Neutral Citation Number: [2013] EWCA Civ 474 Case No: A1/ AND 2912

Size: px
Start display at page:

Download "Neutral Citation Number: [2013] EWCA Civ 474 Case No: A1/ AND 2912"

Transcription

1 Neutral Citation Number: [2013] EWCA Civ 474 Case No: A1/ AND 2912 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE HIGH COURT OF JUSTICE TECHNOLOGY AND CONSTRUCTION COURT, MANCHESTER DISTRICT REGISTRY His Honour Judge Stephen Davies (sitting as a Judge of the High Court) 0MA50090 Royal Courts of Justice Strand, London, WC2A 2LL Before : Date: 01/05/2013 LORD JUSTICE LONGMORE LORD JUSTICE RIMER and LORD JUSTICE TOMLINSON Between : Co-operative Group Limited - and - Birse Developments Ltd - and - Stuarts Industrial Flooring Limited (in Administration) Respondent Appellant Third Party Appellant Simon Hughes QC and Tom Owen (instructed by DAC Beachcroft LLP) for the Respondent Fiona Sinclair (instructed by Clyde and Co Solicitors) for the Appellant Mark Cannon QC and Katie Powell (instructed by Reynolds Porter Chamberlain LLP) for the Third Party Appellant Hearing date : 26 March Judgment

2 Lord Justice Tomlinson: Introduction 1. This appeal raises the short question whether the Claimant/Respondent has in Paragraph 33A of its Re-Amended Particulars of Claim sought to add a new cause of action to those upon which it already relied in the proceedings. The judge below, His Honour Judge Stephen Davies, sitting in Manchester as a judge of the Queen s Bench Division in the Technology and Construction Court, held that it had not. He granted permission to appeal to this court. 2. The Claimant is the leasehold owner of a distribution centre known as Swift Valley Central in Rugby. It comprises two very large warehouses connected by an office accommodation block and an external hardstanding on an eleven acre site. It was developed by Kingspark Development Ltd ( Kingspark ) who contracted with the Defendant/Appellant, Birse Developments Limited ( Birse ) as main design and build contractor. Birse in turn sub-contracted the design and building of the internal warehouse floors to the Third Party/Appellant, Stuarts Industrial Flooring Limited ( Stuarts ). Since Birse seeks an indemnity from Stuarts in respect of any relevant liability to the Claimant, they have made common cause on this appeal as they did before the judge. 3. On completion of the contractual works in September 1998 the distribution centre was leased to and occupied by the Claimant. In connection with the intended lease Birse provided to the Claimant collateral warranties in relation to the work which effectively put the Claimant into the position of the Employer under the head building contract. Hence the Claimant asserts against Birse a claim in breach of contract. Because the warranties were contained in a contract made under seal the relevant limitation period is twelve years. 4. A Claim Form was issued in September 2010 with Particulars of Claim attached. It was common ground for the purposes of the appeal before us that the causes of action with which we are concerned accrued in September 1998 and that the September 2010 proceedings were brought in time so far as concerns causes of action then asserted. It follows that any amendment to the Particulars of Claim sought to be made after September 2010 with a view to introducing a cause of action upon which reliance had not hitherto been placed will be impermissible unless the new claim arises out of the same or substantially the same facts as are already in issue on any claim made in the original action Limitation Act 1980, section 35; CPR 17.4(2). The judge held that the claim sought to be made in the re-amendment did not seek to introduce a new cause of action. Although the point did not therefore arise the judge went on to hold that the claim sought to be introduced by the re-amendment did not arise out of the same or substantially the same facts as are already in issue on any claim made in the original action. By a Respondent s Notice the Claimant challenges this latter conclusion in the event that this court concludes that the proposed re-amendment does seek to introduce a new cause of action. 5. In broad terms the Claimant complained in the original Particulars of Claim of a number of defects to three distinct areas of the property (i) the external concrete hardstanding, (ii) the drainage system and (iii) the concrete floor slabs in the warehouses. Numerous breaches of contract are asserted in respect of each alleged

3 defect. On this appeal we are concerned only with the allegations concerning the concrete floor slab inside the two warehouses. The existing statement of case 6. The claims made in the original action are for present purposes to be found in the Amended Particulars of Claim. Paragraph 13 sets out relevant contractual terms concerning Concrete Work.... the Employer s Requirements which formed part of the Building Contract contained the Specification for the substructure which provided inter alia as follows: CONCRETE WORK Concrete work will comply with BS8110 and carried out to the Structural Engineer s requirements GROUND FLOOR SLAB A reinforced concrete ground slab will be provided to all ground floor areas within the buildings. The slab in respect of the warehouse areas will be designed in accordance with the BCA Interim Technical Note ll, Loading Category 3, Classification: Heavy and will accommodate a uniformly distributed superimposed loading of KN/m 2 (1000 lbs/ft 2 ) and pallet racking of 70 KN/leg (racking leg loading based on leg centres of 2.70m along length, 0.09m centres across width and 0.20m centres for back legs where positioned back to back). Ground floor movement joints will be designed so that no vertical movement occurs. The ground floor slab will be constructed so that the top surface is within the tolerances as defined in Concrete Society Technical Report No 34 of FM2 Property IV and free movement areas, and ±10mm from datum. Local level variations shall not exceed ±3mm in a 3.0m straight edge in any direction. Each warehouse floor slab shall be constructed with not more than 9 No. bays and saw cut joints within the slab shall not be made less than 9.0m apart, unless constrained by pallet layout. Saw cut and bay joints shall be infilled with suitable filler during construction and to accessible floor areas twelve months after the date of practical completion. A floor joint design drawing shall be produced and issued to the Tenant s representative for agreement before construction commences.

4 On completion of each warehouse area floor slab a profileograph survey will confirm the achieved surface tolerance, prior to any fitting out works taking place. Where appropriate, the slab will be designed and constructed in accordance with the recommendations of The Cement and Concrete Association Technical Report No 550 and BCA Interim Technical Note II. The surface will be power floated and treated with a proprietary surface hardener and penetrating dust inhibitor in accordance with the manufacturer s instructions. A 1,200 gauge P.I.F.A. polythene damp-proof membrane will be laid beneath the ground floor slab. The office ground floor slab to be designed to take an imposed loading of 15kN/m 2 (300 lbs/ft 2 ) with a surface tolerance and finish appropriate to the specified floor finishes. Paragraph 15 is also relevant to the pleaded duties:- The Defendant also had the following further obligations arising out of or in connection with the Building Contract: (i) There was a term necessarily implied into the Building Contract that the Defendant would carry out and complete the Building Contract Works so that, upon completion, they would be fit for their intended purpose, namely a high quality distribution warehouse complex. (ii) There was a term necessarily implied into the Building Contract that the Defendant would carry out and complete the Building Contract Works in a good and workmanlike manner. (iii) There was a further term necessarily implied into the Building Contract that the Defendant would carry out and complete the Building Contract Works using materials of good quality. (iv) Further, insofar as the Defendant was a specialist carrying out specialist design and/or construction as part of the Building Contract Works, the Defendant owed to its employer a duty of care at common law in the performance of that specialist design and/or construction work. Paragraph 28 is headed The Defects in the Property and so far as relevant provides as follows:- 28. The Property suffers from defects, which may be summarised in this way:

5 ... (iii) The slab in Warehouses 1 and 2 has failed inter alia in the following general respects: (a) In Warehouse 1 there are cracks up to 20mm wide in the floor that run parallel to the main movement (IDC) joints. Mid-bay cracking has appeared in numerous locations, with crack widths of up to 6mm, substantially exceeding the normal width of structural cracks of 0.3mm. There are misplaced dowels at the IDC joints, preventing them opening and closing properly. (b) In Warehouse 2 mid-bay cracking has appeared in some locations, with crack widths of up to 1mm, substantially exceeding the normal width of structural cracks of 0.3mm. The slab is below the design thickness of 150mm (less 15mm tolerance), being only 112mm thick in places. The arrises to the main construction joints have deteriorated to such an extent that the central aisle is unusable, because the IDC joints were not designed to be armoured. At certain locations, particularly in the north-west bay, there is severe cracking and displacement, with a 100mm step in the surface of the slab, attributable to defects in the underlying foundation. It will be apparent from the foregoing that there are two deletions from the original Particulars of Claim. Paragraph 30 deals with Breach and Causation. It reads:- The defects in and damage to the Property described in paragraph 28 above have been caused by the breaches of contract and/or breaches of duty of the Defendant, as more particularly set out below. It is in paragraph 33 that particulars are given of the breaches said to be relevant to Failure of the Slab in Warehouses 1 and 2. That paragraph reads:- 33. The failure of the slab in Warehouses 1 and 2, described in paragraph 28(iii) above, has resulted from poor and/or inadequate workmanship and/or design in respect of the slab and/or in respect of the preparation and/or improvement of the ground underneath the slab and/or a failure to adhere to the Employer s Requirements contained in the Main Contract. In particular: (i) The failure to design the floor to meet the intended use as an industrial warehouse, in particular provision of nonarmoured joints in conjunction with 50m bay sizes, which has resulted in damaged arrises in Warehouses 1 and 2.

6 (ii) The failure to construct to the design intent and in accordance with good practice, in particular the installation of locked IDC joints resulting in wide cracking and areas of the slab that are below the required thickness. (iii) The inadequacy of the ground improvement works in the area underneath the slab in Warehouse 2, which failed to deal with the tendency of the existing sub-base material, given its physical and chemical composition, to cause movement and/or heave which would then adversely impact upon the condition of the slab. (iv) The absence of sawn joints at not less that 9m centres within the slab, which resulted in inadequate provision for expansion and contraction of the slab which, in turn, has resulted in the cracking and other damage evident within the slab in Warehouses 1 and Pausing there, it is apparent that the allegations thus far are of cracking of the concrete slab, damaged arrises, areas which are below the required thickness and movement and/or heave. 8. Paragraph 36 of the pleading seeks to tie in the generalised allegations of breach made in paragraph 33 with the particular terms of the contract said to have been broken by Birse. Paragraph 36 reads:- 36. The defects in, and damage to, the slab in Warehouses 1 and 2 have been caused by the breaches of contract of the Defendant. In particular: (i) The slab in Warehouses 1 and 2 did not comply with sections 2.06 and 2.08 of the Specification within the Employer s Requirements in that the slab was not a reinforced concrete slab designed to BS8110 or was not designed or built in accordance with industry standards such as Concrete Society Technical Report TR34. Further, this was a breach of clauses 2.1, , , , , of the Building Contract and also a breach of the further obligations set out in paragraph 15 above, together with a breach of clauses , and/or of the Defendant s Warranty. (ii) The slab in Warehouses 1 and 2 did not comply with section 2.08 of the Specification with the Employer s Requirements in that the slab did not contain sawn joints at not less than 9m centres. Further, this was a breach of clauses 2.1, , , , , of the Building Contract and also a breach of the further obligations set out in paragraph 15 above, together with a breach of clauses 4.1.1, and/or of the Defendant s Warranty.

7 (iii) The sub-base beneath Warehouses 1 and 2 did not comply with the requirements of TR34 such that, as a result, the slab was of insufficient thickness in places which has, in its turn, led to cracking in the slab; in the alternative, the slab was of insufficient thickness in any event. This was a breach of clauses 2.1, , , , , of the Building Contract and also a breach of the further obligations set out in paragraph 15 above, together with a breach of clauses 4.1.1, and/or of the Defendant s Warranty. (iv) The jointing system used in Warehouses 1 and 2 was not fit for its intended purpose and/or it was not installed correctly, in that the joint was not armoured against normal wear and tear; it was experimental in its design; and was laid with debonded dowels that were not horizontal leading to locking of the joints and cracking in the slab. This was in turn a breach of clauses 2.1, , , , , and/or of the Building Contract; a breach of the further obligations set out in paragraph 15 above; and accordingly a breach of clauses 4.1.1, and of the Defendant s Warranty. 9. In the introductory words to paragraph 36 the reference to defects in the slab is a reference back to paragraph 28(iii) and the reference to damage to the slab is a reference to paragraph 33. I note in particular the reliance upon BS 8110 and Concrete Society Technical Report TR 34, both of which are pleaded at paragraph 13. I draw attention also to the reliance upon clause 2.08 of the Specification pleaded at paragraph 13 as the source of the obligation to provide saw cut joints not less than 9m apart. 10. It is also of importance to have regard to the consequences said to flow from these alleged breaches of contract and/or duty. Paragraphs 41 and 42 read:- Loss and Damage Resulting from Breach 41. As a result of the breaches of contract and/or duty of the Defendant, set out above, the Claimant has suffered loss and damage, namely to the extent that there are very substantial defects in the Property. This means that: (i) A repair scheme addressing all of the defects, together with the material risk of future damage, will need to be designed and constructed at the Property, at very significant expense to the Claimant. (ii) There will be engineering and other professional fees associated with the design and implementation of a repair scheme at the Property.

8 (iii) The Claimant has suffered lost rental in circumstances where, as a result of the defects, the Claimant has been unable to find a commercial tenant. (iv) Further commercial and/or operational losses have been, and continue to be, incurred by the Claimant as a consequence of the defects in the Property. 42 Accordingly, the Claimant is entitled to claim, and claims in these proceedings, damages for breach of contract and/or breach of duty. The Claimant s claim for damages is was set out in a Schedule of Loss and Damage dated 25 November 2011 and a draft Amended Schedule of Loss is to be served on the Parties by Friday 20 July 2012, pursuant to the Court order of 19 June The (unamended) Schedule of 25 November 2011 is a substantial document. Paragraph 63 identifies the remedial works required as follows:- 63. In addition to the general matters described above, the remedial works in the warehouses generally fall within the following categories: (i) Remedial works to cracks in the floor slab: (a) Replacement of sections of the cracked and/or damaged floor slab; and (b) Repair of individual cracks not covered by replacement works. (ii) (a) (b) Remedial works to IDC joints: Replacement of IDC joints; and Repair of IDC joints. The work required is then exhaustively particularised. The cost is put at about 381,000. It is relevant to note that the work allegedly required falls far short of complete replacement of the floor slabs. The proposed re-amendment 12. It is against this background that the proposed re-amendment falls to be examined. It is contained in paragraph 33A. Paragraph 33A is a very long paragraph which it is unnecessary to set out in full. The judge set out at paragraph 35 of his judgment the opening sentences and then summarised the effect of the fifteen sub-paragraphs and I reproduce here that part of his judgment beginning with the quotation from paragraph 33A itself: A In the course of works being carried out, and testing, in connection with the remedial work, the claimant has

9 discovered that the steel fibre content of the concrete used by the defendant for the construction of the internal slab warehouse floor is substantially less than the value that had previously been assumed. The consequence of this finding, which follows from testing, is that all of the internal slab is now understrength and liable to early failure if not replaced, particularly when this finding is considered together with the available evidence on inadequate thickness of the slab in many areas. (It is then pleaded that the foregoing is a breach of specified clauses of the building contract, of implied terms and duty of care, and of specified clauses of the defendant s warranties.) 36. I do not intend to set out the following 15 subparagraphs in full. In summary, the case has (sic) advanced is that: (i) Prior to testing during the course of the remedial works the claimant and its advisers had reasonably assumed that the slabs were designed to be 150 mm thick with a steel fibre content of 30kg/m 3. (ii) However testing revealed that the steel fibre content was significantly less than assumed, with the result that it would not meet the racking leg load requirement found in the Employers Requirements. The structural capacity of the floor is also significantly reduced by reason of the reduced steel fibre content, both by itself and/or coupled with the reduced floor thicknesses found in a number of areas on inspection during the course of the remedial works. (iii) The conclusion, in subparagraph (n) is that there remains a high probability that the floor could fail in service due to undetected thin areas beneath or adjacent to racking legs, irrespective of the fibre content. However, the evidence now available that the fibre content is also low and below what would be needed in a design of compliant 150 mm thickness, is also reason to condemn the floor. To this summary by the judge I would add sub-paragraphs (m) and (n) of the proposed paragraph 33A of the Re-Amended Particulars of Claim which read as follows:- (m) Significantly, the floor has never seen, as far as the Claimant is aware, the intended racking leg load of 70kN, which would require five levels of racking stacked with 1.4t euro-pallets either side of the central frame, back to back. This type of loading was never intended to be used by Woolworths, and the racking was only rated at 50kN leg load. However, these loads could easily happen when a future tenant re-rates the racking at 70kN and stores pallets of paint or other

10 liquids, steel components, stone/cement, or paper ream. Loads from the wheels of heavy-duty high-reach fork-lift trucks would also be much more severe than has been the case previously. (n) There remains a high probability that the floor could fail in service due to undetected thin areas beneath or adjacent to tracking legs, irrespective of the fibre content. However, the evidence now available that the fibre content is also low and below what would be needed in a design of compliant 150mm thickness, is also reason to condemn the floor. 13. I also set out here as relevant paragraphs 37 and 38 of the judge s judgment:- 37. There is no amendment to paragraph 36. However, during the course of the hearing, I suggested to Mr Hughes QC that if, as appeared clear from the content of paragraph 33A, the claimant was contending that the effect of the reduced steel fibre content, whether by itself or in conjunction with the reduced floor thicknesses, rendered the defendant in breach of specific obligations imposed by the Employers Requirements, particularly the obligation appearing in paragraph 2.08, set out in full in paragraph 13, that the slab should be designed to accommodate a pallet racking leg loading requirement of 70 KN/leg, then that would need to be pleaded in terms in paragraph 36. Although Mr Hughes submitted that it was sufficient that paragraph 36 pleaded that the slabs did not comply with paragraph 2.08 of the Employers Requirements, I have to say that I remain of the view that it would be necessary to plead this specific non-compliance expressly in order to allow that claim to be advanced in these proceedings. 38. There was no amendment to paragraphs 41 and 42, other than to refer to the draft amended schedule of loss which was to be served in accordance with the order of 19 June 2012 but which, as I have already identified, has not in fact yet been served. It is common ground nonetheless, as I have also already identified, that if permission is given the amended schedule of Loss will include a claim that it is necessary to take up and replace the existing slabs in both warehouse floors at a very substantial cost, both direct and indirect, by reason of the matter is [sic] sought to be introduced by paragraph 33A. 14. The cost of replacement of the floor slabs in both warehouses has in fact subsequently been quantified at approximately 2.5M, and substantial consequential losses are also asserted. The allegation that the warehouse floors require complete replacement on account of the insufficient steel fibre content, if successful, renders wholly academic the originally pleaded claim for the cost of replacement of specific sections, repair to individual cracks and replacement and repair of IDC joints.

11 15. The judge was I think right to identify that the specific source of the allegation that the concrete floor should have a steel fibre content of 30 kg per cubic metre is paragraph 2.08 of the specification, in that the allegation is that a steel fibre content of that order was required in order to ensure that the floor could accommodate a pallet racking leg load of 70KN. 16. Mr Simon Hughes QC for the Claimant submitted that paragraph 33A is to be regarded as either further particularisation of an existing allegation of breach of contract as set out in paragraphs 28(3), 33 and 36 of the Particulars of Claim or an explanation of a decision to take up the whole slab rather than to repair it what he termed a technical explanation of the failure. 17. I do not regard either of these characterisations of the proposed paragraph 33A as appropriate. The gravamen of the allegation in this paragraph is that the floor has a fundamental design fault in that it is of insufficient strength to withstand a pallet racking leg load of 70KN. This is attributed principally to the shortfall in required steel fibre content, although also to the variable thickness of the concrete which is alleged to be in some places insufficient. What is said is that the floors have not yet been exposed to the maximum design pallet racking leg load of 70KN but were that to occur there would be a high probability that the floors would fail in service in consequence of which it is necessary that they be wholly replaced. Thus paragraph 33A is not concerned with the existing cracking in the floors or its cause. Paragraph 33A is concerned with cracking in the floors which might, indeed so it is said, would probably occur in the event that the floors are exposed to their full warranted design pallet racking leg load. Central to paragraph 33A is the hitherto unpleaded allegation that the steel fibre content of the concrete was less than contractually required. 18. The question for decision is whether paragraph 33A introduces a new cause of action, not previously relied upon in the original action. The law 19. A cause of action is, as Diplock LJ famously observed in Letang v Cooper [1965] 1 QB 232 at 242/3, a factual situation the existence of which entitles one person to obtain from the court a remedy against another person. Longmore LJ in Berezovsky v Abramovich [2011] 1 WLR 2290 at 2309 expressed the concept in essentially the same way: A cause of action is that combination of facts which gives rise to a legal right. 20. In the quest for what constitutes a new cause of action, i.e. a cause of action different from that already asserted, it is the essential factual allegations upon which the original and the proposed new or different claims are reliant which must be compared. Thus the pleading of unnecessary allegations or the addition of further instances or better particulars do not amount to a distinct cause of action see Paragon Finance v Thakerar [1999] 1 All ER 400 at 405 per Millett LJ. So in identifying a new cause of action the bare minimum of essential facts abstracted from the original pleading is to be compared with the minimum as it would be constituted under the amended pleading - see per Robert Walker LJ in Smith v Henniker-Major [2003] Ch 182 at 210.

12 21. The court is therefore concerned with the comparison of the essential factual elements in a cause of action already pleaded with the essential factual elements in the cause of action as proposed see per David Richards J in HMRC v Begum [2010] EWHC 1799 (Ch) at paragraph 32. A change in the essential features of the factual basis (rather than, say, giving further particulars of existing allegations) will introduce a new cause of action ibid, paragraph Where an amendment pleads a duty which differs from that pleaded in the original action, it will usually assert a new cause of action see per Sir Iain Glidewell in Darlington Building Society v O Rourke [1999] PNLR 365 at 370. However as Sir Iain went on to observe, where different facts are alleged to constitute a breach of an already pleaded duty, the courts have had more difficulty in deciding whether a new cause of action is pleaded. Particularly has this been so in construction cases. Thus in Steamship Mutual Underwriting Association v Trollope and Colls [1986] 33 BLR 77 a claim in respect of a defect in brickwork caused by a breach of the self-same duty as had earlier been relied upon to found a claim in respect of air-conditioning pipes in the cavity walls was regarded by the Court of Appeal as a new claim, whereas on apparently indistinguishable facts the Court of Appeal had in Idyll Limited v Dinerman [1971] 1 CLJ 294 regarded claims in respect of the roof as asserting the same cause of action as the original claim founding on the same duty in relation to defects in the brickwork and functions of the building. In the former case May LJ offered the guidance that one must look not only to the duty, but also to the nature and extent of the breach relied upon, as well as to the nature and extent of the damage complained of in deciding whether, as a matter of degree, a new cause of action is sought to be relied upon. The question to be resolved is therefore one of fact and degree. For my part I am not convinced that one needs to look further than for a change in the essential features of the factual basis relied upon, bearing in mind that the factual basis will include the facts out of which the duty is to be spelled as well as those which allegedly give rise to breach and damage. I respectfully agree with Lloyd LJ, as he then was, later Lord Lloyd of Berwick, who observed in the Trollope and Colls case, at page 101, that in most cases it will be easy to say on which side of the line the case falls. But as Lloyd LJ observed, there will sometimes be a grey area, where different views are possible. I would not therefore dissent from the following distillation of the principles by Jackson J, as he then was, in Secretary of State for Transport v Pell Frischmann [2006] EWHC 2909 (TCC) at paragraph 38:- (i) If the claimant asserts a duty which was not previously pleaded and alleges a breach of such duty, this usually amounts to a new claim. (ii) If the claimant alleges a different breach of some previously pleaded duty, it will be a question of fact and degree whether that constitutes a new claim. (iii) In the case of a construction project, if the claimant alleges breach of a previously pleaded duty causing damage to a different element of the building, that will generally amount to a new claim.

13 I would simply add my own gloss to the effect that if the new breach does not arise out of the same or substantially the same facts as those already in issue on a claim previously made in the original action, it is likely to be a new cause of action. A new cause of action? Discussion 23. In my judgment it is very clear on which side of the line the present case falls. As Miss Fiona Sinclair for Birse succinctly submitted, the original allegation here was of a group of relatively disparate defects in the floors capable of disparate replacement and repair. There was no existing case of structural inadequacy of the entirety of the concrete floors in the two warehouses. What is now alleged is that the concrete of which the floors are constructed suffers from a systemic defect which must result in its entire condemnation and replacement because of its inability to withstand the design load to which it has never yet been subjected. The allegation by way of reamendment is in my judgment an allegation of an entirely new and different cause of action. It relies upon a particular and specific facet of the contractual duty owed of which no breach was hitherto asserted, viz the design capability to withstand a pallet racking leg load of 70KN. The relevant specific duties of which breach had hitherto been alleged are the obligation to design to BS8110, to design and build in accordance with Concrete Society Technical Report TR 34 and to comply with that part of the Specification which requires sawn joints at not less than 9m spacing. There is no reference to any of these duties in paragraph 33A because they are irrelevant to the case being there advanced. The new allegation relies upon facts wholly different in kind from those hitherto relied upon, viz, the inadequate steel fibre content. Finally the consequences alleged are, again, wholly different in kind from those hitherto alleged, giving rise to the need to replace the entirety of the two floors and thereby rendering academic the question whether the contractors were, so far as concerns the concrete floors in the warehouses, in breach of duty in the manner hitherto alleged. 24. The judge below directed himself by reference to the appropriate principles but, in my view, failed properly to apply them when it came to the point of decision. Thus at paragraph 43 he asked himself What is the existing claim about?, a question which in my view fails to focus upon the relevant enquiry, which is as to the essential features of the factual basis relied upon. It is I think possible that the judge was led astray by the language used by Millett LJ in Paragon Finance at page 405 where he spoke of making the selection of the material facts to define the cause of action at the highest level of abstraction. I think that Millett LJ meant no more than that one must look to the bare minimum of essential facts, and that these are to be abstracted from the original pleading, as Robert Walker LJ put it in Smith v Henniker-Major. 25. However it was at paragraph 46 of his judgment that the judge, I consider, fell into clear error. He there said this:-... It is clear that this development, like those under consideration in the Steamship Mutual, WDA and Aldi cases, is a substantial and complex structure (or series of structures). My view is that since the existing claim is advancing a claim for damages for breach of contract in relation to design, workmanship and non-compliance with the Employers Requirements which is limited to 3 specified elements of that development, one being the internal warehouse concrete floor

14 slabs, then it follows that further allegations of further defects in those slabs, even though they involve separate and distinct allegations of breach and allegations of loss, are nonetheless part of the same cause of action I cannot agree with the judge that an allegation of a further defect in the slabs arising out of design, workmanship or failure to comply with the contractual requirements must, necessarily, be an assertion of the same cause of action as that upon which reliance has already been placed, simply because breaches in relation to design, workmanship and failure to comply with contractual requirements are already in play. That approach ignores the importance which the judge had earlier recognised of identifying the essential facts upon which reliance is placed. Furthermore the judge s (correct) conclusion that the further allegations involve separate and distinct allegations of breach and separate and distinct allegations of loss is in my view incompatible with his ultimate conclusion that they are part of the same cause of action. It is, rather, indicative that they comprise a new and different cause of action. 27. Thus the judge never asked himself whether as a matter of fact and degree the further allegations assert a new cause of action. Since that question is a question of mixed law and fact, we would not in any event be formally constrained by the judge s conclusion in the same manner as where the court is concerned with an exercise of discretion. As it is however we must simply resolve the question ourselves. I am quite clear, for the reasons which I have given, that paragraph 33A seeks to assert a new cause of action. Arising out of the same or substantially the same facts? 28. Mr Hughes valiantly attempted to persuade us that the judge was wrong to conclude, as he did at paragraphs 51 and 52 of his judgment, that the new claim does not arise out of the same or substantially the same facts as are already in issue in the action. As Robert Walker LJ pointed out in Smith v Henniker-Major at page 210, in applying s.35(5)(a) of the Limitation Act 1980 the court is concerned with all the evidence likely to be adduced at trial. As Hobhouse LJ observed in Lloyds Bank plc v Rogers The Times, 24 March 1997; Court of Appeal (Civil Division) Transcript No 1904 of 1996: The policy of the section is that, if factual issues are in any event going to be litigated between the parties, the parties should be able to rely upon any cause of action which substantially arises from those facts. 29. At paragraph 51 of his judgment, under the sub-heading The same or substantially the same facts, the judge said this:- If I am wrong in my conclusion in relation to the new claim, I consider that the claimant cannot successfully rely in the alternative upon this argument. That is because I do accept the arguments of Ms Sinclair and Mr Cannon QC that to introduce the steel fibre content claim would involve a major investigation, both pre-trial and at trial, into facts and matters which are not on the existing statement of case on the agenda at all for trial. In particular, I accept their submissions that if the steel fibre content claim was allowed to be added, that would involve a major investigation into:

15 (1) The original design for the floor slabs in terms of thickness and steel fibre content. I accept Mr Cannon s submission that notwithstanding the references in the existing Particulars of Claim to isolated areas of floor thickness, there would have been no need to consider the design so far as thickness or steel fibre content on the existing pleading. (2) The extent to which the floor slabs have been constructed using steel fibres with a content below 30kg/m 3, and the consequences of that in terms of the structural adequacy of the floor slabs in the long term. Mr Hughes QC submitted that this would inevitably have been raised at trial, because now that it is known it is a factor which the experts would undoubtedly have wished to raise in order to support or to criticise (as the case may be) the remedial works solution adopted by the claimant. However I do not accept that submission. On the current pleaded case the claim would be limited to damages for the repair costs. There would be no slab replacement claim in play. It follows that there would be no necessity to investigate the structural adequacy of the slabs. Furthermore, even if I was wrong about that, it would be perfectly possible for the claimant s expert to refer to the steel fibre content issue to support the remedial scheme on a technical basis, without it becoming in issue at trial. That is because it would be no different to other cases where a particular remedial scheme is being justified by reference to one factor or series of factors which are said to be the defendant s legal responsibility and others which are not. The court would be concerned with the latter category only as relevant to the question whether the remedial scheme was justified by reference to the matters for which the defendant was liable, which is very different to the enquiry necessary where they are also relied upon as further allegations of breach by the defendant. (3) Whether or not the use of concrete with a steel fibre content of below 30kg/m 3 rendered the defendant in breach of its obligations in relation to design, workmanship or the Employers Requirements, including an investigation into whether or not it meant that the specified rack loading requirement could not be guaranteed, and the consequences of that upon the lettability of the unit. (4) The nature and extent of the proposed remedial scheme to address this particular problem, i.e. complete replacement, and its justification on cost and other grounds. The costs incurred. Whether or not the claimant could also claim what would not appear to be the wasted costs already incurred in undertaking the more limited remedial works previously identified.

16 30. I agree with the judge s analysis and with his conclusion at paragraph 52 that It cannot be said that the steel fibre content claim arises out of the same or substantially the same facts. Costs 31. Mr Hughes had an outstanding application for permission to appeal against the judge s costs order below, contending that an award to the Claimant of its costs of the application to amend only in the case as opposed to in any event was insufficiently generous and contrary to the modern approach. I have some sympathy with this argument but in the event the proposed cross-appeal on costs does not arise. 32. Accordingly I would allow the appeal and disallow the proposed Paragraph 33A of the Re-Amended Particulars of Claim. I would invite counsel to agree how best the judge s complex order of 1 November 2012 should be amended in order to reflect the outcome of the appeal. Lord Justice Rimer: 33. I agree. Lord Justice Longmore: 34. I agree also.

(b) The test is that for summary judgment under CPR Part 24.

(b) The test is that for summary judgment under CPR Part 24. Late amendments and amendments after the expiry of the limitation period Whether a party obtains permission to amend can make or break a case. Litigants seeking to amend very late and/or after the expiry

More information

LOWIN. and W PORTSMOUTH & CO. JUDGMENT (As Approved)

LOWIN. and W PORTSMOUTH & CO. JUDGMENT (As Approved) [2016] EWHC 2301 (QB) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION Case No: QB/2016/0049 The Royal Courts of Justice Strand London WC2A 2LL Monday, 20 June 2016 BEFORE: MRS JUSTICE ELISABETH LAING

More information

B e f o r e: MR JUSTICE OUSELEY. SECRETARY OF STATE FOR COMMUNITIES AND LOCAL GOVERNMENT Defendant

B e f o r e: MR JUSTICE OUSELEY. SECRETARY OF STATE FOR COMMUNITIES AND LOCAL GOVERNMENT Defendant Neutral Citation Number: [2015] EWHC 488 (Admin) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION THE ADMINISTRATIVE COURT CO/4082/2014 Royal Courts of Justice Strand London WC2A 2LL Friday, 6 February

More information

Before : LADY JUSTICE ARDEN LORD JUSTICE LEWISON LADY JUSTICE ASPLIN Between :

Before : LADY JUSTICE ARDEN LORD JUSTICE LEWISON LADY JUSTICE ASPLIN Between : Neutral Citation Number: [2018] EWCA Civ 62 Case No: A3/2017/2781 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE HIGH COURT OF JUSTICE, COMMERCIAL COURT Mr Richard Salter QC sitting as a Deputy

More information

White Young Green Consulting v Brooke House Sixth Form College [2007] APP.L.R. 05/22

White Young Green Consulting v Brooke House Sixth Form College [2007] APP.L.R. 05/22 JUDGMENT : Mr Justice Ramsey : TCC. 22 nd May 2007 Introduction 1. This is an application for leave to appeal under s.69(3) of the Arbitration Act 1996. The arbitration concerns the appointment of the

More information

TERMS AND CONDITIONS OF SALES

TERMS AND CONDITIONS OF SALES 1. Acceptance No Contract, Order or information (literature, drawings etc.) provided to or by the Purchaser shall be binding on Infra Green Ltd unless confirmed in the Infra Green Ltd Order Confirmation.

More information

RECENT DEVELOPMENTS CONCERNING THE LIABILITY OF BUILDING PROFESSIONALS IN NSW

RECENT DEVELOPMENTS CONCERNING THE LIABILITY OF BUILDING PROFESSIONALS IN NSW RECENT DEVELOPMENTS CONCERNING THE LIABILITY OF BUILDING PROFESSIONALS IN NSW Paper given by Brian Walton to the Annual Conference of the Australian Institute of Building Surveyors 21 22 July 2014 Introduction

More information

B e f o r e: THE LORD CHIEF JUSTICE OF ENGLAND AND WALES (The Lord Woolf of Barnes) LORD JUSTICE WALLER and LORD JUSTICE LAWS

B e f o r e: THE LORD CHIEF JUSTICE OF ENGLAND AND WALES (The Lord Woolf of Barnes) LORD JUSTICE WALLER and LORD JUSTICE LAWS Neutral Citation Number: [2002] EWCA Civ 879 IN THE SUPREME COURT OF JUDICATURE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION (HIS HONOUR JUDGE BRADBURY)

More information

Before : THE HONOURABLE MR JUSTICE SUPPERSTONE Between :

Before : THE HONOURABLE MR JUSTICE SUPPERSTONE Between : Neutral Citation Number: [2015] EWHC 1483 (Admin) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION ADMINISTRATIVE COURT Case No: CO/17339/2013 Royal Courts of Justice Strand, London, WC2A 2LL Date:

More information

The material in this paper is based upon the law of England and Wales.

The material in this paper is based upon the law of England and Wales. DESIGN LIABILITY: REASONABLE SKILL AND CARE OR FITNESS FOR PURPOSE May 2016 ADAM ROBB The material in this paper is based upon the law of England and Wales. This material is only intended to provoke and

More information

Neutral Citation Number: [2009] EWHC 2452 (QB) IN THE HIGH COURT OF JUSTICE QUEEN S BENCH DIVISION Royal Courts of Justice Strand London WC2A 2LL

Neutral Citation Number: [2009] EWHC 2452 (QB) IN THE HIGH COURT OF JUSTICE QUEEN S BENCH DIVISION Royal Courts of Justice Strand London WC2A 2LL Case No: HQ09XO3460 & IHQ09/1716 Neutral Citation Number: [2009] EWHC 2452 (QB) IN THE HIGH COURT OF JUSTICE QUEEN S BENCH DIVISION Royal Courts of Justice Strand London WC2A 2LL Wednesday, 26 August 2009

More information

Galliford Try Construction Ltd v Mott MacDonald Ltd [2008] APP.L.R. 03/14

Galliford Try Construction Ltd v Mott MacDonald Ltd [2008] APP.L.R. 03/14 JUDGMENT : Mr Justice Coulson : TCC. 14 th March 2008 Introduction 1. This is an application by the Defendant for an order that paragraphs 39 to 48 inclusive of the witness statement of Mr Joseph Martin,

More information

Before: NEIL CAMERON QC Sitting as a Deputy High Court Judge. Between:

Before: NEIL CAMERON QC Sitting as a Deputy High Court Judge. Between: Neutral Citation Number: [2016] EWHC 2647 (Admin) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION ADMINISTRATIVE COURT Case No: CO/2272/2016 Royal Courts of Justice Strand, London, WC2A 2LL Date: 28/10/2016

More information

Nick Consulting Architecture Ltd TERMS AND CONDITIONS OF QUOTATION / SALES

Nick Consulting Architecture Ltd TERMS AND CONDITIONS OF QUOTATION / SALES Nick Consulting Architecture Ltd TERMS AND CONDITIONS OF QUOTATION / SALES 1. DEFINITIONS Agreement means the agreement between NCA and the Customer for the supply of Goods pursuant to an application made

More information

Ahmad Al-Naimi (t/a Buildmaster Construction Services) v. Islamic Press Agency Inc [2000] APP.L.R. 01/28

Ahmad Al-Naimi (t/a Buildmaster Construction Services) v. Islamic Press Agency Inc [2000] APP.L.R. 01/28 CA on Appeal from High Court of Justice TCC (HHJ Bowsher QC) before Waller LJ; Chadwick LJ. 28 th January 2000. JUDGMENT : Lord Justice Waller: 1. This is an appeal from the decision of His Honour Judge

More information

IN THE COURT OF APPEAL THE ROMAN CATHOLIC BISHOP OF GRENADA AND RANDOLPH CAPE : July 1... JUDGMENT

IN THE COURT OF APPEAL THE ROMAN CATHOLIC BISHOP OF GRENADA AND RANDOLPH CAPE : July 1... JUDGMENT GRENADA CIVIL APPEAL NO 8 OF 2002 BETWEEN: IN THE COURT OF APPEAL THE ROMAN CATHOLIC BISHOP OF GRENADA AND RANDOLPH CAPE Appellant Respondent Before: The Honourable Sir Dennis Byron The Honourable Mr Albert

More information

B e f o r e: LORD JUSTICE JACKSON LORD JUSTICE LINDBLOM. BRADFORD TEACHING HOSPITALS NHS FOUNDATION TRUST Respondent

B e f o r e: LORD JUSTICE JACKSON LORD JUSTICE LINDBLOM. BRADFORD TEACHING HOSPITALS NHS FOUNDATION TRUST Respondent Neutral Citation Number: [2016] EWCA Civ 1001 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION (HIS HONOUR JUDGE GOSNELL) A2/2015/0840 Royal Courts

More information

ENFRANCHISEMENT OF MIXED USE PREMISES

ENFRANCHISEMENT OF MIXED USE PREMISES ENFRANCHISEMENT OF MIXED USE PREMISES WHICH MIXED USE BUILDINGS ARE HOUSES Is the Property a house? 1. For the purposes of the 1967 Act a house is defined by s2 as follows, so far as relevant (1) For the

More information

Before : SIR GEORGE NEWMAN (sitting as a Deputy High Court Judge) Between :

Before : SIR GEORGE NEWMAN (sitting as a Deputy High Court Judge) Between : Neutral Citation Number: [2008] EWHC 3046 (Admin) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION ADMINISTRATIVE COURT Case No: CO/3755/2007 Royal Courts of Justice Strand, London, WC2A 2LL Date: 10

More information

Before: HIS HONOUR JUDGE PLATTS Between: - and -

Before: HIS HONOUR JUDGE PLATTS Between: - and - IN THE COUNTY COURT AT MANCHESTER Case No: D75YX571 Justice Centre 1 Bridge Street West Manchester M60 9DJ Date: Start Time: 12.42 Finish Time: 13.16 Page Count: 6 Word Count: 2629 Number of Folios: 37

More information

JUDGMENT. In the matter of an application by Hugh Jordan for Judicial Review (Northern Ireland)

JUDGMENT. In the matter of an application by Hugh Jordan for Judicial Review (Northern Ireland) Hilary Term [2019] UKSC 9 On appeal from: [2015] NICA 66 JUDGMENT In the matter of an application by Hugh Jordan for Judicial Review (Northern Ireland) before Lady Hale, President Lord Reed, Deputy President

More information

Before : MR JUSTICE KNOWLES CBE Between : (1) C1 (2) C2 (3) C3. - and

Before : MR JUSTICE KNOWLES CBE Between : (1) C1 (2) C2 (3) C3. - and Neutral Citation Number: [2016] EWHC 1893 (Comm) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION COMMERCIAL COURT Case No: CL-2015-000762 Royal Courts of Justice Strand, London, WC2A 2LL Date: 29/07/2016

More information

Construction Warranties

Construction Warranties Construction Warranties Jon W. Gilchrist Payne & Jones, Chartered Sealant, Waterproofing & Restoration Institute Fall Technical Meeting September 2006 Montreal Definition: What is a warranty? warranty?

More information

COGNE UK LTD of Uniformity Steel Works, Don Road, Sheffield, S9 2UD General Conditions of Contract

COGNE UK LTD of Uniformity Steel Works, Don Road, Sheffield, S9 2UD General Conditions of Contract COGNE UK LTD of Uniformity Steel Works, Don Road, Sheffield, S9 2UD General Conditions of Contract THE CONDITIONS BELOW EXCLUDE OR LIMIT OUR LIABILITY, FOR US TO INSURE AGAINST UNLIMITED LIABILITY WOULD

More information

Before: MR JUSTICE EDWARDS-STUART Between:

Before: MR JUSTICE EDWARDS-STUART Between: Neutral Citation Number: [2011] EWHC 3313 (Admin) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION ADMINISTRATIVE COURT Case No: CO/7435/2011 Royal Courts of Justice Strand, London, WC2A 2LL Date: 13/12/2011

More information

Before : LORD JUSTICE MCFARLANE LORD JUSTICE BRIGGS and LORD JUSTICE FLAUX Between :

Before : LORD JUSTICE MCFARLANE LORD JUSTICE BRIGGS and LORD JUSTICE FLAUX Between : Neutral Citation Number: [2017] EWCA Civ 355 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM CARDIFF CIVIL AND FAMILY JUSTICE CENTRE District Judge T M Phillips b44ym322 Before : Case No: A2/2016/1422

More information

Sufficiency of information to establish code compliance of a floor slab for a proposed dwelling at lot 26 Anchorage Drive, Karaka Lakes, Papakura

Sufficiency of information to establish code compliance of a floor slab for a proposed dwelling at lot 26 Anchorage Drive, Karaka Lakes, Papakura Determination 2010/132 Sufficiency of information to establish code compliance of a floor slab for a proposed dwelling at lot 26 Anchorage Drive, Karaka Lakes, Papakura 1. The matters to be determined

More information

Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business.

Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business. Geldbach UK Ltd The customer's attention is drawn in particular to the provisions of clause 9. 1. INTERPRETATION 1.1 Definitions. In these Conditions, the following definitions apply: Business Day: a day

More information

Before : MR EDWARD PEPPERALL QC SITTING AS A DEPUTY HIGH COURT JUDGE Between : ABDULRAHMAN MOHAMMED Claimant

Before : MR EDWARD PEPPERALL QC SITTING AS A DEPUTY HIGH COURT JUDGE Between : ABDULRAHMAN MOHAMMED Claimant Neutral Citation: [2017] EWHC 3051 (QB) Case No: HQ16X01806 IN THE HIGH COURT OF JUSTICE QUEEN S BENCH DIVISION Before : MR EDWARD PEPPERALL QC SITTING AS A DEPUTY HIGH COURT JUDGE - - - - - - - - - -

More information

Amendments to Statements of Case Learning the Hard Way: PJSC Tatneft v Bogolyubov and others [2016] EWHC 2816 (Comm)

Amendments to Statements of Case Learning the Hard Way: PJSC Tatneft v Bogolyubov and others [2016] EWHC 2816 (Comm) Amendments to Statements of Case Learning the Hard Way: PJSC Tatneft v Bogolyubov and others [2016] EWHC 2816 (Comm) Simon P. Camilleri * Associate, Fried, Frank, Harris, Shriver & Jacobson (London) LLP,

More information

Before: MR A WILLIAMSON QC (sitting as a Deputy High Court Judge) Between :

Before: MR A WILLIAMSON QC (sitting as a Deputy High Court Judge) Between : Neutral Citation Number: [2017] EWHC 1353 (TCC) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION TECHNOLOGY AND CONSTRUCTION COURT Case No: HT-2017-000042 Royal Courts of Justice Strand, London, WC2A

More information

CARBON LINK LTD T/A CPL ACTIVATED CARBONS: CONDITIONS OF SALE

CARBON LINK LTD T/A CPL ACTIVATED CARBONS: CONDITIONS OF SALE CARBON LINK LTD T/A CPL ACTIVATED CARBONS: CONDITIONS OF SALE 1. GENERAL In these conditions the company means Carbon Link Ltd, trading as CPL Activated Carbons and the customer means the person or company

More information

Before: MRS JUSTICE O'FARRELL DBE Between:

Before: MRS JUSTICE O'FARRELL DBE Between: Neutral Citation Number: [2017] EWHC 2395 (TCC) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION TECHNOLOGY AND CONSTRUCTION COURT Case No: HT-2017-000173 Royal Courts of Justice Strand, London, WC2A

More information

Case Nos: QB/2013/0589 IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION ON APPEAL FROM THE CENTRAL LONDON COUNTY COURT HHJ BAILEY.

Case Nos: QB/2013/0589 IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION ON APPEAL FROM THE CENTRAL LONDON COUNTY COURT HHJ BAILEY. Neutral Citation Number: [2014] EWHC 1219 (QB) Case Nos: QB/2013/0589 IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION ON APPEAL FROM THE CENTRAL LONDON COUNTY COURT HHJ BAILEY Before: MR JUSTICE AKENHEAD

More information

IN THE HIGH COURT OF JUSTICE DENISE VIOLET STEVENS

IN THE HIGH COURT OF JUSTICE DENISE VIOLET STEVENS THE EASTERN CARIBBEAN SUPREME COURT SAINT CHRISTOPHER AND NEVIS IN THE HIGH COURT OF JUSTICE CLAIM NO. SKBHCV2013/0069 BETWEEN: DENISE VIOLET STEVENS and Claimant LUXURY HOTELS INTERNATIONAL MANAGEMENT

More information

Before: LORD JUSTICE BRIGGS and LORD JUSTICE SALES Between:

Before: LORD JUSTICE BRIGGS and LORD JUSTICE SALES Between: Neutral Citation Number: [2016] EWCA Civ 1260 Case No: C1/2016/0625 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE HIGH COURT (QUEEN S BENCH) THE HON. MR JUSTICE JAY CO33722015 Royal Courts

More information

Friday, 18th July 2003

Friday, 18th July 2003 Neutral Citation Number: [2003] EWCA Civ 1651 IN THE SUPREME COURT OF JUDICATURE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION MANCHESTER DISTRICT REGISTRY

More information

Consumer Protection Act 1987 recent cases on causation

Consumer Protection Act 1987 recent cases on causation Consumer Protection Act 1987 recent cases on causation There have been several recent judgments in relation to cases pursued under the Consumer Protection Act 1987 ( CPA ) which provide helpful guidance

More information

B e f o r e: LORD JUSTICE LEWISON LORD JUSTICE FLOYD

B e f o r e: LORD JUSTICE LEWISON LORD JUSTICE FLOYD A2/2014/1626 Neutral Citation Number: [2015] EWCA Civ 984 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE MANCHESTER DISTRICT REGISTRY QUEEN'S BENCH DIVISION (HIS HONOUR JUDGE ARMITAGE QC) Royal

More information

Skanska Rashleigh Weatherfoil Ltd v Somerfield Stores Ltd [2006] ABC.L.R. 11/22

Skanska Rashleigh Weatherfoil Ltd v Somerfield Stores Ltd [2006] ABC.L.R. 11/22 CA on appeal from QBD (Mr Justice Ramsey) before Neuberger LJ; Richards LJ; Leveson LJ. 22 nd November 2006 LORD JUSTICE NEUBERGER: 1. This is an appeal from the decision of Ramsey J on the preliminary

More information

Before: LORD JUSTICE CARNWATH LORD JUSTICE LLOYD and LORD JUSTICE SULLIVAN Between:

Before: LORD JUSTICE CARNWATH LORD JUSTICE LLOYD and LORD JUSTICE SULLIVAN Between: Neutral Citation Number: [2011] EWCA Civ 1606 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE UPPER TRIBUNAL (ADMINISTRATIVE APPEALS CHAMBER) JUDGE EDWARD JACOBS GIA/2098/2010 Before: Case No:

More information

Before: HIS HONOUR JUDGE PELLING QC SITTING AS A JUDGE OF THE HIGH COURT Between:

Before: HIS HONOUR JUDGE PELLING QC SITTING AS A JUDGE OF THE HIGH COURT Between: Neutral Citation Number: [2017] EWHC 2146 (Ch) IN THE HIGH COURT OF JUSTICE CHANCERY DIVISION MANCHESTER DISTRICT REGISTRY Case No: C31MA092 Civil Justice Centre 1 Bridge street West Manchester M60 9DJ

More information

1. The matter to be determined

1. The matter to be determined Determination 2014/064 Regarding the authority s exercise of its powers of decision in requiring a Record of Work for tanking as Restricted Building Work for a building consent at 7 Marsh Way, Kaiwharawhara,

More information

The Contractor s building defects liability in England and Wales

The Contractor s building defects liability in England and Wales The Contractor s building defects liability in England and Wales We discuss in this paper in what circumstances can a contractor be found liable for defects discovered by the building occupier several

More information

B e f o r e: MR JUSTICE BURTON. Between: THE QUEEN ON THE APPLICATION OF ASSOCIATION FOR INDIVIDUAL AND GROUP PSYCHOTHERAPY & OTHERS Claimant

B e f o r e: MR JUSTICE BURTON. Between: THE QUEEN ON THE APPLICATION OF ASSOCIATION FOR INDIVIDUAL AND GROUP PSYCHOTHERAPY & OTHERS Claimant Neutral Citation Number: [2010] EWHC 3702 (Admin) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION THE ADMINISTRATIVE COURT CO/3229/10 Royal Courts of Justice Strand London WC2A 2LL Friday, 10th December

More information

Before : LADY JUSTICE ARDEN and LORD JUSTICE BRIGGS Between : - and -

Before : LADY JUSTICE ARDEN and LORD JUSTICE BRIGGS Between : - and - Neutral Citation Number: [2016] EWCA Civ 1034 Case No: B5/2016/0387 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM Civil and Family Justice Centre His Honour Judge N Bidder QC 3CF00338 Royal Courts

More information

Before: MR JUSTICE AKENHEAD Between:

Before: MR JUSTICE AKENHEAD Between: IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION TECHNOLOGY AND CONSTRUCTION COURT [2014] EWHC 3491 (TCC) Case No: HT-14-295 Royal Courts of Justice Strand, London, WC2A 2LL Date: 24 th October 2014

More information

Before : LORD JUSTICE LONGMORE LORD JUSTICE BEATSON and LORD JUSTICE DAVID RICHARDS Between:

Before : LORD JUSTICE LONGMORE LORD JUSTICE BEATSON and LORD JUSTICE DAVID RICHARDS Between: Neutral Citation Number: [2017] EWCA Civ 1131 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE HIGH COURT OF JUSTICE QUEEN S BENCH DIVISION COMMERCIAL COURT MR JUSTICE ANDREW BAKER Case No: A3/2017/0190

More information

Case No: B3/2015/0832 & 1137 & 1168 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM LIVERPOOL CIVIL AND FAMILY COURT 3YK54788.

Case No: B3/2015/0832 & 1137 & 1168 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM LIVERPOOL CIVIL AND FAMILY COURT 3YK54788. Neutral Citation Number: [2018] EWCA Civ 72 Case No: B3/2015/0832 & 1137 & 1168 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM LIVERPOOL CIVIL AND FAMILY COURT 3YK54788 Royal Courts of Justice

More information

Before: LORD JUSTICE THORPE LORD JUSTICE LLOYD and LORD JUSTICE PATTEN Between: KOTECHA

Before: LORD JUSTICE THORPE LORD JUSTICE LLOYD and LORD JUSTICE PATTEN Between: KOTECHA Neutral Citation Number: [2011] EWCA Civ 105 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM LEICESTER COUNTY COURT (HER HONOUR JUDGE HAMPTON) Case No: B2/2010/0231 Royal Courts of Justice Strand,

More information

Before:

Before: Neutral Citation Number: [2017] EWCA Civ 1054 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE HIGH COURT QUEEN S BENCH DIVISION COMMERCIAL COURT THE HONOURABLE MR JUSTICE MANN Case No: A3/2017/1597

More information

Terms and Conditions of the Supply of Goods

Terms and Conditions of the Supply of Goods Terms and Conditions of the Supply of Goods 1. INTERPRETATION 1.1 Definitions. Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business. Conditions:

More information

Before: HIS HONOUR JUDGE WULWIK Between: - and -

Before: HIS HONOUR JUDGE WULWIK Between: - and - IN THE COUNTY COURT AT CENTRAL LONDON Case No: B 90 YJ 688 Thomas More Building Royal Courts of Justice Strand, London, WC2A 2LL Date: 13/12/2018 Start Time: 14:09 Finish Time: 14:49 Page Count: 12 Word

More information

Before : LORD JUSTICE MUMMERY LORD JUSTICE LONGMORE and MR JUSTICE LEWISON Between :

Before : LORD JUSTICE MUMMERY LORD JUSTICE LONGMORE and MR JUSTICE LEWISON Between : Case No: A2/2005/1312 Neutral Citation Number: [2006] EWCA Civ 102 IN THE SUPREME COURT OF JUDICATURE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE EMPLOYMENT APPEAL TRIBUNAL HIS HONOUR JUDGE D SEROTA

More information

SUPPLY AGREEMENT TERMS AND CONDITIONS OF PURCHASE (INFLIGHT SERVICES) SELLER IS ADVISED TO READ THESE TERMS & CONDITIONS CAREFULLY

SUPPLY AGREEMENT TERMS AND CONDITIONS OF PURCHASE (INFLIGHT SERVICES) SELLER IS ADVISED TO READ THESE TERMS & CONDITIONS CAREFULLY SUPPLY AGREEMENT TERMS AND CONDITIONS OF PURCHASE (INFLIGHT SERVICES) SELLER IS ADVISED TO READ THESE TERMS & CONDITIONS CAREFULLY THIS SUPPLY AGREEMENT (the Agreement ) is made on the applicable dates

More information

Cuthbert v Gair (t/a The Bowes Manor Equestrian Centre) [2008] APP.L.R. 09/03

Cuthbert v Gair (t/a The Bowes Manor Equestrian Centre) [2008] APP.L.R. 09/03 JUDGMENT : Master Haworth : Costs Court. 3 rd September 2008 1. This is an appeal pursuant to CPR Rule 47.20 from a decision of Costs Officer Martin in relation to a detailed assessment which took place

More information

Before : MR JUSTICE LEGGATT Between : LONDON BOROUGH OF RICHMOND UPON THAMES. - and

Before : MR JUSTICE LEGGATT Between : LONDON BOROUGH OF RICHMOND UPON THAMES. - and Neutral Citation Number: [2012] EWCA Civ 3292 (QB) Case No: QB/2012/0301 IN THE COURT OF APPEAL (QUEEN S BENCH DIVISION) ON APPEAL FROM THE KINGSTON COUNTY COURT HER HONOUR JUDGE JAKENS 2KT00203 Royal

More information

B e f o r e: LORD JUSTICE FLOYD EUROPEAN HERITAGE LIMITED

B e f o r e: LORD JUSTICE FLOYD EUROPEAN HERITAGE LIMITED Neutral Citation Number: [2014] EWCA Civ 238 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION B2/2012/0611 Royal Courts of Justice Strand,London WC2A

More information

BUILDING AGREEMENT. Between

BUILDING AGREEMENT. Between BUILDING AGREEMENT Between BRICK N BOARD PROPERTY DEVELOPERS (PTY) LTD Registration/ID Number: 2007/027222/07 ( Contractor ) And Registration/ID Number: ( Employer ) Stage Phase Erf No. 1 House Type COVERING

More information

IN THE SOUTHEND COUNTY COURT CASE NO 0BQ IRVING BENJAMIN GRAHAM. SAND MARTIN HEIGHTS RESIDENTS COMPANY LIMITED Respondent JUDGMENT

IN THE SOUTHEND COUNTY COURT CASE NO 0BQ IRVING BENJAMIN GRAHAM. SAND MARTIN HEIGHTS RESIDENTS COMPANY LIMITED Respondent JUDGMENT IN THE SOUTHEND COUNTY COURT CASE NO 0BQ 12347 HHJ MOLONEY QC BETWEEN IRVING BENJAMIN GRAHAM Appellant And SAND MARTIN HEIGHTS RESIDENTS COMPANY LIMITED Respondent JUDGMENT [handed down at Southend Crown

More information

Neutral Citation Number: [2017] EWCA Civ 1711

Neutral Citation Number: [2017] EWCA Civ 1711 Neutral Citation Number: [2017] EWCA Civ 1711 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM LIVERPOOL COUNTY COURT MR GARSIDE QC A07LV01 Before : Case No: B3/2016/2244 Royal Courts of Justice

More information

CONDITIONS OF SALE DEFINITIONS

CONDITIONS OF SALE DEFINITIONS CONDITIONS OF SALE 1. DEFINITIONS In these Terms and Conditions (the Conditions ), the following words shall have the following meanings:- "Company" shall mean Marshalls Mono Limited or any member of the

More information

B e f o r e: LORD JUSTICE STAUGHTON LORD JUSTICE ALDOUS SIR JOHN MAY B E T W E E N : GEORGE SAVVA AMALIA SAVVA Plaintiff/Appellant.

B e f o r e: LORD JUSTICE STAUGHTON LORD JUSTICE ALDOUS SIR JOHN MAY B E T W E E N : GEORGE SAVVA AMALIA SAVVA Plaintiff/Appellant. Neutral Citation Number: [2000] EWCA Civ 1295 IN THE SUPREME COURT OF JUDICATURE IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM CENTRAL LONDON COUNTY COURT (JUDGE COTRAN) CCRTF 95/0298/H Royal

More information

TERMS AND CONDITIONS OF BUSINESS- SALES OF GOODS & SERVICES. The buyer's attention is in particular drawn to the provisions of condition 10.4.

TERMS AND CONDITIONS OF BUSINESS- SALES OF GOODS & SERVICES. The buyer's attention is in particular drawn to the provisions of condition 10.4. TERMS AND CONDITIONS OF BUSINESS- SALES OF GOODS & SERVICES. The buyer's attention is in particular drawn to the provisions of condition 10.4. 1. INTERPRETATION 1.1 The definitions and rules of interpretation

More information

Determination regarding a dispute about a house built by one shareholder of a jointly owned block of Maori land at 41 Rarapua Place, Te Puna, Tauranga

Determination regarding a dispute about a house built by one shareholder of a jointly owned block of Maori land at 41 Rarapua Place, Te Puna, Tauranga Determination 2009/115 Determination regarding a dispute about a house built by one shareholder of a jointly owned block of Maori land at 41 Rarapua Place, Te Puna, Tauranga 1. The matters to be determined

More information

Company Policies CHEMIDOSE LIMITED. Chemical dosing specialists

Company Policies CHEMIDOSE LIMITED. Chemical dosing specialists Company Policies CHEMIDOSE LIMITED Chemical dosing specialists Unit 1 Centre 2000 St.Michael s Road Sittingbourne Kent ME10 3DZ Tel:01795 425169 www.chemidose.co.uk Chemidose Policies, Terms and Conditions

More information

- and - Judgment Judgment date: 3 April 2018 Transcribed from 15:18:09 until 15:55:42. Reporting Restrictions Applied: No

- and - Judgment Judgment date: 3 April 2018 Transcribed from 15:18:09 until 15:55:42. Reporting Restrictions Applied: No Case No: D70CF001 IN THE CARDIFF CIVIL AND FAMILY JUSTICE CENTRE 2 Park Street Cardiff CF10 1ET BEFORE: HIS HONOUR JUDGE MILWYN JARMAN QC BETWEEN: ZULFKAR AHMED - and - MRS MAUREEN PARSONS APPLICANT RESPONDENT

More information

The Civil Procedure (Amendment) Rules 2013

The Civil Procedure (Amendment) Rules 2013 STATUTORY INSTRUMENTS 2013 No. 262 (L. 1) SENIOR COURTS OF ENGLAND AND WALES COUNTY COURTS, ENGLAND AND WALES The Civil Procedure (Amendment) Rules 2013 Made - - - - 31st January 2013 Laid before Parliament

More information

Before MASTER OF THE ROLLS LORD JUSTICE FLOYD LORD JUSTICE SIMON. Between: ENGEHAM. - and - LONDON & QUADRANT HOUSING TRUST

Before MASTER OF THE ROLLS LORD JUSTICE FLOYD LORD JUSTICE SIMON. Between: ENGEHAM. - and - LONDON & QUADRANT HOUSING TRUST Case No: A2/2014/3086 Neutral Citation Number: [2015] EWCA Civ 1530 IN THE COURT OF APPEAL ON APPEAL FROM THE CENTRAL LONDON COUNTY COURT (His Honour Judge Mitchell) Royal Courts of Justice Strand London,

More information

Before: SIR RAYMOND JACK. - and -

Before: SIR RAYMOND JACK. - and - IN THE HIGH COURT OF JUSTICE QUEEN S BENCH DIVISION [2013] EWHC 759 (QB) No.QB/2013/0057 Royal Courts of Justice Wednesday, 27 th March 2013 Before: SIR RAYMOND JACK B E T W E E N : BAKER TILLY (a firm)

More information

Before: THE HON. MR JUSTICE CRANSTON Between:

Before: THE HON. MR JUSTICE CRANSTON Between: Neutral Citation Number: [2015] EWHC 287 (Admin) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION ADMINISTRATIVE COURT Case No: CO/2263/2014 Royal Courts of Justice Strand, London, WC2A 2LL Date: 12/02/2015

More information

IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE UPPER TRIBUNAL (IMMIGRATION AND ASYLUM CHAMBER) McCloskey J and UT Judge Lindsley.

IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE UPPER TRIBUNAL (IMMIGRATION AND ASYLUM CHAMBER) McCloskey J and UT Judge Lindsley. Neutral Citation Number: [2018] EWCA Civ 5 C2/2015/3947 & C2/2015/3948 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE UPPER TRIBUNAL (IMMIGRATION AND ASYLUM CHAMBER) McCloskey J and UT Judge

More information

Version 3.0 December Self-Lay Agreement. for services connecting to our existing network. Scheme Location Reference Date

Version 3.0 December Self-Lay Agreement. for services connecting to our existing network. Scheme Location Reference Date Version 3.0 December 2017 Self-Lay Agreement for services connecting to our existing network Scheme Location Reference Date THIS AGREEMENT is made the day of 20 (note this date to be completed by Thames

More information

Before : MR JUSTICE PETER SMITH Between :

Before : MR JUSTICE PETER SMITH Between : Neutral Citation Number: [2010] EWHC 1023 (Ch) IN THE HIGH COURT OF JUSTICE CHANCERY DIVISION Case No: HC09CO1648 Royal Courts of Justice Strand, London, WC2A 2LL Date: 11/05/2010 Before : MR JUSTICE PETER

More information

THE COURTS ACT. Rules made by the Chief Justice, after consultation with the Rules Committee and the Judges, under section 198 of the Courts Act

THE COURTS ACT. Rules made by the Chief Justice, after consultation with the Rules Committee and the Judges, under section 198 of the Courts Act THE COURTS ACT Rules made by the Chief Justice, after consultation with the Rules Committee and the Judges, under section 198 of the Courts Act 1. Title These rules may be cited as the Supreme Court (International

More information

General Terms and Conditions of Sale and Delivery of ECKART GmbH

General Terms and Conditions of Sale and Delivery of ECKART GmbH General Terms and Conditions of Sale and Delivery of ECKART GmbH (September 2010) 1. GENERAL 1.1 These General Terms and Conditions of Sale and Delivery (hereinafter called General Sales and Delivery Conditions

More information

Before : DAVID CASEMENT QC (Sitting as a Deputy High Court Judge) Between :

Before : DAVID CASEMENT QC (Sitting as a Deputy High Court Judge) Between : Neutral Citation Number: [2015] EWHC 7 (Admin) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION ADMINISTRATIVE COURT Case No: CO/5130/2012 Royal Courts of Justice Strand, London, WC2A 2LL Date: 09/01/2015

More information

Multiplex Constructions (UK) Ltd v Mott Macdonald Ltd [2007] Adj.L.R. 01/10

Multiplex Constructions (UK) Ltd v Mott Macdonald Ltd [2007] Adj.L.R. 01/10 JUDGMENT: MR JUSTICE JACKSON: TCC. 10 th January 2007. 1. This judgment is in six parts, namely Part 1 Introduction; Part 2 The Facts; Part 3 The Present Proceedings; Part 4 The Adjudicator's Jurisdiction;

More information

Frank Cowl & Ors v Plymouth City Council

Frank Cowl & Ors v Plymouth City Council Neutral Citation Number: [2001] EWCA Civ 1935 2001 WL 1535414 Frank Cowl & Ors v Plymouth City Council 2001/2067 Court of Appeal (Civil Division) 14 December 2001 Before: The Lord Chief Justice of England

More information

incorporate, or which are implied by trade, custom, practice or course of dealing.

incorporate, or which are implied by trade, custom, practice or course of dealing. CUSTOMER TERMS AND CONDITIONS 1. INTERPRETATION 1.1 Definitions. Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business. Conditions: the terms

More information

1.1 Definitions. In these Conditions, the following definitions apply:

1.1 Definitions. In these Conditions, the following definitions apply: ORION FUTURE TECHNOLOGY LIMITED STANDARD CONDITIONS OF SALE Table Of Contents 1. Interpretation... 1 2. Basis of contract... 2 3. Goods... 3 4. Delivery... 3 5. Quality... 4 6. Title and risk... 5 7. Price

More information

Before : LADY JUSTICE ARDEN LORD JUSTICE UNDERHILL and LORD JUSTICE BRIGGS with MASTER GORDON SAKER (Senior Costs Judge) sitting as an Assessor

Before : LADY JUSTICE ARDEN LORD JUSTICE UNDERHILL and LORD JUSTICE BRIGGS with MASTER GORDON SAKER (Senior Costs Judge) sitting as an Assessor Neutral Citation Number: [2016] EWCA Civ 1096 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM BIRKENHEAD COUNTY COURT AND FAMILY COURT District Judge Campbell A89YJ009 Before : Case No: A2/2015/1787

More information

Before: MR RECORDER BERKLEY MISS EASHA MAGON. and ROYAL & SUN ALLIANCE INSURANCE PLC

Before: MR RECORDER BERKLEY MISS EASHA MAGON. and ROYAL & SUN ALLIANCE INSURANCE PLC IN THE COUNTY COURT AT CENTRAL LONDON Case No: B53Y J995 Court No. 60 Thomas More Building Royal Courts of Justice Strand London WC2A 2LL Friday, 26 th February 2016 Before: MR RECORDER BERKLEY B E T W

More information

Before : MR JUSTICE DAVID STEEL Between :

Before : MR JUSTICE DAVID STEEL Between : Neutral Citation Number: [2011] EWHC 1820 (Comm) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION COMMERCIAL COURT Case No: 2010 FOLIO 445 Royal Courts of Justice Strand, London, WC2A 2LL Date: 14/07/2011

More information

Before: LORD JUSTICE SULLIVAN LORD JUSTICE TOMLINSON and LORD JUSTICE LEWISON Between:

Before: LORD JUSTICE SULLIVAN LORD JUSTICE TOMLINSON and LORD JUSTICE LEWISON Between: Neutral Citation Number: [2014] EWCA Civ 1386 Case No: C1/2014/2773, 2756 and 2874 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE HIGH COURT OF JUSTICE QUEENS BENCH DIVISION PLANNING COURT

More information

ARMED SERVICES BOARD OF CONTRACT APPEALS

ARMED SERVICES BOARD OF CONTRACT APPEALS ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of -- ) ) Northrop Grumman Corporation ) ASBCA Nos. 52785, 53699 ) Under Contract No. N00024-92-C-6300 ) APPEARANCES FOR THE APPELLANT: Stanley R. Soya,

More information

DISTRICT OF LAKE COUNTRY BYLAW 628, CONSOLIDATED VERSION (Includes amendment as of July 18, 2017)

DISTRICT OF LAKE COUNTRY BYLAW 628, CONSOLIDATED VERSION (Includes amendment as of July 18, 2017) DISTRICT OF LAKE COUNTRY BYLAW 628, 2007 CONSOLIDATED VERSION (Includes amendment as of July 18, 2017) This is a consolidated copy to be used for convenience only. Users are asked to refer to the Highway

More information

Before : MR. JUSTICE EDWARDS-STUART Between :

Before : MR. JUSTICE EDWARDS-STUART Between : Neutral Citation Number: [2014] EWHC 4006 (TCC) IN THE HIGH COURT OF JUSTICE QUEEN S BENCH DIVISION TECHNOLOGY AND CONSTRUCTION COURT Case No: HT-2014-000022 (Formerly HT-14-372) Royal Courts of Justice

More information

Before : - and - THE HIGH COMMISSION OF BRUNEI DARUSSALAM

Before : - and - THE HIGH COMMISSION OF BRUNEI DARUSSALAM Neutral Citation Number: [2014] EWCA Civ 1521 IN THE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE HIGH COURT OF JUSTICE QUEEN S BENCH DIVISION The Honourable Mr Justice Bean QB20130421 Case No:

More information

MR PETER WHITE MRS OLGA WHITE. And MR STEPHEN LITTLE MRS MICHELLE LITTLE AUTHORISED JUDGMENT

MR PETER WHITE MRS OLGA WHITE. And MR STEPHEN LITTLE MRS MICHELLE LITTLE AUTHORISED JUDGMENT MR PETER WHITE MRS OLGA WHITE Appellants And MR STEPHEN LITTLE MRS MICHELLE LITTLE Respondents AUTHORISED JUDGMENT - 9.2.17 1. The Appellants appeal against a Party Wall Award, dated 6.10.16, made by the

More information

ON APPEAL FROM THE MILTON KEYNES COUNTY COURT

ON APPEAL FROM THE MILTON KEYNES COUNTY COURT IN THE COURT OF APPEAL CIVIL DIVISION LORD JUSTICE TOMLINSON Appeal Number: B2/2015/0594 ON APPEAL FROM THE OXFORD COUNTY COURT HH JUDGE TOLSON QC ON APPEAL FROM THE MILTON KEYNES COUNTY COURT DISTRICT

More information

PFIZER NEW ZEALAND LIMITED trading as Pfizer Consumer Healthcare (NZ) ("PCH") ("Supplier")

PFIZER NEW ZEALAND LIMITED trading as Pfizer Consumer Healthcare (NZ) (PCH) (Supplier) PFIZER NEW ZEALAND LIMITED trading as Pfizer Consumer Healthcare (NZ) ("PCH") ("Supplier") TERMS AND CONDITIONS OF SALE 1. ORDERS 1.1 The Supplier reserves the right to accept or decline, in whole or in

More information

Legal Briefing. Lungowe & Others v Vedanta Resources Plc & Konkola Copper Mines [2017]

Legal Briefing. Lungowe & Others v Vedanta Resources Plc & Konkola Copper Mines [2017] Legal Briefing Lungowe & Others v Vedanta Resources Plc & Konkola Copper Mines [2017] Friday 13th October: An auspicious day for Zambian claimants On Friday 13 October 2017 the Court of Appeal handed down

More information

BUILDING SERVICES CORPORATION ACT 1989 Na 147

BUILDING SERVICES CORPORATION ACT 1989 Na 147 BUILDING SERVICES CORPORATION ACT 1989 Na 147 NEW SOUTH WALES 1. Short title 2. Commencement 3. Definitions TABLE OF PROVISIONS PART 1 - PRELIMINARY PART 2 - REGULATION OF RESIDENTIAL BUILDING WORK AND

More information

IMAGE ON FOOD LIMITED TERMS AND CONDITIONS OF SALE TO BUSINESS CUSTOMERS

IMAGE ON FOOD LIMITED TERMS AND CONDITIONS OF SALE TO BUSINESS CUSTOMERS IMAGE ON FOOD LIMITED TERMS AND CONDITIONS OF SALE TO BUSINESS CUSTOMERS 1. INTERPRETATION 1.1 Definitions. In these Conditions, the following definitions apply: "Business Day": a day (other than a Saturday,

More information

IN THE COUNTY COURT AT NEWCASTLE UPON TYNE Case No: B54YJ494. Before: HIS HONOUR JUDGE FREEDMAN. and JUDGMENT

IN THE COUNTY COURT AT NEWCASTLE UPON TYNE Case No: B54YJ494. Before: HIS HONOUR JUDGE FREEDMAN. and JUDGMENT IN THE COUNTY COURT AT NEWCASTLE UPON TYNE Case No: B54YJ494 Hearing date: 11 th August 2017 Before: HIS HONOUR JUDGE FREEDMAN B E T W E E N: DEBORAH BOWMAN Claimant and NORFRAN ALUMINIUM LIMITED (1) R

More information

R v JAMES BINNING RULING ON COSTS. 1. On 18 October 2012 Dean Henderson-Smith died as a result of falling

R v JAMES BINNING RULING ON COSTS. 1. On 18 October 2012 Dean Henderson-Smith died as a result of falling IN THE OXFORD CROWN COURT HHJ ECCLES QC R v JAMES BINNING RULING ON COSTS 1. On 18 October 2012 Dean Henderson-Smith died as a result of falling through a Perspex skylight in the roof of a large barn known

More information

If this Judgment has been ed to you it is to be treated as read-only. You should send any suggested amendments as a separate Word document.

If this Judgment has been  ed to you it is to be treated as read-only. You should send any suggested amendments as a separate Word document. Neutral Citation Number: [2017] EWHC 165 (Admin) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION ADMINISTRATIVE COURT Case No: CO/3081/2016 Royal Courts of Justice Strand, London, WC2A 2LL Date: 9

More information

Why did the MF/1 terms not apply? The judge had concluded that the MF/1 terms did not apply because:

Why did the MF/1 terms not apply? The judge had concluded that the MF/1 terms did not apply because: United Kingdom Letters of intent and contract formation RTS Flexible Systems Limited (Respondents) v Molkerei Alois Muller Gmbh & Company KG (UK Production) (Appellants) [2010] UKSC 14C Chris Hill and

More information

IN THE COURT OF APPEAL BETWEEN ADRIANA RALPH LEE RALPH AND

IN THE COURT OF APPEAL BETWEEN ADRIANA RALPH LEE RALPH AND REPUBLIC OF TRINIDAD AND TOBAGO CIVIL APPEAL No. 98 of 2011 CV 2008-04642 IN THE COURT OF APPEAL BETWEEN ADRIANA RALPH LEE RALPH AND APPELLANTS/CLAIMANTS WEATHERSHIELD SYSTEMS CARIBBEAN LIMITED RESPONDENT/

More information