Bid Protests. Presented By: Keith Romanowski, Watkins Meegan LLC Dan Herzfeld, Pillsbury
|
|
- Blaze Cross
- 6 years ago
- Views:
Transcription
1 Bid Protests Presented By: Keith Romanowski, Watkins Meegan LLC Dan Herzfeld, Pillsbury
2 Agenda Who can file What is a protest Why file a protest When to File Where to File Protest Types 2 Proprietary and Confidential
3 What is a Bid Protest? Written objection by interested party to Federal government procurement solicitation Cancellation of solicitation Award or proposed award Termination or cancellation of award Alleged violation of statute or regulation in connection with a procurement or proposed procurement Prejudicial violation. 3 Proprietary and Confidential
4 Protest Types Pre award (e.g. terms of solicitation) Post award (e.g. award or proposed award) 4 Proprietary and Confidential
5 Who can file protest? Interested party Actual or prospective bidder or offeror Direct economic interest 5 Proprietary and Confidential
6 Who can intervene? Pre Award: All bidders or offerors who appear to have a substantial prospect of receiving an award if protest is denied (GAO only) Post Award: Awardee A party that has an interest in procurement and disposition of case may impair or impede its interest (Court only) 6 Proprietary and Confidential
7 Where to Protest? Agency Government Accountability Office U.S. Court of Federal Claims Federal Aviation Administration, Office of Dispute Resolution for Acquisition 7 Proprietary and Confidential
8 GAO Protests Relatively inexpensive Respectable chance of success Automatic stay of award Pre award Automatic stay of performance if timely filed 8 Proprietary and Confidential
9 GAO Bid Protest Statistics FY 2013 FY 2012 FY 2011 FY 2010 FY 2009 Cases Filed (down 2%2) 2,475 (up 5%) 2,353 (up 2%) 2,299 (up 16%) 1,989 (up 20%) Cases Closed 2,5383 2,495 2,292 2,226 1,920 Merit (Sustain + Deny) Decisions Number of Sustains Sustain Rate 17% 18.6% 16% 19% 18% Effectiveness Rate4 43% 42% 42% 42% 45% ADR5 (cases used) ADR Success Rate6 86% 80% 82% 80% 93% Hearings7 3.36% (31 cases) 6.17% (56 cases) 8% (46 cases) 10% (61 cases) 12% (65 cases) 9 Proprietary and Confidential
10 Timely Filed GAO Protest Pre award Before the time proposals were due Post award Within 10 days of when you knew or should have know of your grounds for protest or Within 10 days of requested and required debriefing under FAR Part Proprietary and Confidential
11 Automatic Stay GAO must notify Agency of protest Within 10 days of contract award or Within 5 days of debriefing, whichever is later 11 Proprietary and Confidential
12 GAO Process GAO notifies agency of filing triggers stay of performance Protest reviewed for sufficiency Agency report and relevant documents to GAO within 30 days Protester/counsel comments with 10 days of agency report GAO hearing (<10% of protests) GAO decision within 100 days 12 Proprietary and Confidential
13 Reasons for Sustaining Protests Failure to follow solicitation evaluation criteria Inadequate documentation of the record Unequal treatment of offerors Unreasonable price or cost evaluation 13 Proprietary and Confidential
14 GAO will not consider Untimely protests Subcontractor protests Small business size standards, NAICS Code classifications, 8(a) determinations Challenge of affirmative finding of responsibility under FAR Part 9 Contract administration 14 Proprietary and Confidential
15 More on GAO Protests Protective order Disclosure of protected materials prohibited Outside counsel allowed access to all relevant documents Makes client discussions difficult 15 Proprietary and Confidential
16 Supplemental Protests Additional protests may be filed at any time must be timely under GAO rules New protest based on agency report must be filed within 10 days of receipt 16 Proprietary and Confidential
17 GAO Protest Sustained Re evaluation of existing proposals Modification of solicitation and final proposal revisions Exclusion of awardee Recommendation of awardee GAO can only make recommendations Recommend reimbursement of protest fees 17 Proprietary and Confidential
18 What if you lose? Reconsideration, but no appeal with GAO Can file protest at U.S. Court of Federal Claims 18 Proprietary and Confidential
19 What if you win? Original awardee may file protest at U.S. Court of Federal Claims challenging corrective action GAO protester can also challenge corrective action at the U.S. Court of Federal Claims 19 Proprietary and Confidential
20 U.S. Court of Federal Claims Timeliness: Post award: 6 year statute of limitations, laches Pre award: Challenge solicitation improprieties before award No automatic stay Must seek injunctive relief preliminary injunction or temporary restraining order When you file is considered in that calculus 20 Proprietary and Confidential
21 U.S. Court of Federal Claims Protester files: Complaint Motion for Temporary Restraining Order or Preliminary Injunction Motion to Seal & Motion for Protective Order Status Conference with Judge usually within 24 hours sometimes the same day as filing complaint. Administrative Record: Agency usually must present entire record of procurement larger and faster than at GAO. 21 Proprietary and Confidential
22 Process at Court of Federal Claims TRO/Preliminary Injunction Briefing if Agency will not voluntarily stay award. Cross Motions for Judgment on the Administrative Record. Hearings and discovery unusual. 22 Proprietary and Confidential
23 Court of Federal Claims Remedies Remedy: Injunction Court Order. 28 U.S.C. 1491(b)(2): 1. Success on the merits 2. Irreparable Harm 3. Balance of Hardships 4. Public Interest Remedy: Bid Preparation & Proposal Costs Appeal to U.S. Court of Appeals for the Federal Circuit (and then to U.S. Supreme Court). 23 Proprietary and Confidential
24 Prepare to Protest or Not Pre Award: Use the Question & Answer Process Post award: FAR Part 15 entitles you to debriefing Win or lose you should request debrief Request must be in writing within 3 days of notice of award FAR (d) identifies required information Ask questions about your and awardees evaluation 24 Proprietary and Confidential
25 Should I Protest? Incumbent good faith protest could result in four to sixth month contract extension Other Factors Strength of protest grounds Current or pending contracts with customer Cost of protest 25 Proprietary and Confidential
26 What Costs are Recoverable? Protest Costs Expressly unallowable per FAR f(8) unless incurred pursuant to a written request from Contracting Officer Protest Sustained, GAO generally recommends reimbursement of protest costs: Attorney fees Consultants Expert Witnesses 60 days to file detailed claim for reimbursement Court of Federal Claims cannot generally recover protest costs 26 Proprietary and Confidential
27 What Costs are Recoverable? Bid Preparation & Proposal Costs Cost principles allow recovery as indirect costs if allocable and reasonable. FAR (c). GAO Usually awarded when no other relief is available. Court of Federal Claims May award such costs, sometimes with other equitable relief 27 Proprietary and Confidential
28 Questions? 28 Proprietary and Confidential
29 Contact Us Tysons, VA 8000 Towers Crescent Drive Suite 950 Tysons, VA P: Bethesda, MD 6720 B Rockledge Drive Suite 750 Bethesda, MD P: Annapolis, MD 888 Bestgate Road Suite 401 Annapolis, MD P: Herndon, VA Dulles Technology Drive Suite 220 Herndon, VA P: lunchandlearn@watkinsmeegan.com 29 Proprietary and Confidential
30 Presenters Keith Romanowski, Senior Manager Watkins Meegan Dan Herzfeld, Counsel Pillsbury Winthrop Shaw Pittman LLP Proprietary and Confidential
Bid Protests. David T. Ralston, Jr. Frank S. Murray. October 2008
Bid Protests David T. Ralston, Jr. Frank S. Murray October 2008 Bid Protest Topics Why bid protests are filed? Where filed? Processing time Decision deadlines How to get a stay of contract performance
More informationBID PROTEST WINNING THE BATTLE WITHOUT LOSING THE WAR. June 18, FLUET HUBER + HOANG PLLC
BID PROTEST WINNING THE BATTLE WITHOUT June 18, 2015 ABOUT FLUET HUBER + HOANG PLLC 2 ABOUT FH+H Fluet Huber + Hoang PLLC FH+H is a veteran owned law firm focused on helping corporate clients thrive FH+H
More informationGAO Bid Protests: An Overview of Time Frames and Procedures
GAO Bid Protests: An Overview of Time Frames and Procedures Kate M. Manuel Legislative Attorney Moshe Schwartz Specialist in Defense Acquisition January 19, 2016 Congressional Research Service 7-5700 www.crs.gov
More informationChapter 7 Protests, Claims, Disputes,
CHAPTER CONTENTS Key Points...248 Introduction...248 Protests...248 Contract Claims...256 Seizures...258 Contract Disputes and Appeals...260 Contract Settlements and Alternative Dispute Resolution...262
More informationWHAT TO DO IF YOU THINK A BID LOWER THAN YOURS SHOULD BE THROWN OUT AND THE JOB AWARDED TO YOU
WHAT TO DO IF YOU THINK A BID LOWER THAN YOURS SHOULD BE THROWN OUT AND THE JOB AWARDED TO YOU Almost all public contracts are awarded pursuant to competitive bid. Generally, public construction contracts
More informationGovernment Contracts: COFC Bid Protests
View the online version at http://us.practicallaw.com/1-583-9427 Government Contracts: COFC Bid Protests DAVID T. RALSTON JR. AND FRANK S. MURRAY, JR., FOLEY & LARDNER, LLP, WITH PRACTICAL LAW COMMERCIAL
More informationGAO Bid Protests: An Overview of Time Frames and Procedures
GAO Bid Protests: An Overview of Time Frames and Procedures Kate M. Manuel Legislative Attorney Moshe Schwartz Specialist in Defense Acquisition October 3, 2014 CRS Report for Congress Prepared for Members
More informationIn the United States Court of Federal Claims
In the United States Court of Federal Claims No. 16-1365 C Filed: November 3, 2016 FAVOR TECHCONSULTING, LLC, Plaintiff, v. THE UNITED STATES, Defendant. 28 U.S.C. 1491(b)(2) (Administrative Dispute Resolution
More informationIn the United States Court of Federal Claims
In the United States Court of Federal Claims BID PROTEST No. 16-1684C (Filed Under Seal: December 23, 2016 Reissued: January 10, 2017 * MUNILLA CONSTRUCTION MANAGEMENT, LLC, v. Plaintiff, THE UNITED STATES
More informationGeneral Conditions for Non-Construction Contracts Section I (With or without Maintenance Work)
General Conditions for Non-Construction Contracts Section I (With or without Maintenance Work) U.S. Department of Housing and Urban Development Office of Public and Indian Housing Office of Labor Relations
More informationIn the United States Court of Federal Claims
In the United States Court of Federal Claims CHEROKEE NATION TECHNOLOGIES, LLC, v. Plaintiff, THE UNITED STATES, and Defendant. CHENEGA FEDERAL SYSTEMS, LLC, No. 14-371C (Filed Under Seal: June 10, 2014)
More informationRegister, 2014 Commerce, Community, and Ec. Dev.
3 AAC is amended by adding a new chapter to read: Chapter 109. Procurement Alaska Energy Authority Managed Grants. Article 1. Roles and Responsibilities. (3 AAC 109109.010-3 AAC 109109.050) 2. Source Selection
More informationGeneral Conditions for Non-Construction Contracts Section I (With or without Maintenance Work)
General Conditions for Non-Construction Contracts Section I (With or without Maintenance Work) U.S. Department of Housing and Urban Development Office of Public and Indian Housing Office of Labor Relations
More informationElectronic Protest Docketing System Instructions. (Version 1.0 June 2016)
I. INTRODUCTION Electronic Protest Docketing System Instructions (Version 1.0 June 2016) 1. In General. These Instructions govern electronic filings for protests, requests for reconsideration, and either
More informationAPPENDIX F PUBLIC PRIVATE PARTNERSHIP PROCUREMENT PROCEDURES
APPENDIX F PUBLIC PRIVATE PARTNERSHIP PROCUREMENT PROCEDURES PURPOSE The purpose of these Procurement Procedures ("Procedures") is to establish procedures for the procurement of services for public private
More informationMARYLAND STADIUM AUTHORITY RESOLUTIONS PROCUREMENT POLICIES AND PROCEDURES
MARYLAND STADIUM AUTHORITY RESOLUTIONS PROCUREMENT POLICIES AND PROCEDURES WHEREAS, the Maryland Stadium Authority desires to formalize its policies and procedures with respect to procurement; and WHEREAS,
More informationFocus. Vol. 49, No. 31 August 22, 2007
Reprinted from The Government Contractor, with permission of Thomson West. Copyright 2007. Further use without the permission of West is prohibited. For further information about this publication, please
More informationUniversity Research Company, LLC
United States Government Accountability Office Washington, DC 20548 Decision Comptroller General of the United States DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below was subject to a
More informationIn the United States Court of Federal Claims
In the United States Court of Federal Claims No. 15-189C (Filed: March 23, 2016) EXCELSIOR AMBULANCE SERVICE, INC., Plaintiff, RCFC 24; Postjudgment Motion for Leave v. to Intervene; Timeliness; Bid Protest
More informationRules of Practice for Protests and Appeals Regarding Eligibility for Inclusion in the U.S.
This document is scheduled to be published in the Federal Register on 03/30/2018 and available online at https://federalregister.gov/d/2018-06034, and on FDsys.gov Billing Code: 8025-01 SMALL BUSINESS
More informationIn the United States Court of Federal Claims
In the United States Court of Federal Claims No. 09-542C FILED UNDER SEAL: October 30, 2009 REFILED FOR PUBLICATION: November 5, 2009 THE ANALYSIS GROUP, LLC, Competition in Contracting Act, 31 U.S.C.
More informationIn the United States Court of Federal Claims
In the United States Court of Federal Claims No. 13-116C (Filed under seal February 22, 2013) (Reissued February 27, 2013) * * * * * * * * * * * * * * * * * * * * * * * * * * METTERS INDUSTRIES, INC.,
More informationUnited States Court of Federal Claims
United States Court of Federal Claims No. 16-1704 C (Filed Under Seal: October 31, 2017) (Reissued: November 16, 2017) DYNCORP INTERNATIONAL, LLC, v. Plaintiff, UNITED STATES OF AMERICA, and Defendant,
More informationRESOLUTION OF BOARD OF TRUSTEES ADOPTING PROCUREMENT POLICIES AND PROCEDURES WHEREAS, the Maryland Health Benefit Exchange Act of 2011 ( the Exchange
RESOLUTION OF BOARD OF TRUSTEES ADOPTING PROCUREMENT POLICIES AND PROCEDURES WHEREAS, the Maryland Health Benefit Exchange Act of 2011 ( the Exchange Act ) directs the Board of Trustees of the Maryland
More informationADR Roundtable. American Bar Association Annual Meeting. August 9, 2014
ADR Roundtable American Bar Association Annual Meeting August 9, 2014 Comments by the Alternative Dispute Resolution Committee of the Public Contract Law Section Alternative Dispute Resolution (ADR) techniques
More informationTHE PROCUREMENT INTEGRITY ACT
Welcome THE CONFLICTING EVOLUTION OF THE PROCUREMENT INTEGRITY ACT James G. Peyster 226 The Procurement Integrity Act: Background The Procurement Integrity Act ( PIA ); 41 U.S.C 2101 2017 (Formerly 41
More informationPART III GENERAL INFORMATION, INSTRUCTIONS AND CONDITIONS FOR OFFERORS
PART III GENERAL INFORMATION, INSTRUCTIONS AND CONDITIONS FOR OFFERORS SECTION TITLE F G H General Information About the RFP General Instructions for Offerors General Conditions for Offerors 18 SECTION
More informationGAO Bid Protests: Trends, Analysis, and Options for Congress
GAO Bid Protests: Trends, Analysis, and Options for Congress Moshe Schwartz Specialist in Defense Acquisition Kate M. Manuel Legislative Attorney August 5, 2011 Congressional Research Service CRS Report
More informationNotice and Protest Procedures for Protests Related to a University s Contract Procurement Process.
18.002 Notice and Protest Procedures for Protests Related to a University s Contract Procurement Process. (1) Purpose. The procedures set forth in this Regulation shall apply to protests that arise from
More informationIN THE COMMONWEALTH COURT OF PENNSYLVANIA
IN THE COMMONWEALTH COURT OF PENNSYLVANIA UnitedHealthcare of Pennsylvania, Inc., : : Petitioner : : v. : No. 1978 C.D. 2016 : Argued: September 11, 2017 Department of Human Services, : : Respondent :
More informationPART III GENERAL INFORMATION, INSTRUCTIONS AND CONDITIONS FOR BIDDERS
PART III GENERAL INFORMATION, INSTRUCTIONS AND CONDITIONS FOR BIDDERS SECTION TITLE F G H General Information About the IFB General Instructions for Bidders General Conditions for Bidders 18 SECTION F
More informationThe Bid Protest Process
BID PROTESTS INVOLVING HUBZONE PROCUREMENTS 2015 HUBZone Contractors National Council Annual Conference Bid Protests David J. Taylor, General Counsel HUBZone Contractors National Council October 29, 2015
More informationPiquette & Howard Electric Service, Inc.
United States Government Accountability Office Washington, DC 20548 Decision Comptroller General of the United States DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below was subject to a
More informationCase 1:16-cv WHP Document 4-1 Filed 08/18/16 Page 1 of 10 NO. 1:16-CV-6544
Case 1:16-cv-06544-WHP Document 4-1 Filed 08/18/16 Page 1 of 10 UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF NEW YORK U.S. COMMODITY FUTURES TRADING COMMISSION, PLAINTIFF, NO. 1:16-CV-6544
More informationJOINT MARKETING AND SALES REFERRAL AGREEMENT
This Referral Agreement (the Agreement) is made effective as of 2012 (the Effective Date) by and between Aerospike, Inc., a Delaware corporation, with an address at 2525 E. Charleston Road, Suite 201,
More informationPublic Private Partnership Legislation: Ohio
Public Private Partnership Legislation: Ohio D. BRUCE GABRIEL, JEFFREY A. BOMBERGER AND GREG R. DANIELS, SQUIRE SANDERS (US) LLP, WITH PRACTICAL LAW FINANCE A Q&A guide to Ohio public private partnership
More informationNo C (Judge Lettow) IN THE UNITED STATES COURT OF FEDERAL CLAIMS BID PROTEST. CASTLE-ROSE, INC., Plaintiff, THE UNITED STATES, Defendant.
Case 1:11-cv-00163-CFL Document 22 Filed 05/11/11 Page 1 of 18 PROTECTED INFORMATION TO BE DISCLOSED ONLY IN ACCORDANCE WITH UNITED STATES COURT OF FEDERAL CLAIMS PROTECTIVE ORDER No. 11-163C (Judge Lettow)
More informationIN THE SUPREME COURT OF THE STATE OF HAWAIʻI. ---o0o--- SCWC CERTIFIED CONSTRUCTION, INC., Petitioner/Petitioner-Appellant,
Electronically Filed Supreme Court SCWC-14-0001160 20-SEP-2016 07:56 AM IN THE SUPREME COURT OF THE STATE OF HAWAIʻI ---o0o--- SCWC-14-0001160 CERTIFIED CONSTRUCTION, INC., Petitioner/Petitioner-Appellant,
More informationR Definitions
R7-2-1001. Definitions ARIZONA ADMINISTRATIVE CODE TITLE 7. EDUCATION CHAPTER 2. STATE BOARD OF EDUCATION ARTICLE 10. SCHOOL DISTRICT PROCUREMENT IN GENERAL Added Acceptance period Actual energy production
More informationChapter VIII. Challenge proceedings 1
UNCITRAL Model Procurement Law Article 64: Right to challenge and appeal Chapter VIII. Challenge proceedings 1 1. A supplier or contractor that claims to have suffered or claims that it may suffer loss
More informationMNsure. DRAFT Procurement Policies and Procedures. Section 1. Statement of Purpose. Section 2. Statutory Authority. Section 3. Conflicts of Interest
MNsure DRAFT Procurement Policies and Procedures Section 1 Statement of Purpose These procurement policies and procedures are intended to establish an open, competitive and transparent procurement process
More informationTable of Contents. Date Issued: June 12, 2009 Date Last Revised: December 15, 2010
Date Issued: June 12, 2009 Date Last Revised: December 15, 2010 CHAPTER 28. Protests Table of Contents CHAPTER 28. Protests... 28 1 28.1 General... 28 2 28.1.1 Policy... 28 2 28.1.2 Notice to Offerors...
More informationPerini Management Services, Inc. B ; B ; B ; B
United States Government Accountability Office Washington, DC 20548 Decision Comptroller General of the United States DOCUMENT FOR PUBLIC RELEASE The decision issued on the date below was subject to a
More informationTOWN OF HERNDON, VIRGINIA ORDINANCE DECEMBER 13, 2016
TOWN OF HERNDON, VIRGINIA ORDINANCE DECEMBER 13, 2016 Ordinance-to amend and reenact Chapter 30 (Finance & Taxation), Article VIII (Fiscal Procedures), Division 2 (Procurement), of the Herndon Town Code,
More informationCase 1:18-cv TCW Document 218 Filed 05/18/18 Page 1 of 9 IN THE UNITED STATES COURT OF FEDERAL CLAIMS BID PROTEST
Case 1:18-cv-00204-TCW Document 218 Filed 05/18/18 Page 1 of 9 IN THE UNITED STATES COURT OF FEDERAL CLAIMS BID PROTEST FMS Investment Corp. et al., Plaintiffs, v. THE UNITED STATES, Defendant, and PERFORMANT
More informationTEAMING AGREEMENT 1.0 PROPOSAL ACTIVITIES
TEAMING AGREEMENT This teaming agreement (this Agreement ), by and between COMPANY, Inc. (hereinafter INC ) and SETECS, Inc. (hereinafter SETECS ) (each, a Party and collectively, the Parties ), is effective
More informationGovernment Contract Management: Preventing, Resolving, and (Where Necessary) Litigating Disputes. Handling Procurement Disputes: Issues & Challenges
Government Contract Management: Preventing, Resolving, and (Where Necessary) Litigating Disputes International Master in Public Procurement Management Handling Procurement Disputes: Issues & Challenges
More informationRichard J. Webber, Arent Fox, LLP, Washington, D.C., Counsel for Plaintiff.
In the United States Court of Federal Claims No. 08-660C Filed: December 15, 2008 * TO BE PUBLISHED *************************************** * Administrative Dispute Resolution Act of * 1996, Pub. L. No.
More informationDIVISION PROCUREMENT CONTRACTS FOR GOODS AND SERVICES DIVISION PROCUREMENT CONTRACTS FOR GOODS AND SERVICES GENERALLY; EXCEPTIONS
DIVISION 100 - PROCUREMENT CONTRACTS FOR GOODS AND SERVICES 100-1 DIVISION 100 - PROCUREMENT CONTRACTS FOR GOODS AND SERVICES GENERALLY; EXCEPTIONS 10.100 General Procurement Contracts; Exceptions Except
More informationIn the United States Court of Federal Claims
In the United States Court of Federal Claims BID PROTEST No. 16-1576C Filed Under Seal: February 2, 2017 Reissued for Publication: February 15, 2017 * LIMCO AIREPAIR, INC., Plaintiff, v. THE UNITED STATES,
More informationChapter 11: Reorganization
Chapter 11: Reorganization This chapter has numerous sections relevant to reorganizations, including railroad reorganizations. Committees, trustees and examiners, conversion and dismissal, collective bargaining
More informationOrganizational Conflicts of Interest and Post Government Employment Restrictions
888 17 th Street, NW, 11 th Floor Washington, DC 20006 Tel: (202) 857-1000 Fax: (202) 857-0200 Organizational Conflicts of Interest and Post Government Employment Restrictions In Partnership with A PilieroMazza
More informationIN THE UNITED STATES COURT OF FEDERAL CLAIMS BID PROTEST
Case 1:15-cv-00158-MBH Document 25 Filed 03/15/15 Page 1 of 18 IN THE UNITED STATES COURT OF FEDERAL CLAIMS BID PROTEST Number 15-158C Judge Marian Blank Horn VISUAL CONNECTIONS, LLC, v. Plaintiff, THE
More informationIn the United States Court of Federal Claims
In the United States Court of Federal Claims Nos. 15-616C, 15-617C, 15-618C, 15-619C, 15-620C (Originally Filed: September 9, 2015) (Re-filed: September 17, 2015) 1 * * * * * * * * * * * * * * * * * *
More informationIn the United States Court of Federal Claims
In the United States Court of Federal Claims No. 11-867C (Filed Under Seal: March 5, 2012) Reissued: March 21, 2012 1 BOSTON HARBOR DEVELOPMENT PARTNERS, LLC., Plaintiff, Preaward bid protest; Review of
More informationIn the United States Court of Federal Claims
In the United States Court of Federal Claims No. 04-1553 C (Filed: November 23, 2004) ) CHAPMAN LAW FIRM, ) ) Plaintiff, ) Post-Award Bid Protest; ) 28 U.S.C. 1491(b)(2); v. ) Challenge to size determination
More information1. Prohibition on Contracting with Inverted Domestic Corporations Representation.
1. Prohibition on Contracting with Inverted Domestic Corporations Representation. (a) Definitions. Inverted domestic corporation and subsidiary have the meaning given in the clause of this contract entitled
More informationIn the United States Court of Federal Claims
In the United States Court of Federal Claims No. 09-332C Filed: October 28, 2009 Reissued: December 1, 2009 1 * * * * * * * ALATECH HEALTHCARE, L.L.C., * Bid Protest, 28 U.S.C. 1491(b)(1); Preference for
More information6Gx13-8C School Board--Methods of Operation LOBBYISTS. I. Purpose
School Board--Methods of Operation LOBBYISTS I. Purpose The School Board of Miami-Dade County, Florida, determines and declares that the operation of responsible government requires that the fullest opportunity
More informationB&B Medical Services, Inc.; Rotech Healthcare, Inc.
United States Government Accountability Office Washington, DC 20548 Comptroller General of the United States Decision Matter of: File: B&B Medical Services, Inc.; Rotech Healthcare, Inc. Date: January
More informationGAO Bid Protests: Trends and Analysis
Moshe Schwartz Specialist in Defense Acquisition Kate M. Manuel Legislative Attorney July 21, 2015 Congressional Research Service 7-5700 www.crs.gov R40227 Summary Bid protests on federal government contracts
More informationWilliam G. Kanellis, United States Department of Justice, Civil Division, Washington, D.C., Counsel for Defendant.
In the United States Court of Federal Claims No. 07-532C Filed: July 7, 2008 TO BE PUBLISHED AXIOM RESOURCE MANAGEMENT, INC., Plaintiff, Bid Protest; Injunction; v. Notice Of Appeal As Of Right, Fed. R.
More informationI. OVERVIEW. A. Purchases below statutory bid threshold
PP O4 09 BID PROTESTS AND APPEALS I. OVERVIEW It is the policy of the District to afford due process to suppliers that have participated in a competitive procurement process and believe they have not been
More informationCase 1:16-cv TJS Document 1 Filed 04/01/16 Page 1 of 22 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND
Case 1:16-cv-00968-TJS Document 1 Filed 04/01/16 Page 1 of 22 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND TIFFANY JADE SMITH * 3318 Curtis Drive, Apt. 202 Suitland, MD 20746, * on
More informationUnited States Court of Appeals for the Federal Circuit
Case 1:17-cv-00449-SGB Document 177 Filed 07/18/17 Page 1 of 7 NOTE: This order is nonprecedential. United States Court of Appeals for the Federal Circuit CONTINENTAL SERVICE GROUP, INC. PIONEER CREDIT
More informationIn the United States Court of Federal Claims
EXCELSIOR AMBULANCE SERVICE, INC. v. USA Doc. 50 In the United States Court of Federal Claims No. 15-189C (Filed Under Seal: December 4, 2015) (Reissued for Publication: December 15, 2015) * *****************************************
More informationFINANCIAL SERVICES AND MARKETS REGULATIONS 2015
FINANCIAL SERVICES AND MARKETS REGULATIONS 2015 *In this Annex, underlining indicates new text and strikethrough indicates deleted text, unless otherwise indicated. FINANCIAL SERVICES AND MARKETS REGULATIONS
More informationCITY OF ROANOKE, VIRGINIA REQUEST FOR PROPOSAL FOR EXECUTIVE SEARCH SERVICES RFP NUMBER OPENING DATE: JULY 23, 2009 OPENING TIME 2:00 P.M.
CITY OF ROANOKE, VIRGINIA REQUEST FOR PROPOSAL FOR EXECUTIVE SEARCH SERVICES RFP NUMBER 10-01-02 OPENING DATE: JULY 23, 2009 OPENING TIME 2:00 P.M. The Request for Proposal and related documents may be
More informationStreamlined Arbitration Rules and Procedures
RESOLUTIONS, LLC s GUIDE TO DISPUTE RESOLUTION Streamlined Arbitration Rules and Procedures 1. Scope of Rules The RESOLUTIONS, LLC Streamlined Arbitration Rules and Procedures ("Rules") govern binding
More informationMARYLAND FALSE CLAIMS ACT. SECTION 1. BE IT ENACTED BY THE GENERAL ASSEMBLY OF MARYLAND, That the Laws of Maryland read as follows:
MARYLAND FALSE CLAIMS ACT SECTION 1. BE IT ENACTED BY THE GENERAL ASSEMBLY OF MARYLAND, That the Laws of Maryland read as follows: 8 101. (a) In this title the following words have the meanings indicated.
More informationEQUIPMENT LEASE ORIGINATION AGREEMENT
EQUIPMENT LEASE ORIGINATION AGREEMENT THIS EQUIPMENT LEASE ORIGINATION AGREEMENT (this "Agreement") is made as of this [ ] day of [ ] by and between Ascentium Capital LLC, a Delaware limited liability
More informationThe Brooks Act: Federal Government Selection of Architects and Engineers
The Brooks Act: Federal Government Selection of Architects and Engineers Public Law 92-582 92nd Congress, H.R. 12807 October 27, 1972 An Act To amend the Federal Property and Administrative Services Act
More informationIn the United States Court of Federal Claims
In the United States Court of Federal Claims BID PROTEST No. 15-1527C Filed Under Seal: January 13, 2016 Reissued for Publication: April 20, 2016 * WALLACE ASSET MANAGEMENT, LLC, v. Plaintiff, THE UNITED
More informationIn the United States Court of Federal Claims
In the United States Court of Federal Claims Case No. 08-261C Filed Under Seal April 25, 2008 Reissued for Publication May 2, 2008 FOR PUBLICATION * * * * * * * * * * * * * * * * * * * * * * * * * * *
More informationTallahassee Community College Procedure for Contract Solicitation or Award Bid Protest
Tallahassee Community College Procedure for Contract Solicitation or Award Bid Protest Purpose The purpose of this procedure is to establish the dispute resolution process for protests arising from College
More informationNIGP North Shreveport, La February 9, 2017
NIGP North Shreveport, La February 9, 2017 Who may file a Protest and to Whom Shall it be Addressed? Any person who is aggrieved in connection with the solicitation or award of a contract issued by the
More informationCHAPTER PUBLIC SCHOOL SYSTEM PROCUREMENT RULES AND REGULATIONS
CHAPTER 60-40 PUBLIC SCHOOL SYSTEM PROCUREMENT RULES AND REGULATIONS Part 001 General Provisions Subpart A General 60-40-001 Purpose 60-40-005 Authority 60-40-010 Supplementary General Principles of Law
More informationH SUBSTITUTE HOUSE BILL State of Washington 58th Legislature 2004 Regular Session
H-4810.1 SUBSTITUTE HOUSE BILL 3187 State of Washington 58th Legislature 2004 Regular Session By House Committee on Commerce & Labor (originally sponsored by Representatives Romero, Hudgins, Conway, Hunt,
More informationAppendix E. Reservation of ESI Rights and Other RFP Terms. For
Appendix E Reservation of ESI Rights and Other RFP Terms 2016 Request Proposals Long-Term Renewable Generation Resources Entergy Louisiana, LLC Entergy Services, Inc. June 8, 2016 APPENDIX E RESERVATION
More informationCHAPTER 468L TRAVEL AGENCIES
Part I. General Provisions CHAPTER 468L TRAVEL AGENCIES SECTION 468L-1 Definitions 468L-2 Registration and renewal 468L-2.5 Denial of registration 468L-2.6 Revocation, suspension, and renewal of registration
More informationTitle 10: COMMERCE AND TRADE
Title 10: COMMERCE AND TRADE Chapter 302: UNIFORM TRADE SECRETS ACT Table of Contents Part 4. TRADEMARKS AND NAMES... Section 1541. SHORT TITLE... 3 Section 1542. DEFINITIONS... 3 Section 1543. INJUNCTIVE
More informationICAO VENDOR SANCTION POLICY. Approved by the Council and published by its decision
ICAO VENDOR SANCTION POLICY Approved by the Council and published by its decision 23 March 2017 Table of Contents 1. BACKGROUND... 3 2. PURPOSE AND OBJECTIVE... 3 3. DEFINITIONS... 3 4. THE SANCTIONS BOARD...
More informationApril 4, 2016 at 10:00am. 506 N. Chadbourne Ave, San Angelo, Texas
1. Site Visit (Construction). (a) The clauses at, Differing Site Conditions, and, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation.
More informationAtlantic Cruising Yachts, LLC. Sales Associate Agreement. (hereinafter referred to as Sales Associate or SA ). ADDRESS:
Atlantic Cruising Yachts, LLC Sales Associate Agreement This is an Agreement (the Agreement) made by and between: Atlantic Cruising Yachts, LLC (hereinafter referred to as ACY ), located at 312 Third Street,
More informationCircuit Court for Anne Arundel County Case No. 02-C UNREPORTED IN THE COURT OF SPECIAL APPEALS OF MARYLAND. No September Term, 2017
Circuit Court for Anne Arundel County Case No. 02-C-13-178732 UNREPORTED IN THE COURT OF SPECIAL APPEALS OF MARYLAND No. 0545 September Term, 2017 JOSEPH M. BILZOR, v. FRANK A. RUFF Fader, C.J., Shaw Geter,
More informationDecision. Nilson Van & Storage, Inc. Matter of: File: B Date: December 10, 2007
United States Government Accountability Office Washington, DC 20548 Comptroller General of the United States Decision Matter of: Nilson Van & Storage, Inc. File: B-310485 Date: December 10, 2007 Alan F.
More information!! 1 Page! 2014 PEODepot. All rights reserved. PEODepot and peodepot.com are trademarks of PEODepot. INITIAL! BROKER AGREEMENT
BROKER AGREEMENT THIS BROKER AGREEMENT (the Agreement ) is by and between you (the Broker ) and PEODepot, Inc., a Florida corporation (together with its affiliates and subsidiaries, MGA ) with an address
More information1. Communications with Bidders
1. Communications with Bidders Communications with Bidders and potential Bidders will only be done in writing. All communication must be in writing to CVCOG Procurement at the following address: CVCOG
More informationSANTANDER CONSUMER USA HOLDINGS INC. (Exact name of registrant as specified in its charter)
UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C. 20549 FORM 8-K CURRENT REPORT Pursuant to Section 13 or 15(d) of the Securities Exchange Act of 1934 Date of Report (Date of earliest event
More informationCommonwealth of Kentucky Court of Appeals
RENDERED: JANUARY 30, 2015; 10:00 A.M. NOT TO BE PUBLISHED Commonwealth of Kentucky Court of Appeals NO. 2013-CA-001073-MR PIONEER PLAZA OF GEORGETOWN, LLC; APPELLANT APPEAL FROM FRANKLIN CIRCUIT COURT
More informationUnited States Court of Appeals for the Federal Circuit
United States Court of Appeals for the Federal Circuit CLEVELAND ASSETS, LLC, Plaintiff-Appellant v. UNITED STATES, Defendant-Appellee 2017-2113 Appeal from the United States Court of Federal Claims in
More informationIn the United States Court of Federal Claims
In the United States Court of Federal Claims No. 16-296C (Originally Filed: April 13, 2016) (Re-issued: April 21, 2016) 1 * * * * * * * * * * * * * * * * * * * * * * REO SOLUTION, LLC, v. Plaintiff, Post-Award
More informationPURCHASE ORDER TERMS AND CONDITIONS
PURCHASE ORDER TERMS AND CONDITIONS 1. SERVICES & DELIVERABLES. Seller agrees to provide to CORTEC PRECISION SHEETMETAL (or its subsidiaries, if such subsidiaries are designated as the contracting parties
More informationIN THE COMMONWEALTH COURT OF PENNSYLVANIA
IN THE COMMONWEALTH COURT OF PENNSYLVANIA CenturyLink Public Communications, : Inc., : Petitioner : : v. : No. 1183 C.D. 2014 : Submitted: January 9, 2015 Department of Corrections, : Respondent : BEFORE:
More informationREQUEST FOR PROPOSALS. Concept Plan and Implementation Matrix for the Patapsco Regional Greenway
REQUEST FOR PROPOSALS Concept Plan and Implementation Matrix for the Patapsco Regional Greenway Due Date: August 19, 2016 Submit Qualifications to: Baltimore Metropolitan Council ATTN: Jamie Bridges 1500
More informationIn the United States Court of Federal Claims
In the United States Court of Federal Claims No. 13-144C (Originally Filed: May 9, 2013) (Reissued: May 29, 2013) 1 * * * * * * * * * * * * * * * * * * * * * * CHAMELEON INTEGRATED SERVICES, INC., v. UNITED
More informationJAMS International Arbitration Rules & Procedures
JAMS International Arbitration Rules & Procedures Effective September 1, 2016 JAMS INTERNATIONAL ARBITRATION RULES JAMS International and JAMS provide arbitration and mediation services from Resolution
More informationCase Document 19 Filed in TXSB on 04/14/16 Page 1 of 42
Case 16-31959 Document 19 Filed in TXSB on 04/14/16 Page 1 of 42 IN THE UNITED STATES BANKRUPTCY COURT FOR THE SOUTHERN DISTRICT OF TEXAS HOUSTON DIVISION ----------------------------------------------------------------
More informationSUPREME COURT OF THE UNITED STATES
Cite as: 547 U. S. (2006) 1 NOTICE: This opinion is subject to formal revision before publication in the preliminary print of the United States Reports. Readers are requested to notify the Reporter of
More informationCGI FEDERAL INC. OPINION BY v. Record No JUSTICE ELIZABETH A. McCLANAHAN June 7, 2018 FCi FEDERAL, INC.
PRESENT: All the Justices CGI FEDERAL INC. OPINION BY v. Record No. 170617 JUSTICE ELIZABETH A. McCLANAHAN June 7, 2018 FCi FEDERAL, INC. FROM THE CIRCUIT COURT OF FAIRFAX COUNTY Michael F. Devine, Judge
More information