRICA Respondent Heard:

More information

BUILDING SERVICES CORPORATION ACT 1989 Na 147

BUILDING SERVICES CORPORATION ACT 1989 Na 147 BUILDING SERVICES CORPORATION ACT 1989 Na 147 NEW SOUTH WALES 1. Short title 2. Commencement 3. Definitions TABLE OF PROVISIONS PART 1 - PRELIMINARY PART 2 - REGULATION OF RESIDENTIAL BUILDING WORK AND

More information

AMZ v AXX [2015] SGHC September 2014 Arbitration Award Recourse against award Setting aside 30 October 2015

AMZ v AXX [2015] SGHC September 2014 Arbitration Award Recourse against award Setting aside 30 October 2015 This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher s duty in compliance with the law, for publication in LawNet and/or the Singapore

More information

SINGAPORE INTERNATIONAL ARBITRATION CENTRE (SIAC)

SINGAPORE INTERNATIONAL ARBITRATION CENTRE (SIAC) GUIDE TO INTERNATIONAL ARBITRATION IN SINGAPORE INTERNATIONAL ARBITRATION CENTRE (SIAC) Written By S. Ravi Shankar Advocate on Record - Supreme Court of India National President of Arbitration Bar of India

More information

THE SMALL CLAIMS COURT BILL, 2007

THE SMALL CLAIMS COURT BILL, 2007 Small Claims Courts Bill, 2007 Section THE SMALL CLAIMS COURT BILL, 2007 ARRANGEMENT OF CLAUSES PART 1 - PRELIMINARY 1 - Short title and commencement 2 - Purpose 3 - Interpretation PART II ESTABLISHMENT

More information

THE SUPREME COURT OF APPEAL OF SOUTH AFRICA JUDGMENT

THE SUPREME COURT OF APPEAL OF SOUTH AFRICA JUDGMENT THE SUPREME COURT OF APPEAL OF SOUTH AFRICA JUDGMENT In the matter between: Not Reportable Case no: 20714/14 LORRAINE DU PREEZ APPELLANT and TORNEL PROPS (PTY) LTD RESPONDENT Neutral citation: Du Preez

More information

RULES OF PROCEDURE OF THE DISCIPLINE COMMITTEE OF THE COLLEGE OF REGISTERED PSYCHOTHERAPISTS AND REGISTERED MENTAL HEALTH THERAPISTS OF ONTARIO INDEX

RULES OF PROCEDURE OF THE DISCIPLINE COMMITTEE OF THE COLLEGE OF REGISTERED PSYCHOTHERAPISTS AND REGISTERED MENTAL HEALTH THERAPISTS OF ONTARIO INDEX RULES OF PROCEDURE OF THE DISCIPLINE COMMITTEE OF THE COLLEGE OF REGISTERED PSYCHOTHERAPISTS AND REGISTERED MENTAL HEALTH THERAPISTS OF ONTARIO INDEX RULE 1 - INTERPRETATION AND APPLICATION... 3 1.01 Definitions...

More information

WIPO WORLD INTELLECTUAL PROPERTY ORGANISATION ARBITRATION RULES

WIPO WORLD INTELLECTUAL PROPERTY ORGANISATION ARBITRATION RULES APPENDIX 3.17 WIPO WORLD INTELLECTUAL PROPERTY ORGANISATION ARBITRATION RULES (as from 1 October 2002) I. GENERAL PROVISIONS Abbreviated Expressions Article 1 In these Rules: Arbitration Agreement means

More information

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory Arbitration Act 1996 1996 CHAPTER 23 1 Part I Arbitration pursuant to an arbitration agreement Introductory 1. General principles. 2. Scope of application of provisions. 3. The seat of the arbitration.

More information

Vee Networks Ltd. v Econet Wireless International Ltd. [2004] APP.L.R. 12/14

Vee Networks Ltd. v Econet Wireless International Ltd. [2004] APP.L.R. 12/14 JUDGMENT : Mr Justice Colman : Commercial Court. 14 th December 2004 Introduction 1. The primary application before the court is under section 67 of the Arbitration Act 1996 to challenge an arbitration

More information

The Rules of the Foreign Trade Court of Arbitration of the Chamber of Commerce and Industry of Serbia

The Rules of the Foreign Trade Court of Arbitration of the Chamber of Commerce and Industry of Serbia The Rules of the Foreign Trade Court of Arbitration of the Chamber of Commerce and Industry of Serbia ( Official Journal of the Republic of Serbia, no. 2/2014) I GENERAL PROVISIONS Definition and Status

More information

1 Tax Appeals Tribunal Act, 2013 Viva Africa Consulting LLP

1 Tax Appeals Tribunal Act, 2013 Viva Africa Consulting LLP 1 Tax Appeals Tribunal Act, 2013 Viva Africa Consulting LLP While all reasonable care has been taken in the preparation of this updated version of the Kenya Tax Appeals Tribunal, Viva Africa Consulting

More information

IN THE HIGH COURT OF JUSTICE Sub-Registry, Tobago BETWEEN AGATHA DAY THOMAS DAY AND ANTHONY HENRY AND ASSOCIATES CO. LTD REASONS

IN THE HIGH COURT OF JUSTICE Sub-Registry, Tobago BETWEEN AGATHA DAY THOMAS DAY AND ANTHONY HENRY AND ASSOCIATES CO. LTD REASONS REPUBLIC OF TRINIDAD AND TOBAGO CV 2011-01102 IN THE HIGH COURT OF JUSTICE Sub-Registry, Tobago BETWEEN AGATHA DAY THOMAS DAY AND ANTHONY HENRY AND ASSOCIATES CO. LTD Claimants Defendant Before The Hon.

More information

TERMS OF REFERENCE. Issued Date: 3 January 2011

TERMS OF REFERENCE. Issued Date: 3 January 2011 TERMS OF REFERENCE Issued Date: 3 January 2011 Last Revised Date: 21 March 2017 List of Revisions Revision No. Revision Date Effective Date Revision 1 23 November 2015 1 December 2015 Revision 2 21 March

More information

General Terms of Contract

General Terms of Contract APPENDIX III General Terms of Contract GENERAL CONDITIONS OF CONTRACT 1. GENERAL PROVISIONS 1. 1 Definitions Unless the context otherwise requires, the following terms whenever used in this Contract have

More information

Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland

Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland (Royaume-Uni - Royaume-Uni de Grande-Bretagne et d'irlande du Nord) ARBITRATION ACT 1996 1996 CHAPTER 23 An Act to

More information

Re Calibre Solicitors Ltd (in administration) Justice Capital Ltd v Murphy and another (Administrators of Calibre Solicitors Ltd)

Re Calibre Solicitors Ltd (in administration) Justice Capital Ltd v Murphy and another (Administrators of Calibre Solicitors Ltd) Page 1 Judgments Re Calibre Solicitors Ltd (in administration) Justice Capital Ltd v Murphy and another (Administrators of Calibre Solicitors Ltd) [2014] Lexis Citation 259 Chancery Division, Companies

More information

THE TAX APPEALS TRIBUNAL ACT, 2013 ARRANGEMENT OF SECTIONS PART I PRELIMINARY

THE TAX APPEALS TRIBUNAL ACT, 2013 ARRANGEMENT OF SECTIONS PART I PRELIMINARY 1081 2013 Tax Appeals Tribunal No. 40 Section THE TAX APPEALS TRIBUNAL ACT, 2013 ARRANGEMENT OF SECTIONS 1 Short title and commencement. 2 Interpretation. PART I PRELIMINARY PART II ESTABLISHMENT AND FUNCTIONS

More information

CHAIR S DIRECTIONS (for Standard Dwellinghouse claims)

CHAIR S DIRECTIONS (for Standard Dwellinghouse claims) CHAIR S DIRECTIONS (for Standard Dwellinghouse claims) 1. Introduction 1.1 These directions are effective from 21 September 2015 and are issued pursuant to s114 of the Weathertight Homes Resolution Services

More information

A Company Limited by Guarantee Constitution

A Company Limited by Guarantee Constitution A Company Limited by Guarantee Constitution of The Real Estate Institute of Queensland Ltd ABN 49 009 661 287 Adopted 31 August 2015 TABLE OF CONTENTS 1. Preliminary... 1 1.1. Definitions and interpretation...

More information

REPUBLIC OF SINGAPORE GOVERNMENT GAZETTE ACTS SUPPLEMENT. Published by Authority NO. 23] FRIDAY, NOVEMBER 4 [2016 EMPLOYMENT CLAIMS ACT 2016

REPUBLIC OF SINGAPORE GOVERNMENT GAZETTE ACTS SUPPLEMENT. Published by Authority NO. 23] FRIDAY, NOVEMBER 4 [2016 EMPLOYMENT CLAIMS ACT 2016 REPUBLIC OF SINGAPORE GOVERNMENT GAZETTE ACTS SUPPLEMENT Published by Authority NO. 23] FRIDAY, NOVEMBER 4 [2016 First published in the Government Gazette, Electronic Edition, on 1st November 2016 at 5:00

More information

Staying court proceedings in favour of arbitration

Staying court proceedings in favour of arbitration On the publication of the second edition of Singapore International Arbitration Law and Practice (2 nd edition) (LexisNexis, 2018), David Joseph QC and David Foxton QC, the editors, offer some thoughts

More information

ARCHITECTS REGISTRATION COUNCIL SEMINARS

ARCHITECTS REGISTRATION COUNCIL SEMINARS ARCHITECTS REGISTRATION COUNCIL SEMINARS CONTRACT FORMATION FRED PHIRI ARCH.Bw May 27, 2017 1 Contents Legal Systems Legal Systems Examples Legal System Applications Civil Law Relationships Law of Obligations

More information

Building and Construction Industry Security of Payment Act 1999

Building and Construction Industry Security of Payment Act 1999 Building and Construction Industry Security of Payment Act 1999 Reprint history: Reprint No 1 30 September 2003 Long Title An Act with respect to payments for construction work carried out, and related

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: Matrix Projects (Qld) Pty Ltd v Luscombe [2013] QSC 4 PARTIES: MATRIX PROJECTS (QLD) PTY LTD ACN 089 633 607 trading as MATRIX HOMES (Applicant) v TONY JASON LUSCOMBE

More information

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS ICON DRILLING ABN 75 067 226 484 PURCHASE ORDER TERMS & CONDITIONS Acceptance of this offer is subject to the terms and conditions of this Agreement. Acceptance of materials, work or services, payment

More information

PT Tugu Pratama Indonesia v Magma Nusantara Ltd

PT Tugu Pratama Indonesia v Magma Nusantara Ltd [2003] 4 SLR(R) SINGAPORE LAW REPORTS (REISSUE) 257 PT Tugu Pratama Indonesia v Magma Nusantara Ltd [2003] SGHC 204 High Court Originating Motion No 9 of 2003 Judith Prakash J 11 August; 10 September 2003

More information

LONDON PHARMA & CHEMICALS GROUP LTD TERMS AND CONDITIONS OF SALE

LONDON PHARMA & CHEMICALS GROUP LTD TERMS AND CONDITIONS OF SALE LONDON PHARMA & CHEMICALS GROUP LTD TERMS AND CONDITIONS OF SALE 1. INTERPRETATION 1.1. The definitions and rules of interpretation set out below apply in these terms and conditions. Company: London Pharma

More information

L W Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd and another appeal

L W Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd and another appeal [2013] 1 SLR SINGAPORE LAW REPORTS 125 L W Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd and another appeal [2012] SGCA 57 Court of Appeal Civil Appeals Nos 17 and 26 of 2012 Chan Sek Keong

More information

ICDR INTERNATIONAL CENTRE FOR DISPUTE RESOLUTION ARBITRATION RULES

ICDR INTERNATIONAL CENTRE FOR DISPUTE RESOLUTION ARBITRATION RULES APPENDIX 3.8 ICDR INTERNATIONAL CENTRE FOR DISPUTE RESOLUTION ARBITRATION RULES (Rules Amended and Effective June 1, 2009) (Fee Schedule Amended and Effective June 1, 2010) Article 1 a. Where parties have

More information

TERMS AND CONDITIONS OF SALES

TERMS AND CONDITIONS OF SALES 1. Acceptance No Contract, Order or information (literature, drawings etc.) provided to or by the Purchaser shall be binding on Infra Green Ltd unless confirmed in the Infra Green Ltd Order Confirmation.

More information

BELIZE EQUAL PAY ACT CHAPTER 302:01 REVISED EDITION 2011 SHOWING THE SUBSTANTIVE LAWS AS AT 31 ST DECEMBER, 2011

BELIZE EQUAL PAY ACT CHAPTER 302:01 REVISED EDITION 2011 SHOWING THE SUBSTANTIVE LAWS AS AT 31 ST DECEMBER, 2011 BELIZE EQUAL PAY ACT CHAPTER 302:01 REVISED EDITION 2011 SHOWING THE SUBSTANTIVE LAWS AS AT 31 ST DECEMBER, 2011 This is a revised edition of the Substantive Laws, prepared by the Law Revision Commissioner

More information

Unit 5 : ADJUDICATION

Unit 5 : ADJUDICATION Unit 5 : ADJUDICATION WHAT IS ADJUDICATION? Adjudication is a quick and inexpensive process in which an independent third party makes binding decisions on construction contract disputes. The adjudicator

More information

STANDARD TERMS AND CONDITIONS

STANDARD TERMS AND CONDITIONS STANDARD TERMS AND CONDITIONS EDL GROUP OPERATIONS PTY LTD ACN 055 555 416 of Building 17, 2404 Logan Road, Eight Mile Plains, Queensland, Australia ("EDL") EDL requires that the Supplier supply EDL with

More information

Version 3.0 December Self-Lay Agreement. for services connecting to our existing network. Scheme Location Reference Date

Version 3.0 December Self-Lay Agreement. for services connecting to our existing network. Scheme Location Reference Date Version 3.0 December 2017 Self-Lay Agreement for services connecting to our existing network Scheme Location Reference Date THIS AGREEMENT is made the day of 20 (note this date to be completed by Thames

More information

GUTSCHE FAMILY INVESTMENTS (PTY) LIMITED

GUTSCHE FAMILY INVESTMENTS (PTY) LIMITED IN THE HIGH COURT OF SOUTH AFRICA EASTERN CAPE LOCAL DIVISION, PORT ELIZABETH CASE NO: 4490/2015 DATE HEARD: 02/03/2017 DATE DELIVERED: 30/03/2017 In the matter between GUTSCHE FAMILY INVESTMENTS (PTY)

More information

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV JUDGMENT OF COOPER J

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV JUDGMENT OF COOPER J IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV 2006-404-004969 UNDER the District Courts Act 1947 IN THE MATTER OF BETWEEN AND an appeal against a Judgment of the District Court at Auckland dated

More information

BEFORE THE IMMIGRATION ADVISERS COMPLAINTS AND DISCIPLINARY TRIBUNAL. Decision No: [2013] NZIACDT 28. Reference No: IACDT 027/11

BEFORE THE IMMIGRATION ADVISERS COMPLAINTS AND DISCIPLINARY TRIBUNAL. Decision No: [2013] NZIACDT 28. Reference No: IACDT 027/11 BEFORE THE IMMIGRATION ADVISERS COMPLAINTS AND DISCIPLINARY TRIBUNAL Decision No: [2013] NZIACDT 28 Reference No: IACDT 027/11 IN THE MATTER of a referral under s 48 of the Immigration Advisers Licensing

More information

SCHINDLER LIFTS (HONG KONG) LTD v SHUI ON CONSTRUCTION CO LTD - [1994] 3 HKC 598

SCHINDLER LIFTS (HONG KONG) LTD v SHUI ON CONSTRUCTION CO LTD - [1994] 3 HKC 598 SCHINDLER LIFTS (HONG KONG) LTD v SHUI ON CONSTRUCTION CO LTD - [1994] 3 HKC 598 HIGH COURT KAPLAN J ACTION NO 7005 OF 1991 2 July 1992 Civil Procedure -- Stay of proceedings -- Summary judgment -- Payment

More information

Sobati General Trading LLC v PT Multistrada Arahsarana

Sobati General Trading LLC v PT Multistrada Arahsarana [2010] 1 SLR SINGAPORE LAW REPORTS 1065 Sobati General Trading LLC v PT Multistrada Arahsarana [2009] SGHC 245 High Court Originating Summons No 412 of 2009 Tay Yong Kwang J 17 September 2009 Arbitration

More information

Sabah Shipyard (Pakistan) Ltd v Government of the Islamic Republic of Pakistan

Sabah Shipyard (Pakistan) Ltd v Government of the Islamic Republic of Pakistan 184 SINGAPORE LAW REPORTS (REISSUE) [2004] 3 SLR(R) Sabah Shipyard (Pakistan) Ltd v Government of the Islamic Republic of Pakistan [2004] SGHC 109 High Court Originating Motion No 31 of 2003 Judith Prakash

More information

DEPARTMENT OF PUBLIC WORKS

DEPARTMENT OF PUBLIC WORKS DEPARTMENT OF PUBLIC WORKS No.692 9 June 2004 REGULATIONS IN TERMS OF THE CONSTRUCTION INDUSTRY DEVELOPMENT BOARD ACT, 2000 (ACT NO. 38 OF 2000) The Minister of Public Works has under section 33 of the

More information

Published on e-first 1 June AGENCY LAW

Published on e-first 1 June AGENCY LAW Published on e-first 1 June 2018 3. AGENCY LAW Pearlie KOH LLB (Hons) (National University of Singapore), LLM (University of Melbourne); Advocate & Solicitor (Singapore); Associate Professor, Singapore

More information

PARLIAMENT OF THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA ARBITRATION ACT NO. 11 OF 1995

PARLIAMENT OF THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA ARBITRATION ACT NO. 11 OF 1995 PARLIAMENT OF THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA ARBITRATION ACT NO. 11 OF 1995 (Certified on 30 th June-1995) Arbitration Act. No. 11 of 1995 1 (Certified on 30 th June-1995) L.D. O.10/93

More information

Northern Elevator Manufacturing Sdn Bhd v United Engineers (Singapore) Pte Ltd

Northern Elevator Manufacturing Sdn Bhd v United Engineers (Singapore) Pte Ltd 494 SINGAPORE LAW REPORTS (REISSUE) [2004] 2 SLR(R) Northern Elevator Manufacturing Sdn Bhd v United Engineers (Singapore) Pte Ltd [2004] SGCA 11 Court of Appeal Civil Appeal No 57 of 2003 Chao Hick Tin

More information

APPLICATION FOR COMMERCIAL CREDIT ACCOUNT TRADING TERMS AND CONDITIONS

APPLICATION FOR COMMERCIAL CREDIT ACCOUNT TRADING TERMS AND CONDITIONS APPLICATION FOR COMMERCIAL CREDIT ACCOUNT TRADING TERMS AND CONDITIONS These Trading Terms and Conditions are to be read and understood prior to the execution of the Application for Commercial Credit Account.

More information

TERMS AND CONDITIONS OF BUSINESS- SALES OF GOODS & SERVICES. The buyer's attention is in particular drawn to the provisions of condition 10.4.

TERMS AND CONDITIONS OF BUSINESS- SALES OF GOODS & SERVICES. The buyer's attention is in particular drawn to the provisions of condition 10.4. TERMS AND CONDITIONS OF BUSINESS- SALES OF GOODS & SERVICES. The buyer's attention is in particular drawn to the provisions of condition 10.4. 1. INTERPRETATION 1.1 The definitions and rules of interpretation

More information

Mott MacDonald Ltd v London & Regional Properties Ltd [2007] Adj.L.R. 05/23

Mott MacDonald Ltd v London & Regional Properties Ltd [2007] Adj.L.R. 05/23 JUDGMENT : HHJ Anthony Thornton QC. TCC. 23 rd May 2007 1. Introduction 1. The claimant, Mott MacDonald Ltd ( MM ) is a specialist engineering multi-disciplinary consultancy providing services to the construction

More information

ADJUDICATION: RAISING OBJECTIONS TO THE ADJUDICATOR S JURISDICTION OR BREACH OF SOP ACT AT THE EARLIEST POSSIBLE OPPORTUNITY

ADJUDICATION: RAISING OBJECTIONS TO THE ADJUDICATOR S JURISDICTION OR BREACH OF SOP ACT AT THE EARLIEST POSSIBLE OPPORTUNITY ADJUDICATION: RAISING OBJECTIONS TO THE ADJUDICATOR S JURISDICTION OR BREACH OF SOP ACT AT THE EARLIEST POSSIBLE OPPORTUNITY Grouteam Pte Ltd v UES Holdings Pte Ltd [2016] SGCA 59 In Summary This Singapore

More information

STATUTORY INSTRUMENTS. S.I. No. 443 of 2014 EUROPEAN UNION (EUROPEAN MARKETS INFRASTRUCTURE) REGULATIONS 2014

STATUTORY INSTRUMENTS. S.I. No. 443 of 2014 EUROPEAN UNION (EUROPEAN MARKETS INFRASTRUCTURE) REGULATIONS 2014 STATUTORY INSTRUMENTS. S.I. No. 443 of 2014 EUROPEAN UNION (EUROPEAN MARKETS INFRASTRUCTURE) REGULATIONS 2014 2 [443] S.I. No. 443 of 2014 EUROPEAN UNION (EUROPEAN MARKETS INFRASTRUCTURE) REGULATIONS 2014

More information

SME Care Pte Ltd v Chan Siew Lee Jannie

SME Care Pte Ltd v Chan Siew Lee Jannie This judgment is subject to final editorial corrections approved by the court and/or redaction pursuant to the publisher s duty in compliance with the law, for publication in LawNet and/or the Singapore

More information

COURT OF APPEAL RULES, 1997 (C.I 19)

COURT OF APPEAL RULES, 1997 (C.I 19) COURT OF APPEAL RULES, 1997 (C.I 19) IN exercise of the powers conferred on the Rules of Court Committee by Article 157(2) of the Constitution these Rules are made this 24th day of July, 1997. PART I-GENERAL

More information

Under the terms of sale the following meaning shall apply:- You means the person seeking to purchase the goods from us

Under the terms of sale the following meaning shall apply:- You means the person seeking to purchase the goods from us Bideford Tool Ltd TERMS & CONDITIONS OF SALE 1. DEFINITIONS Under the terms of sale the following meaning shall apply:- We and us means You means the person seeking to purchase the goods from us The goods

More information

Mehrzad Nabavieh & Anor v Chong Shao Fen & Anor and Another Appeal

Mehrzad Nabavieh & Anor v Chong Shao Fen & Anor and Another Appeal Mehrzad Nabavieh & Anor v Chong Shao Fen & Anor and Another Appeal COURT OF APPEAL, PUTRAJAYA CIVIL APPEALS NOs: W 02 (NCVC) (W) 1698 07/2013 & W 0 2(NCVC) (W) 1699 07/2013 ALIZATUL KHAIR OSMAN JCA, LIM

More information

OLIVIA WAIYEE LEE Appellant. WHANGAREI DISTRICT COUNCIL Respondent. Winkelmann, Simon France and Woolford JJ

OLIVIA WAIYEE LEE Appellant. WHANGAREI DISTRICT COUNCIL Respondent. Winkelmann, Simon France and Woolford JJ IN THE COURT OF APPEAL OF NEW ZEALAND CA656/2015 [2016] NZCA 258 BETWEEN AND OLIVIA WAIYEE LEE Appellant WHANGAREI DISTRICT COUNCIL Respondent Hearing: 4 May 2016 Court: Counsel: Judgment: Winkelmann,

More information

Professional Services Agreement (short form)

Professional Services Agreement (short form) Professional Services Agreement (short form) Contract Details Item No Item Details 1 Project [#insert name of project and description] 2 JCU Name: James Cook University Address: 1 James Cook Drive, Townsville,

More information

Supplement No. 12 published with Gazette No. 22 of 24th October, DORMANT ACCOUNTS LAW. (2011 Revision)

Supplement No. 12 published with Gazette No. 22 of 24th October, DORMANT ACCOUNTS LAW. (2011 Revision) Supplement No. 12 published with Gazette No. 22 of 24th October, 2011. DORMANT ACCOUNTS LAW (2011 Revision) Law 28 of 2010 consolidated with Law 41 of 2010. Revised under the authority of the Law Revision

More information

Saudi Center for Commercial Arbitration King Fahad Branch Rd, Al Mutamarat, Riyadh, KSA PO Box 3758, Riyadh Tel:

Saudi Center for Commercial Arbitration King Fahad Branch Rd, Al Mutamarat, Riyadh, KSA PO Box 3758, Riyadh Tel: SCCA Arbitration Rules Shaaban 1437 - May 2016 Saudi Center for Commercial Arbitration King Fahad Branch Rd, Al Mutamarat, Riyadh, KSA PO Box 3758, Riyadh 11481 Tel: 920003625 info@sadr.org www.sadr.org

More information

THE BLACK MONEY (UNDISCLOSED FOREIGN INCOME AND ASSETS) AND IMPOSITION OF TAX BILL, 2015

THE BLACK MONEY (UNDISCLOSED FOREIGN INCOME AND ASSETS) AND IMPOSITION OF TAX BILL, 2015 AS PASSED BY LOK SABHA ON 11 MAY, Bill No. 84-C of THE BLACK MONEY (UNDISCLOSED FOREIGN INCOME AND ASSETS) AND IMPOSITION OF TAX BILL, ARRANGEMENT OF CLAUSES CHAPTER I CLAUSES PRELIMINARY 1. Short title,

More information

Enterprise Managed Services Ltd v East Midland Contracting Ltd [2007] Adj.L.R. 03/27

Enterprise Managed Services Ltd v East Midland Contracting Ltd [2007] Adj.L.R. 03/27 JUDGEMENT : HHJ STEPHEN DAVIES. Manchester District Registry, TCC, 27 th March 2008 A. Introduction 1. On 11 December 2007 the claimant issued these proceedings, in which it seeks to reverse the decision

More information

Developments in Construction Law in Singapore (2014)

Developments in Construction Law in Singapore (2014) Developments in Construction Law in Singapore (2014) Ho Chien Mien Partner Litigation and Dispute Resolution 20 January 2015 1 H P Construction & Engineering Pte Ltd v Chin Ivan [2014] SGHC 137 Architect

More information

IN THE HIGH COURT OF SOUTH AFRICA (WESTERN CAPE DIVISION, CAPE TOWN)

IN THE HIGH COURT OF SOUTH AFRICA (WESTERN CAPE DIVISION, CAPE TOWN) IN THE HIGH COURT OF SOUTH AFRICA (WESTERN CAPE DIVISION, CAPE TOWN) Case No: 20123/2017 20124/2017 In the matter between: SANRIA 21 (PTY) LTD Applicant and NORDALINE (PTY) LTD Respondent (Case no. 20123/2017)

More information

Abridged general conditions. for consultancy services for building and construction works (ABR Abridged)

Abridged general conditions. for consultancy services for building and construction works (ABR Abridged) Abridged general conditions for consultancy services for building and construction works (ABR Abridged) These 'Abridged general conditions for consultancy services for building and construction works (ABR

More information

APPENDIX FOR MARGIN ACCOUNTS

APPENDIX FOR MARGIN ACCOUNTS APPENDIX FOR MARGIN ACCOUNTS This Appendix applies if the Client opens or maintains a Margin Account in respect of margin facilities for trading in Securities. Unless otherwise defined in this Appendix,

More information

CITATION: Firedam Civil Engineering Pty Ltd v Shoalhaven City Council [2009] NSWSC 802

CITATION: Firedam Civil Engineering Pty Ltd v Shoalhaven City Council [2009] NSWSC 802 NEW SOUTH WALES SUPREME COURT CITATION: Firedam Civil Engineering Pty Ltd v Shoalhaven City Council [2009] NSWSC 802 JURISDICTION: Equity FILE NUMBER(S): 55037/2009 HEARING DATE(S): 24 July 2009 JUDGMENT

More information

IN THE LABOUR COURT OF SOUTH AFRICA, JOHANNESBURG ELIZABETH MATLAKALA BODIBE

IN THE LABOUR COURT OF SOUTH AFRICA, JOHANNESBURG ELIZABETH MATLAKALA BODIBE IN THE LABOUR COURT OF SOUTH AFRICA, JOHANNESBURG Not Reportable Case no: JR 490/15 In the matter between: ELIZABETH MATLAKALA BODIBE Applicant and PUBLIC SERVICE CO-ORDINATING BARGAINING COUNCIL DANIEL

More information