China International Economic & Trade Arbitration Commission CIETAC (PRC) Arbitration Award

Size: px
Start display at page:

Download "China International Economic & Trade Arbitration Commission CIETAC (PRC) Arbitration Award"

Transcription

1 China International Economic & Trade Arbitration Commission CIETAC (PRC) Arbitration Award - Particulars of the proceeding - Facts - Position of the parties - Opinion of the Arbitration Tribunal - Award PARTICULARS OF THE PROCEEDING AOE and PECD machines case (18 December 2003) Translation [*] by Zheng Xie [**] The China International Economic and Trade Arbitration Commission (hereafter, the "Arbitration Commission") accepted the case (Case number: M...) according to: - The arbitration clauses in Contract No. 0-NET-0001 (the "Contract") signed by Claimant [Seller], Limited., and Respondent [Buyer], Technology (Shenzhen) Ltd., on 7 November 2000; and - The written arbitration application submitted by the [Seller] on 18 February The Arbitration Rules of the Arbitration Commission [hereafter, the "Arbitration Rules"], which took effect on 1 October, 2000, apply to this case. On 10 March 2003 the Secretariat of the Arbitration Commission by express mail sent the Arbitration Notice (2003) CIETAC No., the [Seller]'s arbitration application with evidentiary material attached, the Arbitration Rules, and the Arbitrators List to the [Buyer]. This package was returned, because "the receiver was out," and "the package was not picked up within the stipulated time." The Secretariat noticed the [Seller] of the above situation and requested the [Seller] to check and provide the [Buyer]'s correct address. On 8 April 2003, the [Seller] re-provided the [Buyer]'s business place to the Arbitration Commission. The Secretariat re-sent the Arbitration Notice and relevant documents by express mail to the [Buyer]'s address the [Seller] re-provided. The package was returned again, because "the package was not picked up within the stipulated time," "the party moved, the new address should be provided," and "no one answered the phone," etc. According to Rule 87 of the Arbitration Rules, the package was deemed to be validly served. On 3 June 2003, the Presiding Arbitrator, Dong, appointed by Article 24 of the Arbitration Rules, arbitrator, Zhang, appointed by the [Seller], and arbitrator, Wang, appointed by the Chairman for the [Buyer] according to Article 26 of the Arbitration Rules, formed the Arbitration Tribunal to hear this case. On the same day, the Secretariat sent the Notice of Formation of the Arbitration Tribunal (2003) CIETAC No. to the [Seller] and the [Buyer].

2 On 6 June 2003, the [Buyer] sent a letter to the Arbitration Commission alleging that it had already received the Notice of Formation of the Arbitration Tribunal sent by the Secretariat, but did not receive the Arbitration Notice, and provided its current address. Although the Arbitration Notice had been validly served, considering the actual situation in this case, on 9 June 2003 the Secretariat re-sent the Arbitration Notice and relevant documents to the [Buyer], and requested the [Buyer] to re-appoint an arbitrator and jointly with the [Seller] appoint or authorize the Chairman to appoint the Presiding Arbitrator, and to submit the Response on time. On 3 July 2003, the [Buyer] informed the Arbitration Commission in writing that it appointed as arbitrator. On 11 July 2003, the Presiding Arbitrator, Liu, appointed by the Chairman of the Arbitration Commission according to Article 24 of the Arbitration Rules, arbitrator, Zhang, appointed by the [Seller], and arbitrator, Fu, appointed by the [Buyer], constituted the Tribunal to hear this case. On the same day, the Secretariat by express mail sent the Notice (2003) CIETAC No. to the [Seller] and the [Buyer]. On 14 July 2003, the Secretariat sent the Court Session Notice (2003) CIETAC No. via fax and express mail, respectively, to the [Seller] and the [Buyer]. The court session was scheduled for 18 August 2003 in Beijing. On 24 July 2003, the [Buyer] submitted its response and evidentiary material to the Arbitration Commission. On 11 August 2003, the [Buyer] submitted a counterclaim and evidentiary material, and completed the procedure of counterclaim fee payment. According to Article 18 of the Arbitration Rules, the [Buyer]'s counterclaim and the [Seller]'s claim were jointly heard in this case. On 13 August 2003, the [Seller] submitted its response and evidentiary material with respect to the [Buyer]'s counterclaim. On 18 August 2003, the Arbitration Tribunal opened as scheduled in Beijing. The [Seller]'s legal representative and arbitration agent, and the [Buyer]'s arbitration agent attended the court session. In the court session, the parties presented the facts and opinions, crossexamined the evidence, made their arguments, and answered the Arbitration Tribunal's questions. After the court session, the parties submitted supplementary opinions and evidentiary material. The Secretariat exchanged these documents between the parties, asked the parties whether they requested to open another court session to cross-examine the supplementary evidence. Neither party requested another court session within the stipulated time, but they submitted the written opinions on the evidence. This case was closed. According to the facts ascertained in the court session, all written material and the relevant law, the Arbitration Tribunal handed down this award by consent. The facts, the Arbitration Tribunal's opinion and award are as follows:

3 FACTS On 7 November 2000, the [Seller] and the [Buyer] signed a Contract, which stipulates: - Goods: The [Seller] shall sell to the [Buyer] a set of Multiplex AOE ("AOE") and a set of PECVD ("PECVD") machines; - Total price: 661, CIF Shenzhen; - Payment terms: "Deposit (cash) and L/C"; - Amount and time of payment: The [Buyer] shall pay 20,000 within two weeks after the Contract is executed, and pay the remaining amount by L/C after the goods arrive at Shenzhen Customs; the [Buyer] shall pay 90% of the remaining amount, i.e., 577, (it shall be 577,619.86: note by the Arbitration Tribunal) after the goods are delivered, and the L/C shall be issued one month before the goods are delivered; within 30 days after the goods arrive at the [Buyer]'s company, and the parties examine and accept the goods, and sign a confirmation or, within 60 days after the goods arrive, the [Buyer] shall pay the remaining 10%, i.e., 64, (it should be 64,179.98: note by the Arbitration Tribunal); - Shipping time: The PECVD shipment shall arrive at Shenzhen Port before 10 April 2001, and the AOE shipment shall arrive at Shenzhen Port before 10 June Article 15. Claims: "Within 90 days after the goods arrive at the destination port, if the quality, specification, or quality of the goods are found inconsistent with the Contract except for the liability which an insurance company or carrier shall bear, the [Buyer] shall request replacement or claim damages with a certificate issued by a commodities inspection bureau." - Article 18. Warranty: "Warranty period: one year (calculated from the day when the goods are installed, adjusted and operated). Within the warranty period, the [Seller] shall be responsible to supply and replace the parts (excluding vulnerable parts) for the machines (AOE and PECVD) due to damages caused by non-personal factors. The [Seller] shall bear all expenses (the transportation fee which the [Buyer] shall bear is only limited to the parts which could be delivered from Hong Kong, and could be delivered only from the headquarters in the UK). After the one year warranty period, the [Seller] shall supply parts within eight years. This provision shall not apply to any damages which are caused by negligence, misuse, clash, dropping, intentional destroying, and exposure, etc." - Article 20(d). Delay penalties: "If any delayed delivery is caused by force majeure, the [Seller] shall pay the [Buyer] penalty for delay, i.e., 0.5% of the price of goods delayed per week, but the total penalty shall not exceed 5% of the price of goods delayed; if the delay is not less than one week, it shall be calculated as one week. If the delay is longer than ten weeks, the [Buyer] is entitled to revoke the Contract, and the [Seller] shall refund the deposit ( 20,000) to the [Buyer]. However, the [Seller] shall still pay the [Buyer] the above stipulated penalty, and shall not refuse or delay." The Contract also contains provisions on packaging, adjustment and testing, arbitration, etc.

4 During the performance of the Contract, disputes arose between the parties. No agreement was reached after negotiation. The [Seller] filed this arbitration application with the Arbitration Commission. POSITION OF THE PARTIES [Seller]'s claims In the arbitration application, the [Seller] raised the following claims: (1) The [Buyer] shall pay the [Seller] the unpaid contract price, i.e., 66,179.78; (2) The [Buyer] shall compensate the [Seller] for loss of interest on the delayed payment, calculated at a 6.5% annual interest rate from 9 October 2001 to the day when the payment is actually made; (3) The [Buyer] shall bear all expenses incurred due to this arbitration including the arbitration fee, and compensate the [Seller] for the actual expenses including the attorneys' fee of renminbi [RMB] 52,000 and traveling expenses, etc. [Seller]'s support for its claims The facts and reasons to support the [Seller]'s claims are as follows: The Contract stipulates that the [Buyer] shall open a L/C one month before the goods arrive in Shenzhen, so the [Buyer] should have issued the L/C to the [Seller] before 10 March However, in this case, the [Buyer] did not issue the L/C until 18 May 2001, more than two months later than the stipulated time, which caused the delay of the [Seller]'s delivery; the goods arrived Shenzhen Port on 21 June and 9 August 2001, respectively. After the goods arrived at the port, the [Buyer] paid 90% of the contract price in accordance to the Contract, but failed to pay the remaining amount, i.e., 66, According to the Contract, the [Seller] was obligated to pay the remaining 10% of the contract price no later than 9 October According to Article 53 of United Nations Convention on Contracts for the International Sales of Goods (CISG), "The buyer must pay the price for the goods and take delivery of them as required by the contract and this Convention," The [Buyer]'s action constituted a breach of the Contract. The [Seller] negotiated with the [Buyer] many times in order to resolve the issue of the remaining payment and mediate the economic loss, but the [Buyer] first postponed by alleging change of internal employees, and then refused to make payment by alleging that the delivery was delayed. The [Buyer] offered many excuses for its refusal to make the payment. Article 74 CISG states: "Damages for breach of contract by one party consist of a sum equal to the loss, including loss of profit, suffered by the other party as a consequence of the breach..." Article 78 of CISG stipulates: "If a party fails to pay the price or any other sum that is in arrears, the other party is entitled to interest on it, without prejudice to any claim for damages recoverable under article 74."

5 Accordingly, the [Buyer] should pay the [Seller] the remaining price and interest on it. [Buyer]'s position The [Buyer] alleged: The [Seller] delayed the delivery first, and the condition for the remaining payment was not satisfied because of the [Seller]'s delayed delivery, so the [Buyer] has the reason for not paying the remaining price. 1. The [Seller] should be held liable for the delay of delivery. The [Buyer] issued the L/C on time and had no fault. Article 6 of Contract No. 0-NET-001 signed by the [Seller] and the [Buyer] on 7 November specifies the time when the goods shall arrive at Shenzhen Port; however, according to the import date recorded in the Customs Declaration Form: - The PECVD arrived at port on 22 June 2001, seventy-three (73) days (about eleven weeks) later than the time stipulated in the Contract (before 10 April 2001); and - The AOE arrived at the port on 9 August 2001, sixty (60) days (about nine weeks) later than the time (before 10 June 2001) stipulated in the Contract. It is unjustifiable for the [Seller] to allege that the delayed delivery was caused by the [Buyer]'s delayed issuance of the L/C; the fact is that at the beginning of 2001, because of the increasing demand in the market, the [Seller] could not deliver the goods on time, so it orally requested to postpone the delivery, but the [Buyer] requested the [Seller] to continue the performance of Contract and bear the liability for breach. Thereafter, the [Seller] informed the [Buyer] that the delayed delivery day was 18 June Accordingly, the [Buyer] issued the L/C on 18 May 2001, which is consistent with the stipulation in the Contract that "the L/C shall be issued one month before the goods are delivered," and with the relevant business customs. In addition, according to business customs regarding issuance of a L/C, the [Seller] should have informed the [Buyer] of the specific shipping time, so the [Buyer] could issue a valid L/C. However, in this case, the [Seller] did not send such notice in accordance with the Contract, but sent a notice of delayed delivery, so the [Buyer] properly issued the L/C according to the [Seller]'s notice and the stipulation in the Contract. It is the [Seller]'s fault to request delay of delivery. The process of signing Contract No. 0- NET-0009 (the No. 9 Contract) between the [Seller] and the [Buyer] can prove this. On 14 March 2001 at 11:54 a.m., the [Buyer] received the [Seller]'s fax, which was a draft of a sales contract, i.e., the draft of the No. 9 Contract. The shipping time stipulated in Article 6 is, "the goods shall be shipped with those under Contract 0-NET-0001 on 10 June 2001," and the [Buyer] sent the signed and sealed draft via fax; when the [Seller] received this fax, the No. 9 Contract was established. At 14:32 of the same day, the [Buyer] received the fax of the No. 9 Contract with the [Seller]'s authorized representative's signature. Accordingly, the [Seller] requested to delay delivery in the form of an offer via fax, but the [Buyer]'s agreement should not be deemed as exemption of the [Seller]'s liability for breach. Therefore, in this case, the [Seller] is the supplier of the Contract, and its delay of delivery constituted the first breach of the Contract.

6 In sum, the [Buyer] should not bear any liability for the [Seller]'s delay of delivery. Furthermore, according to Article 20(6) of the Contract, the [Seller] shall pay the [Buyer] a penalty for delay of delivery, totaling 31, , which is calculated as follows: The delivery of the PECVD was eleven (11) weeks delayed, and the penalty shall be 5% of the total contract price ( 265, %= 13,279.12); the delivery of the AOE was nine (9) weeks delayed, and the penalty shall be 4.5% of the total contract price ( 396, %= 17, ). 2. The remaining contract price was not paid due to the [Seller]'s breach, so there is a legal basis for the [Buyer] to refuse to make the payment. (1) The [Seller]'s delay in installing and adjusting the machines due to its own fault constituted a breach of the Contract. Article 14 of the Contract stipulates that the [Seller] shall guarantee that the machines can perform their proper functions, and the [Seller] shall guarantee the machines run properly and, the [Seller] shall complete installation of the machines within 25 days and adjust to the design required by the [Buyer]. This Article also specifies the requirements of the design which the machines shall be adjusted to. The [Buyer] alleged that it is the [Seller]'s essential contractual duty to guarantee the design, and the [Seller] shall strictly follow and perform the requirements. However, the [Seller] failed to complete the above duties within the stipulated time (within 56 days), and breached the Contract again. According to the Contract, the PECVD machine should have arrive at the port on 22 June 2001, and the installation and adjustment period should start from the following day, and should be completed on 17 August 2001; the installation and adjustment period should start from 10 August 2001, and should have been completed on 4 October However, the [Seller] completed installation and adjustment on 6 December 2001, far later than the stipulated time in the Contract, so the [Seller] breached the Contract. Therefore, the [Seller] was at fault and should be liable for its breach. During the adjustment, because the frequent replacement of main parts of the PECVD and AOE machines severely affected the adjustment process, the [Seller] delayed completing the adjustment report. The delivery list signed by the [Buyer] from November 2001 to January 2002 recorded the arrival of the goods after the main parts were replaced. (2) The [Seller] stopped all warranty services and breached the Contract again. The [Seller] requested the approval of Certificate of Acceptance of the machines shortly after the adjustment was completed. However, because disputes arose regarding the starting time of the warranty period, and the [Seller] stopped all warranty services, the [Buyer] did not approve this Certificate. The [Buyer] alleged that the warranty period should start from 1 January 2002, i.e., following the completion of adjustment and testing acceptance of the machines, because Article 18 of the Contract stipulates the warranty period "shall be calculated from the day when the machines start running after the adjustment and testing acceptance"; in addition, Article 9.3 of Item 2825 in Appendix I regarding amendment of quoted price stipulates definition "the machines start running," i.e., when the [Seller] installs and adjust the machines at the [Buyer]'s place, and the machines and design are consistent with the stipulations in Article 14

7 of the Contract, the machines can start running. However, the [Seller] refused to perform its promise, and rejected the [Buyer]'s reasonable requests. When the parties failed reach any agreement after negotiation, on 6 May 2002 the [Seller] notified the [Buyer] that it was stopping all warranty services including the services for the equipment for which the payment had been made. As to this, the [Buyer] reserved its right to claim damages and requested the [Seller] to perform warranty services, but the [Seller] did not agree. Obviously, the [Seller] had apparent faults, so it should be liable for the breach. (3) The condition for the remaining payment was not satisfied, and the [Seller] severely breached the Contract, so the [Buyer] reasonably refused to make the payment. Article regarding the time for the remaining payment, stipulates that when the goods arrive at the [Buyer]'s company and the parties sign and confirm after the acceptance according to the Contract, the remaining price (i.e., 10% of the total contract price) shall be paid within 30 days or 60 days after the goods arrive. This Article specifies two payment methods for the parties to choose. The [Seller] alleged that the remaining price should be paid no later than 9 October 2001, which was counted as the standard of "within 60 days after the goods arrive." This obviously lacks factual and legal basis, because Article 46 A of Notice of L/C (reciting the contents in the L/C issued by the [Buyer]) issued by Jia Hua Bank, Evidence II submitted by the [Seller], stipulates that the remaining price (i.e., 10% of the total contract price) should be paid off within 30 days after the applicant (the [Buyer]) and the beneficiary (the [Seller]) officially sign the certificate of acceptance. The [Buyer] alleged that parties had accepted the payment terms stipulated in the L/C, which proved that the [Seller] and the [Buyer] did not choose the method "60 days after the goods arrive," but "30 days after the parties sign and confirm the acceptance according to the Contract," as stipulated in Article Because the [Seller] delayed installation and adjustment of design, and stopped the warranty services even for the equipment for which the payment had already been made, it is the only remedial measure for the [Buyer] to refuse to approve the Certificate of Testing Acceptance; thus, the [Buyer] could not make the remaining payment according to the above payment terms agreed by the parties. In a conclusion, the penalty which the [Seller] should pay to the [Buyer] due to its delayed delivery should be deducted from the remaining contract price. Because the [Seller] delayed performing its duty to install the machines and adjust the design, and refused to perform warranty services, the [Buyer] refused to pay the remaining amount; the [Seller] shall bear the liability. Thus, the [Buyer] justifiably refused to make the remaining payment without any fault. Therefore, the [Buyer] asked the Arbitration Tribunal to dismiss the [Seller]'s claim. On 11 August 2003, the [Buyer] submitted a counterclaim application to the Arbitration Tribunal, and filed the following counterclaims: [Buyer]'s counterclaim (1) The [Seller] shall pay to the [Buyer] the penalty due to the delay of delivery, totaling 31, ; (2) The [Seller] shall compensate the [Buyer] for the loss caused by the [Seller]'s stopping warranty services, totaling RMB 2,368,535.05;

8 (3) The [Seller] shall bear all expenses including the arbitration fee incurred due to this arbitration, and compensate the [Buyer] for the attorneys' fee, traveling expenses, etc., incurred due to this case. The attorneys' fee include the basic fee of RMB 30,000 and contingency (calculated according to actual amount); the round trip traveling expenses (including the round trip airfares of RMB 4,500, and the airport construction fee of RMB 200) which the [Buyer]'s agents Wang and Zuo incurred to attend the court session in Beijing, the accommodation expenses of RMB 1,920, and notarization fee of RMB 2,000 which the [Buyer] incurred in order to preserve the evidence. The [Buyer]'s counterclaims are based on the following facts and reasons: 1. The [Seller] should be held liable for its delay of delivery, and pay the [Buyer] the relevant penalty. According to the import date recorded in the Customs Declaration form, the time when PECVD machine actually arrived at the port was seventy-three (73) days (counted as eleven weeks according to the Contract) later than that stipulated in the Contract; and the time when the AOE machine arrived at the port was sixty (60) days (counted as nine weeks) later than that stipulated in the Contract. Therefore, the [Seller] should be held liable for its delay of delivery and pay the [Buyer] the penalty due to its delayed delivery. According to business customs regarding issuing a L/C, the [Seller] as a supplier should have given the [Buyer] early notice of the shipping date, so the [Buyer] could issue a valid L/C. In this case, the [Seller] delayed its notice due to the delay of delivery, so it was proper for the [Buyer] to issue the L/C according to the [Seller]'s notice and the time stipulated in the Contract. The [Seller] should not deny the fact that it breached the Contract first due to delay in delivering the goods; the process of signing the No. 9 Contract can prove this. The [Seller] requested to delay delivering the goods in the form of an offer in its former fax, and the [Buyer]'s approval should not be deemed as an exemption of the [Seller]'s liability for breach of the Contract, because the [Seller] is the supplier under the Contract. The [Seller] breached the Contract first due to delay of delivery; the [Buyer] did not give up its right to claim damages caused by delay of delivery according to the Contract. In sum, the [Buyer] was not at fault regarding the [Seller]'s delay of delivery and, the [Seller] should be held liable for its breach. According to Article 20(d) of the Contract, the [Seller] shall pay the [Buyer] a penalty, totaling 31, The [Seller] should compensate the [Buyer] for its damages caused by the [Seller]'s stoppage of warranty services. (1) The [Seller] stopped all warranty services to the [Buyer] without any reason, and severely breached the Contract. Article 14 of the Contract stipulates that the [Seller] shall guarantee that the machines can perform their proper functions, and the [Seller] shall guarantee the machines run properly and, the [Seller] shall complete installation of the machines within 25 days and adjust to the design required by the [Buyer]. However, the [Seller] failed to complete this task within the time stipulated in the Contract, and breached the Contract again. After the adjustment testing, the

9 [Seller] requested the [Buyer] to approve the Certificate of Acceptance Testing. However, because the disputes regarding the starting day of warranty period arose, and the [Seller] stopped all warranty services, the [Buyer] did not approve this Certificate. When the parties failed to reach any agreement after negotiation, on 15 March 2002 the [Seller]'s engineers in the [Buyer]'s company left, which severely affected the timely maintenance of the machines. Thereafter, the [Seller] sent a written notice to the [Buyer] on 6 May 2002 informing that the [Seller] would stop all warranty services. As to this, the [Buyer] reserved its right to claim damages, and requested the [Seller] to continue its warranty services, but the [Seller] did not agree. The [Seller]'s above conduct directly caused the machines could not run normally, and caused the [Buyer] to suffer severe damages, and the machines which the [Buyer] bought for a large amount of money had stayed useless for one year. This breached the [Seller]'s contractual duty, because regardless of how one counts the starting day of warranty period, May 2002 was within the warranty period, and the [Seller] stopped warranty services of the PEVCD and AOE machines, and severely breached the Contract (2) The [Seller] should compensate the [Buyer] for the loss caused by stopping warranty services. The [Seller] breached the Contract by arbitrarily stopping all warranty services. The [Seller]'s above conduct caused the machines to stop running from 6 May 2002, and it had been more than one year, and the [Buyer] suffered severe damages, which includes: a. The stoppage of operation meant that the AWG products could not be manufactured, and the fiber materials purchased for the production were wasted. The loss totaled HK $281, (equal to RMB 296,422.60). b. In order to manufacture AWG products, the [Buyer] had also purchased electric materials; because of the stoppage of operation, the quality warranty period expired, which caused the [Buyer] to suffer the total loss of RMB of 155, 673. c. From the stoppage of operation to the day when the counterclaim was filed, the [Buyer] incurred rent of RMB 123,750 to store the machines. d. The stoppage of operation caused the machines to stay without running for more than one year, and the [Buyer] suffered loss of RMB 1,792,689.45, for which the [Seller] should compensate. According to Articles and Article 29 of the Implementing Rules of Income Tax Law of Foreign Investment Enterprises and Foreign Enterprises of the People's Republic of China, and the relevant stipulations in Accounting Principles, the [Buyer]'s loss of the non-operating machines is calculated as follows: - The depreciation per month = the original value X (1 - the remaining value)/60 months (five years); PECVD depreciation per month = RMB 3,197, X (1-10%)/60 months = RMB 47,963.18; - AOE depreciation per month = RMB 4,769, X (1-10%) / 60 months = RMB 71, From May 2002 to the time when the [Buyer] filed the counterclaim, the

10 machines stayed without running for 15 months. Therefore, the loss of non-operation of the PECVD machine is RMB 719,447.70, and the loss of non-operation of the AOE machine is RMB 1,073,241.75; the total loss of the above two items is RMB 1,792, Article 74 of CISG states: "Damages for breach of contract by one party consist of a sum equal to the loss, including loss of profit, suffered by the other party as a consequence of the breach. Such damages may not exceed the loss which the party in breach foresaw or ought to have foreseen at the time of the conclusion of the contract, in the light of the facts and matters of which he then knew or ought to have known, as a possible consequence of the breach of contract." Therefore, the [Seller] should compensate for the [Buyer]'s loss. [Seller]'s response to [Buyer]'s counterclaim On 13 August 2003, the [Seller] submitted the following opinions with respect to the [Buyer]'s counterclaim: 1. It lacks legal basis for the [Buyer] to request the [Seller] bear the liability for delay of delivery and pay the penalty; it should not be the [Seller] but the [Buyer] to bear the liability for breach. (1) The [Seller]'s delay of delivery was caused by the [Buyer]'s delayed issuance of the L/C. The [Buyer] does not have a correct view of its delayed issuance of L/C. The [Seller] performed its duty in accordance with the Contract. According to the Contract, the PECVD and AOE machines were to be delivered on 10 April and 10 June 2001, respectively, and the L/C was to be issued one month before the delivery. The [Seller] did not receive the L/C within the stipulated time, and sent a letter to urge the [Buyer] to issue the L/C as soon as possible; however, the [Buyer] neither made any response, nor issued the L/C until 18 May According to the relevant law, the [Seller] could claim damages for the [Buyer]'s breach, but in order to maintain good cooperation, the [Seller] still delivered the goods to the [Buyer] and did not claim damages. With respect to the [Buyer]'s allegation that the [Seller] should have informed the [Buyer] of the specific delivery time, the [Seller] alleged that the Contract definitely specified the delivery time, so the [Seller] had no duty to inform the [Buyer] of the shipping time again, and the parties need only follow the stipulation and perform the duties under the Contract. According to the Contract, the [Seller] should have issued the L/Cs before 10 March and 10 May 2005, respectively, but it failed to issue the L/Cs on time, which caused the [Seller]'s delay of delivery. According to Article 80 CISG: "A party may not rely on a failure of the other party to perform, to the extent that such failure was caused by the first party's act or omission."

11 Accordingly, the [Seller]'s delayed delivery was caused by the [Buyer]'s delayed issuance of the L/C. The [Seller] as a supplier could not deliver the goods when the [Buyer] did not issue the L/C. Therefore, it was the [Buyer] who caused the delay of delivery. (2) The Stipulation in Article 6 of the No. 9 Contract. The [Buyer] cited the shipping time "shipped on 10 June 2001 with the goods under the Contract No. 0-NET-0001" stipulated in Article 6 of the No. 9 Contract. This was cited by the [Buyer] in order to prove that the [Seller] agreed on the delay of delivery. This is a misunderstanding. Article 6 of the No. 9 Contract stipulates, "shipped on 10 June 2001 with the goods under Contract No. 0-NET-0001," and this proves that the [Seller] did not breach the Contract. The Contract in this case stipulates, "AOE shall arrive on 10 June 2001," and the [Seller] included the same term in the No. 9 Contract, but did not specify PECVD or AOE. However, according to the Contract and the situation at that time, it is not hard to determine that the goods in this draft refer to AOE, but not PECVD. The reason for including this stipulation is that according to the Contract, the [Seller] should deliver two machines, one of which should arrive at Shenzhen Port before 10 June, and the contract term was CIF Shenzhen, so that the [Seller] could ship the goods under the No. 9 Contract together with AOE under the Contract in this case in order to save freight charges. Therefore, the correct understanding is that the goods should be shipped together with those under the No. 9 Contract, but it was not the [Seller] who requested to delay delivering the goods. (3) The penalty for the [Seller]'s delay of delivery alleged by the [Buyer]. The Contract stipulates a penalty, but the [Seller]'s delay of delivery was caused by the [Buyer]'s delayed issuance of the L/C. When the [Buyer] issued the L/C two months later than the stipulated time, the [Seller] could not perform its plan, but it still tried its best to adjust the plan to deliver the goods to the [Buyer], and delivered the two machines to Shenzhen on 21 June and 9 August 2001, respectively. Thus, the [Seller] should not be held liable for this; it is the [Buyer] who should be liable. 2. It is the defense right of first performance for the [Seller] to stop the warranty services, because the [Buyer] failed to make the payments after the [Seller] urged many times and gave sufficient and reasonable time for the [Buyer]. (1) The time for payment of the remaining amount and the [Buyer]'s refusal. Regarding the internationally applied defense right of first performance, Article 80 of CISG stipulates: "A party may not rely on a failure of the other party to perform, to the extent that such failure was caused by the first party's act or omission." According to the relevant stipulations in the Contract, after the [Seller] delivered the goods, the parties' respective duties are as follows: the supplier (the [Seller]: note by the Arbitration Tribunal) shall guarantee that the machines would run normally and bear the responsibility to repair the goods within a period of time; the buyer shall make the payment (including the remaining amount) on time. Therefore, the [Seller] had the duty to install, adjust, and start

12 running the machines, and the [Buyer] should pay the remaining contract price. Article of the Contract stipulates: "After the goods arrive at the [Buyer]'s company, and the parties sign and confirm the acceptance, the [Buyer] shall pay the remaining 10% of the contract price within 30 days or 60 days after the goods arrive." The [Buyer] alleged that the condition to issue the remaining amount stipulated in the L/C is "the [Buyer] shall pay off within 30 days after the applicant (the [Buyer]) and the beneficiary (the [Seller]) officially sign and confirm the Certificate of Acceptance Testing." The [Seller] alleged that L/C is only a payment method, and the condition to make the remaining payment stipulated in the L/C could not be used to determine the payment method for the remaining amount, i.e., only when the remaining payment is made by L/C, the payment conditions stipulated in the L/C apply, and the conditions could not be deemed as the amendment of the Contract. Therefore, the [Buyer] should have made the remaining payments for the PECVD and AOE machines on 21 August 2001 and 9 October 2001, respectively, but the [Buyer] refused to perform the duty to make the remaining payment. Even if based on the payment method alleged by the [Buyer], the [Buyer] should "pay off the remaining amount within 30 days after the parties officially sign and confirm the Certificate of Acceptance." According to the letter sent by Mr. Dong Chenju of the [Buyer], "the parties signed the Certificate on 6 December 2001," so the [Buyer] should have paid the remaining price one month after 6 December, i.e., 6 January However, the [Buyer] failed to make the payment even after the [Seller] urged many times. Article 59 CISG stipulates: "The buyer must pay the price on the date fixed by or determinable from the contract and this Convention without the need for any request or compliance with any formality on the part of the seller." The [Seller] alleged that it had given the [Buyer] sufficient and reasonable time, and the [Buyer] should have performed its contractual duties within this period. On 6 May 2002, the [Seller] sent the last payment notice to the [Buyer], which was the exercising of defense right of first performance. (2) The starting time of the warranty period. Article 18 of the Contract stipulates: "The warranty period is one year (counted from the day when the machines start running after installation and adjustment testing..." With respect to the construction of "start running," the parties held different opinions; the [Seller] did not want to dispute on this issue, and agreed to count the starting date based on the method alleged in the [Buyer]'s counterclaim, i.e., the warranty period started from 6 December 2001 when the machines and design were consistent with the Contract. Therefore, when the [Buyer] did not breach the Contract, the [Seller]'s warranty period started from 6 December 2001 and 5 December 2001, respectively. (3) The replacement of parts during the adjustment testing.

13 It was not as the [Buyer] alleged that the replacement of essential parts affected the process of adjustment testing. The fact was that most of the replaced parts were consuming products; as to a large machine, it is normal to replace the consuming parts. (4) The [Buyer] did not request warranty service during the warranty period. From 6 December 2001 (the starting time of the warranty period), the machines had been running normally, and no problem occurred; according to either the Contract or custom, the [Buyer] should have timely paid the remaining amount, but it failed to make the payment. After the [Seller] exercised the defense right of first performance and stopped the warranty services, the machines were still running normally, and the [Buyer] did not request the [Seller] or Factory in the UK to perform any warranty services. However, at present, the [Buyer] suddenly alleged that because the [Seller] stopped warranty services, the machines could not run. The [Seller] alleged that this had no basis. If the machine could not run because of stopping the warranty services, the [Buyer] should have immediately sent a letter to the [Seller] requesting warranty services or requested the manufacturer to impose pressure on the [Seller] to perform warranty services. However, the fact is that neither the [Seller] nor the manufacturer received any such information within the warranty period. Meanwhile, the [Seller] raised suspicion on the evidence submitted by the [Buyer], and alleged that this evidence is meaningless to this case, and the [Buyer] did not use this evidence in its counterclaim at all. [Buyer]'s clarification On 2 September 2003, the [Buyer] submitted a clarification regarding the third element of its counterclaim application to the Arbitration Tribunal, and also provided its agent's opinion regarding the facts and legal issues in this case. The main contents are as follows: 1. The [Seller] should not deny its liability of breach due to delayed delivery. The allegation that the [Seller]'s delayed delivery was caused by the [Buyer]'s delayed issuance of the L/C was not established due to following reasons: (1) According to the principle of good faith and trade practice of issuing L/Cs between the parties, the [Seller] was obligated to timely inform the [Buyer] of the determined shipping time. (2) The [Seller] misstated Article 6 of the No. 9 Contract, and its reason was not justifiable. Article 6 of the No. 9 Contract stipulates the shipping time as "shipped on 10 June 2001 with the goods under the Contract 0-NET-0001," and this shows that the [Seller] would delay delivering the goods including PECVD and AOE under the Contract. A reasonable and prudent person under the common circumstances would understand Article 6 of the No. 9 Contract as the shipping time of the PECVD and AOE machines as 10 June Therefore, the [Seller] sent a written notice of delayed delivery in form of offer for establishing a contract to the [Buyer], and requested that the shipping time of the PECVD and AOE machines be delayed to 10 June According to the custom regarding issuance of L/Cs as above described, the [Buyer] had to issue the L/C based on the delayed shipping time. However, the [Buyer]'s acceptance should not be deemed as an exemption of the [Seller]'s

14 liability for breach, because the [Seller] as the supplier breached the Contract first because of delay in delivering the goods. (3) The [Seller]'s delay of delivery was caused by its own fault. a. The manufacturer clearly explained the essential reason for the [Seller]'s delayed delivery. On 23 May 2002, in the (Evidence X) to Yang of the [Buyer] responsible for this transaction, L the Asian market sales supervisor of the manufacturer of the PECVD and AOE machines, Company in the UK, admitted that increasing demand in the market was the essential reason that caused the [Seller]'s delay of delivery, and the [Buyer] should be compensated. The [Seller] argued that Evidence X was not related to this case, but its reason was not justified. Evidence X showed the essential reason for the [Seller] to delay delivering the goods. Company admitted that the increasing demands in the market caused the [Seller] to be unable to deliver the goods to the [Buyer] on time; under such circumstances, the [Seller] as the sales agent of could not deliver the goods to the [Buyer] on time at all. The evidence submitted by the [Buyer] also proved that the [Seller] had negotiated with the [Buyer] regarding the penalty for delayed delivery, and also cited Lu Lin's (the sales person of the [Seller] at that time) words, "he was not going to ask for the penalty if the delivery was delayed," in order to avoid its liability for breach. b. The [Seller] amended the shipping time many times and also revised the payment method stipulated in the Contract, which caused the [Buyer] to issue the L/C on 18 May In fact, the [Seller] amended the shipping time many times because it could not deliver the goods on time; the Evidence VI submitted by the [Buyer] could prove this. On 14 March 2001, the [Seller] informed the [Buyer] in form of an offer for the No. 9 Contract that the goods would be shipped on 10 June Thereafter, the [Buyer] faxed the main provisions in the L/C to the [Seller] for its confirmation in order to avoid delaying the delivery of the goods because if the [Seller] could not deliver the goods after the [Buyer] issued the L/C, the L/C had to be amended. According to the delayed shipping time, the [Buyer] proposed to stipulate in the L/C that the latest shipping time was 30 July, and expiration day was 30 October In the fax sent on 25 April of the same year, the [Seller] amended the latest shipping time as 15 August 2001, and the expiration date as 15 November 2001 (see E of the [Seller]'s amended handwriting), and sent back to the [Buyer]. This shows that when the shipping day had already been delayed, the [Seller] still failed to determine the specific date. In order to have sufficient time to prepare goods, the [Seller] again postponed the shipping time stipulated in the L/C. At the court session, Mr. Xiao, the [Seller]'s president, alleged that because of the time difference between the two places, Shenzhen Bank needed more than one week to issue the L/C; this was the essential reason for the [Seller] to amend the shipping time stipulated in the [Buyer]'s fax regarding the provisions of L/C. However, it must be pointed out that there is no time difference between Shenzhen and Hong Kong at all, and Shenzhen Bank's working efficiency is very high, and only needs two working days to issue the L/C, so this should not be the essential reason for the [Seller] to postpone the shipping time. There is another detail that the amount, in the L/C which was amended by the [Seller], was 641,797.84, which was not the contract price in this case; however, the amount in the L/C issued by the [Buyer] was 661,797.84, which was consistent with the amended Contract.

15 After 25 April, the [Seller] requested the [Buyer]'s sales person to revise the payment method in the Contract as by L/C for 100% of the contract price, and then the parties signed a new Contract in this case revising the payment method as by L/C for the total contract price. In addition, because of the May first holiday, the [Buyer] finally issued the L/C on 18 May In sum, the [Buyer] issued the L/C one month before the [Seller] delivered the goods in accordance with the Contract, and had no fault at all; the [Seller] delayed delivering the goods because of its own fault, and should not avoid its liability for the delay of delivery. The [Seller] should pay the [Buyer] the penalty for the delayed delivery according to the Contract. It should be pointed out that the [Buyer] requested the [Seller] to pay the penalty as early as February and April The [Seller] arbitrarily exercised the defense right of first performance, and stopped all warranty services, so it should be liable for this. (1) The [Seller]'s stoppage of warranty services did not satisfy the conditions of exercising of defense right of first performance, and lacks legal basis. a. The [Seller] cited Article 80 of CISG as the basis to stop the warranty services to the [Buyer]; this was a misunderstanding and arbitrary application of this Article. b. In this case, the [Seller]'s stoppage of warranty services obviously did not satisfy the conditions of exercising of defense right of first performance. The Contract and its Appendix stipulate that the [Buyer] shall make the payment for the remaining amount when some conditions are satisfied, and the [Seller] shall be responsible for warranty services within a period of time, which are the parties' respective obligations. The [Seller]'s obligation of warranty services is not conditioned on the [Buyer]'s payment of the remaining amount, and the [Buyer]'s payment of the remaining price is not the precondition for the [Seller] to perform the warranty services for the [Buyer]. These two obligations are neither conditioned nor related to each other, nor constitute "the parties' mutual obligations," and there is not a performance order for these two obligations. Therefore, the [Seller] was not entitled to the exercising of defense right of first performance stipulated in Article 80 CISG. According to the Contract, it is an essential contractual duty for the [Seller] to perform warranty services; if the [Seller] failed to perform this obligation, the normal operation of the PECVD and AOE machines could not be guaranteed. This obligation was not the counterpart of the [Buyer]'s obligation to pay the remaining amount. The [Seller] knew the importance of the warranty service, so it stopped the warranty services. (2) The [Seller]'s stoppage of warranty services directly caused that the machines could not be operated. The [Seller] alleged that after stopping the warranty services, the [Buyer]'s machines had been working normally, and the [Buyer] had never requested the [Seller] or the manufacturer, Company in the UK to provide the warranty services; this is inconsistent with the facts. The Evidence XIII and XIV submitted by the [Buyer] prove that after stopping the warranty services, the [Seller] not only rejected the [Buyer]'s reasonable request for technical support, but also arbitrarily prevented the [Buyer] from taking reasonable measures to repair the machines.

16 (3) The [Seller] should compensate the [Buyer] for the [Buyer]'s loss due to operation stoppage of machines. Article 45 CISG stipulates: "If the seller fails to perform any of his obligations under the contract or this Convention, the buyer may... claim damages as provided in articles 74..." and "[t]he buyer is not deprived of any right he may have to claim damages by exercising his right to other remedies." Therefore, when the [Seller] severely breached the Contract by stopping the warranty services, the [Buyer] could take remedial measures which did not deprive its right to other remedies. The [Buyer]'s loss could have been foreseen when the [Seller] breached the Contract; according to Article 74 of CISG, the [Seller] should compensate. Regarding the [Buyer]'s claimed loss, the [Buyer] submitted the following supplementary opinions: a. The loss of fabric materials These materials were ordered by the [Buyer] for manufacturing AWG products, and the specification and size were specially designed and produced for the [Buyer]. Because the [Seller] stopped the warranty services, the PECVD and AOE machines could not run normally due to technical problems. This caused the [Buyer] to stop the production of AWG products; in addition, because the materials were specially designed, and could not be used for other products, they were wasted. The [Buyer] spent HK $281,422.77, equal to RMB 155,6722, on the fabric materials. The [Seller] should compensate for this loss. b. The loss of electric gas materials The [Buyer] spent RMB 86,165 on four kinds of electric gas materials for PECVD production. The [Buyer] spent RMB 69,508 on electric gas materials for AOE production. According to technical standards, electric gas materials have a quality warranty period. Referring to the contract for purchase of the electric gas materials submitted by the [Buyer], the above gas materials arrived within the time stipulated in the contract, and all quality warranty periods had expired; so the gas materials were wasted. c. The factory building rented for the two machines and the calculation of rent The [Buyer] rented factory building for the two non-operation machines. According to the building plan, the space for the two machines was 50 m2, and other space for accessory facilities of operation and production was 100 m2, and the total space was 150 m2 (excluding the shared space). The unit rent stipulated in the Building Renting Contract is RMB 65/m2/month; based on the actual unit rent incurred, i.e., RMB 55/m2/month, the monthly rent for PECVD and AOE was

17 55X 150 = RMB 8,250. It had been 15 months from May 2002, when the machines could not run normally after the [Seller] stopped warranty services, to the day when the [Buyer] filed the counterclaim. The total rent claimed was RMB 8,250 X 15 (months) = RMB 123, Because the condition for the [Buyer] to make the remaining payment was not satisfied, it was a remedial measure that the [Buyer] had to postpone signing the Certificate of Acceptance and paying the remaining amount. However, the [Buyer] had never expressed that it would not pay the remaining amount. Before filing the arbitration application, the [Seller] had never requested the [Buyer] to pay interest on the unpaid remaining amount; in addition, the condition for the remaining payment was not satisfied, so the [Buyer] did not delay the payment at all. Therefore, this request lacked factual and legal basis, and should be dismissed. [Seller]'s rebuttal The [Seller]'s arbitration agent alleged that: 1. The [Seller]'s delay of delivery was caused by the [Buyer]'s delayed issuance of L/C, so the [Buyer] should bear the liability for the delay of delivery. (1) According to either the shipping time stipulated in the Contract or international customs, the [Seller] was neither obligated to inform the [Buyer] to issue the L/C, nor obligated to notify the [Buyer] of the shipping time. (2) Since the [Buyer] should bear the liability for the delay of delivery, the [Seller] should not pay the alleged penalty. (3) When receiving the goods, the [Buyer] was obligated to make the payment. 2. After the [Seller] had satisfied the duty to perform warranty services for six months, the [Buyer] still refused to make the remaining payment; after the [Seller] gave the [Buyer] a reasonable period and urged many times, the [Buyer] still failed to pay; therefore, the [Seller] had to exercise the defense right of first performance. OPINION OF THE ARBITRATION TRIBUNAL 1. The applicable law The Arbitration Tribunal noted that Article 17 of the Contract stipulates that the United Convention on Contracts for International Sales of Goods (CISG) applies. The Arbitration Tribunal confirmed that CISG applies to this case. 2. The basic facts in this case After hearing this case, the Arbitration Tribunal confirmed the following facts: a. On 7 July 2000, the [Seller] and the [Buyer] signed the Contract in this case stipulating: - Goods: The [Seller] shall sell to the [Buyer] a set of Multiplex AOE ("AOE") and a set

China International Economic & Trade Arbitration Commission CIETAC (PRC) Arbitration Award

China International Economic & Trade Arbitration Commission CIETAC (PRC) Arbitration Award China International Economic & Trade Arbitration Commission CIETAC (PRC) Arbitration Award Arbitration particulars Facts of the case Position of the parties - [Buyer]'s claims - [Seller]'s response Main

More information

UNITED NATIONS CONVENTION ON CONTRACTS FOR THE INTERNATIONAL SALE OF GOODS (1980) [CISG]

UNITED NATIONS CONVENTION ON CONTRACTS FOR THE INTERNATIONAL SALE OF GOODS (1980) [CISG] Go to CISG Table of Contents Go to Database Directory UNITED NATIONS CONVENTION ON CONTRACTS FOR THE INTERNATIONAL SALE OF GOODS (1980) [CISG] For U.S. citation purposes, the UN-certified English text

More information

INTERNATIONAL SALE OF GOODS ACT

INTERNATIONAL SALE OF GOODS ACT c t INTERNATIONAL SALE OF GOODS ACT PLEASE NOTE This document, prepared by the Legislative Counsel Office, is an office consolidation of this Act, current to December 2, 2015. It is intended for information

More information

Guangdong Higher People's Court [10 October 2004]

Guangdong Higher People's Court [10 October 2004] [PROCEEDINGS] Guangdong Higher People's Court [10 October 2004] Translation [*] by Meihua Xu [**] PARTIES AND COUNSEL. Plaintiff (Appellant, Defendant of counterclaims, hereafter, [Seller]): Inland Sea

More information

SALE OF GOODS (VIENNA CONVENTION) ACT 1986 No. 119

SALE OF GOODS (VIENNA CONVENTION) ACT 1986 No. 119 SALE OF GOODS (VIENNA CONVENTION) ACT 1986 No. 119 NEW SOUTH WALES TABLE OF PROVISIONS 1. Short title 2. Commencement 3. Interpretation 4. Act binds Crown 5. Convention to have the force of law 6. Convention

More information

United Nations Convention On Contracts For The International Sale Of Goods, 1980 (CISG) United Nations (UN)

United Nations Convention On Contracts For The International Sale Of Goods, 1980 (CISG) United Nations (UN) United Nations Convention On Contracts For The International Sale Of Goods, 1980 (CISG) United Nations (UN) Copyright 1980 United Nations (UN) ii Contents Contents PART I - Sphere of Application and General

More information

Standard Conditions of Sale and Terms of Delivery of

Standard Conditions of Sale and Terms of Delivery of Standard Conditions of Sale and Terms of Delivery of I. General 1. These Standard Conditions of Sale and Terms of Delivery (hereinafter referred to as Terms of Delivery ) apply exclusively to our goods

More information

Russian Federation arbitration proceeding 155/2003 of 16 March 2005

Russian Federation arbitration proceeding 155/2003 of 16 March 2005 Russian Federation arbitration proceeding 155/2003 of 16 March 2005 1. SUMMARY OF RULING Translation [*] by Sophie Tkemaladze [**] 1.1 The decision is made in respect of the Respondent [Seller], which

More information

Gafta No.125. Copyright THE GRAIN AND FEED TRADE ASSOCIATION

Gafta No.125. Copyright THE GRAIN AND FEED TRADE ASSOCIATION Effective for contracts dated from 1 st January 2006 Gafta No.125 Copyright THE GRAIN AND FEED TRADE ASSOCIATION ARBITRATION RULES GAFTA HOUSE 6 CHAPEL PLACE RIVINGTON STREET LONDON EC2A 3SH Tel: +44 20

More information

General Terms and Conditions of Sale and Delivery of ERC Emissions-Reduzierungs-Concepte GmbH ( ERC )

General Terms and Conditions of Sale and Delivery of ERC Emissions-Reduzierungs-Concepte GmbH ( ERC ) 1. General General Terms and Conditions of Sale and Delivery of 1.1 The following Terms and Conditions shall exclusively apply to all business transactions with the Purchaser. They apply to business transactions

More information

GENERAL TERMS & CONDITIONS FOR SUPPLYING MATERIALS AND SERVICES TO COCA-COLA SABCO MOZAMBIQUE (GTCCCSM)

GENERAL TERMS & CONDITIONS FOR SUPPLYING MATERIALS AND SERVICES TO COCA-COLA SABCO MOZAMBIQUE (GTCCCSM) Signed for (all pages) on behalf of SUPPLIER and hereby warrants that (s)he is duly authorised to sign and accept this complete GTCCCSM, consisting of 9 (nine) pages and all it Appendices, on behalf of

More information

MICROSOFT DEVICE SERVICE TERMS AND CONDITIONS

MICROSOFT DEVICE SERVICE TERMS AND CONDITIONS MICROSOFT DEVICE SERVICE TERMS AND CONDITIONS SECTION 20 CONTAINS A BINDING ARBITRATION CLAUSE AND CLASS ACTION WAIVER IF YOU LIVE IN (OR IF A BUSINESS YOUR PRINCIPAL PLACE OF BUSINESS IS IN) THE UNITED

More information

Section III. Contract for Supply and Delivery of Goods

Section III. Contract for Supply and Delivery of Goods Section III. Contract for Supply and Delivery of Goods FPU.SF 19.18 IOM office-specific Ref. No.: IOM Project Code: LEG Approval Code / Checklist Code AGREEMENT FOR THE SUPPLY AND DELIVERY OF GOODS Between

More information

GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS

GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS 1. Applicability. 2. Delivery. GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS a. These terms and conditions of sale (these "Terms") are the only terms which govern the sale of the goods ("Goods") by

More information

GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS

GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS GENERAL TERMS AND CONDITIONS FOR THE SALE OF GOODS 1. Applicability. (a) These terms and conditions of sale (these "Terms") are the only terms which govern the sale of the goods ("Goods") by Tecogen Inc.

More information

General Terms and Conditions of Lm-therm Elektrotechnik AG, Sulzbachstraße 15, Aldersbach

General Terms and Conditions of Lm-therm Elektrotechnik AG, Sulzbachstraße 15, Aldersbach General Terms and Conditions of Lm-therm Elektrotechnik AG, Sulzbachstraße 15, 94501 Aldersbach 1 General; Scope of Validity (1) These General Terms and Conditions shall apply to all of our business relationships

More information

BAILMENT AGREEMENT FOR EQUIPMENT, TOOLING, CAPITAL AND PACKAGING Minth Purchasing Policy and WI Terms and Conditions of Bailment

BAILMENT AGREEMENT FOR EQUIPMENT, TOOLING, CAPITAL AND PACKAGING Minth Purchasing Policy and WI Terms and Conditions of Bailment BAILMENT AGREEMENT FOR EQUIPMENT, TOOLING, CAPITAL AND PACKAGING Minth Purchasing Policy and WI 3.1.15 Terms and Conditions of Bailment This Bailment Agreement for Equipment, Tooling, Capital or Packaging

More information

Alexandria Center for International Arbitration Semi-dried dates case of 10 January 2005

Alexandria Center for International Arbitration Semi-dried dates case of 10 January 2005 Alexandria Center for International Arbitration Semi-dried dates case of 10 January 2005 I. The Parties (1) The Claimant, (hereinafter referred to as "Claimant"), is a company incorporated and existing

More information

What Constitutes a Supplementary Award of CIETAC Arbitration? A Recent Interpretation by a Hong Kong Court

What Constitutes a Supplementary Award of CIETAC Arbitration? A Recent Interpretation by a Hong Kong Court What Constitutes a Supplementary Award of CIETAC Arbitration? A Recent Interpretation by a Hong Kong Court Steven Wei SU* In an action brought before the Court of First Instance of High Court of Hong Kong

More information

DISTRIBUTOR AGREEMENT

DISTRIBUTOR AGREEMENT DISTRIBUTOR AGREEMENT THIS AGREEMENT is made this day of, 19, by and between [Name of Company], with its principal place of business located at [Address] (the "Company") and [Name of Distributor], [Address]

More information

General Terms and Conditions of Business (GTC)

General Terms and Conditions of Business (GTC) General Terms and Conditions of Business (GTC) www.radys.com 1. Scope 1.1 Our goods offered in the online shop are intended exclusively for customers that are resident or have their registered office in

More information

ROGERS CORPORATION - TERMS AND CONDITIONS OF PURCHASE

ROGERS CORPORATION - TERMS AND CONDITIONS OF PURCHASE ROGERS CORPORATION - TERMS AND CONDITIONS OF PURCHASE THE FOLLOWING TERMS AND CONDITIONS, AND THOSE SPECIFIED ON THE FACE OF THIS PURCHASE ORDER, SHALL EXCLUSIVELY GOVERN THE PURCHASE OF ALL MATERIALS

More information

International Conditions of Sale for Customers not Resident in Germany

International Conditions of Sale for Customers not Resident in Germany International Conditions of Sale for Customers not Resident in Germany I. Application of the International Conditions of Sale 1. These International Conditions of Sale apply to all customers of Feldhaus

More information

DISPUTE RESOLUTION RULES

DISPUTE RESOLUTION RULES DISPUTE RESOLUTION RULES First Issued: March 1998 Amended: November 1999 Amended: July 2000 Amended: September 2001 Amended: September 2003 Amended: October 2004 Amended: May 2005 Amended: September 2005

More information

STANDARD TERMS AND CONDITIONS OF SALE

STANDARD TERMS AND CONDITIONS OF SALE 1. Sale And License STANDARD TERMS AND CONDITIONS OF SALE 1.1 Controlling Conditions of Sale. All purchases and sales of Products, including all parts, kits for assembly, spare parts and components thereof

More information

Shanghai International Economic and Trade Arbitration Commission (Shanghai International Arbitration Center) Arbitration Rules

Shanghai International Economic and Trade Arbitration Commission (Shanghai International Arbitration Center) Arbitration Rules Shanghai International Economic and Trade Arbitration Commission (Shanghai International Arbitration Center) Effective as from January 1, 2015 CONTENTS of Shanghai International Economic and Trade Arbitration

More information

GENERAL COMMERCIAL TERMS AND CONDITIONS FOR PURCHASE OF GOODS AND SERVICES

GENERAL COMMERCIAL TERMS AND CONDITIONS FOR PURCHASE OF GOODS AND SERVICES GENERAL COMMERCIAL TERMS AND CONDITIONS FOR PURCHASE OF GOODS AND SERVICES Definitions "Supplier" "Purchaser" "Goods" "Contract" shall mean the company contracting to supply the goods and/or perform works

More information

c. We shall be entitled to make deliveries in installments.

c. We shall be entitled to make deliveries in installments. page 1 A.W. Faber-Castell Vertrieb GmbH General Terms of Sale and Delivery Version: 02/2012 1. Scope of application These General Terms of Sale and Delivery shall be exclusively applicable to all contracts

More information

1 Application. Contrary conditions of the orderer, which Holmer hereby expressly objects to, shall not become part of the contract.

1 Application. Contrary conditions of the orderer, which Holmer hereby expressly objects to, shall not become part of the contract. General Sales and Delivery Conditions of Holmer Maschinenbau GmbH 1 Application The following conditions shall apply to any offers and contracts of Firma Holmer Maschinenbau GmbH hereinafter: Holmer regarding

More information

TERMS AND CONDITIONS OF SALES

TERMS AND CONDITIONS OF SALES 1. Acceptance No Contract, Order or information (literature, drawings etc.) provided to or by the Purchaser shall be binding on Infra Green Ltd unless confirmed in the Infra Green Ltd Order Confirmation.

More information

General Terms and Conditions of Gechter GmbH Werkzeug- und Maschinenbau Issue date: June, 2010

General Terms and Conditions of Gechter GmbH Werkzeug- und Maschinenbau Issue date: June, 2010 General Terms and Conditions of Gechter GmbH Issue date: June, 2010 I. General 1. Our General Terms and Conditions are applicable to all contracts arising from the business relationship with the contractual

More information

TENDER DOCUMENTS PROCUREMENT OF GOODS PRICE QUOTATIONS. Public Procurement Board. Accra, Ghana

TENDER DOCUMENTS PROCUREMENT OF GOODS PRICE QUOTATIONS. Public Procurement Board. Accra, Ghana TENDER DOCUMENTS PROCUREMENT OF GOODS PRICE QUOTATIONS Public Procurement Board Accra, Ghana October 2003 i Table Contents Table Contents... i Introduction and Instructions... 1 Section I. Invitation for

More information

GENERAL PURCHASING TERMS AND CONDITIONS. Strama-MPS Maschinenbau GmbH & Co. KG

GENERAL PURCHASING TERMS AND CONDITIONS. Strama-MPS Maschinenbau GmbH & Co. KG GENERAL PURCHASING TERMS AND CONDITIONS Strama-MPS Maschinenbau GmbH & Co. KG I. General Provisions 1.1. These Terms and Conditions of Purchase shall exclusively apply to orders of Strama-MPS Maschinenbau

More information

GENERAL PROVISIONS FOR FIXED-PRICE CONTRACTS (MATERIEL) (14 April 2015)

GENERAL PROVISIONS FOR FIXED-PRICE CONTRACTS (MATERIEL) (14 April 2015) GENERAL PROVISIONS FOR FIXED-PRICE CONTRACTS (MATERIEL) (14 April 2015) Clause l - DEFINITIONS As used throughout this contract, the following terms shall have the meaning set forth below: 1.1 The term

More information

General. Sales Conditions. (General Terms and Conditions) Solar Direkt GmbH Solar Direct Vertriebs GmbH Solar Direct Produkt GmbH

General. Sales Conditions. (General Terms and Conditions) Solar Direkt GmbH Solar Direct Vertriebs GmbH Solar Direct Produkt GmbH General Sales Conditions (General Terms and Conditions) Solar Direkt GmbH Solar Direct Vertriebs GmbH Solar Direct Produkt GmbH for commercial business Last amended: March 2010 1 Scope of application (1)

More information

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS

ICON DRILLING PURCHASE ORDER TERMS & CONDITIONS ICON DRILLING ABN 75 067 226 484 PURCHASE ORDER TERMS & CONDITIONS Acceptance of this offer is subject to the terms and conditions of this Agreement. Acceptance of materials, work or services, payment

More information

Trade Rules USPLTA 2016 Trade Rules ADOPTED, OCTOBER 22, 1994 AMENDED AND ADOPTED OCTOBER 17, 2008

Trade Rules USPLTA 2016 Trade Rules ADOPTED, OCTOBER 22, 1994 AMENDED AND ADOPTED OCTOBER 17, 2008 Trade Rules 2016 US Pea & Lentil Trade Association (USPLTA) 2780 W. Pullman Road Moscow, Idaho 83843-4024 USA Telephone: 208-882-3023 Email: info@usapulses.org Website: www.usapulses.org ADOPTED, OCTOBER

More information

Purchase Agreement TERMS AND CONDITIONS PRICES PAYMENT AND PAYMENT TERMS. Bright Ideas. Better Solutions. Benchmark is Branch Automation.

Purchase Agreement TERMS AND CONDITIONS PRICES PAYMENT AND PAYMENT TERMS. Bright Ideas. Better Solutions. Benchmark is Branch Automation. Purchase Agreement The following terms and conditions shall apply to the sale of goods or products ( goods or products ) associated with your invoice: TERMS AND CONDITIONS The obligations and rights of

More information

UNIFORM ACT ON THE CONTRACT FOR THE CARRIAGE OF GOODS BY ROAD

UNIFORM ACT ON THE CONTRACT FOR THE CARRIAGE OF GOODS BY ROAD UNIFORM ACT ON THE CONTRACT FOR THE CARRIAGE OF GOODS BY ROAD 569 570 TABLE OF CONTENTS CHAPTER I SCOPE OF APPLICATION AND DEFINITIONS...573 Scope of application...573 Definitions...573 CHAPTER II CONTRACT

More information

Kosovo. Regulation No. 2001/5

Kosovo. Regulation No. 2001/5 Kosovo Regulation No. 2001/5 on Pledges (adopted on 7 February 2001) Important Disclaimer The text should be used for information purposes only and appropriate legal advice should be sought as and when

More information

THE CYPRUS TOURISM ORGANIZATION (ADMINISTRATIVE AND FINANCIAL) REGULATIONS, 1970 TO 1997

THE CYPRUS TOURISM ORGANIZATION (ADMINISTRATIVE AND FINANCIAL) REGULATIONS, 1970 TO 1997 1.2 REPUBLIC OF CYPRUS P.I. 830/70 P.I. 64/85 P.I. 288/94 P.I. 41/95 P.I. 175/97. THE CYPRUS TOURISM ORGANIZATION (ADMINISTRATIVE AND FINANCIAL) REGULATIONS, 1970 TO 1997 (English translation and consolidation)

More information

Update on United States Court Decisions Concerning the CISG (cases decided in 2007 and 2008) 1

Update on United States Court Decisions Concerning the CISG (cases decided in 2007 and 2008) 1 Update on United States Court Decisions Concerning the CISG (cases decided in 2007 and 2008) 1 I. Formation of Contract. Eason Automation Systems, Inc., Plaintiff v. Thyssenkrupp Fabco, Corp., Defendant.

More information

Terms and Conditions of the Supply of Goods

Terms and Conditions of the Supply of Goods Terms and Conditions of the Supply of Goods 1. INTERPRETATION 1.1 Definitions. Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business. Conditions:

More information

5 TH INTERNATIONAL ADR MOOTING COMPETITION

5 TH INTERNATIONAL ADR MOOTING COMPETITION 5 TH INTERNATIONAL ADR MOOTING COMPETITION 28 JULY-02 AUGUST 2014 HONG KONG Before China International Economic and Trade Arbitration Commission (CIETAC), for Arbitration between CLAIMANTS Conglomerated

More information

Standard terms and conditions

Standard terms and conditions müller quadax gmbh Teslastraße 6 74670 Forchtenberg Germany Tel. +49 7947 828-20 Fax +49 7947 828-14 Email info@quadax.de Website www.quadax.de Section 1 General / scope of application (1) These standard

More information

General Terms and Conditions of Sale and Delivery of ECKART GmbH

General Terms and Conditions of Sale and Delivery of ECKART GmbH General Terms and Conditions of Sale and Delivery of ECKART GmbH (September 2010) 1. GENERAL 1.1 These General Terms and Conditions of Sale and Delivery (hereinafter called General Sales and Delivery Conditions

More information

Arbitration 174. This assertion was supported by a photograph apparently showing the relevant container.

Arbitration 174. This assertion was supported by a photograph apparently showing the relevant container. Arbitration 174 Date of Issue: November 2011 Claimant: & Respondent: DCT Seller DCT Buyer Arbitration Committee (AC) Andrew Wilsdon, nominated by GTA Claim Issues for determination: Dispute 1 underweight

More information

International Purchasing Conditions for Suppliers not Resident in Germany

International Purchasing Conditions for Suppliers not Resident in Germany International Purchasing Conditions for Suppliers not Resident in Germany I. Application of the International Purchasing Conditions 1. These International Purchasing Conditions apply to all suppliers to

More information

Class Unification of Law - Uniform Law (Rechtsvereinheitlichung) Summer term 2015

Class Unification of Law - Uniform Law (Rechtsvereinheitlichung) Summer term 2015 Class Unification of Law - Uniform Law (Rechtsvereinheitlichung) Summer term 2015 Time schedule of the class 09.04.2015 Basics of unification of law: notion, purposes, history 16.04.2015 Methods of unification

More information

STANDARD TERMS AND CONDITIONS OF SALES AND SERVICES ( AGREEMENT )

STANDARD TERMS AND CONDITIONS OF SALES AND SERVICES ( AGREEMENT ) STANDARD TERMS AND CONDITIONS OF SALES AND SERVICES ( AGREEMENT ) 1. BASIS OF SALE 1.1 EXION Asia Pte Ltd ( EXION ) shall sell and the Purchaser shall purchase the Goods and/or Services in accordance with

More information

PFIZER NEW ZEALAND LIMITED trading as Pfizer Consumer Healthcare (NZ) ("PCH") ("Supplier")

PFIZER NEW ZEALAND LIMITED trading as Pfizer Consumer Healthcare (NZ) (PCH) (Supplier) PFIZER NEW ZEALAND LIMITED trading as Pfizer Consumer Healthcare (NZ) ("PCH") ("Supplier") TERMS AND CONDITIONS OF SALE 1. ORDERS 1.1 The Supplier reserves the right to accept or decline, in whole or in

More information

GENERAL TERMS AND CONDITIONS

GENERAL TERMS AND CONDITIONS GENERAL TERMS AND CONDITIONS 1. GENERAL PROVISIONS 1. Applicability These General Terms and Conditions shall apply to all our quotations and any agreements entered into by us. In so far as the other party

More information

Arbitration Rules No.125

Arbitration Rules No.125 Effective for Contracts dated from 1 st September 2016 Arbitration Rules No.125 Copyright Printed in England and issued by Gafta THE GRAIN AND FEED TRADE ASSOCIATION 9 LINCOLN S INN FIELDS, LONDON WC2A

More information

HBE GmbH GENERAL PURCHASING TERMS. Section 1 Scope of validity, General. Section 2 Orders, Delivery contract, Call-off

HBE GmbH GENERAL PURCHASING TERMS. Section 1 Scope of validity, General. Section 2 Orders, Delivery contract, Call-off GENERAL PURCHASING TERMS HBE GmbH Section 1 Scope of validity, General 1. All goods, services and offers from our suppliers shall be rendered solely on the basis of these general purchasing terms (T&Cs).

More information

TRADING TERMS OF KLINGER LTD

TRADING TERMS OF KLINGER LTD 1. INTERPRETATION 1.1 In these terms of trade: (1) Business Day means a day other than Saturday, Sunday or a public holiday in the place in which a document is received or an act is done, as may be applicable;

More information

MEMORANDA for RESPONDENT TEAM 017

MEMORANDA for RESPONDENT TEAM 017 THIRD ANNUAL INTERNATIONAL ALTERNATIVE DISPUTE RESOLUTION MOOT COMPETITION MEMORANDUM FOR RESPONDENT TEAM 017 RESPONDENT CLAIMANT Chan Manufacturing Cadenza Chan Longo Imports Minuet Longo 1 CONTENTS AUTHORITIES...

More information

AGREEMENT WITH BUILDER THIS AGREEMENT MADE BETWEEN:

AGREEMENT WITH BUILDER THIS AGREEMENT MADE BETWEEN: AGREEMENT WITH BUILDER THIS AGREEMENT MADE BETWEEN: LUX RESIDENTIAL WARRANTY PROGRAM INC., a federally incorporated corporation doing business in Atlantic Canada AND BUILDER COMPANY NAME: ADDRESS: POSTAL

More information

APPLICATION FOR COMMERCIAL CREDIT ACCOUNT TRADING TERMS AND CONDITIONS

APPLICATION FOR COMMERCIAL CREDIT ACCOUNT TRADING TERMS AND CONDITIONS APPLICATION FOR COMMERCIAL CREDIT ACCOUNT TRADING TERMS AND CONDITIONS These Trading Terms and Conditions are to be read and understood prior to the execution of the Application for Commercial Credit Account.

More information

Introduction Agreement

Introduction Agreement Introduction Agreement between Spigo Malta Ltd. and Introducer Table of Contents 1.Interpretation...3 2.Introductions...4 3.Anti-bribery compliance...5 4.Commission and payment...6 5.Obligations of Spigo...8

More information

Quotation is not binding on Q4 until the order has been accepted in writing by Q4.

Quotation is not binding on Q4 until the order has been accepted in writing by Q4. Quotation is not binding on Q4 until the order has been accepted in writing by Q4. C. The quantity, quality and description of the goods shall be those set forth in Q4 s written Quotation (or other documentation

More information

COGNE UK LTD of Uniformity Steel Works, Don Road, Sheffield, S9 2UD General Conditions of Contract

COGNE UK LTD of Uniformity Steel Works, Don Road, Sheffield, S9 2UD General Conditions of Contract COGNE UK LTD of Uniformity Steel Works, Don Road, Sheffield, S9 2UD General Conditions of Contract THE CONDITIONS BELOW EXCLUDE OR LIMIT OUR LIABILITY, FOR US TO INSURE AGAINST UNLIMITED LIABILITY WOULD

More information

BIOMASS SUPPLY AGREEMENT Agreement Version 2/9/2018 (Check for updated agreements at:

BIOMASS SUPPLY AGREEMENT Agreement Version 2/9/2018 (Check for updated agreements at: BIOMASS SUPPLY AGREEMENT Agreement Version 2/9/2018 (Check for updated agreements at: http://www.mbioex.com/contracts) THIS BIOMASS SUPPLY AGREEMENT (the Agreement ) is made this day of, 20, by and between

More information

THE NATIONAL TREASURY. Republic of South Africa

THE NATIONAL TREASURY. Republic of South Africa THE NATIONAL TREASURY Republic of South Africa GOVERNMENT PROCUREMENT: GENERAL CONDITIONS OF CONTRACT July 2010 1 GOVERNMENT PROCUREMENT GENERAL CONDITIONS OF CONTRACT July 2010 NOTES The purpose of this

More information

General Terms and Conditions of Sale and Delivery

General Terms and Conditions of Sale and Delivery 1. Scope of the Terms and Provisions 1 Any and all of our sales transactions, deliveries and other services provided by OrganicCrops E.I.R.L. (hereinafter OrganicCrops ) inclusive of all subsequent transactions

More information

RSR LIMITED TERMS AND CONDITIONS OF SUPPLY (GOODS AND SERVICES)

RSR LIMITED TERMS AND CONDITIONS OF SUPPLY (GOODS AND SERVICES) RSR LIMITED TERMS AND CONDITIONS OF SUPPLY (GOODS AND SERVICES) 1. DEFINITIONS In these Conditions: Business Day means a day other than a Saturday, Sunday or public holiday in England when banks in London

More information

TERMS AND CONDITIONS OF BUSINESS- SALES OF GOODS & SERVICES. The buyer's attention is in particular drawn to the provisions of condition 10.4.

TERMS AND CONDITIONS OF BUSINESS- SALES OF GOODS & SERVICES. The buyer's attention is in particular drawn to the provisions of condition 10.4. TERMS AND CONDITIONS OF BUSINESS- SALES OF GOODS & SERVICES. The buyer's attention is in particular drawn to the provisions of condition 10.4. 1. INTERPRETATION 1.1 The definitions and rules of interpretation

More information

STANDARD TERMS AND CONDITIONS FOR THE PURCHASE OF GOODS. 1. Application

STANDARD TERMS AND CONDITIONS FOR THE PURCHASE OF GOODS. 1. Application STANDARD TERMS AND CONDITIONS FOR THE PURCHASE OF GOODS 1. Application The Buyer orders and the Supplier, by accepting the Order, agrees that it will supply the Goods specified and subject to these Conditions

More information

General Terms and Conditions (Updated: September 2018)

General Terms and Conditions (Updated: September 2018) ETHEN ROHRE GmbH Grüner Weg 5 D-52070 Aachen Telephone: +49 241 900716-0 Fax: +49 241 900716-29 E-mail: info@ethen-rohre.de Internet: www.ethen-rohre.de Aachen Commercial Register HRB 3129 Managing Directors:

More information

Please print and fax this to us. If you d prefer to sign electronically, please send an to:

Please print and fax this to us. If you d prefer to sign electronically, please send an  to: Please print and fax this to us. If you d prefer to sign electronically, please send an email to: dealers@fullfactorydistro.com 13502 Pumice St. Norwalk, CA 90650 Phone: (562) 623-9995 Fax: (562) 623-9885

More information

Standard Terms and Conditions for Sale of Goods

Standard Terms and Conditions for Sale of Goods Standard Terms and Conditions for Sale of Goods These Standard Terms and Conditions for the Sale of Goods (the Terms ) are applicable to all quotes, bids and sales of products and goods (the Goods ) by

More information

I GENERAL II OFFERS III PRICES IV PAYMENT

I GENERAL II OFFERS III PRICES IV PAYMENT I GENERAL 1. These terms and conditions are applicable to any and all offers made by REA Industrie en Handelsonderneming B.V., hereinafter referred to as: REA, as also to any and all other legal relationships

More information

Arbitration 187 This Arbitration was governed by the International Arbitration Act 1974 (Cth). Contract type - GTA FOB Contract No.

Arbitration 187 This Arbitration was governed by the International Arbitration Act 1974 (Cth). Contract type - GTA FOB Contract No. Arbitration 187 This Arbitration was governed by the International Arbitration Act 1974 (Cth). Contract type - GTA FOB Contract No. 1 Date of Issue: January 2014 Claimant: & Respondent: Export FOB seller

More information

General Terms and Conditions of MMG (March 2018) 1. Scope of Application

General Terms and Conditions of MMG (March 2018) 1. Scope of Application General Terms and Conditions of MMG (March 2018) 1. Scope of Application (1) All contractual relationships between MMG Aluminium AG, headquartered in Mayen, Germany, hereinafter referred to as MMG and

More information

Consultancy Agreement

Consultancy Agreement Consultancy Agreement between National IT and Telecom Agency Holsteinsgade 63 2100 Copenhagen Ø CVR number 26 76 93 88 ("NITA") and [ ] [ ] [ ] (Company registration number [ ]) ("The Consultant") concerning.

More information

General Terms and Conditions

General Terms and Conditions General Terms and Conditions I. General, Conclusion of Contract. 1. Our delivery and payment conditions are binding and ufficially acknowledged by the customer when placing an order. They shall also apply

More information

General Terms and Conditions of Business. Article 1 Conclusion of the Agreement. Article 2 Delivery. Article 3 Delivery Deadline and Acceptance

General Terms and Conditions of Business. Article 1 Conclusion of the Agreement. Article 2 Delivery. Article 3 Delivery Deadline and Acceptance Article 1 Conclusion of the Agreement 1. Unless otherwise expressly agreed, the "General Delivery Terms and Conditions" alone shall apply to all agreements, deliveries and other services included in the

More information

[INSERT NAME OF DEPOSIT PLACING ENTITY/PARTY A] as Principal. and. [INSERT NAME OF DEPOSIT TAKING ENTITY/PARTY B] as Agent

[INSERT NAME OF DEPOSIT PLACING ENTITY/PARTY A] as Principal. and. [INSERT NAME OF DEPOSIT TAKING ENTITY/PARTY B] as Agent Dated: 14 th August 2008 As approved by Shari'ah (pursuant to the Fatwa signed on 7 th September 2008) This document is in a non-binding, recommended form and intended to be used as a starting point for

More information

PRECIOUS METALS STORAGE AGREEMENT

PRECIOUS METALS STORAGE AGREEMENT PRECIOUS METALS STORAGE AGREEMENT This PRECIOUS METALS STORAGE AGREEMENT (this Agreement ) is dated as of, 201_, by and between TRANSCONTINENTAL DEPOSITORY SERVICES, LLC, a Delaware limited liability company

More information

TERMS AND CONDITIONS OF SALE MEDICAL EQUIPMENT

TERMS AND CONDITIONS OF SALE MEDICAL EQUIPMENT FUJINON Inc. Web Version: 01 (March 1, 2011) TERMS AND CONDITIONS OF SALE MEDICAL EQUIPMENT 1. Each quotation provided by FUJINON INC. (the Seller ), together with the Terms and Conditions of Sale provided

More information

AGREEMENT WITH BUILDER. NAME or COMPANY NAME: ADDRESS:

AGREEMENT WITH BUILDER. NAME or COMPANY NAME: ADDRESS: Rev. 04/15 AGREEMENT WITH BUILDER THIS AGREEMENT MADE BETWEEN: ATLANTIC HOME WARRANTY ( AHW ), a body corporate, carrying on business in the Atlantic Provinces and NAME or COMPANY NAME: ADDRESS: POSTAL

More information

3M GENERAL PURCHASE TERMS AND CONDITIONS

3M GENERAL PURCHASE TERMS AND CONDITIONS 1. Definitions 1.1. For the purposes of these General Purchase Terms and Conditions the following phrases are assigned the following meanings: a) 3M shall mean: 3M Wrocław Sp. z o.o. a company incorporated

More information

CENTRAL HUDSON GAS & ELECTRIC CORP. CONSOLIDATED BILL BILLING SERVICES AGREEMENT

CENTRAL HUDSON GAS & ELECTRIC CORP. CONSOLIDATED BILL BILLING SERVICES AGREEMENT CENTRAL HUDSON GAS & ELECTRIC CORP. CONSOLIDATED BILL BILLING SERVICES AGREEMENT This Agreement sets forth the terms and conditions under which Central Hudson will provide rate ready billing service to

More information

STANDARD TERMS AND CONDITIONS ACKNOWLEDGEMENT DELUXE PLASTICS

STANDARD TERMS AND CONDITIONS ACKNOWLEDGEMENT DELUXE PLASTICS STANDARD TERMS AND CONDITIONS ACKNOWLEDGEMENT DELUXE PLASTICS 1. Acceptance. This acknowledgment shall operate as Deluxe Plastics ( Deluxe ) acceptance of Buyer s purchase order, but such acceptance is

More information

PRECIOUS METALS STORAGE AGREEMENT

PRECIOUS METALS STORAGE AGREEMENT PRECIOUS METALS STORAGE AGREEMENT This PRECIOUS METALS STORAGE AGREEMENT (this Agreement ) is dated as of, 201_, by and between TRANSCONTINENTAL DEPOSITORY SERVICES, LLC, a Delaware limited liability company

More information

ARBITRATION RULES FOR THE TRANSPORTATION ADR COUNCIL

ARBITRATION RULES FOR THE TRANSPORTATION ADR COUNCIL ARBITRATION RULES FOR THE TRANSPORTATION ADR COUNCIL TABLE OF CONTENTS I. THE RULES AS PART OF THE ARBITRATION AGREEMENT PAGES 1.1 Application... 1 1.2 Scope... 1 II. TRIBUNALS AND ADMINISTRATION 2.1 Name

More information

The terms defined in this Article shall have the meanings ascribed to them herein whenever used in this Agreement :

The terms defined in this Article shall have the meanings ascribed to them herein whenever used in this Agreement : DISTRIBUTORSHIP AGREEMENT II This Distributorship Agreement (this "Agreement") is made and entered into this day of 20 by and between. a corporation duly organized and existing under the laws of the Republic

More information

EFTEC Engineering GmbH General Terms and Conditions of Purchase

EFTEC Engineering GmbH General Terms and Conditions of Purchase EFTEC Engineering GmbH General Terms and Conditions of Purchase (Update February 2010) 1 General provisions Scope of application (1) Our General Terms and Conditions of Purchase shall apply exclusively.

More information

International Conditions of Sale for Customers not Resident in Germany

International Conditions of Sale for Customers not Resident in Germany I. Application of the International Conditions of Sale 1. These International Conditions of Sale apply to all customers of Dr. Günther Kast GmbH & Co. Technische Gewebe Spezial-Fasererzeugnisse KG - hereinafter

More information

VIRTUALSCADA SOFTWARE LLC TERMS AND CONDITIONS OF SALE

VIRTUALSCADA SOFTWARE LLC TERMS AND CONDITIONS OF SALE VIRTUALSCADA SOFTWARE LLC TERMS AND CONDITIONS OF SALE VirtualSCADA Software LLC ("VIRTUALSCADA") and Customer, in consideration of the mutual covenants, agreements and provisions set forth herein and

More information

Subject: Supply and Delivery of Personal Protective Devices (PPD) - Respirators (N95 masks)

Subject: Supply and Delivery of Personal Protective Devices (PPD) - Respirators (N95 masks) Request for Quotation Date: 10 August 2012 Dear Sir/Madam, Subject: Supply and Delivery of Personal Protective Devices (PPD) - Respirators (N95 masks) 1. We hereby solicit your quotation for the supply

More information

S P P U R C H A S I N G S P WI- 03 P U R C H A S E O R D E R G T C DATE OF ISSUE: 15/11/2015 REVISION: 01

S P P U R C H A S I N G S P WI- 03 P U R C H A S E O R D E R G T C DATE OF ISSUE: 15/11/2015 REVISION: 01 S P. 1 0. 0 1 P U R C H A S I N G P U R C H A S E O R D E R G T C DATE OF ISSUE: 15/11/2015 REVISION: 01 1.0 PURPOSE These terms and conditions shall apply to the procurement of all goods, equipment, material

More information

STANDARD TERMS AND CONDITIONS FOR THE SUPPLY OF GOODS AND SERVICES

STANDARD TERMS AND CONDITIONS FOR THE SUPPLY OF GOODS AND SERVICES . DEFINITIONS: In this document the following words shall have the following meanings: 1.1 "Agreement" means these Terms and Conditions; 1.2 "Customer" means the organisation or person who purchases goods

More information

TERMS AND CONDITIONS FOR THE SALE OF GOODS AND SERVICES

TERMS AND CONDITIONS FOR THE SALE OF GOODS AND SERVICES 1. Applicability. These terms and conditions of sale ( Terms ) and the accompanying proposal for services or proposal for goods, as applicable, ( Proposal ) are the only terms which govern the sale of

More information

TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES

TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES THE CUSTOMER'S ATTENTION IS PARTICULARLY DRAWN TO THE PROVISIONS OF CLAUSE 8 (LIMITATION OF LIABILITY). 1. Interpretation The following definitions and rules

More information

a) " Agreement " means the agreement between B.C. Ltd dba Edge Telecom Consultants and Customer which is composed of:

a)  Agreement  means the agreement between B.C. Ltd dba Edge Telecom Consultants and Customer which is composed of: 1. Definitions In this agreement, the following capitalized words have the following meanings: a) " Agreement " means the agreement between 0997473 B.C. Ltd dba Edge Telecom Consultants and Customer which

More information

incorporate, or which are implied by trade, custom, practice or course of dealing.

incorporate, or which are implied by trade, custom, practice or course of dealing. CUSTOMER TERMS AND CONDITIONS 1. INTERPRETATION 1.1 Definitions. Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business. Conditions: the terms

More information

MEMORANDUM FOR CLAIMANT

MEMORANDUM FOR CLAIMANT SECOND ANNUAL INTERNATIONAL ALTERNATIVE DISPUTE RESOLUTION MOOT COMPETITION MEMORANDUM FOR CLAIMANT On behalf of: Mr. Charles Peng (Peng Importing Corporation) Against: Mr. Sigmund Freud (Freud Exporting)

More information

General Terms and Conditions of Sale

General Terms and Conditions of Sale General Terms and Conditions of Sale 1 Definitions and interpretation 1.1 In these Conditions the following terms have the following meanings: "Conditions" means the terms and conditions of sale set out

More information

BASF Tanzania Limited Standard Terms and Conditions of Sale

BASF Tanzania Limited Standard Terms and Conditions of Sale 1. SCOPE OF APPLICATION All current and future supplies of products and services (including any literature or other information) offered by BASF to the Customer (collectively referred to as the Goods )

More information

SaaS Software Escrow Agreement [Agreement Number EL ]

SaaS Software Escrow Agreement [Agreement Number EL ] SaaS Software Escrow Agreement [Agreement Number EL ] This Escrow Agreement ( Agreement ) is made on [INSERT DATE] by and among: 1) [Depositor Name, registered company number ######] located at [registered

More information