FORUM FOR REDRESSAL OF CONSUMER GRIEVANCES DAKSHIN HARYANA BIJLI VITRAN NIGAM D-BLOCK,

Size: px
Start display at page:

Download "FORUM FOR REDRESSAL OF CONSUMER GRIEVANCES DAKSHIN HARYANA BIJLI VITRAN NIGAM D-BLOCK,"

Transcription

1 Case No. DH/CGRF-997/2015 Date of Institution: Date of Hearing: Date of Order: Before the, DHBVN. Present:- Sh. Daljit Singh, Chairman Sh. R.V.Bari, Member Sh. Satish Malik, Member In the matter o f co mplaint o f S mt. S antosh W/o S h. B albir S ingh, H.No. 219, T.P.Scheme, Sector-5, Hisar regarding refund of development charges... Complainant/Petitioner V/s 1. Xen/Operation Division No.1, DHBVN, Hisar. 2AEE, City Sub-Division, Double Phatak, DHBVN, Hisar. Appearance:- For Complainant: For the Respondent: 1.None..Respondents 1.Nodal Officer/CGRF,DHBVN,Hisar 2.SDO/Counsel of Sub Divn., DHBVN, Hisar.

2 ORDER Smt. Santosh W/o Sh. Balbir Singh, H.No. 219, T.P.Scheme, Surajmal Enclave, Sector-5, Hisar has got an electricity connection bearing A/C No. BTM-4413 under AEE/Op. City Sub-Division, DHBVN, Hisar, hence this Forum has jurisdiction to hear the complaint. The complainant has filed the present complaint stating therein that the respondent has charged development charges at the time of release of electricity connection and demanded the refund of the same and to r elease p ermanent el ectricity c onnection in H ouse No. 219, T.P.Scheme, S urajmal E nclave, Sector-5, Hisar. The consumer stated that the area of Surajmal Enclave, Sector-5, Hisar is authorized colony vide Govt. of Haryana Endst.No. 8/76/91-6CI dated 06/11/2006 and bearing drawing No. DTP(H)3414 dated 20/07/2006. The c omplaint was f orwarded t o t he N odal O fficer for f iling t he N igam s v ersion and bot h t he par ties were asked to appear before the Forum on 06/02/2015 at Hisar for hearing of the case. To-day, t he pr oceedings h eld a t H isar on 0 6/02/2015. T he c onsumer i s not pr esent but r espondent SDO/Counsel of r espondent s ub-division is pr esent. T he r espondent SDO s ubmitted r eply t hrough N odal Officer/CGRF, DHB VN, v ide h is of fice m emo N o. 375/76 dated 05/02/2015, s tating therein t hat Surajmal Enclave, Sector-5, Hisar area is not authorized, it is not included in the list of authorized colonies circulated by M.C. Hisar. Therefore, the development charges are recoverable from the consumer. Moreover, the charges of street lighting are being paid by the Colonizer and not by the Municipal Committee. The respondent SDO also stated that she since long had availed/took an electric connection from the respondent after making necessary payment of development charges and now she is stopped at such a fag end to raise a question mark upon her own act which she did voluntarily. After going through the case file, the information/documents supplied by the appellant as well as by the respondent on t he dat e of hear ing and d iscussion h eld d uring t he c ourse of hear ing i n t he c ase, t he F orum decides t o di smiss t he pet ition of t he pet itioner c onsidering itself i ncompetent t o dec ide t he i ssue. T he consumer is at liberty to file the case in appropriate Forum/Court to get the matter decided as to whether the Surajmal Enclave, Sector-5, Hisar is authorized colony or not. File be consigned to record. Given under out hands on this day of 6 th February, (Daljit Singh) (R.V.Bari) (Satish Malik) Chairman Member Member

3 Case No. DH/CGRF-998/2015 Date of Institution: Date of Hearing: Date of Order: Before the, DHBVN. Present:- Sh. Daljit Singh, Chairman Sh. R.V.Bari, Member Sh. Satish Malik, Member In the matter of complaint of Smt. Pavita W/o Sh. Baljeet S ingh, H.No. 303, T.P.Scheme, Sector-5, Hisar regarding refund of development charges... Complainant/Petitioner V/s 1. Xen/Operation Division No.1, DHBVN, Hisar. 2AEE, City Sub-Division, Double Phatak, DHBVN, Hisar. Appearance:- For Complainant: For the Respondent: 1.None..Respondents 1.Nodal Officer/CGRF,DHBVN,Hisar 2.SDO/Counsel of Sub Divn., DHBVN, Hisar.

4 ORDER Smt. Pavita W/o Sh. Baljeet Singh, H.No. 303, T.P.Scheme, Surajmal Enclave, Sector-5, Hisar has got an electricity connection bearing A/C No. SM under AEE/Op. City Sub-Division, DHBVN, Hisar, hence this Forum has jurisdiction to hear the complaint. The complainant has filed the present complaint stating therein that the respondent has charged development charges at the time of release of electricity connection and demanded the refund of the same and to r elease p ermanent el ectricity c onnection in H ouse No. 219, T.P.Scheme, S urajmal E nclave, Sector-5, Hisar.. The consumer stated that the area of Surajmal Enclave, Sector-5, Hisar is authorized colony vide Govt. of Haryana Endst.No. 8/76/91-6CI dat ed 06/11/2006 and bearing drawing No. DTP(H)3414 dated 20/07/2006. The c omplaint was f orwarded t o t he N odal O fficer for f iling t he N igam s v ersion and bot h t he par ties were asked to appear before the Forum on 06/02/2015 at Hisar for hearing of the case. To-day, the proceedings held at Hisar on 06/02/2015. The consumer is not present but SDO/Counsel of r espondent s ub-division i s pr esent. T he r espondent SDO s ubmitted r eply t hrough N odal O fficer/cgrf, DHBVN, v ide his of fice m emo No. 377/78 d ated 05/ 02/2015, s tating therein t hat Surajmal Enclave, Sector-5, Hisar ar ea i s not au thorized, it is no t i ncluded i n t he list of aut horized c olonies c irculated b y M.C. H isar. Therefore, t he dev elopment c harges ar e r ecoverable f rom t he c onsumer. Mor eover, t he c harges of s treet lighting are being paid by the Colonizer and not by the Municipal Committee. The respondent SDO also stated that s he s ince l ong ha d availed/took an el ectric c onnection f rom t he r espondent af ter making nec essary payment of development charges and now she is stopped at such a fag end to raise a question mark upon her own act which she did voluntarily. After going through the case file, the information/documents supplied by the appellant as well as by the respondent on t he dat e of hear ing and d iscussion h eld d uring t he c ourse of hear ing i n t he c ase, t he F orum decides t o di smiss t he pet ition of t he pet itioner c onsidering itself i ncompetent t o dec ide t he i ssue. T he consumer is at liberty to file the case in appropriate Forum/Court to get the matter decided as to whether the Surajmal Enclave, Sector-5, Hisar is authorized colony or not. File be consigned to record. Given under our hands on this day of 6 th February, (Daljit Singh) (R.V.Bari) (Satish Malik) Chairman Member Member

5 Case No. DH/CGRF-999/2015 Date of Institution: Date of Hearing: Date of Order: Before the, DHBVN. Present:- Sh. R.V.Bari, Member Sh. Satish Malik, Member In the matter of complaint of Smt. Bala Rajbala W/o Sh. Subhash Chand, H.No. 181, Sector- 2, Palwal regarding billing problem... Complainant/Petitioner V/s 1. Xen/Op. Division, DHBVN, Palwal. 2.SDO/Op. S/Division, DHBVN, Palwal. Appearance:- For Complainant: 1.Present..Respondents For the Respondent: 1.Nodal Officer,CGRF, DHBVN, Hisar. 2.Representative of Sub-Divn., DHBVN, Palwal. ORDER

6 Smt. Bala Rajbala W/o Sh. Subhash Chand, H.No. 181, Sector-2, Palwal has got an electricity connection bearing A/C No under SDO/Op. Sub-Division, DHBVN, Palwal, hencthe SDOe this Forum has jurisdiction to hear the complaint. The complainant has filed the complaint, stating therein that; 1. On dated 18/03/2008 an inspection team authorized by DHBVN inspected the premises of the applicant and vide its test report No Book No found the meter burnt. 2. After this inspection, DHBVN started issuing bill on av erage basis and it continued during so years together but vide bill No dated 27/01/2014 found the meter to be working properly and charged Rs.9415/- as sundry charges. 3. The applicant requested to SDO concerned vide his letter dated 15/04/2014 for waiving off the sundry charges and for correction of the bill and showing his willingness to pay the corrected bill. 4. The a foresaid l etter w as marked to JE o f t he ar ea w ho af ter p hysical verification recommended for issuance of MCO. 5. The SDO Urban S/Divn. instead of getting the bill corrected used coercive methods to recover the di sproportionate am ount and v ide i ts order N o. 7/ 1002 dat ed 21 /04/2014 or dered for disconnection of the electric supply to the applicant. 6. Having no other alternative applicant was forced to deposit the disproportionate billed amount including Rs.9415/- as sundry charges vide CCR Book No. 90 page No.27 item No.144 dated 23/04/ On 06/06/2014 applicant was informed by DHBVN to get the defective meter replaced and to deposit an am ount of Rs.1100/- for new meter. T he applicant deposited the said amount on 06/06/2014 vide memo No The DHBVN took more than a month to replaced the meter despite the deposition of required amount. 9. Despite the installation of new meter, DHBVN vide bill No dated 24/10/2014 issued bill for 123 days on average basis. 10. Vide bill No dat ed 28/12/2014, applicant has been shown to have consumed 2015 uni ts from 25 /05/2014 t o 28/ 11/2014 bel iving t he de fective m eter t o hav e worked properly before its replacement. The consumer requested to get the sundry charges of Rs.9415 refunded with interest and not to charge for 576 units rather 744 units of the defective meter and oblige. -: 2 :-

7 The complaint was forwarded to the Nodal Officer for filing the Nigam s version and bot h the parties were asked to appear before the Forum on 10/02/2015 at Palwal for hearing of the case. To-day, the proceedings held at Palwal on 10/02/2015. The consumer as well as representative of respondent SDO is present. The SDO submitted reply through Nodal Officer/CGRF, DHBVN, vide his office memo No. 187 dated 09/02/2015, stating therein that bill raised from 06/2012 to 10/2013 of the consumer on average 240 units due to D-Code, but reading recorded regularly by the meter reader. But average charged by the system is less than consumption recorded in meter/system, hence account is overhauled by the local audit party and charge the amount of Rs.9415/- vide SC&AR No. 55/R-92. After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing and discussion held during the course of hearing in the case, the Forum directed the SDO that his account may be overhauled after six billing cycles on the basis of reading recorded by new meter installed in 07/2014. The representative of respondent SDO stated that for other grievance of the consumer needful will be done in the next bill. The Forum disposed off the petition without any cost on either side and case is closed from the Forum. File be consigned to record. Given under our hands on this day of 10 th February, (R.V.Bari) Member (Satish Malik) Member

8 Case No. DH/CGRF-1000/2015 Date of Institution: Date of Hearing: & Date of Order: Before the, DHBVN. Present:- Sh. Daljit Singh, Chairman Sh. R.V.Bari, Member Sh. Satish Malik, Member In the matter of complaint of Sh. Roshan Lal S/o Late Sh. Vijay Ram, V&P.O. Ladwa, Tehsil & Distt., Hisar regarding billing problem... Complainant/Petitioner V/s 1. Xen/Operation Division No.II, DHBVN, Hisar. 2 SDO/Op. Sub-Division, DHBVN, Satrod, Hisar. Appearance:- For Complainant: For the Respondent:.Respondents 1.Present. 1.Nodal Officer/CGRF,DHBVN,Hisar 2.SDO/Counsel of Sub Divn., DHBVN, Satrod, Hisar.

9 ORDER Sh. R oshan La l S /o L ate Sh. V ijay R am, V &P.O. L adwa, Tehsil & D istt., H isar has got an el ectricity connection be aring A /C N o. E -587 un der S DO/Op. S ub-division, D HBVN, S atrod, he nce t his F orum has jurisdiction to hear the complaint. The complainant has filed the present complaint stating therein that he has applied for PDCO on 28/02/2001. On dated 28/02/2006, the respondent has issued bill. His premises was checked on 26/02/2009 by the JE. The JE reported that there is no meter entered in CA-22 of A/C No. E-587. On dated 04/09/2010, an Open Darbar was held in Vidyut Nagar where the complainant was assured that bill will not be issued in future. After f our months, he v isited t he r espondent office and r espondent t old him t hat h is c onnection has be en disconnected. But the e lectric bill is s till being s ent to him. T he c omplainant h as r equested f or issue of No Dues certificate against A/C No. E-587 and stoppage of further issuance of bill. The c omplaint was f orwarded t o t he N odal O fficer for f iling t he N igam s v ersion and bot h t he par ties were asked to appear before the Forum on 06/02/2015 at Hisar for hearing of the case. During the proceedings held at H isar on 06 /02/2015, t he c onsumer as well a s representative/counsel of r espondent S DO was pr esent. T he r epresentative/counsel of r espondent S DO stated that his office could not prepare reply due to late receipt of complaint and requested for next date. After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing and discussion held during the course of hearing in the case, the Forum decides to adjourn the case for next date due to non-submission of reply by the respondent SDO. To-day, the proceedings held at Hisar on 05/03/2015. The consumer as well as respondent SDO/Counsel of respondent sub-division is present. The respondent SDO has submitted copy of sundry charges and allowance register vide which wrong amount has been withdrawn and the grievance of the consumer has been redressed. The respondent SDO submitted that there is no amount pending and he will issue the No Dues Certificate to the complainant. After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing and discussion held during the course of hearing in the case, the Forum decided that the grievances of the consumer has been redressed as per reply submitted by the respondent SDO. The Forum disposed off the petition without any cost on either side and case is closed from the Forum. File be consigned to record. Given under our hands on this day of 5 th March, (Daljit Singh) (R.V.Bari) (Satish Malik) Chairman Member Member

10 Case No. DH/CGRF-1001/2015 Date of Institution: Date of Hearing: & Date of Order: Before the, DHBVN. Present:- Sh. Daljit Singh, Chairman Sh. R.V.Bari, Member Sh. Satish Malik, Member In the matter of complaint of Smt. Sunehri Devi W/o Sh. Bharat Singh, V&P.O. Barwala, Ward No.2, Barwala, Distt., Hisar regarding tube well connection... Complainant/Petitioner V/s 1. Xen/Operation Division No.II, DHBVN, Hisar. 2 SDO/Op. Sub-Division, DHBVN, Barwala, Distt., Hisar. Appearance:- For Complainant: For the Respondent:.Respondents 1.None. 1.Nodal Officer/CGRF,DHBVN,Hisar 2.Representative of Sub Divn., DHBVN, Barwala.

11 ORDER Smt. Sunehri Devi W/o Sh. Bharat Singh, Ward No.2, Barwala, Distt., Hisar has applied for tube well connection under S DO/Op. S ub-division, D HBVN, Barwala, h ence this Forum has j urisdiction t o h ear t he complaint. The c omplainant h as f iled t he pr esent c omplaint s tating t herein t hat s he h as app lied f or t ube well connection in After that, the respondent had issued notice of dated 07/07/2013 for depositing Rs.67500/-. The c omplainant deposited R s.67500/- on 0 8/07/2013. She visited t he X EN office and t hen t he c ontractor erected his t ube well l ine in O ctober, But t he c ontractor has not got i nspected her line f rom C hief Electrical Inspector. In Open Darbar, her husband again met with XEN who assured that 63 KVA T/F would be soon installed after inspection of line by the Chief Electrical Inspector. The consumer requested for release her tube well connection immediately. The c omplaint was f orwarded t o t he N odal Officer for f iling t he N igam s v ersion and bot h t he par ties were asked to appear before the Forum on 06/02/2015 at Hisar for hearing of the case. During the proceedings held at Hisar on 06/02/2015, the consumer not present but respondent SDO was present. The SDO submitted reply of XEN/Op. Division No.II, DHBVN, Hisar through Nodal Officer/CGRF, DHBVN, vide his office memo No dated 05/02/2015, stating therein that Smt. Sunehari Devi W/o S h. B harat S ingh had a pplied f or new t ube w ell c onnection v ide a pplication N o /AP d ated 07/09/2011 and de posited t he ACD an d pr ocess c harges am ounting t o Rs T he SDO, Barwala framed an es timate of 3 N o. LT s pans and au gmentation of a lready existing 2 5 K VA T /F t o 63 KVA T /F f or release of ne w c onnection to the c omplainant a nd t he es timate was s anctioned b y his of fice vide m emo No. 100/BR/ T he demand not ice was s ent t o t he c omplainant vide his office memo N o d ated 12/06/2013. T he c omplainant c omplied with the d emand notice and s ubmitted the t est r eport a long with t he required documents on dated 08/07/2013 and also deposited Rs.37500/- + Rs.30,000/- = Rs.67500/- as cost of spans and partial cost of T/F. The work for erection of HT/LT lines were allotted to M/s Aadhar Group & the said Firm has completed the line work except the Inspection of CEI, Hisar. The SDO/Op. Sub-Divn., Barwala has also requested to the CEI, Hisar for inspection vide his office memo No. 119/20 dat4ed 07/01/2015. The inspection of the line was carried by the CEI, Hisar on dated 14/01/2015 and the approval was given by them to energize t he l ine with s ome obs ervations. T he SCO w as i ssued by the r espondent S DO, B arwala v ide his office SCO No. 14/0361 dated 15/01/2015. After removing the observations of CEI, the tube well connection of the complainant was released on 17/01/2015.

12 -: 2 :- After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing and discussion held during the course of hearing in the case, the Forum decides to adjourn the case for next date due to non-presence of consumer. To-day, the proceedings held at Hisar on 05/03/2015. The consumer is not present but representative of respondent SDO is present. The representative of respondent SDO stated that the connection of the consumer has already been released and grievance of the consumer has been redressed. After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing and discussion held during the course of hearing in the case, the Forum decided/concluded that the grievance of the consumer has been redressed by the respondent SDO. The Forum disposed off the petition without any cost on either side and case is closed from the Forum. File be consigned to record. Given under our hands on this day of 5 th March, (Daljit Singh) (R.V.Bari) (Satish Malik) Chairman Member Member

13 Case No. DH/CGRF-1002/2015 Date of Institution: Date of Hearing: Date of Order: Before the, DHBVN. Present:- Sh. Daljit Singh, Chairman Sh. R.V.Bari, Member Sh. Satish Malik, Member In the matter of complaint of Smt. Shilpa Rani W/o Sh. Gulshan Kumar, New Rishi Nagar, Near Naveen Public School, Hisar regarding billing problem... Complainant/Petitioner V/s 1. Xen/Operation Division No.1, DHBVN, Hisar. 2AEE, City Sub-Division, Double Phatak, DHBVN, Hisar. Appearance:- For Complainant: For the Respondent:.Respondents 1.Representative. 1.Nodal Officer/CGRF,DHBVN,Hisar 2.SDO/Counsel of Sub Divn., DHBVN, Hisar.

14 ORDER Smt. S hilpa R ani W/o S h. G ulshan K umar, N ew R ishi Nagar, N ear N aveen P ublic School, Hisar has got an electricity connection bearing A/C No. S101/2289 under AEE/Op. City Sub-Division, DHBVN, Hisar, hence this Forum has jurisdiction to hear the complaint. The complainant has filed the present complaint stating therein that she had deposited the energy bill upto Oct., Her electricity meter has been replaced by the respondent without any co mplaint and af ter 20 day s, t he r espondent has issued bi ll of uni ts amounting t o Rs.77045/-. H er pr emises is 43 sq. y ards and her sa nctioned l oad i s 1.60 KW. The co mplainant requested for correction of her bill. The complaint was forwarded to the Nodal Officer for filing the Nigam s version and bot h the parties were asked to appear before the Forum on 06/02/2015 at Hisar for hearing of the case. To-day, t he pr oceedings held at H isar on 0 6/02/2015. T he r epresentative of consumer as well as SDO/Counsel of respondent Sub-division is present. T he respondent SDO submitted reply through Nodal Officer/CGRF, DHBVN, vide his office memo No. 379/80 dated 05 /02/2015, s tating t herein t hat t he e lectric meter o f t he p etitioner st ands relocated from inside to outside as per policy of the Nigam on dated 22/11/2014 having a consumption reading of units and had installed a new meter with IR of 2 and the concerned JE had submitted i ts respective r eport o f M CO with t he o ffice o f r espondent and t he o ffice of respondent after receipt of MCO had tallied the reading with the consumer ledger and after checking the same, an astonishing fact came into the knowledge of the respondent on t hat relevant day, in the consumer ledger, the reading of the electric connection in question was found recorded only 6271, despite the fact that at the spot, the electric meter of the petitioner records consumption reading 16316, which amply proves the version qua the accumulation of reading by the petitioner in collusion with the concerned Meter Reader. So, on account of accumulation of r eading, t he o ffice of t he respondent h ad i ssued t he bill am ounting to Rs.77046/- which i ncludes difference r eading of a nd 1 30 r eading r ecorded by n ew meter, but the petitioner had not made the payment towards the same and t he respondent looking into the same had disconnected the electricity supply of the premises of the petitioner and the electric connection of t he petitioner can be restored only after making payment of entire outstanding amount.

15 -: 2 :- After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing and discussion held during the course of hearing in the case, the Forum is of the opinion that taking into consideration, the reading pattern of the old meter together with the sanctioned load which is 1.6 KW and also one subsequent reading (around 130 units) of new meter. There is a case of sudden jump of the meter and not accumulation of reading. The Forum, therefore, directed. the respondent SDO that he will overhaul the account of the consumer on the basis of succeeding three cycle billing of new meter and accept the current bill from the consumer till then. After three cycles billing, the impugned amount i.e. Rs.77046/- be adjusted and account be overhauled on the basis of succeeding three cycle billing. The Forum disposed off the petition without any cost on either side and case is closed from the Forum. File be consigned to record. Given under our hands on this day of 6 th February, (Daljit Singh) (R.V.Bari) (Satish Malik) Chairman Member Member

16 Case No. DH/CGRF-1003/2015 Date of Institution: Date of Hearing: Date of Order: Before the, DHBVN. Present:- Sh. Daljit Singh, Chairman Sh. R.V.Bari, Member Sh. Satish Malik, Member In the matter of complaint of Sh. Satish Kumar S/o Sh. Raj Kumar, V&P.O. Buda Khera, Tehsil, Uklana, Distt., Hisar regarding billing problem... Complainant/Petitioner V/s 1. Xen/Operation Division, DHBVN, Tohana. 2 SDO/Op. Sub-Division, DHBVN, Uklana, Distt., Hisar. Appearance:- For Complainant: For the Respondent:.Respondents 1.Present. 1.Nodal Officer/CGRF,DHBVN,Hisar 2.SDO of Sub Divn., DHBVN, Uklana.

17 ORDER Sh. S atish K umar S /o Sh. R aj K umar, V &P.O. Buda K hera, T ehsil, U kalan, D istt., H isar has got an electricity c onnection bearing A/C No. BD1D-0841 u nder SDO/Op. S ub-division, DHB VN, Uklana, he nce t his Forum has jurisdiction to hear the complaint. The complainant has filed the present complaint stating therein that the respondent had issued bill of Rs.30,000/- and his meter removed. The consumer requested for installation of meter and deposited the amount in installments of Rs.2000/- per installment. The c omplaint was f orwarded t o t he N odal O fficer for f iling t he N igam s v ersion and bot h t he par ties were asked to appear before the Forum on 06/02/2015 at Hisar for hearing of the case. To-day, t he pr oceedings h eld at H isar on 06 /02/2015. T he c onsumer as well a s r espondent SDO is present. T he r espondent SDO s ubmitted r eply through N odal O fficer/cgrf, DHBVN, vide his office memo No. 275 dated 06/02/2015, stating therein that connection of the complainant has been disconnected on dated 05/12/2013 vide PDCO No. 20/1223 on defaulting amount Rs.31906/- which is outstanding against the consumer. The c onnection c annot b e r eleased of d efaulter c onsumer. T he c onsumer w ants t o m ake t he payment i n installments of R s.2000/- only p er bi ll, but as per N igam i nstruction, R CO of def aulter c onsumer cannot be affected without payment of full defaulting amount. After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing and discussion held during the course of hearing in the case, the Forum noted that the consumer is physically handicapped and very poor and hardly able to have his both ends meet. The Forum, therefore, directed the respondent SDO to release connection of the consumer by getting deposited 1/6 th of the defaulting amount. The balance defaulting amount be recovered in 5 equal installments along with current bill payment. The consumer is also directed that he will deposit 1/6 th of defaulting amount with the respondent Nigam and Nigam will release his connection after depositing 1/6 th amount of defaulting amount. The Forum disposed off the petition without any cost on either side and case is closed from the Forum. File be consigned to record. Given under our hands on this day of 6 th February, (Daljit Singh) (R.V.Bari) (Satish Malik) Chairman Member Member

18 Case No. DH/CGRF-1004/2015 Date of Institution: Date of Hearing: Date of Order: Before the, DHBVN. Present:- Sh. R.V.Bari, Member Sh. Satish Malik, Member In the matter of complaint of Sh. Manish Gulati S/o Sh. T.C. Gulati, H.No. 462, Sector-14, Faridabad (M/s Sugu Fabrics & Linings, 49 KM Mile Stone, Village Prithla, Palwal) regarding metering problem... Complainant/Petitioner V/s 1. Xen/Op. Division, DHBVN, Palwal. 2.SDO, S/U S/Division, DHBVN, Palwal. Appearance:- For Complainant: 1.Present..Respondents For the Respondent: 1.Nodal Officer,CGRF, DHBVN, Hisar. 2.SDO of S/U Sub-Divn., DHBVN, Palwal.

19 ORDER Sh. Manish Gulati S/o Sh. T.C. Gulati, H.No. 462, Sector-14, Faridabad (M/s Sugu Fabrics & Linings, 49 K M Mile Stone, Fillage Prithla, Palwal has got an electricity connection bearing A/C No. F42-GLHT-18 under SDO, S/U Sub-Division, DHBVN, Palwal, hence this Forum has jurisdiction to hear the complaint. The complainant has filed the complaint, stating therein that there is problem in the display of meter reading due to which wrong readings are coming and he is paying extra money. The consumer has already filed the complaint on 25/07/2014 to the SDO, Palwal and the same has been registered in the file on S r. No. 422 dat ed 25/07/2014 but no action took place. The consumer again filed the complaint t o S DO, Mr. Singla on 21/ 11/2014. The S DO passe d m eter ch ange or der on the s ame dqate and fees of Rs.7100/- was deposited but till date nothing has been done by the respondent. The co nsumer requested t o ask the aut hority co ncerned t o ch ange t he m eter and till dat e pr ovide relief in the bill amount. The complaint was forwarded to the Nodal Officer for filing the Nigam s version and bot h the parties were asked to appear before the Forum on 10/02/2015 at Palwal for hearing of the case. To-day, the proceedings held at Palwal on 10/02/2015. The consumer as well as respondent SDO is present. The SDO submitted reply through Nodal Officer/CGRF, DHBVN, vide his office memo No. 361 dated 10/02/2015, stating therein that defective meter of the consumer has been replaced on dated 09/02/2015 and there is no grievance pending. The consumer submitted in writing that he is satisfied. After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing and discussion held during the course of hearing in the case, the Forum decided that since the meter has been replaced by the respondent SDO and consumer has given in writing that he is satisfied, the petition is disposed off without any cost on either side and case is closed from the Forum. File be consigned to record. Given under our hands on this day of 10 th February, (R.V.Bari) Member (Satish Malik) Member

20 Case No. DH/CGRF-1005/2014 Date of Institution: Date of Hearing: Date of Order: Before the, DHBVN. Present:- Sh. R.V.Bari, Member Sh. Satish Malik, Member In t he m atter o f co mplaint o f S h. G ulshan K umar, H.No.412, S BI S treet, A ggarsain C olony, S irsa regarding billing problem... Complainant/Petitioner V/s 1. Xen/Op. City Division, DHBVN, Sirsa. 2.SDO, City Sub-Division, DHBVN, Sirsa. Appearance:- For Complainant: For the Respondent: 1.Present..Respondents 1. Nodal Officer/ CGRF,DHBVN,Hisar. 2..Representative of City Sub Divn., DHBVN,Sirsa

21 ORDER Sh. Gulshan Kumar, H.No. 412, SBI Street, Aggarsain Colony, Sirsa has got an electricity connection bearing A/C No. TT under SDO, City Sub-Division, DHBVN, Sirsa, hence this Forum has jurisdiction to hear the complaint. The complainant has filed the present complaint stating therein that the respondent had issued wrong bill of dated 11/09/2012 to 10/10/2012. His energy meter recorded very high consumption due to jump during the said period. He has no high energy consuming electrical equipment in his shop. He stated that does the work of tailor in his shop and requested for correction of his bill. The c omplaint was f orwarded t o t he N odal O fficer for f iling t he N igam s v ersion and bot h t he par ties were asked to appear before the Forum on 18/02/2015 at Sirsa for hearing of the case. To-day, the proceedings held at Sirsa on The consumer as well as representative of the respondent SDO is pr esent. T he SDO s ubmitted r eply through N odal O fficer/cgrf, DHBVN, vide his office memo N o. 436 dat ed 10 /02/2015, s tating t herein t hat a c heck meter i nstalled v ide SJO N o d ated 24/01/2013 and removed on 01/02/2013. The check meter recorded 48 units. Existing meter did not show the reading, being meter was dead stop. The meter replaced vide MCO No. 18/5512 dated 06/03/2013, FR-17958, IR-5. The average charged in the month of 03/2013 was adjusted of Rs.5217 against SC&AR No. 4/111. After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing and discussion held during the course of hearing in the case, the Forum directed the respondent SDO to overhaul the account of the consumer on the basis of consumption pattern of new meter installed in the month of March, The account of the consumer be overhauled on the basis of new meter reading recorded for one year for the period 04/2013 to March, The Forum disposed off the petition without any cost on either side and case is closed from the Forum. File be consigned to record. Given under our hands on this day of 18 th February, (R.V.Bari) Member (Satish Malik) Member

22 Case No. DH/CGRF-1006/2015 Date of Institution: Date of Hearing: & Date of Order: Before the, DHBVN. Present:- Sh. Daljit Singh, Chairman Sh. R.V.Bari, Member Sh. Satish Malik, Member In the matter of complaint of Sh. Balbir Singh S/o Sh. Harkaran Lal, H.No.14/14, PNB Bank Street, Ram Colony, Barnala Road, Sirsa regarding billing problem... Complainant/Petitioner V/s 1. Xen/Op. City Division, DHBVN, Sirsa. 2.SDO, City Sub-Division, DHBVN, Sirsa. Appearance:- For Complainant: For the Respondent:.Respondents 1.Present. 1. Nodal Officer/ CGRF,DHBVN,Hisar. 2..SDO of City Sub Divn.,DHBVN,Sirsa

23 ORDER Sh. B albir S ingh S /o Sh. Harkaran Lal, H.No.14/14, P NB B ank S treet, R am Colony, Barnala R oad, Sirsa has got an electricity connection bearing A/C No. T12/ST under SDO, City Sub-Division, DHBVN, Sirsa, hence this Forum has jurisdiction to hear the complaint. The complainant has filed the present complaint stating therein that; 1. He r eceived e lectricity b ill of R s.9583/- due dat e 2 9/08/2013 which was be yond h is ex pectation & consumption. 2. Previous bills of all the times were between Rs.1000/-, Rs.1200/- & Rs.1500/-. After installation of new meter, the bills are in between Rs.1200/-, Rs.1500/- & Rs.1800/-. 3. Only bill of August jumped to Rs.9583/- and he made complaint to replace the defective meter and take the average of previous bill by installing the check meter. But without installing check meter, new meter installed When he made the representation of adjustment of excess bill, he was told that the same will be done after one year. F inally af ter one year, when h e ap proached Sirsa of fice, he w as t old t hat h is bi ll i s correct and no adjustment is required because no check meter was installed. The consumer requested the Forum to redress his grievances on the basis of his representation along with request for next date. Request granted. The c omplaint was f orwarded t o t he N odal O fficer for f iling t he N igam s v ersion and bot h t he par ties were asked to appear before the Forum on 18/02/2015 at Sirsa for hearing of the case. During the proceedings held at Sirsa on , the consumer was not present but representative of the respondent SDO was present. The SDO submitted reply through Nodal Officer/CGRF, DHBVN, vide his office memo No. 435 dated 10/02/2015, stating therein that the complaint was checked by the area In-charge and found meter display defective. The meter was replaced vide MCO No dated 17/09/2013, FR-NV, IR-2 and bill raised to consumer on actual consumption, no average charged. After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing and discussion held during the course of hearing in the case, the Forum decides to adjourn the case for next date on the request of the consumer. To-day, t he pr oceedings hel d at Sirsa on 20/ 03/2015. The c onsumer as well a s r espondent S DO i s present. T he c onsumer r equested t hat hi s ac count may be o verhauled o n t he bas is of c onsumption of electricity as recorded by new meter. The SDO replied that if adjustment is made on t he basis of reading of new meter, the average consumption per month will come to additional 402 units and he may have to pay more than the amount charged.

24 -: 2 :- After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing and discussion held during the course of hearing in the case, the Forum concludes that keeping in view the pattern of consumption prior to replacement of meter and after that, the amount charged is reasonable. The Forum disposed off the petition without any cost on either side and case is closed from the Forum. File be consigned to record. Given under our hands on this day of 20 th March, (Daljit Singh) (R.V.Bari) (Satish Malik) Chairman Member Member

25 Case No. DH/CGRF-1007/2015 Date of Institution: Date of Hearing: & Date of Order: Before the, DHBVN. Present:- Sh. Daljit Singh, Chairman Sh. Satish Malik, Member In the matter of complaint of Smt. Rajni Bagla W/o Sh. Ajay Bagla, C/o M/s Haryana Wire Drawing, Rohtak Road, Charkhi Dadri, Distt., Bhiwani regarding billing problem... Complainant/Petitioner V/s 1. Xen/Op. Division, DHBVN, Charkhi Dadri. 2.SDO/Op. City S/Division, DHBVN, Charkhi Dadri. Appearance:- For Complainant: For the Respondent:.Respondents 1.Representative. 1. Nodal Officer /CGRF,DHBVN,Hisar 2.SDO/Op. C ity S ub-divn., DHB VN, Ch arkhi Dadri.

26 ORDER Smt. R ajni B agla W/o S h. A jay Bagla C /o M/s H aryana Wire D rawing, R ohtak R oad, C harkhi D adri, Distt., B hiwani has go t a n el ectricity c onnection A /C N o. R W under S DO/Op. C ity Sub-Division, DHBVN, Charkhi Dadri, hence this Forum has jurisdiction to hear the complaint. The c omplainant has f iled t he c omplaint, s tating t herein t hat s he had l odged a c omplaint t o t he respondent in Oct./Nov., 2013 that her energy meter was not showing the reading. After that respondent had got deposited Rs.3300/- as meter cost and CT purchased from the market by her. Then the respondent stated that CT may be got checked from Hisar. She got checked the CT from Hisar Lab and again deposited in the office of respondent SDO. The respondent installed the meter in July, 2014 after so many visits. After installing new meter, the respondent issued bill on average basis and not the correct bill. The consumer requested the Forum t o ov erhaul her ac count f rom S ept., t o Oct., 2014 an d d irect t he department t o pay i nterest on security also. The c omplaint was f orwarded t o t he N odal O fficer for f iling t he N igam s v ersion and bot h t he par ties were asked to appear before the Forum on 23/01/2015 at Bhiwani for hearing of the case. During the proceedings held at Bhiwani on 23/01/2015, the consumer representative as well as respondent SDO was present. The respondent SDO submitted reply through Nodal Officer/CGRF, DHBVN, vide his office memo No dated 23/01/2015, stating therein that the account of the consumer will be overhauled after getting the approval from XEN/Op. Divn., DHBVN, Charkhi Dadri and requested the Forum to list the case for next date. It was also added that the bill of the consumer had already been corrected for the period from Sep., 2013 to Oct., 2014 and Rs.72470/- refunded to the consumer vide SC&AR No. 287/125 and the same was refunded in th month of Nov. & Dec., 2014 (Nov. Rs.67188/ /- = Rs.72470/-). However, the consumer was not fully satisfied with the reply of respondent SDO and stated that initial reading in the month of Nov., 2014 was taken as 2 units whereas it should have been taken as 444 units. The respondent SDO agreed to this and stated that he will rectify the bill and issue correct bill to the consumer. After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing and discussion held during the course of hearing in the case, the Forum directed the respondent SDO that he will issue correct bill to the consumer and submit compliance report on or before the next date of hearing. To-day, the proceedings held at Bhiwani on 20/02/2015. The consumer representative as well as respondent SDO is present. The SDO submitted reply through Nodal Officer/CGRF, DHBVN, vide his office memo No dated 19/02/2015, stating therein that the account of the consumer again overhauled in continuation of his office SC&AR No. 287/125 and Rs.45897/- refunded to the consumer vide SC&AR No. 31/130 dated 12/02/2015. The contention of the consumer that his account may be overhauled on the basis of consumption of 4-6 months and the average consumption of 6 months may be taken while overhauling the account of the consumer. Previously, the account of the consumer was overhauled on the basis of consumption of 3 months for which the consumer did not agree.

27 -: 2 :- After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing and discussion held during the course of hearing in the case, the Forum admitted the contention of the consumer and the account of the consumer may be overhauled by taking the average of the 6 months basis and redressed the grievance of the consumer. The Forum disposed off the petition without any cost on either side and case is closed from the Forum. File be consigned to record. Given under our hands on this day of 20 th February, (Daljit Singh) Chairman (Satish Malik) Member

28 Case No. DH/CGRF-1008/2014 Date of Institution: Date of Hearing: Date of Order: Before the, DHBVN. Present:- Sh. R.V.Bari, Member Sh. Satish Malik, Member In t he m atter o f co mplaint o f Sh. A rvind G upta, H.No. A -1773, Fi rst Fl oor, B ack side Green F ield Colony, Faridabad regarding billing problem... Complainant/Petitioner V/s 1. Xen/Operation Division, DHBVN, Old Faridabad. 2.SDO/Op. Sub-Division, Mathura Road, DHBVN, Faridabad. Appearance:-.Respondents For Complainant: 1.Present.. For the Respondent: 1.Nodal Officer/CGRF,DHBVN,Hisar 2. CA of sub-division, M/Road, Faridabad.

29 ORDER Sh. Arvind Gupta, H.No. A-1773, First Floor, Back side Green Field Colony, Faridabad has got an electricity connection A/C No. GF under SDO/Op. Sub-Division, Mathura Road, DHBVN, Faridabad, hence this Forum has jurisdiction to hear the complaint. The complainant has filed the present complaint stating therein that he received a bill of Rs.21023/- for a consumption of 1361 units ( ) in September, When he contacted SDO office at Palla, DHBVN, he was told that sundry charges of Rs.12669/- have been charged in this bill the reason being that SDO ordered a surprise checking for several meters with in colony and his meter was one them. At the time of surprise checking his meter was found working properly and it showed a reading of 4596 units. For a difference of 351 units ( = 351 units), he was charged Rs.4315 ( ). He was to pay Rs.12669/- which he failed to pay and waited for the next bill. Now in Nov., 2014 he received a bill of 1260 units ( ) for Rs. 6514/- & arrear of Rs.12669/- total Rs.19809/-. After receipt of bill, he found that he was being charged twice for the reading of 351 units ( ). The consumer again contacted the Palla office and they realized the mistake but Mr. Surinder dealing clerk told him that they can give him a rebate of Rs.1040/- only instead of Rs.4315/- which he was charged in September, 2014, so total difference = Rs.3275/-. The consumer requested to resolve his case at the earliest and be given a relief as being a senior citizen. The consumer also stated that no action be taken against him for the non-payment of bill till the matter is resolved. The complaint was forwarded to the Nodal Officer for filing the Nigam s version and both the parties were asked to appear before the Forum on 13/02/2015 at Faridabad for hearing of the case. To-day, the proceedings held at Faridabad on 13/02/2015. The consumer as well as CA of the subdivision is present. The respondent SDO submitted reply through his Nodal Officer/CGRF, DHBVN, vide his office memo No dated 09/02/2015, stating therein that bill of the consumer has been corrected and adjusted Rs.4315/- in the consumer account vide SC&AR No. 42/R-48. The consumer further requested that his amount of surcharge of Rs.1935/- may be refunded to him. After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing, this Forum directed the respondent SDO that the amount of surcharge be refunded to him. The Forum disposed off the petition without any cost on either side and case is closed. File be consigned to record. Given under our hands on this day of 13 th February, (R.V.Bari) Member (Satish Malik) Member

30 Case No. DH/CGRF-1009/2015 Date of Institution: Date of Hearing: Date of Order: Before the, DHBVN. Present:- Sh. Daljit Singh, Chairman Sh. R.V.Bari, Member Sh. Satish Malik, Member In the matter of complaint of Sh. Vikram Singh, H.No. 52/14, Bank Colony, Tohana, Distt., Fatehabad regarding billing problem... Complainant/Petitioner V/s 1. Xen/Operation Division, DHBVN, Tohana. 2 SDO/Op. Sub-Division, DHBVN, Tohana. Appearance:- For Complainant: For the Respondent:.Respondents 1.Present. 1.Nodal Officer/CGRF,DHBVN,Hisar 2.Representative of Sub Divn., DHBVN, Tohana.

31 ORDER Sh. Vikram Singh, H.No. 52/14, Bank Colony, Tohana, Distt., Fatehabad has got an electricity connection bearing A/C No. J under SDO/Op. Sub-Division, DHBVN, Tohana, hence this Forum has jurisdiction to hear the complaint. The c omplainant ha s f iled t he pr esent c omplaint s tating therein t hat t he r espondent h as r emoved hi s meter due to non-depositing of energy bill. The consumer stated that due to some circumstances, he could not deposit the energy bill in time and the respondent disconnected his premises in March, The consumer met with XEN, Tohana on 25/03/2013, SDO, City Tohana on 12/11/2014 and Chief Engineer, Vidyut Nagar, Hisar and lodged the complaint, but no action has been taken uptill now. The consumer requested for correction of his bill and reconnect his connection. The complaint was forwarded to the Nodal Officer for filing the Nigam s version and both the parties were asked to appear before the Forum on 06/02/2015 at Hisar for hearing of the case. To-day, t he pr oceedings he ld at H isar on 06/02/2015. The c onsumer as w ell a s r epresentative of respondent SDO is present. T he respondent SDO submitted reply through Nodal Officer/CGRF, DHBVN, vide his office memo No. 101 dated 05/02/2015, stating therein that the supply was disconnected due to non-payment of energy bill during the month of 03/2013. But meter could not be removed due to premises locked. Moreover, connection was released during 2001 and the consumer has paid only Rs.5000/- during these period. It is wrong that meter was removed on 25/03/2013 as the reading w as taken by H ESL s taff upto S eptember, 2014, a s p er r ecord of m eter r eading maintained by H ESL. Moreover, bill of consumer has been set right and delivered at the time of first appellant authority-cum-se/op. Circle, Hisar on dated 15/01/2015 under acknowledgement and MMC along with surcharge have been levied for the period 03/2013 to 09/2014, for making the payment. Where about of meter is well known by the applicant as the area in-charge Sh. Hanuman Singh, JE-F has reported that he has not removed the meter of the consumer. The respondent requested that the Forum may direct the petitioner to make the payment for restoration of power supply after fulfilling the requisite formalities. After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing and discussion held during the course of hearing in the case, the Forum directed the respondent SDO that he should accept the disconnection date as March, 2013 and bill be made upto March, 2013 only and surcharge be charged upto March, 2013 and correct bill be issued to the consumer, so that he may deposit the same immediately. The connection may be restored after getting deposited the amount so arrived at. The Forum disposed off the petition without any cost on either side and case is closed from the Forum. File be consigned to record. Given under our hands on this day of 6 th February, (Daljit Singh) (R.V.Bari) (Satish Malik) Chairman Member Member

32 Case No. DH/CGRF-1010/2015 Date of Institution: Date of Hearing: & Date of Order: Before the, DHBVN. Present:- Sh. R.V. Bari, Member Sh. Satish Malik, Member In t he m atter o f co mplaint o f S h. O m P arkash S aini S /o S h. N et R am S aini, R am Koriawas Road, N arnaul, D istt., M ohindergarh r egarding new d omestic electricity connection... Complainant/Petitioner V/s 1. Xen/Operation Division, DHBVN, Narnaul. 2.SDO/Op. City Sub-Division, DHBVN, Narnaul. Appearance:- For Complainant: For the Respondent:.Respondents 1. Present. 1. Nodal Officer /CGRF,DHBVN,Hisar 2.SDO of City S/Divn., DHBVN, Narnaul.

33 ORDER Sh. Om Parkash Saini S/o Sh. Net Ram Saini, Ram Koriawas Road, Narnaul, Distt., Mohindergarh has applied for new domestic electricity connection application No dated 09/ 01/2015 unde r S DO/Op. C ity S ub-division, D HBVN,Narnaul, hence t his Forum has jurisdiction to hear the complaint. The complainant has filed the present complaint stating therein that he has applied for new domestic electricity co nnection by deposi ting R s.1570/- with t he r espondent t hree m onths ago, but the respondent has taken no action uptill now. The consumer requested for release his new domestic electricity connection. The complaint was forwarded to the Nodal Officer for filing the Nigam s version and bot h the parties were ask ed t o appear before t he For um on 16/ 02/2015 at Narnaul f or hear ing of t he case. During the proceedings held at Narnaul on 16/02/2015, the consumer as well as respondent SDO was present. The SDO could not submit reply and requested for next date. Request granted. After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing and discussion held during the course of hearing in the case, the Forum decides to adjourn the case for next date on the request of respondent SDO. To-day, the proceedings held at Narnaul on 17/03/2015. The consumer as well as respondent SDO is present. The SDO submitted reply through Nodal Officer/CGRF, DHBVN, vide his office memo No.304 dated 16/03/2015, stating therein that the connection of the consumer has been released by his office. The consumer also submitted his written consent that his grievance has been redressed by the SDO and requested for closure of the case. After going through the case file, the information/documents supplied by the appellant as well as by the respondent on the date of hearing and discussion held during the course of hearing in the case, the Forum concludes/decides that grievance of the consumer has been redressed as per reply submitted by the respondent SDO as well as written consent by the consumer. The Forum disposed off the petition without any cost on either side and case is closed from the Forum. File be consigned to record. Given under our hands on this day of 17 th March, (R.V.Bari) Member (Satish Malik) Member

Case No. DH/CGRF-1595/2017 Date of Institution: Date of Hearing: Date of Order: 25/01/2017

Case No. DH/CGRF-1595/2017 Date of Institution: Date of Hearing: Date of Order: 25/01/2017 FORUM FOR REDRESSAL OF CONSUMER GRIEVANCES DAKSHIN HARYANA BIJLI VITRAN NIGAM D-BLOCK, Ground Floor, Vidyut Sadan, Vidyut Nagar, Hisar-125 005 Telephone No. 01662-223081 (website: www.dhbvn.com) (e-mail

More information

Case No. DH/CGRF- 2138/2018 Date of Institution: Date of Hearing: Date of Order:

Case No. DH/CGRF- 2138/2018 Date of Institution: Date of Hearing: Date of Order: FORUM FOR REDRESSAL OF CONSUMER GRIEVANCES DAKSHIN HARYANA BIJLI VITRAN NIGAM D-BLOCK, Ground Floor, Vidyut Sadan, Vidyut Nagar, Hisar-125 005 Telephone No. 01662-223081 (website: www.dhbvn.com) (e-mail

More information

Before the Forum for Redressal of Consumer Grievances, DHBVN.

Before the Forum for Redressal of Consumer Grievances, DHBVN. FORUM FOR REDRESSAL OF CONSUMER GRIEVANCES DAKSHIN HARYANA BIJLI VITRAN NIGAM D-BLOCK, Ground Floor, Vidyut Sadan, Vidyut Nagar, Hisar-125 005 Telephone No. 01662-223081 (website: www.dhbvn.com) (e-mail

More information

BEFORE THE DISTRICT CONSUMER DISPUTES REDRESSAL FORUM, FEROZEPUR. C.C. No. 137 of 2017

BEFORE THE DISTRICT CONSUMER DISPUTES REDRESSAL FORUM, FEROZEPUR. C.C. No. 137 of 2017 BEFORE THE DISTRICT CONSUMER DISPUTES REDRESSAL FORUM, FEROZEPUR. C.C. No. 137 of 2017 Date of Institution:27.02.2017 Date of Decision: 04.01.2018 Tehal Singh aged 63 years son of Lachhman Singh, resident

More information

BEFORE THE CHAIRMAN FORUM FOR REDRESSAL OF CONSUMER GRIEVANCES DAKSHIN HARYANA BIJLI VITRAN NIGAM D-BLOCK,

BEFORE THE CHAIRMAN FORUM FOR REDRESSAL OF CONSUMER GRIEVANCES DAKSHIN HARYANA BIJLI VITRAN NIGAM D-BLOCK, BEFORE THE CHAIRMAN FORUM FOR REDRESSAL OF CONSUMER GRIEVANCES DAKSHIN HARYANA BIJLI VITRAN NIGAM D-BLOCK, Ground Floor, Vidyut Sadan, Vidyut Nagar, Hisar-125 005 (website: www.dhbvn.com) (e-mail ID: cgrfdhbvn@gmail.com)

More information

REGISTERED CONSUMERS GRIEVANCES REDRESSAL FORUM AT KASUMPTI SHIMLA-9 No. CGRF/Comp. No. 1453/1/17/005

REGISTERED CONSUMERS GRIEVANCES REDRESSAL FORUM AT KASUMPTI SHIMLA-9 No. CGRF/Comp. No. 1453/1/17/005 REGISTERED CONSUMERS GRIEVANCES REDRESSAL FORUM AT KASUMPTI SHIMLA-9 No. CGRF/Comp. No. 1453/1/17/005 Dated:- KBM Food Product, V/s. HPSEBL & Others. Complaint No 1453/1/17/005 1. KBM Food Product, 2.

More information

CONSUMER GRIEVANCES REDRESSAL FORUM; NAGPUR (RURAL) COMPLAINT NO. 352/2011

CONSUMER GRIEVANCES REDRESSAL FORUM; NAGPUR (RURAL) COMPLAINT NO. 352/2011 CONSUMER GRIEVANCES REDRESSAL FORUM; NAGPUR (RURAL) COMPLAINT NO. 352/2011 Shri Saibaba Mahila Bachat Gat, C/o Smt. Shraddha Raman Agrawal, Bachpai Chouk, Near Kundan Kuti, Murri Road, Gondiya-441601.,,VS....

More information

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH. Smt.Romila Dubey, Chairperson Shri Gurinder Jit Singh, Member

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH. Smt.Romila Dubey, Chairperson Shri Gurinder Jit Singh, Member PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO. 220-221, SECTOR 34-A, CHANDIGARH Petition No.70 of 2014 Date of Order: 22.04.2015 Present: Smt.Romila Dubey, Chairperson Shri Gurinder Jit Singh,

More information

Before the Appellate Board National Electric Power Regulatory Authority (NEPRA) Islamic Republic of Pakistan

Before the Appellate Board National Electric Power Regulatory Authority (NEPRA) Islamic Republic of Pakistan Before the Appellate Board National Electric Power Regulatory Authority (NEPRA) Islamic Republic of Pakistan No. NEPRA/AB/Appeal-170/POI-2016/89/..le/ NEPRA Office, Atta Turk Avenue (East), G5/1, Islamabad

More information

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW. Notice dated U/s130 of Electricity Act2003.

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW. Notice dated U/s130 of Electricity Act2003. UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW In the matter of : Notice dated 12.5.2007 U/s130 of Electricity Act2003. AND In the matter of : 1. Managing Director, U.P.Power Corporation Limited,

More information

Memo No. Ch- 43/GM/Comml./ R-16/139/04 Dated:

Memo No. Ch- 43/GM/Comml./ R-16/139/04 Dated: DAKSHIN HARYANA BIJLI VITRAN NIGAM Sales Circular No. D-43/2007 From GM/Commercial, DHBVN, Hisar. To All CGMs/GMs/DGMs/AGMs (OP), FM- I/C Sub offices in DHBVNL. Memo No. Ch- 43/GM/Comml./ R-16/139/04 Dated:

More information

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO. 220-221, SECTOR 34-A, CHANDIGARH Petition No. 58 of 2017 Date of order: 11.06.2018 Present: Ms. Kusumjit Sidhu, Chairperon Sh. S.S. Sarna, Member

More information

SOUTHERN ELECTRICITY SUPPLY COMPANY OF ORISSA LIMITED

SOUTHERN ELECTRICITY SUPPLY COMPANY OF ORISSA LIMITED SOUTHERN ELECTRICITY SUPPLY COMPANY OF ORISSA LIMITED COMPLAINT HANDLING PROCEDURE OF DISTRIBUTION LICENSEE (APPROVED BY OERC) 1. This "Complaint Handling Procedure relating to Distribution Activity (Complaint

More information

Sri. Alex Soharab. V.F, M/s. Southern Engineering Corporation, V/830-A, Development Area, Edayar, Muppathadom , Aluva.

Sri. Alex Soharab. V.F, M/s. Southern Engineering Corporation, V/830-A, Development Area, Edayar, Muppathadom , Aluva. 1 CONSUMER GRIEVANCE REDRESSAL FORUM CENTRAL REGION (Formed under Section 42(5) of the Electricity Act 2003) 220 kv Substation Compound, HMTColony P.O. Kalamasery, Pin 683 503 Phone No. 0484-2556500 Website

More information

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SUIT FOR INJUNCTION Date of Judgment: RSA No.55/2009 & CM No.

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SUIT FOR INJUNCTION Date of Judgment: RSA No.55/2009 & CM No. IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SUIT FOR INJUNCTION Date of Judgment: 06.04.2011 RSA No.55/2009 & CM No.6268/2009 NEW DELHI MUNICIPAL COUNCIL Through: Mr.Arjun Pant, Advocate...Appellant

More information

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ELECTRICITY ACT, 2003 Date of decision: 19th April, 2011 W.P.(C) 8647/2007

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ELECTRICITY ACT, 2003 Date of decision: 19th April, 2011 W.P.(C) 8647/2007 IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ELECTRICITY ACT, 2003 Date of decision: 19th April, 2011 W.P.(C) 8647/2007 JINGLE BELL AMUSEMENT PARK P. LTD. Through: Mr. V.K. Goel, Advocate... Petitioner

More information

Case No. 16 of 2007 Date: 19/12/2007. In the matter of Shri Sachin P. Sakpal V/S

Case No. 16 of 2007 Date: 19/12/2007. In the matter of Shri Sachin P. Sakpal V/S Before Maharashtra State Electricity Distribution Co. Limited Consumer Grievances Redressal Forum, Pune Zone, 925,Kasabapeth Building, IInd flr. Pune-11 Case No. 16 of 2007 Date: 19/12/2007 In the matter

More information

HARYANA ELECTRICITY REGULATORY COMMISSION. Notification. The 10th August, Electricity Supply Code. (1) recovery of electricity charges,

HARYANA ELECTRICITY REGULATORY COMMISSION. Notification. The 10th August, Electricity Supply Code. (1) recovery of electricity charges, HARYANA ELECTRICITY REGULATORY COMMISSION Regulation No: HERC/ 05 /2004 Notification The 10th August, 2004 Electricity Supply Code Where as the Electricity Act, 2003 provides that the Commission shall

More information

Case No. 99 of Smt. Chandra Iyengar, Chairperson Shri Vijay. L. Sonavane, Member Shri. Azeez M. Khan, Member

Case No. 99 of Smt. Chandra Iyengar, Chairperson Shri Vijay. L. Sonavane, Member Shri. Azeez M. Khan, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Email: mercindia@merc.gov.in Website: www.mercindia.org.in / www.merc.gov.in

More information

* HIGH COURT OF DELHI : NEW DELHI. 1. Sh. Hari Prakash Sharma (deceased) S/o Late Shri Kehar Singh Sharma, Through Legal Heirs.

* HIGH COURT OF DELHI : NEW DELHI. 1. Sh. Hari Prakash Sharma (deceased) S/o Late Shri Kehar Singh Sharma, Through Legal Heirs. * HIGH COURT OF DELHI : NEW DELHI CM (M) Nos. 1201/2010 & CM No. 16773/2010 % Judgment reserved on: 17 th September, 2010 Judgment delivered on: 09 th November, 2010 1. Sh. Hari Prakash Sharma (deceased)

More information

ORDER (passed on 02/07/2015)

ORDER (passed on 02/07/2015) 5(A Govt. of Maharashtra Undertaking) CIN : U40109MH2005SGC153645 PHONE NO. : 25664314/25664316 Consumer Grievance Redressal Forum FAX NO. 26470953 Vidyut Bhavan, Gr. Floor, Email: cgrfbhandupz@mahadiscom.in

More information

4. PROCEDURE FOR RELEASE OF NEW CONNECTION AND MODIFICATION IN EXISTING CONNECTION

4. PROCEDURE FOR RELEASE OF NEW CONNECTION AND MODIFICATION IN EXISTING CONNECTION 4. PROCEDURE FOR RELEASE OF NEW CONNECTION AND MODIFICATION IN EXISTING CONNECTION Licensee s obligation to supply 4.1 The licensee shall, on an application by the owner or occupier of any premises located

More information

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur Case No.

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur Case No. Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur Case No. CGRF(NUZ)/71/2014 Applicant Non applicant Quorum Present : M/s. Sanvijay Rolling

More information

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION PUNJAB STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION The 4th October, 2013 No. PSERC/Secy/Regu. 88 Punjab State Electricity Regulatory Commission hereby approves the guidelines for handling of consumer

More information

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003)

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003) BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING (Constituted under section 42(5) of Electricity Act 2003) Ground Floor, Multistoried Annex Building, BEST s Colaba Depot Colaba, Mumbai

More information

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003)

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003) BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING (Constituted under section 42(5) of Electricity Act 2003) Ground Floor, Multistoried Annex Building, BEST s Colaba Depot Colaba, Mumbai

More information

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) WP(C) No. 2882/2005 M/s. Ladi Steel Industries Pvt. Limited, a private limited company duly incorporated under

More information

M/s Kotak Mahindra Bank Ltd. Vs. Sewa Singh Dhiman. Sh. Mukesh Singh, AR of the DH in person. Sh. Varinder Singh, advocate for JD

M/s Kotak Mahindra Bank Ltd. Vs. Sewa Singh Dhiman. Sh. Mukesh Singh, AR of the DH in person. Sh. Varinder Singh, advocate for JD M/s Kotak Mahindra Bank Ltd. Vs. Sewa Singh Dhiman Sh. Mukesh Singh, AR of the DH in person Sh. Varinder Singh, advocate for JD been settled. It is submitted by both the parties that the matter has On

More information

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003)

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003) BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING (Constituted under section 42(5) of Electricity Act 2003) Ground Floor, Multistoried Annex Building, BEST s Colaba Depot Colaba, Mumbai

More information

Case No. CGRF(NZ)/91/2018

Case No. CGRF(NZ)/91/2018 Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redresses Forum Nagpur Zone, Nagpur Case No. CGRF(NZ)/91/2018 Applicant Non applicant : Shri Ramesh Krishnarao Pawar, Usuer Shri

More information

* HIGH COURT OF DELHI : NEW DELHI. Judgment delivered on: 22 nd January, 2010

* HIGH COURT OF DELHI : NEW DELHI. Judgment delivered on: 22 nd January, 2010 * HIGH COURT OF DELHI : NEW DELHI FAO. No.42/2008 & CM No. 1368/08 % Judgment reserved on: 10 th November, 2009 1. S. Gurbaksh Singh S/o. S. Tej Singh B-45, Greater Kailash I New Delhi 110048 2. S. Baljit

More information

CASE No. 156 of In the matter of

CASE No. 156 of In the matter of Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

M/s. Heer Enterprises - Applicant

M/s. Heer Enterprises - Applicant (A Govt. of Maharashtra Undertaking) CIN : U40109MH2005SGC153645 PHONE NO. : 25664314/25664316 Consumer Grievance Redressal Forum FAX NO. 26470953 Vidyut Bhavan, Gr. Floor, Email: cgrfbhandupz@mahadiscom.in

More information

W.P. (C) No of 2005

W.P. (C) No of 2005 -1- W.P. (C) No. 1992 of 2005 WITH W.P. (C) No. 3105 of 2007 [In the matter of an application under Article 226 of the Constitution of India] By Court: Jharkhand State Electricity Board through Electrical

More information

Case No. 2 of Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member

Case No. 2 of Shri V. P. Raja, Chairman Shri Vijay L. Sonavane, Member Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in

More information

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL Nos OF Surat Singh (Dead).Appellant(s) VERSUS

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL Nos OF Surat Singh (Dead).Appellant(s) VERSUS IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION REPORTABLE CIVIL APPEAL Nos.9118-9119 OF 2010 Surat Singh (Dead).Appellant(s) VERSUS Siri Bhagwan & Ors. Respondent(s) J U D G M E N T Abhay Manohar

More information

THE TAMIL NADU ELECTRICITY REGULATORY COMMISSION

THE TAMIL NADU ELECTRICITY REGULATORY COMMISSION THE TAMIL NADU ELECTRICITY REGULATORY COMMISSION (Constituted under Section 82(1) of the Electricity Act, 2003) (Central Act 36 of 2003) PRESENT : Thiru S. Kabilan Thiru B. Jeyaraman - Chairman - Member

More information

BEFORE THE KERALA STATE ELECTRICITY REGULATORY COMMISSION. PETITION No. CP 02/17

BEFORE THE KERALA STATE ELECTRICITY REGULATORY COMMISSION. PETITION No. CP 02/17 BEFORE THE KERALA STATE ELECTRICITY REGULATORY COMMISSION PETITION No. CP 02/17 In the matter of : Non implementation of the order dated 29.05.2017 in P/005/2016 of Kerala State Electricity Ombudsman.

More information

BEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA

BEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA BEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA Petition No. 82 of 2012 M/S Himachal Chamber of Commerce and Industry C/O Goel Diesel Service, Bhupper, Poanta Sahib, Distt. Sirmour

More information

The Orissa Electricity (Duty) Act, 1961.

The Orissa Electricity (Duty) Act, 1961. The Orissa Electricity (Duty) Act, 1961. An Act to levy a duty on the consumption of electrical energy on the State of Orissa. Be it enacted by the legislature of the State of Orissa in the Twelfth year

More information

ORDER Dated: 11 th August, 2004

ORDER Dated: 11 th August, 2004 Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai 400 005. Tel. 22163964 / 22163965, Fax No. 22163976 E-mail mercindia@mercindia.com

More information

BEFORE THE FORUM FOR REDRESSAL OF CONSUMER GRIEVANCES IN SOUTHERN POWER DISTRIBUTION COMPANY OF A.P LIMITED TIRUPATI

BEFORE THE FORUM FOR REDRESSAL OF CONSUMER GRIEVANCES IN SOUTHERN POWER DISTRIBUTION COMPANY OF A.P LIMITED TIRUPATI BEFORE THE FORUM FOR REDRESSAL OF CONSUMER GRIEVANCES IN SOUTHERN POWER DISTRIBUTION COMPANY OF A.P LIMITED TIRUPATI On this the ----------- day of July 2014 In C.G.No: 201/2013-14/ Kadapa Circle Present

More information

Date of Admission : Date of Decision :

Date of Admission : Date of Decision : 1 Case No. 668/2018 BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM AURANGABAD ZONE, AURANGABAD. Case No. CGRF/AZ/AUR/R/668/2018/08 Registration No. 2018020042 Date of Admission : 14.02.2018 Date of Decision

More information

Supply shall generally be given at the following voltages on the basis of contracted load:

Supply shall generally be given at the following voltages on the basis of contracted load: Classification of Supply- Supply shall generally be given at the following voltages on the basis of contracted load: Consumers availing supply at lower voltage than above classification will be required

More information

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003)

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003) BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING (Constituted under section 42(5) of Electricity Act 2003) Ground Floor, Multistoried Annex Building, BEST s Colaba Depot Colaba, Mumbai

More information

Case No.06/2016 Date of Grievance : Date of Order :

Case No.06/2016 Date of Grievance : Date of Order : 1 06/2016 CONSUMER GRIEVANCE REDRESSAL FORUM M.S.E.D.C.L., PUNE ZONE, PUNE Case No.06/2016 Date of Grievance : 15.03.2016 Date of Order : 21.04.2016 In the matter of recovery of arrears in the event of

More information

Suit No. : 570/15 13/01/2016. Counsel for the plaintiff. Counsel for the defendant.

Suit No. : 570/15 13/01/2016. Counsel for the plaintiff. Counsel for the defendant. Suit No. : 570/15 Counsel for the plaintiff. Counsel for the defendant. Vakalatnama filed by the counsel for the defendant alongwith WS. Copy given. Now put up for replication / documents / admission denial

More information

ORDER (Date of hearing 24 th November, 2012) (Date of order 10 th December, 2012)

ORDER (Date of hearing 24 th November, 2012) (Date of order 10 th December, 2012) ORDER (Date of hearing 24 th November, 2012) (Date of order 10 th December, 2012) M/s Birla Corporation Ltd. - Petitioner Unit Satna Cement Works, PO Birla Vikas, Satna 485005 (MP). V/s MP Poorv Kshetra

More information

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003)

BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING. (Constituted under section 42(5) of Electricity Act 2003) BEFORE THE CONSUMER GRIEVANCE REDRESSAL FORUM B.E.S. & T. UNDERTAKING (Constituted under section 42(5) of Electricity Act 2003) Ground Floor, Multistoried Annex Building, BEST s Colaba Depot Colaba, Mumbai

More information

CONSUMER GRIEVANCES REDRESSAL FORUM; MSEDCL NAGPUR (RURAL) ZONE NAGPUR COMPLAINT NO.7 /2015

CONSUMER GRIEVANCES REDRESSAL FORUM; MSEDCL NAGPUR (RURAL) ZONE NAGPUR COMPLAINT NO.7 /2015 CONSUMER GRIEVANCES REDRESSAL FORUM; MSEDCL NAGPUR (RURAL) ZONE NAGPUR COMPLAINT NO.7 /2015 Shri Nilesh M. Kolhe At.Aajanti Po.Tq.Hinganghat District - Wardha.,,VS.. Complainant 1. Executive Engineer,

More information

Brihan Mumbai Electric Supply & Transport Undertaking (Of the Municipal Corporation of Greater Mumbai)

Brihan Mumbai Electric Supply & Transport Undertaking (Of the Municipal Corporation of Greater Mumbai) Brihan Mumbai Electric Supply & Transport Undertaking (Of the Municipal Corporation of Greater Mumbai) "Procedures for Redressal Of Consumer Grievences" As per Section 3.3 of Maharashtra ElectricIty Regulatory

More information

$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI 9.

$~ * IN THE HIGH COURT OF DELHI AT NEW DELHI 9. $~ * IN THE HIGH COURT OF DELHI AT NEW DELHI 9. + W.P.(C) 8568/2009 LALIT GULATI... Petitioner Through : Mr. Rajat Wadhwa, Advocate. versus GOVT. OF NCT OF DELHI... Respondent Through : Ms. Zubeda Begum

More information

8/01/2018, 8/2/2018 Date of Order: 16/02/ K.D.Bansal, Member Technical-cum-Chairman 2 Manu Bishnoi, Independent Member

8/01/2018, 8/2/2018 Date of Order: 16/02/ K.D.Bansal, Member Technical-cum-Chairman 2 Manu Bishnoi, Independent Member FORUM FOR REDRESSAL OF CONSUMER GRIEVANCES DAKSHIN HARYANA BIJLI VITRAN NIGAM D-BLOCK, Ground Floor, Vidyut Sadan, Vidyut Nagar, Hisar-125 005 Telephone No. 01662-223081 (website: www.dhbvn.com) (e-mail

More information

CONSUMER GRIEVANCES REDRESSAL FORUM-I OF SOUTHERN POWER DISTRIBUTION COMPANY OF TELANGANA LIMITED

CONSUMER GRIEVANCES REDRESSAL FORUM-I OF SOUTHERN POWER DISTRIBUTION COMPANY OF TELANGANA LIMITED CONSUMER GRIEVANCES REDRESSAL FORUM-I OF SOUTHERN POWER DISTRIBUTION COMPANY OF TELANGANA LIMITED 01.08.2018 Forum for Redressal of Consumer Grievances TSSPDCL has been established as per Sub-Section (5)

More information

PROCEDURES AND GUIDELINES FOR APPLYING SERVICE CONNECTION AT 11 KV / 33 KV HIGH TENSION (HT) & 132 KV EXTRA HIGH TENSION (EHT)

PROCEDURES AND GUIDELINES FOR APPLYING SERVICE CONNECTION AT 11 KV / 33 KV HIGH TENSION (HT) & 132 KV EXTRA HIGH TENSION (EHT) PROCEDURES AND GUIDELINES FOR APPLYING SERVICE CONNECTION AT 11 KV / 33 KV HIGH TENSION (HT) & 132 KV EXTRA HIGH TENSION (EHT) Note. The procedures and guidelines mentioned herein are in accordance with

More information

* HIGH COURT OF DELHI : NEW DELHI. CM (M) No. 1024/2010 & CM No /2010 (stay)

* HIGH COURT OF DELHI : NEW DELHI. CM (M) No. 1024/2010 & CM No /2010 (stay) * HIGH COURT OF DELHI : NEW DELHI CM (M) No. 1024/2010 & CM No. 14260/2010 (stay) % Judgment reserved on: 10 th August, 2010 Judgment delivered on: 11 th August, 2010 Smt. Kamla Bajaj W/o Sh. Satish Bajaj

More information

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION Non-Reportable IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL No. 7335 of 2008 CHIEF ADMINISTRATOR, H.U.D.A. & ANR. SHAKUNTLA DEVI Versus J U D G M E N T... Appellant(s).Respondent(s)

More information

NEPRA Office Building, G-511, Attaturk Avenue (East), Islamabad "

NEPRA Office Building, G-511, Attaturk Avenue (East), Islamabad 0" 1 National Electric Power Regulatory Authority Islamic Republic of Pakistan wat **-414' NEPRA Office Building, G-511, Attaturk Avenue (East), Islamabad "-- - 06 Phone: 051-9206500, Fax: 051-2600026

More information

(Li. Before the Appellate Board National Electric Power Regulatory Authority (NEPRA) Islamic Republic of Pakistan

(Li. Before the Appellate Board National Electric Power Regulatory Authority (NEPRA) Islamic Republic of Pakistan Before the Appellate Board National Electric Power Regulatory Authority (NEPRA) Islamic Republic of Pakistan NEPRA Office Ana Turk Avenue (East), G5/ 1, Islamabad TeL No.+92 051 2015200 Fax No. +92 051

More information

IN THE MATTER OF GRIEVANCE NO. K/DOS/001/482 OF OF MRS.

IN THE MATTER OF GRIEVANCE NO. K/DOS/001/482 OF OF MRS. Consumer Grievance Redressal Forum, Kalyan Zone Behind Tejashree", Jahangir Meherwanji Road, Kalyan (West) 421301 Ph 2210707, Fax 2210707, E-mail : cgrfkalyan@mahadiscom.in IN THE MATTER OF GRIEVANCE NO.

More information

JANTA VIDYA MANDIR GANPAT RAI RASIWASIA COLLEGE SOCIETY. Byelaws of the Society

JANTA VIDYA MANDIR GANPAT RAI RASIWASIA COLLEGE SOCIETY. Byelaws of the Society JANTA VIDYA MANDIR GANPAT RAI RASIWASIA COLLEGE SOCIETY Ram Krishan Gupta Marg, CHARKHI DADRI, DISTT. BHIWANI (HR.) Byelaws of the Society Name of the Society: JANTA VIDY MANDIR GANPAT RAI RASIAWASIA COLLEGE

More information

Case No. 111 of Shri. V.P. Raja, Chairman Shri. Vijay L. Sonavane, Member. Maharashtra State Electricity Distribution Co.

Case No. 111 of Shri. V.P. Raja, Chairman Shri. Vijay L. Sonavane, Member. Maharashtra State Electricity Distribution Co. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in

More information

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ELECTRICITY MATTER. Date of Decision : January 16, 2007 W.P.(C) 344/2007

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ELECTRICITY MATTER. Date of Decision : January 16, 2007 W.P.(C) 344/2007 IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : ELECTRICITY MATTER Date of Decision : January 16, 2007 W.P.(C) 344/2007 YOGESH JAIN... Petitioner Through Mr. Laliet Kumar, Advocate. versus BSES YAMUNA

More information

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur. Case No.

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur. Case No. Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur Case No. CGRF(NUZ)/33/2012 Applicant : Shri Gangadhar Santosh Raut, At Post Kharbadi,

More information

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 7843 OF 2009 CHAIRMAN, BOARD OF TRUSTEE, APPELLANT(s) SRI RAM MANDIR JAGTIAL KARIMNAGAR DISTRICT, A.P VERSUS S. RAJYALAXMI

More information

Before the Appellate Board National Electric Power Regulatory Authority (NEPRA) Islamic Republic of Pakistan

Before the Appellate Board National Electric Power Regulatory Authority (NEPRA) Islamic Republic of Pakistan Before the Appellate Board National Electric Power Regulatory Authority (NEPRA) Islamic Republic of Pakistan NEPRA Office, Atta Turk Avenue (East), G5/1, Islamabad Tel. No.+92 051 2013200 Fax No. +92 051

More information

IJRFM Volume 2, Issue 5 (May 2012) (ISSN ) WORKING OF REDRESSAL AGENCIES ABSTRACT

IJRFM Volume 2, Issue 5 (May 2012) (ISSN ) WORKING OF REDRESSAL AGENCIES ABSTRACT WORKING OF REDRESSAL AGENCIES Dr. Prof. Hawa Singh* Monika Singh** ABSTRACT India is a vast country where a majority of consumers are poor, helpless & disorganised. It is now realised that every consumer

More information

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur. Case No. CGRF(NUZ)/040/2009

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur. Case No. CGRF(NUZ)/040/2009 Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur Case No. CGRF(NUZ)/040/2009 Applicant : Shri Pratap Jaykisan Kanjwani At, 116, Chikhali,

More information

Case No.25/2016 Date of Grievance : Date of Order :

Case No.25/2016 Date of Grievance : Date of Order : 1 25/2016 CONSUMER GRIEVANCE REDRESSAL FORUM M.S.E.D.C.L., PUNE ZONE, PUNE Case No.25/2016 Date of Grievance : 19.07.2016 Date of Order : 14.09.2016 In the matter of recovery of arrears in the event of

More information

Case No. 20 of 2007 Date: 11/01/2008. In the matter of Mr. Sudhir.V.Batra

Case No. 20 of 2007 Date: 11/01/2008. In the matter of Mr. Sudhir.V.Batra Before Maharashtra State Electricity Distribution Co. Limited Consumer Grievances Redressal Forum, Pune Zone, 925,Kasabapeth Building, IInd flr. Pune-11 Case No. 20 of 2007 Date: 11/01/2008 In the matter

More information

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : CODE OF CRIMINAL PROCEDURE. Reserved on : Date of decision :

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : CODE OF CRIMINAL PROCEDURE. Reserved on : Date of decision : IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : CODE OF CRIMINAL PROCEDURE Reserved on : 05.02.2009 Date of decision : 10.02.2009 Crl.M.C. 2296/2008 BSES RAJDHANI POWER LTD. and ORS. Through: Petitioners

More information

STATE CONSUMER DISPUTES REDRESSAL COMMISSION, MAHARASHTRA, MUMBAI. Complaint No.CC/13/172

STATE CONSUMER DISPUTES REDRESSAL COMMISSION, MAHARASHTRA, MUMBAI. Complaint No.CC/13/172 CC/13/172 1/15 STATE CONSUMER DISPUTES REDRESSAL COMMISSION, MAHARASHTRA, MUMBAI Complaint No.CC/13/172 Galaxy Heights Co-operative Housing Society Ltd., Plot No.56, Sector 20-B, Airoli, Navi Mumbai 400

More information

SURAJ BHAN THR GPA HOLDER & ORS... Appellants Through Mr. Naresh Kaushik, Mr. Vardhman Kaushik, Advocates

SURAJ BHAN THR GPA HOLDER & ORS... Appellants Through Mr. Naresh Kaushik, Mr. Vardhman Kaushik, Advocates IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : LAND ACQUISITION ACT, 1894 DATE OF DECISION : 7th February, 2014 LA.APP. 632/2011 & CM No. 17689/2013 (for stay) SURAJ BHAN THR GPA HOLDER & ORS.... Appellants

More information

Through Mr. Atul Nigam, Mr. Amit Tiwari, Advs. versus

Through Mr. Atul Nigam, Mr. Amit Tiwari, Advs. versus IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : CODE OF CIVIL PROCEDURE OA 92/2013 & IA Nos. 132/2013, 18787/2012, 218/2013, 1581/2013 in CS(OS) 3081/2012 Reserved on: 29th October, 2013 Decided on:

More information

CONSUMER GRIEVANCE REDRESSAL FORUM, AMRAVATI ZONE, AKOLA.

CONSUMER GRIEVANCE REDRESSAL FORUM, AMRAVATI ZONE, AKOLA. CONSUMER GRIEVANCE REDRESSAL FORUM, AMRAVATI ZONE, AKOLA. Vidyut Bhavan, Ratanlal Plots, Akola: 444 001 Tel.No.2434476 February 11, 2014. Complaint No.107/2013 In the matter of grievance in respect of

More information

Before the Appellate Board National Electric Power Regulatory Authority (NEPRA) Islamic Republic of Pakistan

Before the Appellate Board National Electric Power Regulatory Authority (NEPRA) Islamic Republic of Pakistan Before the Appellate Board National Electric Power Regulatory Authority (NEPRA) Islamic Republic of Pakistan NEPRA Office, Atta Turk Avenue (East), G5/1, Islamabad Tel. No.+92 051 2013200 Fax No. +92 051

More information

Appeal, Review and Settlement of Cases

Appeal, Review and Settlement of Cases 1. Introduction: Chapter 31 Appeal, Review and Settlement of Cases 1.1 Like any other taxation statue, the Customs Act contains detailed provisions for judicial review, for resolution of disputes, by way

More information

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL NO OF 2013 [Arising out of SLP (C) No.

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION. CIVIL APPEAL NO OF 2013 [Arising out of SLP (C) No. 1 REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO. 6150 OF 2013 [Arising out of SLP (C) No. 5230 of 2013] D.H.B.V.N.L. Vidyut Nagar, Hisar & Others.. Appellants Versus

More information

$~28 * IN THE HIGH COURT OF DELHI AT NEW DELHI Date of decision: 15 th February, CS(OS) 3324/2014

$~28 * IN THE HIGH COURT OF DELHI AT NEW DELHI Date of decision: 15 th February, CS(OS) 3324/2014 $~28 * IN THE HIGH COURT OF DELHI AT NEW DELHI Date of decision: 15 th February, 2019. + CS(OS) 3324/2014 DEEPA BHURE & ORS... Plaintiffs Through: Mr. Hemant Mehla, Advocate (9810270050) and petitioner

More information

By:- Chief Electoral Officer, Haryana 3 rd Floor, 30 Bays Building, Sector- 17, Chandigarh

By:- Chief Electoral Officer, Haryana 3 rd Floor, 30 Bays Building, Sector- 17, Chandigarh Information Handbook under Right to Information Act 2005 By:- Chief Electoral Officer, Haryana 3 rd Floor, 30 Bays Building, Sector- 17, Chandigarh F:\Right to Information Act-2005-Book-YEAR-2011.doc Right

More information

NORTHERN POWER DISTRIBUTION COMPANY OF A.P. LIMITED WARANGAL

NORTHERN POWER DISTRIBUTION COMPANY OF A.P. LIMITED WARANGAL NORTHERN POWER DISTRIBUTION COMPANY OF A.P. LIMITED WARANGAL FORUM FOR REDRESSAL OF CONSUMER GRIEVANCES Forum for Redressal of Consumer Grievances APNPDCL has been established as per Sub - Section (5)

More information

Grievances No.K/DOS/015/874 of and No. K/DOS/016/875 of

Grievances No.K/DOS/015/874 of and No. K/DOS/016/875 of Consumer Grievance Redressal Forum, Kalyan Zone Behind Tejashree", Jahangir Meherwanji Road, Kalyan (West) 421301 Ph 2210707, Fax 2210707, E-mail : cgrfkalyan@mahadiscom.in Date of Grievance : 08/10/2013

More information

National Electric Power Regulatory Authority Islamic Republic of Pakistan

National Electric Power Regulatory Authority Islamic Republic of Pakistan a MSc National Electric Power Regulatory Authority Islamic Republic of Pakistan '' 0. s-. -. ss Registrar NEPRA Tower, Attaturk Avenue (East), G-5/1, Islamabad Ph: +92-51-9206500, Fax: +92-51-2600026 Web:

More information

1. The Chief Engineer (OP).

1. The Chief Engineer (OP). "SlVI iolllzv foe tht kjtfitofstltandnltton: HIMACHAL '''911&1 'TY BOARD LIMITED No.: HPSEB/CE (Comm.)lElecty.Act.2003 (NottficaHons)l2011-12.\/ Dated: t ~,"3 ~.< ol2.} To..to~Gl-2.\l"'o - -~--~- 1. The

More information

BEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA. The H.P. State Electricity Board, Vidyut Bhawan, Shimla-4

BEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA. The H.P. State Electricity Board, Vidyut Bhawan, Shimla-4 BEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA In the matter of:- The H.P. State Electricity Board, Vidyut Bhawan, Shimla-4 V/s M/S Padmavati Steels Ltd; Vill Johron, Trilokpur Road,

More information

West Bengal State Electricity Distribution Company Limited

West Bengal State Electricity Distribution Company Limited West Bengal State Electricity Distribution Company Limited C:\ (SOP) regulation 2010.docAnnexure A1 Application form to be used for transfer of service/meter in case of change of ownership or occupancy

More information

Consumer Protection Digest on Electricity Services

Consumer Protection Digest on Electricity Services 1 Consumer Protection Digest on Electricity Services Act of God - Frequent stoppage of electric supply due to Force majeur - No deficiency in service on the part of Electricity Board established - 1997(1)

More information

Karnataka Power... vs Ashok Iron Works Pvt. Ltd on 9 February, Karnataka Power... vs Ashok Iron Works Pvt. Ltd on 9 February, 2009

Karnataka Power... vs Ashok Iron Works Pvt. Ltd on 9 February, Karnataka Power... vs Ashok Iron Works Pvt. Ltd on 9 February, 2009 Supreme Court of India Karnataka Power... vs Ashok Iron Works Pvt. Ltd on 9 February, 2009 Bench: Markandey Katju, R.M. Lodha 1 Reportable IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL

More information

GOVT. OF NCT OF DELHI OFFICE OF THE COMMISIONER OF INDUSTRIES 419, UDYOGSADAN, FIE, PATPARGANJ,DELHI -92

GOVT. OF NCT OF DELHI OFFICE OF THE COMMISIONER OF INDUSTRIES 419, UDYOGSADAN, FIE, PATPARGANJ,DELHI -92 GOVT. OF NCT OF DELHI OFFICE OF THE COMMISIONER OF INDUSTRIES 419, UDYOGSADAN, FIE, PATPARGANJ,DELHI -92 No. DCI/ILMAC/CI/2011/ I-t ~ 7- 'L - J'D. Dated: 81 ft I J Minutes of the meetina of the Industrial

More information

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO. 220-221, SECTOR 34-A, CHANDIGARH Petition No.49 of 2013 Date of Order: 18.11.2014 In the matter of: Petition for proposal regarding inclusion of availability

More information

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI FIRST APPEAL NO. 535 OF 2015

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI FIRST APPEAL NO. 535 OF 2015 NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI FIRST APPEAL NO. 535 OF 2015 (Against the Order dated 27/05/2015 in Complaint No. 151/1998 of the State Commission Uttar Pradesh) 1. PAWAN KUMARI

More information

CONSUMER GRIEVANCE REDRESSAl FORUM,

CONSUMER GRIEVANCE REDRESSAl FORUM, CONSUMER GRIEVANCE REDRESSAl FORUM, AMRAVATI ZONE, AMRAVATI. 11 Vidyut Bhavan" Shivaji Nagar, Amravati, PIN :- 444603 Tel No 0721.2551158 Dt. 15/12/2016 Complaint No.15/2016 In the matter of grievance

More information

$~9. * IN THE HIGH COURT OF DELHI AT NEW DELHI. % RSA 228/2015 and C.M. No.12883/2015. versus CORAM: HON'BLE MR. JUSTICE VIPIN SANGHI

$~9. * IN THE HIGH COURT OF DELHI AT NEW DELHI. % RSA 228/2015 and C.M. No.12883/2015. versus CORAM: HON'BLE MR. JUSTICE VIPIN SANGHI $~9. * IN THE HIGH COURT OF DELHI AT NEW DELHI + Date of Decision: 03.09.2015 % RSA 228/2015 and C.M. No.12883/2015 SHRI BABU LAL Through: Mr. V. Shukla, Advocate.... Appellant versus DELHI DEVELOPMENT

More information

IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION WRIT PETITION NO OF 2016

IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION WRIT PETITION NO OF 2016 ssk 1/11 WP 8075/16-8/8/16 IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION WRIT PETITION NO. 8075 OF 2016 M/s. Gada Properties Pvt. Ltd. Petitioner vs. The Municipal Corporation

More information

AGREEMENT FOR SUPPLY OF LT ENERGY

AGREEMENT FOR SUPPLY OF LT ENERGY AGREEMENT FOR SUPPLY OF LT ENERGY This agreement made on the.. day of.., 200 between the Development Commissioner, Cochin Special Economic Zone, Kakkanad for and on behalf of Cochin Special Economic Zone

More information

BEFORE THE NATIONAL GREEN TRIBUNAL CENTRAL ZONAL BENCH BHOPAL. Original Application No. 16/2014 (CZ) (THC)

BEFORE THE NATIONAL GREEN TRIBUNAL CENTRAL ZONAL BENCH BHOPAL. Original Application No. 16/2014 (CZ) (THC) CORAM: BEFORE THE NATIONAL GREEN TRIBUNAL CENTRAL ZONAL BENCH BHOPAL (CZ) (THC) Hon ble Mr. Justice Dalip Singh (Judicial Member) Hon ble Mr. P.S. Rao (Expert Member) BETWEEN : - 1. Ram Singh S/o Shri

More information

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM; NAGALAND; MIZORAM AND ARUNACHAL PRADESH)

IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM; NAGALAND; MIZORAM AND ARUNACHAL PRADESH) Page 1 IN THE GAUHATI HIGH COURT (THE HIGH COURT OF ASSAM; NAGALAND; MIZORAM AND ARUNACHAL PRADESH) Writ Petition (C) No. 1961 of 2010 Smt. Padma Rani Mudai Hazarika - Versus - - Petitioner Union of India

More information

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SUIT FOR SPECIFIC PERFORMANCE

IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SUIT FOR SPECIFIC PERFORMANCE IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : SUIT FOR SPECIFIC PERFORMANCE LPA 776 OF 2012, CMs No. 19869/2012 (stay), 19870/2012 (additional documents), 19871/2012 (delay) Judgment Delivered on 29.11.2012

More information

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur. Case No.

Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur. Case No. Maharashtra State Electricity Distribution Co. Ltd. s Consumer Grievance Redressal Forum Nagpur Urban Zone, Nagpur Case No. CGRF(NUZ)/52/2012 Applicant : M/s. MPM Pvt.Ltd, M-22, MIDC, Hingna Road, Nagpur

More information

BEFORE THE CONSUMER GRIEVANCES REDRESSAL FORUM O R D E R

BEFORE THE CONSUMER GRIEVANCES REDRESSAL FORUM O R D E R BEFORE THE CONSUMER GRIEVANCES REDRESSAL FORUM M. S. ELECTRICITY DISTRIBUTION CO.LTD. (NAGPUR ZONE RURAL) NAGPUR. Application/Case No. CGRF/NZ/Rural/ 29 of 2006 Applicant : M/S. Shyam Rice Industries,

More information