New South Wales Court of Appeal

Size: px
Start display at page:

Download "New South Wales Court of Appeal"

Transcription

1 Page 1 of 19 Reported Decision: 74 NSWLR 190 New South Wales Court of Appeal CITATION: Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69 HEARING DATE(S): 10 March 2009 JUDGMENT DATE: 15 April 2009 JUDGMENT OF: Allsop P at 1; Macfarlan JA at 17; Handley AJA at 76 DECISION: CATCHWORDS: LEGISLATION CITED: CATEGORY: (a) Leave to appeal granted. (b) Appeal dismissed. (c) The applicant/appellant to pay the respondent's costs of the leave application and of the appeal. CONTRACTS - Building and Construction Industry Security of Payment Act progress claim for amounts the subject of a previous claim - adjudicator's determination that most of previous claim not maintainable - whether further claim precluded by provisions of the Act or principles of estoppel - ESTOPPEL - issue estoppel - adjudication under Building and Construction Industry Security of Payment Act 1999 Building and Construction Industry Security of Payment Act 1999 Workers' Compensation and Rehabilitation Act 1981 (WA) Principal judgment CASES CITED: Bitannia Pty Ltd v Parkline Constructions Pty Ltd (2006) 67 NSWLR 9 Batistatos v Roads and Traffic Authority of New South Wales [2006] HCA 27; (2006) 226 CLR 256 D'Orta-Ekenaike v Victoria Legal Aid [2005] HCA 12; (2005) 223 CLR 1 John Goss Projects v Leighton Contractors & Anor [2006] NSWSC 798 Kuligowski v Metrobus [2004] HCA 34; ( ) 220 CLR 363 Rothnere v Quasar & Ors [2004] NSWSC 1151 Walton v Gardiner [1993] HCA 77; (1992-3) 177 CLR 393 TEXTS CITED: Spencer Bower, Turner and Handley, Res Judicata, 3rd ed

2 Page 2 of 19 (1996) Butterworths PARTIES: Dualcorp Pty Ltd (Appellant) Remo Constructions Pty Ltd (Respondent) FILE NUMBER(S): CA 40264/08 COUNSEL: SOLICITORS: LOWER COURT JURISDICTION: LOWER COURT FILE NUMBER(S): LOWER COURT JUDICIAL OFFICER: LOWER COURT DATE OF DECISION: F Corsaro SC/S Tzouganatos (Appellant) G Inatey SC/F Hicks/P Coady (Respondent) Turner Freeman (Appellant) Blackstone Waterhouse (Respondent) District Court DC 1685/08 Quirk DCJ 10 March 2009 IN THE SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL CA 50264/08 DC 1685/08 DUALCORP PTY LTD v REMO CONSTRUCTIONS PTY LTD Judgment ALLSOP P MACFARLAN JA HANDLEY AJA WEDNESDAY 15 APRIL ALLSOP P: I have had the advantage of reading in draft the reasons of Macfarlan JA. I agree with the orders proposed by his Honour. His Honour s reasons relieve me of the need to set out much of the background to and context of the appeal, as well as many of the provisions of the Building and Construction Industry Security of Payment Act 1999 (the Act ). 2 I agree with Macfarlan JA that the Act was not intended to permit the repetitious use of the

3 Page 3 of 19 adjudication process to require an adjudicator or successive adjudicators to execute the same statutory task in respect of the same claim on successive occasions. A party in the position of the applicant (Dualcorp), here, should not be able to re-ignite the adjudication process at will in order to have a second or third or fourth go at the process provided by the Act merely because it is dissatisfied with the result of the first adjudication. 3 The principal provisions of the Act that are directed to this question of repetition are ss 13(5) and (6) and 22(4). Macfarlan JA has dealt with s 22(4). I will return to that provision. 4 Subsections 13(5) and (6) should be read with s 8 and the definition of the phrase progress payment in s 4. Section 8 is in the following terms: (1) On and from each reference date under a construction contract, a person: (a) who has undertaken to carry out construction work under the contract, or (b) who has undertaken to supply related goods and services under the contract, is entitled to a progress payment. (2) In this section, reference date, in relation to a construction contract, means: (a) a date determined by or in accordance with the terms of the contract as the date on which a claim for a progress payment may be made in relation to work carried out or undertaken to be carried out (or related goods and services supplied or undertaken to be supplied) under the contract, or (b) if the contract makes no express provision with respect to the matter the last day of the named month in which the construction work was first carried out (or the related goods and services were first supplied) under the contract and the last day of each subsequent named month. The definition of progress payment in s 4 is as follows: In this Act: progress payment means a payment to which a person is entitled under section 8, and includes (without affecting any such entitlement): (a) the final payment for construction work carried out (or for related goods and services supplied) under a construction contract, or (b) a single or one-off payment for carrying out construction work (or for supplying related goods and services) under a construction contract, or (c) a payment that is based on an event or date (known in the building and construction industry as a milestone payment ). 5 In the relevant design and construction contract between Dualcorp Pty Ltd (as subcontractor) and Remo Construction Pty Ltd (as contractor), clause 8 dealt with contracting sum, payment and security. Clause 8.3 dealt with payment claims and certificates and, relevantly, stated: (a) At the times stated in Annexure A, item 11, and upon the times set out in Clauses 8.9 and 8.13, the Subcontractor may submit a Payment Claim to the Contractor. Save for the formalities of Clauses 8.9 and 8.13, a Payment Claim must include the value and description of work carried out by the Subcontractor in the performance of the Agreement

4 Page 4 of 19 to the permissible reference date ( Payment Claim ). (b) Within 10 days after receipt of a Payment Claim, the Contractor must issue to the Subcontractor a Payment Certificate ( Payment Certificate ) stating the amount of payment, which in the opinion of the Contractor, is to be made by the Contractor to the Subcontractor or by the Subcontractor to the Contractor ( Certified Amount ). The Contractor shall set out in the Payment Certificate the calculations employed to arrive at the Certified Amount and, if the Certified Amount is more than or less than the amount claimed in the Payment Claim, the reasons for the difference. (c) A Payment Claim must be submitted and received by the Contractor on each permissible reference date as provided within Annexure A, item 11, and upon the times set out in Clauses 8.9 and (d) In the event that the reference date falls on a day other than a defined business day, then the Subcontractor must submit a Payment Claim on the subsequent business day. 6 Annexure A, Item 11 was in the following form: Date for submission of payment claims: 15th of each month (reference date) 7 Clause 8.9 dealt with retention moneys. Clause 8.13 dealt with final payment claim in the following terms: Within 10 days after ground floor slab is formed up, the Subcontractor must submit to the Contractor a final Payment Claim endorsed as ( Final Payment Claim ) being a Payment Claim subject to the terms of this Agreement under Clause 8, together with all claims showing all claimed adjustments to the Contract Sum and all amounts received by the Subcontractor up to the date of the expiration of the Defects Liability Period. 8 As can be seen from the Act, s 13(5) a claimant is limited to one payment claim in respect of each reference date. Section 13(6) permits, however, inclusion in another payment claim (necessarily by reference to another reference date) of an amount that has been the subject of a previous claim. Amongst other usual and uncontroversial examples, this permits the submission of cumulative payment claims by reference to later reference dates, which include an amount the subject of a previous claim. In such circumstances, if there has been an adjudication, s 22(4) will apply to require the same value to be given to such work, subject to the qualification in that subsection. 9 Here, Dualcorp, after undertaking the works, left the site in November It claimed to have substantially completed the works under the contract in November A payment claim was made on 29 January 2008 attaching six invoices, four of which were dated 24 January 2008 and two of which were dated 29 January The relevant reference date was not identified on the claim or invoices. 11 On 3 March 2008, Dualcorp purported to serve a second payment claim annexing the same invoices and claiming the same amount. Again, no reference date was identified on the documentation.

5 Page 5 of Whether or not this was a final claim or a progress claim does not matter. The claim represented by the six invoices must have been in respect of only one reference date either 15 December 2007 or 15 January 2008, if pursuant to Annexure A, Item 11 or the reference date pursuant to the operation of cl 8.13, if a final payment claim. In either case, there must have been one reference date under the contract or the last day of the month as provided for by the Act, s 8(2)(b). 13 I see no warrant under either the contract or the Act, s 8 for permitting a party in Dualcorp s position to create fresh reference dates by lodging the same claim for the same completed works in successive payment claims. That is not the intended operation of the last phrase of s 8(2)(b) ( and the last day of each subsequent named month ). 14 Here, the work had been done; Dualcorp, the subcontractor, had left the site; it claimed payment by six invoices; six weeks later it repeated that claim by reference to the same invoices and, in my view, in respect of the same reference date. Dualcorp was prevented from serving the second payment claim. The terms of s 13(5) are a prohibition. The words cannot serve more than one payment claim are a sufficiently clear statutory indication that a document purporting to be a payment claim that is in respect of the same reference date as a previous claim is not a payment claim under the Act and does not attract the statutory regime of the Act. 15 For these reasons, Dualcorp was not entitled to proceed to judgment on a claim founded on the operation of the Act premised on the second payment claim of 3 March 2008 being a payment claim under the Act. 16 As to s 22(4) I agree with Macfarlan JA s approval of the approach of McDougall J to this section. I also agree that the Act as a whole generally manifests an intention to prevent repetitious reagitation of the same issues. The primary mechanism for the effectuation of that intention would appear to be ss 13(5) and 22(4). The former is sufficient to deal with the present controversy. I would leave to another occasion, should it be necessary, the consideration of principles of estoppel to prevent any apparently abusive operation of the Act not specifically covered by ss 13(5) and 22(4). 17 MACFARLAN JA: This is an application for leave to appeal from a decision of Quirk DCJ declining to enter summary judgment in favour of the applicant in the full amount claimed by it. The arguments of the parties have extended to those which would be put if leave were granted. Accordingly, it is open to the Court to determine now the appeal which would follow if the Court decided to grant leave. Nature of Case and Conclusion 18 The application for leave to appeal raised the question of whether a person making a progress claim under the Building and Construction Industry Security of Payment Act 1999 ( the Act ) who is dissatisfied with the determination of an adjudicator appointed to resolve disputes in relation to the claim may serve another claim and seek a redetermination of the same issues before the same, or another, adjudicator. My conclusion is that this would be contrary to the intent of the Act and that it is precluded by the principles of issue estoppel. Factual Circumstances 19 The proceedings relate to a subcontract between the respondent ( Remo ) as contractor and the applicant ( Dualcorp ) as sub-contractor for excavation and piling work at a building site at 97 Queens Road, Five Dock, Sydney. The parties agree that the subcontract was a construction

6 Page 6 of 19 contract within the meaning of that term as defined in s 4 of the Act. 20 Evidence called by Remo indicated that Dualcorp undertook the works and left the site in or about November 2007, with no further work having been completed by Dualcorp on site after that time. The proceedings were conducted at first instance on the basis that Dualcorp had substantially completed the work required under the subcontract. 21 On or about 29 January 2008, Dualcorp served a payment claim under the Act (the January Claim ). The claim attached six invoices (numbered 2129, 2130, 2131, 2132, 2136 and 2137) totalling $743, On 11 February 2008, Remo served a Payment Schedule pursuant to s 14 of the Act (a Payment Schedule ) which disputed the bulk of the claim in respect of the first four invoices but, save for an immaterial amount, conceded the claims in respect of invoices 2136 and Pursuant to the provisions of the Act, Dualcorp applied for adjudication of its claim in respect of the first four invoices. Mr Anthony Makin was appointed as adjudicator. 24 On 11 March 2008, Mr Makin determined that Dualcorp was entitled to an amount of $75, (which included an amount of $36, which had been accepted by Remo in its Payment Schedule). This was considerably less than the total of $659, of the four invoices the subject of the adjudication. 25 Pursuant to the provisions of the Act, Dualcorp sought and obtained judgment in the District Court for $75, based upon a certificate of the adjudicator. It was agreed between the parties that judgment was entered on 3 April Being dissatisfied with the amount to which Mr Makin determined it was entitled, Dualcorp, on or about 3 March 2008, made a further claim under the Act ( the March Claim ). The claim was based upon, and attached, the same six invoices the subject of the January Claim. The total of the March Claim was accordingly the same as that of the January Claim although for an unexplained reason there was a one cent difference. Neither party sought to attribute significance to that difference. 27 As a result of Remo not serving a Payment Schedule in relation to this claim, Dualcorp commenced proceedings in the District Court for the amount of the March Claim pursuant to the provisions of s 15 of the Act. The present application for leave to appeal is brought from the decision of Quirk DCJ declining to enter summary judgment in favour of Dualcorp in the full amount claimed by it. The Statutory Provisions 28 The Act provides a mechanism by which a person who undertakes construction work is able to obtain progress payments, even if the construction contract does not provide for them to be made. The procedure for obtaining a progress payment involves the making of a payment claim, the provision of a Payment Schedule by the person on whom the claim is made, the referral of any disputed claim to an adjudicator for determination and the payment of the progress payment determined to be payable. 29 The procedure is plainly one designed to facilitate the speedy making and payment of progress claims and, where necessary, the speedy resolution of any disputes. 30 The provisions of the Act of particular relevance to these proceedings are as follows:

7 Page 7 of 19 3 Object of Act (1) The object of this Act is to ensure that any person who undertakes to carry out construction work (or who undertakes to supply related goods and services) under a construction contract is entitled to receive, and is able to recover, progress payments in relation to the carrying out of that work and the supplying of those goods and services. (2) The means by which this Act ensures that a person is entitled to receive a progress payment is by granting a statutory entitlement to such a payment regardless of whether the relevant construction contract makes provision for progress payments. (3) The means by which this Act ensures that a person is able to recover a progress payment is by establishing a procedure that involves: (a) the making of a payment claim by the person claiming payment, and (b) the provision of a payment schedule by the person by whom the payment is payable, and (c) the referral of any disputed claim to an adjudicator for determination, and (d) the payment of the progress payment so determined. (4) It is intended that this Act does not limit: (a) any other entitlement that a claimant may have under a construction contract, or (b) any other remedy that a claimant may have for recovering any such other entitlement. 13 Payment claims (1) A person referred to in section 8 (1) who is or who claims to be entitled to a progress payment (the claimant) may serve a payment claim on the person who, under the construction contract concerned, is or may be liable to make the payment. (2) A payment claim: (a) must identify the construction work (or related goods and services) to which the progress payment relates, and (b) must indicate the amount of the progress payment that the claimant claims to be due (the claimed amount), and (c) must state that it is made under this Act. (3) The claimed amount may include any amount: (a) that the respondent is liable to pay the claimant under section 27 (2A), or (b) that is held under the construction contract by the respondent and that the claimant claims is due for release. (4) A payment claim may be served only within:

8 Page 8 of 19 (a) the period determined by or in accordance with the terms of the construction contract, or (b) the period of 12 months after the construction work to which the claim relates was last carried out (or the related goods and services to which the claim relates were last supplied), whichever is the later. (5) A claimant cannot serve more than one payment claim in respect of each reference date under the construction contract. (6) However, subsection (5) does not prevent the claimant from including in a payment claim an amount that has been the subject of a previous claim. 14 Payment schedules (1) A person on whom a payment claim is served (the respondent) may reply to the claim by providing a payment schedule to the claimant. (2) A payment schedule: (a) must identify the payment claim to which it relates, and (b) must indicate the amount of the payment (if any) that the respondent proposes to make (the scheduled amount). (3) If the scheduled amount is less than the claimed amount, the schedule must indicate why the scheduled amount is less and (if it is less because the respondent is withholding payment for any reason) the respondent s reasons for withholding payment. (4) If: (a) a claimant serves a payment claim on a respondent, and (b) the respondent does not provide a payment schedule to the claimant: (i) within the time required by the relevant construction contract, or (ii) within 10 business days after the payment claim is served, whichever time expires earlier, the respondent becomes liable to pay the claimed amount to the claimant on the due date for the progress payment to which the payment claim relates. 15 Consequences of not paying claimant where no payment schedule (1) This section applies if the respondent: (a) becomes liable to pay the claimed amount to the claimant under section 14 (4) as a consequence of having failed to provide a payment schedule to the claimant within the time allowed by that section, and

9 Page 9 of 19 (b) fails to pay the whole or any part of the claimed amount on or before the due date for the progress payment to which the payment claim relates. (2) In those circumstances, the claimant: (a) may: (i) recover the unpaid portion of the claimed amount from the respondent, as a debt due to the claimant, in any court of competent jurisdiction, or (ii) make an adjudication application under section 17 (1) (b) in relation to the payment claim, and (b) may serve notice on the respondent of the claimant s intention to suspend carrying out construction work (or to suspend supplying related goods and services) under the construction contract. (3) A notice referred to in subsection (2) (b) must state that it is made under this Act. (4) If the claimant commences proceedings under subsection (2) (a) (i) to recover the unpaid portion of the claimed amount from the respondent as a debt: (a) judgment in favour of the claimant is not to be given unless the court is satisfied of the existence of the circumstances referred to in subsection (1), and (b) the respondent is not, in those proceedings, entitled: (i) to bring any cross-claim against the claimant, or (ii) to raise any defence in relation to matters arising under the construction contract. 22 Adjudicator s determination (4) If, in determining an adjudication application, an adjudicator has, in accordance with section 10, determined: (a) the value of any construction work carried out under a construction contract, or (b) the value of any related goods and services supplied under a construction contract, the adjudicator (or any other adjudicator) is, in any subsequent adjudication application that involves the determination of the value of that work or of those goods and services, to give the work (or the goods and services) the same value as that previously determined unless the

10 Page 10 of 19 claimant or respondent satisfies the adjudicator concerned that the value of the work (or the goods and services) has changed since the previous determination. The Judgment at First Instance 31 Having referred to the submissions of the parties, the primary judge expressed the following views: The situation here is that, quite clearly, a large proportion of the monies which comprises this claim for summary judgment was dealt with in accordance with the Building and Construction Industry Security of Payment Act, by the referral to adjudication of those amounts claimed in the four invoices and the subsequent entry of judgment in respect of the amount determined by the adjudicator. Although it is clear that the judgment and the adjudication by the adjudicator itself are not final, and that the rights of the parties under the contract are still open to be litigated, the issues as between the parties in respect of those four invoices were dealt with by the adjudicator under the Act and I accept that to seek to have those same invoices in respect of the same work re-agitated is barred because of principles akin to res judicata at least or constitutes an abuse of process as submitted by Mr Hicks. In respect to that part of the amount claimed in these proceedings which was the subject of the earlier payment claim and consequent determination by the arbitrator, I am of the view that it would be an abuse of process for the Court to grant the application for summary judgment and therefore in respect of the larger proportion of the claim, the Court will not so grant. However, in respect of the two invoices which were not referred to adjudication and which were clearly rejected by Remo, in its letter to which I earlier referred, as valid payment claims, despite the issuing of a payment schedule in respect of those two invoices as well as the four other invoices which were the subject of adjudication, in my view the service of payment claims, that is the service of the two invoices numbered 2136 and 2137 on 3 or 4 March, were valid payment claims and in response to which there is no payment schedule served. Although the defence filed by Remo would suggest that all six invoices were dealt with initially in the same manner, I do not accept that this was the case. Nor do I accept the submission made in respect to the claim being a substantial completion payment claim, as that was rejected by Remo at the time of service. Therefore although the submissions and the pleadings by Remo are apposite to the four invoices numbered 2129 to 2132, they do not apply in my view to the other two invoices, 2136 and Although it is submitted by Remo that Dualcorp could have availed itself of the remedy available under s 16 of the Act, I do not necessarily agree. Because of the position taken by Remo upon the service of the six invoices in January 2008 it could have been argued by Remo that Dualcorp was not entitled to the benefit of section 16 because it had not served a valid or proper payment claim in respect of those two invoices. I therefore propose to enter summary judgment for the plaintiff in the amount claimed in those two invoices, which is in respect of invoice

11 Page 11 of , $1, and invoice 2137, $82, which amount total $83, plus interest to be agreed between the parties. Dualcorp s Submissions on Appeal 32 Dualcorp contended first that the Court was precluded by s 15 of the Act from giving effect to the defence based on principles akin to res judicata or abuse of process found by the primary judge to be applicable. It was said that s 15(4)(b) disentitling a respondent from raising any defence in relation to matters arising under the construction contract was applicable as each of the matters referred to by her Honour was such a defence. 33 Alternatively, it was submitted that the elements of res judicata were not present. In particular, that the decision of the adjudicators was not judicial in the required sense, was not final (reliance being placed on ss 25(4) and 32), was not on the merits (reliance being placed on s 32) and did not determine the same question as arose in the subsequent Court proceedings (reliance being placed on ss 25(4) and 32). 34 Dualcorp also submitted that the primary judge s decision to direct the entry of summary judgment in relation to the fifth and sixth of the invoices involved a denial of procedural fairness to Dualcorp. It was said that the possibility of her Honour taking that course was not raised with the parties and Dualcorp did not therefore have any opportunity to make submissions on the point. I do not consider that this submission should be accepted. It was open to her Honour to enter judgment for a lesser sum than that for which it was sought: the greater included the lesser. No prejudice has been suffered by Dualcorp by reason of the alleged procedural unfairness as the point was one of law and it was open to Dualcorp to put to this Court any reasons why her Honour s approach was inappropriate. In any event, the consequence of the point succeeding would be to Dualcorp s disadvantage as it would result in the judgment which it obtained (albeit limited) being set aside in the event that it was otherwise unsuccessful before this Court. In argument, it disclaimed any desire for this to occur. 35 Another submission made by Dualcorp was that the judgment entered below in its favour should be increased by the amounts of the items which it said the adjudicator did not determine on the merits but in effect decided on a non-suit basis, that is, upon the basis that he had insufficient evidence to accept the claim. It was accepted that this argument was not put at first instance. In my view, particularly bearing in mind the nature of the proceedings before this Court, that is, an application for leave to appeal in relation to a decision on a summary judgment application, the argument should not be entertained. In any event, as will be apparent from the reasons which appear below, the argument would not in my view have succeeded (see [71-72]). Remo s Submissions 36 Remo contended that the primary judge s approach was correct. It joined issue with the submissions of Dualcorp, particularly Dualcorp s contentions that the adjudicator did not constitute a relevant tribunal for the purposes of res judicata principles and that his decision was not sufficiently final to attract those principles. 37 Additionally, Remo contended that the March Claim conflicted with s 13(5) and (6) of the Act. Those subsections prohibit the making of more than one payment claim in respect of a single reference date, subject to the qualification that a claimant may include in a payment claim an amount that has been the subject of a previous claim. Remo contended that the relevant reference date in respect of each claim was the same and that because the claims were identical, subsection (6) did not render the prohibition in subsection (5) inapplicable. It was submitted that subsection (6) did not apply because it only dealt with a situation where the

12 Page 12 of 19 subsequent claim embraced more than the previous one: otherwise it would not be a case of the claimant including an amount from a previous claim in a subsequent claim. Defences able to be raised in Court proceedings seeking Judgment 38 The Act provides two avenues for a claimant to obtain a judgment in its favour. 39 The first is to be found in s 15 which applies where, as here, the recipient of a claim has not served a Payment Schedule. The section provides that in those circumstances the claimant may sue for the unpaid portion of the claimed amount as a debt in any court of competent jurisdiction. Subsection (4) provides that judgment is not to be given in favour of the claimant unless the court is satisfied that a Payment Schedule has not been served by the recipient of the claim and that the claimed amount is still outstanding. It also disentitles the respondent to the claim from bringing any cross claim and, as mentioned earlier, from raising any defence in relation to matters arising under the construction contract. 40 The provision as to cross-claims and defences is mirrored in s 25 which provides the other avenue for the obtaining of judgment. This section applies where there has been an adjudication. In that circumstance, the claimant may file an adjudication certificate as a judgment for a debt in any court of competent jurisdiction and enforce it accordingly. 41 The restrictions in these sections as to the defences that may be raised do not in my view prevent the raising of one based upon or, to use the primary judge s expression, akin to res judicata, or indeed issue estoppel if that defence is otherwise available. Such a defence could not in my view be described as a matter arising under the construction contract. Rather, it is a matter arising out of the proper construction of the Act in conjunction with relevant common law principles. The defence may thus be raised, as may one that service of a payment claim was not effective because it involved misleading or deceptive conduct (Bitannia Pty Ltd v Parkline Constructions Pty Ltd (2006) 67 NSWLR 9 especially at [96] per Basten JA). Finality: General Law Principles 42 In my view, the question of whether proceedings for judgment under s 15 can be defeated by proving that the payment claim (or part thereof) upon which the proceedings are based is inconsistent with an earlier adjudicator s determination under s 22 of the Act is to be determined by construing the Act against the background of relevant common law principles. In particular, it is necessary to determine whether the legislative intention was to confer upon adjudicators determinations a sufficient degree of finality to attract the principles of res judicata, issue estoppel or of the more general concept of abuse of process. Although not expressly mentioned by the primary judge, I include reference to issue estoppel as I consider it to fall within the umbrella of her description of principles akin to res judicata and abuse of process. Indeed, her reference to the issues having earlier been dealt with by the adjudicator suggests she had this principle in mind. 43 Before turning to the provisions of the Act, it is convenient to refer to some relevant general law principles and their possible application in the present circumstances. 44 It is a principle of the law that controversies, once resolved, are not to be reopened except in a few, narrowly defined, circumstances (D Orta-Ekenaike v Victoria Legal Aid [2005] HCA 12; (2005) 223 CLR 1 at [34]. The plurality judgment in D Orta went on to state that: The principal qualification to the general principle that controversies,

13 Page 13 of 19 once quelled, may not be reopened is provided by the appellate system. But even there, the importance of finality pervades the law. Restraints on the nature and availability of appeals, rules about what points may be taken on appeal and rules about when further evidence may be called in an appeal (in particular, the so-called "fresh evidence rule") are all rules based on the need for finality. As was said in the joint reasons in Coulton v Holcombe: "[i]t is fundamental to the due administration of justice that the substantial issues between the parties are ordinarily settled at the trial". (Citations omitted) (at [35]). 45 As pointed out, in D Orta, the principle of finality finds reflection in the doctrines of res judicata and issue estoppel (at [34]). 46 In Spencer Bower, Turner and Handley, Res Judicata, 3rd ed (1996) Butterworths it is said that the principle of res judicata is a substantive rule of law and is to the following effect: Where a final judicial decision has been pronounced on the merits by [a] judicial tribunal with jurisdiction over the parties and the subject matter, any party to such litigation, as against any other party is estopped in any subsequent litigation from disputing such decision on the merits (at [9]). 47 The requirements for issue estoppel incorporate a like requirement of finality of the earlier decision. These requirements were described by the High Court in Kuligowski v Metrobus [2004] HCA 34; ( ) 220 CLR 363 at [21] in the following terms: 21. In his speech in Carl Zeiss Stiftung v Rayner & Keeler Ltd (No 2) Lord Guest, after noting that the doctrine of issue estoppel had been accepted by Australian courts for a number of years, indicated that, for the doctrine to apply in the second set of proceedings, the requirements were: (1) that the same question has been decided; (2) that the judicial decision which is said to create the estoppel was final; and, (3) that the parties to the judicial decision or their privies were the same persons as the parties to the proceedings in which the estoppel is raised or their privies. (citations omitted) 48 It is well accepted that domestic tribunals are within the ambit of the res judicata principles. As Spencer Bower, Turner and Handley say: Every domestic tribunal, including any arbitrator, or other person or body or persons invested with authority to hear and determine a dispute by consent of the parties, court order, or statute, is a judicial tribunal for present purposes and its awards and decisions [are] conclusive unless set aside (citations omitted) (at [25]). The position is no different with issue estoppel, as Kuligowski illustrates. 49 The fact that adjudication proceedings under the Act are abbreviated in character does not mean that they are not of a sufficiently judicial character: the process is put in train because there is a dispute between the parties as to a monetary entitlement; an independent person is appointed to adjudicate the dispute; the issues are defined by a claim and a response to the claim; submissions including relevant documentation are put before the adjudicator (s 22(2)(c)

14 Page 14 of 19 and (d)); the adjudicator is obliged to make a determination in writing and to give reasons for the determination (s 22(3)). 50 In these circumstances I consider the critical question to be answered in deciding whether the principles of res judicata and issue estoppel are capable of applying to adjudicators determinations under the Act to be whether the Act, on its true construction, manifests an intention to confer a sufficient degree of finality on those determinations to attract those principles. Finality: Construction of the Act 51 Important features of the Act relevant to the degree of finality intended to be attached by the Act to adjudicators determinations are as follows: 52 First, the objects of the Act are relevant (see s 3). Clearly the overall intent of these is to provide a simple and quick means of contractors obtaining progress payments, with a mechanism being provided for the speedy resolution of disputes. It would be inconsistent with this objective to allow a claimant who was dissatisfied with an adjudication of its claim to obtain a reconsideration of the claim simply by serving another which was identical to, or included, the previous claim, especially if there was no limit to the number of times that a claimant could seek to have this reconsideration occur. 53 Secondly, as earlier mentioned, under s 13(5) only one payment claim may be served in respect of each reference date under the construction contract. There is a qualification that the claimant may include in a payment claim an amount that has been the subject of a previous claim. However, taking into account the Act s objectives and its provisions, I do not consider that that qualification can, or should, be read as authorising the inclusion in a payment claim of an amount which has been the subject of an earlier adjudication. It would in my view be inconsistent with the carefully structured procedures as to adjudication and the provisions, which I am in the course of mentioning, pointing towards finality of adjudication determinations to give it that construction. 54 Thirdly, in determining an adjudication application, an adjudicator is bound, unless he or she is satisfied that the value of the work has changed since the previous determination, to value construction work consistently with a valuation made in the course of a previous adjudication application (s 22(4)). I will refer to this provision again later. 55 Fourthly, under s 23(2) a respondent is required to pay any amount determined by the adjudicator. 56 Fifthly, under s 24, failure to pay an adjudicated amount may have the consequence that construction work is suspended. 57 Sixthly, s 25 provides that an adjudication certificate signed by the adjudicator may be filed as a judgment for a debt in any court of competent jurisdiction and is enforceable accordingly. If application is made by the respondent to have the judgment set aside, the defences that may be raised are restricted in the way referred to earlier (see [38] to [41] above). As well, it is expressly stated that the respondent is not entitled to challenge the adjudicator s determination. This is a strong indication of an intent to clothe the determination with a significant degree of finality. 58 Seventhly, whilst s 26 permits a new application for adjudication to be made, it narrowly defines the circumstances in which it may be made: that is, to circumstances where an

15 Page 15 of 19 adjudicator s notice of acceptance of appointment is not received within a defined time or the appointed adjudicator fails to determine the application within a defined time. It is implicit that new applications for determination may not be made in other circumstances. It would be curious if these constraints could be circumvented by the claimant simply lodging a new claim and basing a new application for adjudication on that claim, rather than on the earlier claim. 59 Eighthly, the argument in favour of inferring that adjudication determinations were intended to be conclusive is in my view strengthened when one has regard to the fact that they determine rights in relation to progress claims only and, by reason of s 32 of the Act, do not affect contractual rights. Thus, any inability of the claimant to reagitate the issues is confined to its rights as to progress payments. Its rights to put its case as fully and completely as it wishes in pursuit of a contractual claim are preserved. 60 These various provisions in my view indicate a legislative intent to render adjudication determinations relevantly conclusive. Such determinations do not conclude contractual rights. Section 32 expressly so provides. The Act however creates special statutory rights to progress payments. When a claim is made, a dispute arises and an adjudication determination resolves that dispute. I consider that determination to be final and binding between the parties as to the issues determined, except to the extent that the Act allows the determination to be revisited. It would in my view be quite contrary to the scheme of the Act to permit claimants simply to resubmit the already adjudicated claims if they were dissatisfied with the adjudication. 61 In Kuligowski the High Court considered the concept of finality in the context of a case concerned with issue estoppel. It said: A single final decision, then, is one which is not of an interlocutory character, but is completely effective unless and until rescinded, altered or amended. The fact that an appeal lies from a decision does not make it any less final. It must be final and conclusive on the merits : the cause of action must be extinguished by the decision which is said to create the estoppel (at [25], citations omitted). 62 Thus, in that case, decisions of a review officer appointed under the Workers Compensation and Rehabilitation Act 1981 (WA) were held to be sufficiently final for the purposes of the doctrine of issue estoppel. In the course of reaching that conclusion, their Honours said that the legislative goal of having workers compensation disputes heard and determined in an informal, quick and cheap manner would not be assisted by a construction of the legislation which prevented the doctrine of issue estoppel ever applying. That would increase the chance of double litigation of issues and vexation of parties (at [32]). These comments are equally applicable to the informal procedure laid down by the Act for the quick and cheap disposal of claims for progress payments. Section 22(4): previous valuations 63 I return now to s 22(4), as I said I would in [39] above. 64 Section 22(4) has been the subject of consideration by McDougall J in a number of judgments. In Rothnere v Quasar & Ors [2004] NSWSC 1151 his Honour said: 41. There is one other point that needs to be mentioned. Mr Christie submitted that, where s 22(4) referred to the valuation of construction work, it meant, in substance, the value that the respondent to a payment claim was liable to pay. That was a step in his argument which was that

16 Page 16 of 19 s 22(4) was introduced by the Building and Construction Industry Security of Payment (Amendment) Act 2002, to discourage what the Minister, in the Second [Reading] Speech, had referred to as "adjudicator shopping", and that it should be construed (if ambiguous) so as to facilitate the achievement of that end. 42. I do not think that it is possible to read s 22(4) in this way. Section 8 gives an entitlement to a progress payment for construction work. Section 10 sets out how construction work is to be valued. The phrase "construction work" itself is a defined phrase: see section A determination under the Act may involve both questions of quantification - the section 10 issue - and questions of entitlement; or it may involve one or the other. 44. In my judgment, s 22(4) itself makes it clear that an adjudication determination need not necessarily include the valuation of construction work: the use of the introductory word "If" makes this clear. Subsection (4) therefore only applies where a component of a determination - that is to say, in terms of s 22(1)(a), of the determination of the amount of the progress payment (if any) to be paid - includes a determination of the value of construction work. Where it does, then subs (4) applies. Where it does not (either because the work has not at all been valued before or because the value of the work has changed) then s 10(1) applies. But there is nothing in these considerations that indicates that the phase "construction work" when used in s 22(4) should be construed in any way other than the way that it is used throughout the Act. 65 In John Goss Projects v Leighton Contractors & Anor [2006] NSWSC 798; (2006) 66 NSWLR 707, his Honour said: 37. The provisions of the relevant construction contract (s 22(2)(b)) will be relevant for a number of reasons. They may specify the reference dates on and from which a claimant has an entitlement to a progress payment (s 8). They may specify how the amount of the progress payment is to be calculated (s 9). They may specify how the construction work is to be valued (s 10). They may specify the due date for payment (s 11). 38. Although all those matters (and many others that may be taken into consideration under s 22(2)) go to the determination of the amount of the progress payment that is payable, they do not all deal with the valuation of the construction work that is the subject of the payment claim for that progress payment. The adjudicator s task may (and usually will) comprehend more than merely the valuation of the relevant construction work. Attention to the requirements of the contract may indicate that there are to be deducted from, or offset against, that value some particular amounts (for example, retention payments or conceded back charges for defective or incomplete work). Thus, construction work may be valued at a particular sum, but the adjudicated amount of the progress payment may be less than that sum because of some such deduction or offset.

17 Page 17 of Further, there may be a question as to whether the claimant is entitled to be paid at all for construction work: for example, for an unauthorised variation where the contract specifies that the written authority of the respondent is required as a precondition of entitlement. (I leave aside, for present purposes, the possible impact of s 34 on such a provision.) 40. he precise issue that s 22(4) posed for Mr Davenport was not the amount determined by Mr Dutton as the progress payment payable in respect of the March payment claim. It was whether, in determining the amount of that progress payment, Mr Dutton had valued construction work that was required to be valued in the second adjudication pursuant to the May payment claim. Sections 9 and 10 make it clear that there is a distinction between the calculation of the amount of a progress payment (which is, ultimately, what the adjudicator is required to do) and the valuation of construction work. That is the distinction that I sought to point out (on reflection, in a way that was perhaps unduly brief and somewhat delphic) in para [43] of my decision in Rothnere. 66 I agree with the approach taken by McDougall J to the construction of s 22(4). As his Honour points out, there are many issues of potential relevance to a progress claim which could not aptly be described as involving the determination of the value of the construction work. For example, s 11 of the Act provides that if the contract makes a relevant express provision, a progress payment becomes due and payable on the date on which the payment becomes due and payable in accordance with the terms of the contract. If a claim for a progress payment were made prior to a date stipulated by the contract and an adjudicator rejected the claim because it was premature, that determination could not in my view be said to be, or involve, one as to the value of the construction work. 67 I do not consider however that s 22(4) should be regarded as an exhaustive statement of the matters determined by an earlier adjudication which are binding on a subsequent adjudicator. For reasons I have given, I consider that the Act when read as a whole manifests an intention to preclude reagitation of the same issues. Thus, if questions of entitlement have been resolved by an adjudication determination, those findings may not in my view be reopened upon a subsequent adjudication. Likewise, if no subsequent adjudication occurs but a claimant proceeds (as here) to seek judgment following upon the failure of the other party to serve a Payment Schedule the claimant should be denied judgment to the extent that what it seeks is inconsistent with findings of the adjudicator. Issue Estoppel and Abuse of Process 68 Thus the primary judge here was correct in considering that principles akin to res judicata or abuse of process were applicable. Consistent with that broad description, I conclude that the principles of issue estoppel were applicable. Primarily because temporal considerations are of particular significance in relation to progress claims, the analogy between an adjudicator s determination and a completed cause of action which the principles of res judicata would require is an incomplete one. It is best that the applicable principles be recognised to be those of issue estoppel. The more general principle of abuse of process is probably also applicable but it is unnecessary to reach a final view about this. This principle involves a broad concept insusceptible of a formulation comprising closed categories (Batistatos v Roads and Traffic Authority of New South Wales [2006] HCA 27; (2006) 226 CLR 256 at [9]) but certainly including within its ambit an attempt to litigate anew a case which has formerly been disposed

18 Page 18 of 19 of by earlier proceedings (Walton v Gardiner [1993] HCA 77; (1992-3) 177 CLR 378 at 393). 69 As pointed out in Kuligowski, for the principle of issue estoppel to apply, the same issue must have been earlier determined as is later sought to be reagitated (at [40]). Thus, if a progress claim were rejected by an adjudicator because it was premature by reason of the date stipulated for payment by the contract, a later claim made on a timely basis would not be precluded. However (to take as an example the issue which was before McDougall J in John Goss Projects) if a progress claim were rejected because it was not made in accordance with express requirements of the contract, that determination would be binding on a subsequent adjudicator before whom the same issue arose. Similarly, it would be an abuse of process for the claimant to rely upon a later progress claim in response to which no Payment Schedule was served to obtain judgment on a basis conflicting with issues resolved in the earlier determination. 70 I thus disagree with the view ultimately arrived at by McDougall J in John Goss Projects that s 22(4) defines the extent to which an adjudicator is bound by an earlier adjudication. The view that the claimant once disappointed by an adjudicator can seek a different determination from another, or indeed from a succession of others, until a favourable decision is reached would in my view conflict with the policy of the Act to render adjudicators determinations final on issues which they resolved, subject only to provisions of the Act conferring limited rights of correction of determinations. 71 Dualcorp asserts that this approach could produce unfair outcomes where a claim has not been the subject of adjudication on the merits but has been rejected for want of evidence. It was submitted that because of the unfairness that would flow from precluding a claimant bolstering its evidence on another adjudication, it cannot have been intended that adjudications would be conclusive. 72 I do not agree. It is not at all unusual that persons seeking remedies in courts or other forums have a once only opportunity to bring forward evidence and submissions in support of their claim. This is in fact the usual situation and is consistent with what the High Court in D Orta referred to as the central and pervading tenet of the judicial system that controversies, once resolved, are not to be reopened except in a few, narrowly defined, circumstances (at [34]). Conclusion 73 My conclusion is that the primary judge was correct to refuse summary judgment in respect of the amounts which were the subject of the four invoices referred to in the adjudicator s determination. The issues relevant to Dualcorp s rights to progress payments in respect of the amounts in those invoices had been determined by the adjudicator. The application for summary judgment (and judgment) was therefore inconsistent with that determination. 74 As the application for leave to appeal raised an issue of general importance in relation to the construction of the Act, I would grant leave to appeal. As I have concluded that the primary judge was correct in the course she took, the appeal should be dismissed. 75 The orders I propose are as follows: (a) Leave to appeal granted. (b) Appeal dismissed. (c) The applicant/appellant to pay the respondent s costs of the leave application

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: PARTIES: FILE NO: 4490 of 2010 DIVISION: PROCEEDING: ORIGINATING COURT: John Holland Pty Ltd v Schneider Electric Buildings Australia Pty Ltd [2010] QSC 159 JOHN HOLLAND

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: PARTIES: David & Gai Spankie & Northern Investment Holdings Pty Limited v James Trowse Constructions Pty Limited & Ors [2010] QSC 29 DAVID & GAI SPANKIE & NORTHERN

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: ACN 060 559 971 Pty Ltd v O Brien & Anor [2007] QSC 91 PARTIES: FILE NO/S: BS51 of 2007 DIVISION: PROCEEDING: ACN 060 559 971 PTY LTD (ACN 060 559 971) (formerly ABEL

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: Gemini Nominees Pty Ltd v Queensland Property Partners Pty Ltd ATF The Keith Batt Family Trust [2007] QSC 20 PARTIES: GEMINI NOMINEES PTY LTD (ACN 011 020 536) (plaintiff)

More information

HIGH COURT OF AUSTRALIA

HIGH COURT OF AUSTRALIA HIGH COURT OF AUSTRALIA GAGELER J PLAINTIFF S3/2013 PLAINTIFF AND MINISTER FOR IMMIGRATION AND CITIZENSHIP & ANOR DEFENDANTS Plaintiff S3/2013 v Minister for Immigration and Citizenship [2013] HCA 22 26

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: PARTIES: Doolan and Anor v Rubikcon (Qld) Pty Ltd and Ors [07] QSC 68 SANDRA DOOLAN AND STEPHEN DOOLAN (applicants) v RUBIKCON (QLD) PTY LTD ACN 099 635 275 (first

More information

AN OVERVIEW OF THE BUILDING AND CONSTRUCTION INDUSTRY SECURITY OF PAYMENT ACT

AN OVERVIEW OF THE BUILDING AND CONSTRUCTION INDUSTRY SECURITY OF PAYMENT ACT Steven Goldstein - Edmund Barton Chambers AN OVERVIEW OF THE BUILDING AND CONSTRUCTION INDUSTRY SECURITY OF PAYMENT ACT INTRODUCTION Although the Building and Construction Industry Security of Payment

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: Martinek Holdings Pty Ltd v Reed Construction (Qld) Pty Ltd [2009] QCA 329 PARTIES: MARTINEK HOLDINGS PTY LTD ACN 106 533 242 (applicant/appellant) v REED CONSTRUCTION

More information

Projects Disputes in Australia: Recent Cases

Projects Disputes in Australia: Recent Cases WHITE PAPER June 2017 Projects Disputes in Australia: Recent Cases The High Court of Australia and courts in other Australian States have recently ruled on matters of significant importance to the country

More information

Adjudicators Discussion 15 June 2016

Adjudicators Discussion 15 June 2016 Probuild Constructions v DDI Group Alucity v ASC/ Alucity v Hick Adjudicators Discussion 15 June 2016 David Campbell-Williams Two recent cases Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd

More information

Reinforcing Security of Payment in NSW

Reinforcing Security of Payment in NSW Philip Davenport 2011 Despite set backs in the Supreme Court, the NSW Government is firmly behind security of payment and has now strengthened security of payment for subcontractors by giving them the

More information

Brodyn P/L t/as Time Cost and Quality v Davenport [2004] Adj.L.R. 11/03

Brodyn P/L t/as Time Cost and Quality v Davenport [2004] Adj.L.R. 11/03 Brodyn Pty. Ltd. t/as Time Cost and Quality v. Philip Davenport (1) Dasein Constructions P/L (2) Judgment : New South Wales Court of Appeal before Mason P ; Giles JA ; Hodgson JA : 3 rd November 2004.

More information

Building and Construction Industry Security of Payment Act 1999

Building and Construction Industry Security of Payment Act 1999 Building and Construction Industry Security of Payment Act 1999 Reprint history: Reprint No 1 30 September 2003 Long Title An Act with respect to payments for construction work carried out, and related

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: PARTIES: FILE NO/S: DIVISION: PROCEEDING: Vadasz v Bloomer Constructions (Qld) Pty Ltd [2009] QSC 261 MICHAEL CHRISTOPHER VADASZ TRADING AS AUSTRALIAN PILING COMPANY

More information

Mott MacDonald Ltd v London & Regional Properties Ltd [2007] Adj.L.R. 05/23

Mott MacDonald Ltd v London & Regional Properties Ltd [2007] Adj.L.R. 05/23 JUDGMENT : HHJ Anthony Thornton QC. TCC. 23 rd May 2007 1. Introduction 1. The claimant, Mott MacDonald Ltd ( MM ) is a specialist engineering multi-disciplinary consultancy providing services to the construction

More information

Financiers' Certifier Direct Deed

Financiers' Certifier Direct Deed Document for Release Execution Version Stage One - East West Link The Minister for Roads on behalf of the Crown in right of the State of Victoria State Aquenta Consulting Pty Ltd Financiers' Certifier

More information

New South Wales Court of Appeal

New South Wales Court of Appeal BCS Strata Management Pty. Limited t/as Body Corporate Services v. Robinson & Anor.... Page 1 of 10 New South Wales Court of Appeal [Index] [Search] [Download] [Help] BCS Strata Management Pty. Limited

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: Cousins v Mt Isa Mines Ltd [2006] QCA 261 PARTIES: TRENT JEFFERY COUSINS (applicant/appellant) v MT ISA MINES LIMITED ACN 009 661 447 (respondent/respondent) FILE

More information

2010, Federation Press, Sydney.

2010, Federation Press, Sydney. Legal Maxims and Adjudication Philip Davenport 2012 1 This is a paper presented at a seminar by the Adjudication Forum Incorporated in Sydney on 6 March 2012. Section 22(2) of the Building and Construction

More information

Arbitration Act 1996

Arbitration Act 1996 Arbitration Act 1996 An Act to restate and improve the law relating to arbitration pursuant to an arbitration agreement; to make other provision relating to arbitration and arbitration awards; and for

More information

AT MELBOURNE BUSINESS LIST BUILDING CASES DIVISION Case No. CI JOHN ARVANITIS AND GEORGE ARVANITIS --- HIS HONOUR JUDGE SHELTON.

AT MELBOURNE BUSINESS LIST BUILDING CASES DIVISION Case No. CI JOHN ARVANITIS AND GEORGE ARVANITIS --- HIS HONOUR JUDGE SHELTON. !Undefined Bookmark, I IN THE COUNTY COURT OF VICTORIA AT MELBOURNE BUSINESS LIST BUILDING CASES DIVISION Not Restricted Case No. CI-05-04479 AGE OLD BUILDERS PTY LTD (ACN 068 142 638) Plaintiff V JOHN

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: PARTIES: FILE NO: 12888 of 2008 DIVISION: PROCEEDING: ORIGINATING COURT: Taylor v Queensland Law Society Incorporated [2011] QSC 8 SYLVIA PAMELA TAYLOR (appellant)

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: PARTIES: Conveyor & General Engineering Pty Ltd v Basetec Services Pty Ltd and Anor [2014] QSC 30 CONVEYOR & GENERAL ENGINEERING PTY LTD ACN 091 865 235 (Applicant)

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: PARTIES: Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd & Ors [2010] QSC 95 NORTHBUILD CONSTRUCTION PTY LTD (applicant) v CENTRAL INTERIOR LININGS

More information

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory

Arbitration Act CHAPTER Part I. Arbitration pursuant to an arbitration agreement. Introductory Arbitration Act 1996 1996 CHAPTER 23 1 Part I Arbitration pursuant to an arbitration agreement Introductory 1. General principles. 2. Scope of application of provisions. 3. The seat of the arbitration.

More information

Financiers' Certifier Direct Deed

Financiers' Certifier Direct Deed RFP Version Stage One - East West Link [ ] State [ ] Financiers' Certifier Contents 1. Defined terms & interpretation... 1 1.1 Project Agreement definitions... 1 1.2 Defined terms... 1 1.3 Interpretation...

More information

Waiver, Estoppel and Election in the context of adjudication applications

Waiver, Estoppel and Election in the context of adjudication applications 1 Waiver, Estoppel and Election in the context of adjudication applications Adjudication Forum 13 November 2012 Max Tonkin The Pareto Principal Italian economist Vilfredo Pareto observed in 1906 that 80%

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: John Holland Pty Ltd v TAC Pacific Pty Ltd & Ors [2009] QSC 205 PARTIES: FILE NO: BS 2388 of 2009 DIVISION: PROCEEDING: ORIGINATING COURT: JOHN HOLLAND PTY LIMITED

More information

Building and Construction Industry Security of Payment Act 1999 No 46

Building and Construction Industry Security of Payment Act 1999 No 46 Building and Construction Industry Security of Payment Act 1999 No 46 Current version for 27 June 2017 to date (accessed 15 November 2017 at 14:57) Status information New South Wales Status information

More information

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV JUDGMENT OF COOPER J

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV JUDGMENT OF COOPER J IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV 2006-404-004969 UNDER the District Courts Act 1947 IN THE MATTER OF BETWEEN AND an appeal against a Judgment of the District Court at Auckland dated

More information

R B Stewart QC, I Rosic and S S McMullan for Appellant A R B Barker QC and J G Walton for Respondents JUDGMENT OF THE COURT REASONS OF THE COURT

R B Stewart QC, I Rosic and S S McMullan for Appellant A R B Barker QC and J G Walton for Respondents JUDGMENT OF THE COURT REASONS OF THE COURT IN THE COURT OF APPEAL OF NEW ZEALAND CA28/2017 [2017] NZCA 36 BETWEEN AND CUSTOM STREET HOTEL LIMITED Appellant PLUS CONSTRUCTION NZ LIMITED First Respondent PLUS CONSTRUCTION CO LIMITED Second Respondent

More information

PLANNING AND ENVIRONMENT COURT OF QUEENSLAND

PLANNING AND ENVIRONMENT COURT OF QUEENSLAND PLANNING AND ENVIRONMENT COURT OF QUEENSLAND CITATION: PARTIES: Waterman & Ors v Logan City Council & Anor [2018] QPEC 44 NORMAN CECIL WATERMAN AND ELIZABETH HELEN WATERMAN AS TRUSTEE UNDER INSTRUMENT

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: Matrix Projects (Qld) Pty Ltd v Luscombe [2013] QSC 4 PARTIES: MATRIX PROJECTS (QLD) PTY LTD ACN 089 633 607 trading as MATRIX HOMES (Applicant) v TONY JASON LUSCOMBE

More information

GUTSCHE FAMILY INVESTMENTS (PTY) LIMITED

GUTSCHE FAMILY INVESTMENTS (PTY) LIMITED IN THE HIGH COURT OF SOUTH AFRICA EASTERN CAPE LOCAL DIVISION, PORT ELIZABETH CASE NO: 4490/2015 DATE HEARD: 02/03/2017 DATE DELIVERED: 30/03/2017 In the matter between GUTSCHE FAMILY INVESTMENTS (PTY)

More information

THE VALIDITY OF ADJUDICATORS DETERMINATIONS CONTAINING ERRORS OF LAW: THE NSW JUDICIAL APPROACH

THE VALIDITY OF ADJUDICATORS DETERMINATIONS CONTAINING ERRORS OF LAW: THE NSW JUDICIAL APPROACH THE VALIDITY OF ADJUDICATORS DETERMINATIONS CONTAINING ERRORS OF LAW: THE NSW JUDICIAL APPROACH Jeremy Coggins 1 and Timothy O Leary School of Natural & Built Environments, University of South Australia,

More information

Court of Appeal Supreme Court. New South Wales. Abergeldie Contractors Pty Ltd v Fairfield City Council

Court of Appeal Supreme Court. New South Wales. Abergeldie Contractors Pty Ltd v Fairfield City Council Court of Appeal Supreme Court New South Wales Case Name: Abergeldie Contractors Pty Ltd v Fairfield City Council Medium Neutral Citation: [2017] NSWCA 113 Hearing Date(s): 5 May 2017 Decision Date: 26

More information

Issues raised from Adjudication Determinations. The Security of Payment (SOP) Act came into effect on 1 April 2005.

Issues raised from Adjudication Determinations. The Security of Payment (SOP) Act came into effect on 1 April 2005. Security Of Payment Issues raised from Adjudication Determinations Edwin Lee Partner, Rajah & Tann 2 August 2007 1 Presentation Overview The Security of Payment (SOP) Act came into effect on 1 April 2005.

More information

Developments In Building And Construction Law

Developments In Building And Construction Law Page 1 of 6 Print Page Close Window Developments In Building And Construction Law Developments In Building And Construction Law Robert McDougall * 30th Anniversary Conference of Institute of Arbitrators

More information

[2005] VCAT Arrow International Australia Pty Ltd Indevelco Pty Ltd Perpetual Nominees Ltd as custodian of the Colonial First State Income Fund

[2005] VCAT Arrow International Australia Pty Ltd Indevelco Pty Ltd Perpetual Nominees Ltd as custodian of the Colonial First State Income Fund VICTORIAN CIVIL AND ADMINISTRATIVE TRIBUNAL CIVIL DIVISION DOMESTIC BUILDING LIST VCAT REFERENCE NO. D181/2004 CATCHWORDS Requests for Further and Better Particulars and further discovery nature of this

More information

New South Wales Court of Appeal

New South Wales Court of Appeal 1 of 27 23/01/2012 4:04 p.m. New South Wales Court of Appeal CITATION: John Holland Pty. Limited v. Roads & Traffic Authority of New South Wales & Ors. [2007] NSWCA 19 HEARING DATE(S): 16 November 2006

More information

Body Corporate Plan No. PS509946A v VM Romano Construction Group Pty Ltd & Anor (Domestic Building) [2009] VCAT 1662

Body Corporate Plan No. PS509946A v VM Romano Construction Group Pty Ltd & Anor (Domestic Building) [2009] VCAT 1662 VICTORIAN CIVIL AND ADMINISTRATIVE TRIBUNAL CIVIL DIVISION DOMESTIC BUILDING LIST VCAT REFERENCE NO. D679/2007 CATCHWORDS Whether leave to withdraw earlier admissions should be granted APPLICANT FIRST

More information

CITATION: Firedam Civil Engineering Pty Ltd v Shoalhaven City Council [2009] NSWSC 802

CITATION: Firedam Civil Engineering Pty Ltd v Shoalhaven City Council [2009] NSWSC 802 NEW SOUTH WALES SUPREME COURT CITATION: Firedam Civil Engineering Pty Ltd v Shoalhaven City Council [2009] NSWSC 802 JURISDICTION: Equity FILE NUMBER(S): 55037/2009 HEARING DATE(S): 24 July 2009 JUDGMENT

More information

INPEX OPERATIONS AUSTRALIA PTY LTD v JKC AUSTRALIA LNG PTY LTD DENIAL OF NATURAL JUSTICE IN ADJUDICATION PROCEEDINGS A CASE NOTE I.

INPEX OPERATIONS AUSTRALIA PTY LTD v JKC AUSTRALIA LNG PTY LTD DENIAL OF NATURAL JUSTICE IN ADJUDICATION PROCEEDINGS A CASE NOTE I. INPEX OPERATIONS AUSTRALIA PTY LTD v JKC AUSTRALIA LNG PTY LTD DENIAL OF NATURAL JUSTICE IN ADJUDICATION PROCEEDINGS A CASE NOTE GORDON SMITH Barrister & Solicitor* Chartered Arbitrator, and Adjudicator

More information

Index. Volume 21 (2005) 21 BCL

Index. Volume 21 (2005) 21 BCL Index Abandoned claims judgment on, principally concerned with costs, 12-13, 33-44 whether cost reduction appropriate because of, 125 Access to the premises AS 4917-2003, 9-10 Acts Interpretation Act 1954

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: Perpetual Limited v Registrar of Titles & Ors [2013] QSC 296 PARTIES: PERPETUAL LIMITED (ACN 000 431 827) (FORMERLY KNOWN AS PERPETUAL TRUSTEES AUSTRALIA LIMITED (ACN

More information

DISTRICT COURT OF QUEENSLAND

DISTRICT COURT OF QUEENSLAND DISTRICT COURT OF QUEENSLAND CITATION: T&M Buckley Pty Ltd v 57 Moss Rd Pty Ltd [2010] QDC 60 PARTIES: T&M BUCKLEY PTY LTD t/as SHAILER CONSTRUCTIONS (ABN 66 010 052 043) Plaintiff/Applicant v 57 MOSS

More information

CONSTITUTIONAL COURT OF SOUTH AFRICA THE PRESIDENT OF THE REPUBLIC OF SOUTH AFRICA

CONSTITUTIONAL COURT OF SOUTH AFRICA THE PRESIDENT OF THE REPUBLIC OF SOUTH AFRICA CONSTITUTIONAL COURT OF SOUTH AFRICA Case CCT 41/99 JÜRGEN HARKSEN Appellant versus THE PRESIDENT OF THE REPUBLIC OF SOUTH AFRICA THE MINISTER OF JUSTICE THE DIRECTOR OF PUBLIC PROSECUTIONS: CAPE OF GOOD

More information

Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland

Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland Arbitration Act of United Kingdom United Kingdom of Great Britain and Northern Ireland (Royaume-Uni - Royaume-Uni de Grande-Bretagne et d'irlande du Nord) ARBITRATION ACT 1996 1996 CHAPTER 23 An Act to

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: PARTIES: Gladstone & District Leagues Club Ltd v Hutson & Ors [2007] QSC 010 GLADSTONE & DISTRICT LEAGUES CLUB LIMITED ACN 010 187 961 (applicant) v ROBERT HUTSON

More information

CONSTRUCTION ADJUDICATION. The Basis for Setting Aside Adjudication Determinations

CONSTRUCTION ADJUDICATION. The Basis for Setting Aside Adjudication Determinations (2010) 22 SAcLJ Construction Adjudication 583 CONSTRUCTION ADJUDICATION The Basis for Setting Aside Adjudication Determinations The Singapore Building and Construction Industry Security of Payment Act

More information

Eopply New Energy Technology Co Ltd v EP Solar Pty Ltd [2013] FCA 356 (19 April 2013)

Eopply New Energy Technology Co Ltd v EP Solar Pty Ltd [2013] FCA 356 (19 April 2013) http://www.austlii.edu.au/cgibin/sinodisp/au/cases/cth/fca/2013/356.html?stem=0&synonyms=0&query=title%28eopply%2 0%29 Eopply New Energy Technology Co Ltd v EP Solar Pty Ltd [2013] FCA 356 (19 April 2013)

More information

New South Wales Supreme Court

New South Wales Supreme Court State Crest New South Wales Supreme Court CITATION : HEARING DATE(S) : JUDGMENT DATE : JURISDICTION: CORVETINA TECHNOLOGY LTD v CLOUGH ENGINEERING LTD [2004] NSWSC 700 revised - 17/08/2004 29/07/2004 (judgment

More information

Index (2006) 22 BCL

Index (2006) 22 BCL Acceleration costs implied direction to accelerate works requires clearest evidence, 62-74 Accord and satisfaction whether terms of settlement amounted to, 16-30 Accreditation scheme Commonwealth building

More information

GARY OWEN BURGESS Appellant. TSB BANK LIMITED Respondent. Appellant in person D M Lester and G R Burgess for Respondent JUDGMENT OF THE COURT

GARY OWEN BURGESS Appellant. TSB BANK LIMITED Respondent. Appellant in person D M Lester and G R Burgess for Respondent JUDGMENT OF THE COURT DRAFT 5 August 2015 IN THE COURT OF APPEAL OF NEW ZEALAND CA47/2014 [2015] NZCA 361 BETWEEN AND GARY OWEN BURGESS Appellant TSB BANK LIMITED Respondent Hearing: 13 May 2015 Court: Counsel: Judgment: Cooper,

More information

Shalson v DF Keane Ltd [2003] Adj.LR. 02/21

Shalson v DF Keane Ltd [2003] Adj.LR. 02/21 JUDGMENT : Mr Justice Blackburne. Ch. Div. 21 st February 2003. 1. This is an appeal against orders made by Chief Registrar James on 28 November 2002, dismissing two applications by Peter Shalson to set

More information

SECURITY OF PAYMENT SECURITY OF PAYMENT THE PENDULUM HAS SWUNG TOO FAR. Philip Davenport

SECURITY OF PAYMENT SECURITY OF PAYMENT THE PENDULUM HAS SWUNG TOO FAR. Philip Davenport SECURITY OF PAYMENT SECURITY OF PAYMENT THE PENDULUM HAS SWUNG TOO FAR Philip Davenport In [2004] #94 ACLN pp.22 to 28 I criticised decisions of the NSW Supreme Court on the Building and Construction Industry

More information

Practice Guideline 9: Guideline for Arbitrators on Making Orders Relating to the Costs of the Arbitration

Practice Guideline 9: Guideline for Arbitrators on Making Orders Relating to the Costs of the Arbitration Practice Guideline 9: Guideline for Arbitrators on Making Orders Relating to the Costs of the Arbitration 1. Introduction 1.1 One of the most difficult and important functions which an arbitrator has to

More information

Dr. Nael Bunni, Chairman, Dispute Resolution Panel, Engineers Ireland, 22 Clyde Road, Ballsbridge, Dublin 4. December 2000.

Dr. Nael Bunni, Chairman, Dispute Resolution Panel, Engineers Ireland, 22 Clyde Road, Ballsbridge, Dublin 4. December 2000. Preamble This Arbitration Procedure has been prepared by Engineers Ireland principally for use with the Engineers Ireland Conditions of Contract for arbitrations conducted under the Arbitration Acts 1954

More information

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV [2014] NZHC 847. R T VINCENT LIMITED Plaintiff

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV [2014] NZHC 847. R T VINCENT LIMITED Plaintiff IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV-2013-404-004420 [2014] NZHC 847 BETWEEN AND R T VINCENT LIMITED Plaintiff WATTS & HUGHES CONSTRUCTION LIMITED Defendant Hearing: 25 February 2014

More information

Building and Construction Industry Security of Payment Amendment Act 2010 No 103

Building and Construction Industry Security of Payment Amendment Act 2010 No 103 New South Wales Building and Construction Industry Security of Payment Amendment Act Contents Page 1 Name of Act 2 2 Commencement 2 Amendment of Building and Construction Industry Security of Payment Act

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: Westfield Ltd v Stockland (Constructors) P/L & Ors [2002] QCA 137 PARTIES: WESTFIELD LTD ACN 000 317 279 (applicant/applicant) v STOCKLAND (CONSTRUCTORS) PTY LIMITED

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: PARTIES: In the matter of: ACN 103 753 484 Pty Ltd (in liq) formerly Blue Chip Development Corporation Pty Ltd [2011] QSC 64 TERRY GRANT VAN DER VELDE AND DAVID MICHAEL

More information

Court of Appeal Supreme Court New South Wales

Court of Appeal Supreme Court New South Wales Court of Appeal Supreme Court New South Wales Case Name: Capilano Honey Ltd v Dowling (No 1) Medium Neutral Citation: [2018] NSWCA 128 Hearing Date(s): 15 June 2018 Date of Orders: 15 June 2018 Date of

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: PARTIES: LQ Management Pty Ltd & Ors v Laguna Quays Resort Principal Body Corporate & Anor [2014] QCA 122 LQ MANAGEMENT PTY LTD ACN 074 733 976 (first appellant) LAGUNA

More information

Unit 5 : ADJUDICATION

Unit 5 : ADJUDICATION Unit 5 : ADJUDICATION WHAT IS ADJUDICATION? Adjudication is a quick and inexpensive process in which an independent third party makes binding decisions on construction contract disputes. The adjudicator

More information

THE ARBITRATION AND CONCILIATION (AMENDMENT) BILL, 2015

THE ARBITRATION AND CONCILIATION (AMENDMENT) BILL, 2015 1 AS INTRODUCED IN LOK SABHA Bill No. 252 of 2015. THE ARBITRATION AND CONCILIATION (AMENDMENT) BILL, 2015 A BILL to amend the Arbitration and Conciliation Act, 1996. BE it enacted by Parliament in the

More information

JOHN HOLLAND PTY LTD v CHIDAMBARA DENIAL OF NATURAL JUSTICE AND JURISDICTIONAL ERROR IN ADJUDICATION PROCEEDINGS A CASE NOTE I.

JOHN HOLLAND PTY LTD v CHIDAMBARA DENIAL OF NATURAL JUSTICE AND JURISDICTIONAL ERROR IN ADJUDICATION PROCEEDINGS A CASE NOTE I. JOHN HOLLAND PTY LTD v CHIDAMBARA DENIAL OF NATURAL JUSTICE AND JURISDICTIONAL ERROR IN ADJUDICATION PROCEEDINGS A CASE NOTE GORDON SMITH Barrister & Solicitor* Chartered Arbitrator, and Adjudicator I.

More information

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV [2016] NZHC UNDER the Arbitration Act 1996

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV [2016] NZHC UNDER the Arbitration Act 1996 IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV-2016-404-000219 [2016] NZHC 2011 UNDER the Arbitration Act 1996 BETWEEN AND CUSTOM STREET HOTEL LIMITED Plaintiff PLUS CONSTRUCTION NZ LIMITED First

More information

IN THE COURT OF APPEAL OF BELIZE AD 2014 CIVIL APPEAL NO 4 OF 2011 THE ATTORNEY GENERAL OF BELIZE

IN THE COURT OF APPEAL OF BELIZE AD 2014 CIVIL APPEAL NO 4 OF 2011 THE ATTORNEY GENERAL OF BELIZE IN THE COURT OF APPEAL OF BELIZE AD 2014 CIVIL APPEAL NO 4 OF 2011 THE ATTORNEY GENERAL OF BELIZE Appellant v BCB HOLDINGS LIMITED and THE BELIZE BANK LIMITED Respondents BEFORE The Hon Mr Justice Dennis

More information

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV [2015] NZHC JAMES HARDIE NEW ZEALAND Second Plaintiff

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV [2015] NZHC JAMES HARDIE NEW ZEALAND Second Plaintiff IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV-2014-404-002481 [2015] NZHC 2098 BETWEEN AND AND AND AUCKLAND COUNCIL First Plaintiff JAMES HARDIE NEW ZEALAND Second Plaintiff WEATHERTIGHT HOMES

More information

ATTENTION IS DRAWN TO THE ORDER PROHIBITING PUBLICATION OF CERTAIN INFORMATION (REFER PARAGRAPH [4-5]

ATTENTION IS DRAWN TO THE ORDER PROHIBITING PUBLICATION OF CERTAIN INFORMATION (REFER PARAGRAPH [4-5] ATTENTION IS DRAWN TO THE ORDER PROHIBITING PUBLICATION OF CERTAIN INFORMATION (REFER PARAGRAPH [4-5] IN THE EMPLOYMENT RELATIONS AUTHORITY WELLINGTON [2016] NZERA Wellington 158 5637953 BETWEEN AND CAROLINE

More information

CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY -

CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY - CITY INSOLVENCY DISCUSSION GROUP - CONSTRUCTION CONTRACTS AND INSOLVENCY - Background I practice in the building and construction industry as a mediator and conciliator, assisting contracted parties in

More information

FAILURE TO GIVE PROPER, GENUINE AND REALISTIC CONSIDERATION TO THE MERITS OF A CASE: A CRITIQUE OF CARRASCALAO

FAILURE TO GIVE PROPER, GENUINE AND REALISTIC CONSIDERATION TO THE MERITS OF A CASE: A CRITIQUE OF CARRASCALAO 2018 A Critique of Carrascalao 1 FAILURE TO GIVE PROPER, GENUINE AND REALISTIC CONSIDERATION TO THE MERITS OF A CASE: A CRITIQUE OF CARRASCALAO JASON DONNELLY In Carrascalao v Minister for Immigration

More information

Transfield Services (Australia) Pty Ltd

Transfield Services (Australia) Pty Ltd Adjudication No. 30068 15 December 2006 Claimant: Transfield Services (Australia) Pty Ltd Respondent: Roberts & Schaefer Australia Pty Ltd Adjudicator s Decision under the Building and Construction Industry

More information

Vee Networks Ltd. v Econet Wireless International Ltd. [2004] APP.L.R. 12/14

Vee Networks Ltd. v Econet Wireless International Ltd. [2004] APP.L.R. 12/14 JUDGMENT : Mr Justice Colman : Commercial Court. 14 th December 2004 Introduction 1. The primary application before the court is under section 67 of the Arbitration Act 1996 to challenge an arbitration

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: Three P/L v Body Corporate for Savoir Faire Community Titles Scheme 3841 [2008] QCA 167 PARTIES: THREE PTY LTD ACN 069 497 516 (respondent/plaintiff/respondent) v

More information

TERMS OF REFERENCE. Issued Date: 3 January 2011

TERMS OF REFERENCE. Issued Date: 3 January 2011 TERMS OF REFERENCE Issued Date: 3 January 2011 Last Revised Date: 21 March 2017 List of Revisions Revision No. Revision Date Effective Date Revision 1 23 November 2015 1 December 2015 Revision 2 21 March

More information

Online Case 8 Parvez. Mooney Everett Solicitors Ltd

Online Case 8 Parvez. Mooney Everett Solicitors Ltd 125 Online Case 8 Parvez v Mooney Everett Solicitors Ltd [2018] 1 Costs LO 125 Neutral Citation Number: [2018] EWHC 62 (QB) High Court of Justice, Queen s Bench Division, Sheffield District Registry 19

More information

Gafta No.125. Copyright THE GRAIN AND FEED TRADE ASSOCIATION

Gafta No.125. Copyright THE GRAIN AND FEED TRADE ASSOCIATION Effective for contracts dated from 1 st January 2006 Gafta No.125 Copyright THE GRAIN AND FEED TRADE ASSOCIATION ARBITRATION RULES GAFTA HOUSE 6 CHAPEL PLACE RIVINGTON STREET LONDON EC2A 3SH Tel: +44 20

More information

Supreme Court New South Wales

Supreme Court New South Wales Supreme Court New South Wales Case Name: Munsie v Dowling (No. 7) Medium Neutral Citation: Munsie v Dowling (No. 7) [2015] NSWSC 1832 Hearing Date(s): 30 November 2015 Date of Orders: 4 December 2015 Date

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: Maclag (No 11) P/L & Anor v Chantay Too P/L (No 2) [2009] QSC 299 PARTIES: MACLAG (NO 11) PTY LTD ACN 010 611 631 AS TRUSTEE FOR THE BURNS FAMILY TRUST (first plaintiff)

More information

SUPPLEMENT TO CHAPTER 20

SUPPLEMENT TO CHAPTER 20 Plaintiff S157/2002 v Commonwealth (2003) 195 ALR 24 The text on pages 893-94 sets out s 474 of the Migration Act, as amended in 2001 in the wake of the Tampa controversy (see Chapter 12); and also refers

More information

The court annexed arbitration program.

The court annexed arbitration program. NEVADA ARBITRATION RULES (Rules Governing Alternative Dispute Resolution, Part B) (effective July 1, 1992; as amended effective January 1, 2008) Rule 1. The court annexed arbitration program. The Court

More information

CASE NOTES PROBUILD CONSTRUCTIONS (AUST) PTY LTD V SHADE SYSTEMS PTY LTD [2018] HCA 4

CASE NOTES PROBUILD CONSTRUCTIONS (AUST) PTY LTD V SHADE SYSTEMS PTY LTD [2018] HCA 4 PROBUILD CONSTRUCTIONS (AUST) PTY LTD V SHADE SYSTEMS PTY LTD [2018] HCA 4 In Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4 ( Probuild ) the High Court held that the NSW security

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: PARTIES: Ericson v Queensland Building and Construction Commission [2014] QCA 297 IAN JAMES ERICSON (applicant) v QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION (respondent)

More information

THE STATUTES OF THE REPUBLIC OF SINGAPORE ARBITRATION ACT (CHAPTER 10)

THE STATUTES OF THE REPUBLIC OF SINGAPORE ARBITRATION ACT (CHAPTER 10) THE STATUTES OF THE REPUBLIC OF SINGAPORE ARBITRATION ACT (CHAPTER 10) (Original Enactment: Act 37 of 2001) REVISED EDITION 2002 (31st July 2002) Prepared and Published by THE LAW REVISION COMMISSION UNDER

More information

TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES

TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES TERMS AND CONDITIONS FOR THE SUPPLY OF SERVICES THE CUSTOMER'S ATTENTION IS PARTICULARLY DRAWN TO THE PROVISIONS OF CLAUSE 8 (LIMITATION OF LIABILITY). 1. Interpretation The following definitions and rules

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: R v Kelly [2018] QCA 307 PARTIES: R v KELLY, Mark John (applicant) FILE NO/S: CA No 297 of 2017 DC No 1924 of 2017 DIVISION: PROCEEDING: ORIGINATING COURT: Court of

More information

The ABTA Arbitration Scheme Rules

The ABTA Arbitration Scheme Rules 23 rd May 2016 The ABTA Arbitration Scheme Rules 1. Introduction 1.1 This Scheme is supplied exclusively by CEDR, Europe s leading independent dispute resolution service. 1.2 The Scheme has been designed

More information

SINGAPORE INTERNATIONAL ARBITRATION CENTRE (SIAC)

SINGAPORE INTERNATIONAL ARBITRATION CENTRE (SIAC) GUIDE TO INTERNATIONAL ARBITRATION IN SINGAPORE INTERNATIONAL ARBITRATION CENTRE (SIAC) Written By S. Ravi Shankar Advocate on Record - Supreme Court of India National President of Arbitration Bar of India

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: Santos Limited v Fluor Australia Pty Ltd [2016] QSC 129 PARTIES: SANTOS LIMITED ABN 80 007 550 923 (applicant) v FLUOR AUSTRALIA PTY LTD ABN 28 004 511 942 (respondent)

More information

IN THE LABOUR COURT OF SOUTH AFRICA, JOHANNESBURG

IN THE LABOUR COURT OF SOUTH AFRICA, JOHANNESBURG 1 IN THE LABOUR COURT OF SOUTH AFRICA, JOHANNESBURG Reportable In the matter between: Case no: J1812/2016 GOITSEMANG HUMA Applicant and COUNCIL FOR SCIENTIFIC AND INDUSTRIAL RESEARCH First Respondent MINISTER

More information

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV M VAN DER WAL BUILDERS & CONTRACTORS LTD Plaintiff

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV M VAN DER WAL BUILDERS & CONTRACTORS LTD Plaintiff IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV 2011-004-000083 BETWEEN AND M VAN DER WAL BUILDERS & CONTRACTORS LTD Plaintiff PETER WALKER AND PHILIPPA DUNPHY Defendants Hearing: 24 August 2011

More information

Adjudication under the Amended Victorian SOP Act

Adjudication under the Amended Victorian SOP Act Philip Davenport, 2007 The Victorian Building and Construction Industry Security of Payment Act 2002 commenced on 31 January 2003. It was based on the original NSW SOP Act of 1999 but that Act had by then

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: Schepis & Anor v Esanda Finance Corp Ltd & Anor [2007] QCA 263 PARTIES: ANTHONY SCHEPIS (first plaintiff/first appellant) MICHELE SCHEPIS (second plaintiff/second

More information

THE ELECTRICITY ARBITRATION ASSOCIATION

THE ELECTRICITY ARBITRATION ASSOCIATION The Rules of this Association were amended with effect from the 1 st January, 1993 in the manner herein set out. This is to allow for the reference to the Association, in accordance with its Rules, of

More information

The Court view of security of payment legislation in operation

The Court view of security of payment legislation in operation Page 1 of 9 Print Page Close Window The Court view of security of payment legislation in operation "The Court view of security of payment legislation in operation" Robert McDougall[1] 1. Introduction [1]

More information

The Gap in Sub-Clause 20.7 of The 1999 FIDIC Contracts for Major Works

The Gap in Sub-Clause 20.7 of The 1999 FIDIC Contracts for Major Works The Gap in Sub-Clause 20.7 of The 1999 FIDIC Contracts for Major Works by Nael G. Bunni, BSc, MSc, PhD, CEng, FICE, FIEI, FIStructE, FCIArb, FIAE, MConsEI. Chartered Engineer, Conciliator & Registered

More information

SUPREME COURT OF QUEENSLAND

SUPREME COURT OF QUEENSLAND SUPREME COURT OF QUEENSLAND CITATION: PARTIES: Bourne v Queensland Building and Construction Commission [2018] QSC 231 KATRINA MARGARET BOURNE (applicant) v QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION

More information

Judgment delivered on the 21st day of February locations throughout Australia but, so far as relevant here, at its office at 345 Queen

Judgment delivered on the 21st day of February locations throughout Australia but, so far as relevant here, at its office at 345 Queen IN THE COURT OF APPEAL SUPREME COURT OF QUEENSLAND Brisbane CA No 10157 OF 2002 Before McPherson JA Davies JA Philippides J [St George Bank Ltd v McTaggart & Ors; [2003] QCA 59] BETWEEN AND AND AND ST

More information