1 HSE guidelines SApril 2017 WORK PERMITS

2 Work safely or don t work at all There are strict procedures when working on installations and systems. After all, there s a risk for hazardous substances to be released. Therefore read the Permit to Work carefully and check if the described control measures have been taken. Then take the precautionary measures which belong to your job. Always be alert to prevent hazardous substances from being released. When in doubt: always ask or stop working! Speaking the same clear language regarding Health, Safety and Environment, and harmonisation of regulations by focusing primarily on agreements between companies and contractors. That is the goal the member parties of HSElife NL pursue. As well as the information that has already been harmonised, location and company-specific information also applies. Ask for it! Note: Check please at hselifenl.com/en/hse-items if you are using the latest version! 2

3 WORK PERMITS WHY ARE WORK PERMITS USED? to record agreed arrangements to recognize hazards and risks to lay down precautionary measures to promote good communication between the various parties 3

4 PURPOSE OF WORK PERMITS? to ensure the work is done safely to avert incidents WHO ARE INVOLVED IN A WORK PERMIT? Applicant Issuer Validator Holder - usually the contractor s work planner - usually people from the Operations department - usually people from the Operations department - the person who carries out the work 4

5 MINIMUM REQUIREMENTS Applicant SOS-SCC certificate (in Dutch a VOL-VCA certificate) Work permit training Issuer / Validator SOS-SCC certificate (in Dutch a VOL-VCA certificate) Work permit training Holder VCA basic Work permit training validity 10 years validity 2 years validity 10 years validity 2 years validity 10 years validity 2 years At least two people (roles) must be involved with the work permit. An issuer can also be a validator, an applicant can also be a holder. The issuer may only take on the role of applicant in exceptional cases. 5

6 WHEN IS A WORK PERMIT REQUIRED? Applicable to all activities carried out on plants, for instance: non-operations work; e.g. - maintenance and repairs of company plants high risk work; e.g. - working at heights - hoisting work on parts of the plant that are in operation/ under pressure - demolition work - work where fire or sparks are released - work for which additional personal protection equipment is required, incl. compressed air joint work by various disciplines; e.g. - conflicting tasks that could mutually affect each other - (too) many tasks are carried out simultaneously in a small area 6

7 SUPPLEMENTARY WORK PERMITS For (high) risk work, a supplementary work permit may have to be appended to the work permit: working in confined spaces excavation work diving operations If an activity and the associated risks cannot be clearly surveyed and properly managed, it s required to carry out a Task Risk Analysis in addition to the work permit. 7

8 HOW LONG DOES A WORK PERMIT REMAIN VALID? A work permit can be valid for a maximum of 7 successive working days. N.B.: the supplementary work permit for Excavation work can be valid for a maximum of 12 weeks. On the top of the supplementary work permit the corresponding work permit number of that week can be entered 12 times (that s because excavation work often takes longer). 8

9 PARTS OF THE WORK PERMIT Block 1 Work application Filled in by: applicant Block 2 Precautions to be taken by issuing department Filled in by: issuer Block 3 Precautions to be taken by holder Filled in by: applicant Block 4 Confirmation To be signed by: applicant, issuer, holder, and validator 9

10 APPLICANT TASKS AND RESPONSIBILITIES provide an accurate and clear description of the activities indicate the appropriate precautions to be taken in order to work safely, if necessary in consultation with the holder determine the risk category and, if necessary, to ensure that a Task Risk Analysis is carried out, jointly with the issuer 10

11 ISSUER - TASKS AND RESPONSIBILITIES determine the precautionary measures his department must take to create a safe working environment assess the proposed precautions to be taken by the holder provide product information (MSDS / WIK / chemistry cards), if necessary discuss the work permit determine additional requirements, if necessary determine whether gas measurements are necessary 11

12 HOLDER TASKS AND RESPONSIBILITIES carry out the work or provide direct supervision at the workplace study the work permit and assent to the required precautions discuss the work permit with those who carry out the work take the appropriate precautions and to ensue they are adhered to supervise proper execution of the work and to be physically present at the worksite stop the work in the event of any abnormality (alarm, doubt, incident) and contact the site supervisor and his own immediate superior sign off the work It is of crucial importance for the holder of the permit to understand how the work must be done safely. So be critical to the issuer and validator of the permit. After all everyone s safety is at stake. 12

13 VALIDATOR TASKS AND RESPONSIBILITIES check whether all prescribed precautions have been taken daily validation of the permit, provided the circumstances remain unchanged initial permit release must always take place at the worksite give the green light to start the work supervise observance of the permit s requirements and conditions 13

14 FILLING IN THE WORK PERMIT write clearly and legibly for everyone use as few abbreviations and acronyms as possible any (unauthorised) changes made later will invalidate the permit the white form is intended for the holder, who must carry it with him unless agreed otherwise the yellow form is intended for the issuer important information is on the back of the work permit 14

15 QUESTIONS? MORE INFORMATION? You can always approach the site manager/supervisor 15

16 5 TO REMEMBER Take the correct safety precautions and check them regularly Discuss the risks of the job and its safety precautions beforehand, with all involved (toolbox meeting) Conduct a last-minute risk analysis (LMRA) of the workplace immediately before starting the job and after the situation changes in any way Stop work immediately if anything unexpected happens (such as an incident or an alarm sounding) or if you are in any doubt, and contact the site manager or supervisor Tidy up the workplace regularly and sign off the job at the end of the day IMPORTANT! To be sure that everything is safe, ask the site manager or supervisor to explain the safety precautions in place

HSE guidelines. SApril 2017 WORK PERMITS

HSE guidelines. SApril 2017 WORK PERMITS HSE guidelines SApril 2017 WORK PERMITS Work safely or don t work at all There are strict procedures when working on installations and systems. After all, there s a risk for hazardous substances to be

More information

EDITION. March 2011 WORK PERMITS. Health. Safety HSEW A WAY OF LIVING. Standards for professionals, be aware!

EDITION. March 2011 WORK PERMITS. Health. Safety HSEW A WAY OF LIVING. Standards for professionals, be aware! NL EDITION March 2011 H S E W A WAY OF LIVING Safety Health Well-being Environment HSEW Standards for professionals, be aware! Work safely or don't work Work Permits are used within NAM to govern how work

More information

Sample appointment of Site Manager letter COMPANY NAME & LOGO/LETTERHEAD. OCCUPATIONAL HEALTH AND SAFETY ACT, 85 of 1993

Sample appointment of Site Manager letter COMPANY NAME & LOGO/LETTERHEAD. OCCUPATIONAL HEALTH AND SAFETY ACT, 85 of 1993 Sample appointment of Site Manager letter COMPANY NAME & LOGO/LETTERHEAD OCCUPATIONAL HEALTH AND SAFETY ACT, 85 of 1993 SECTION 16(2) ASSISTANT TO THE CHIEF EXECUTIVE OFFICER APPOINTMENT (Appointee s Name)

More information

Permit to Work Procedure

Permit to Work Procedure 1. Purpose The permit to work procedure provides a system for managing certain high risk activities at NT Airports sites. The purpose of this procedure is to: 2. Scope Provide a level of control to ensure

More information

Permit to Work Systems

Permit to Work Systems Permit to Work Systems Guidance Note 12 Jul 16 1 Permits to work systems Introduction This Guidance Note gives practical information about permit to work systems. A sample template has been included in

More information

OFFICE OF STATE HUMAN RESOURCES

OFFICE OF STATE HUMAN RESOURCES OFFICE OF STATE HUMAN RESOURCES NUMBER: HWP-1 TOTAL PAGES: 6 SUBJECT: Hot Work Program Effective Date: Revision Date: Revision #: RELATED LEGISLATION: This program outlines procedures for [Agency/University]

More information

Using the WPTW System: Frequently Asked Questions

Using the WPTW System: Frequently Asked Questions Using the WPTW System: Frequently Asked Questions The Wellsite Permit to Work (WPTW) System is a robust and comprehensive approach to the planning and authorisation of work activities on onshore wellsites.

More information

PRO Hot Work

PRO Hot Work MS&L Procedure PRO-4.5-0001-1-07 Hot Work Document Owner: Bill Kruesi HSSE Manager - Asset Mgmt. Owen Quake ANZ Engineering Authority Approved By: Bill Kruesi HSSE Manager - Asset Mgmt. Control of Work

More information

Work Health and Safety Act 2011 No 10

Work Health and Safety Act 2011 No 10 New South Wales Work Health and Safety Act 2011 No 10 Contents Part 1 Preliminary Page Division 1 Introduction 1 Name of Act 2 2 Commencement 2 Division 2 Object 3 Object 2 Division 3 Interpretation Subdivision

More information

Hot Work Procedures. Competent means possessing knowledge, experience and training to perform a specific duty.

Hot Work Procedures. Competent means possessing knowledge, experience and training to perform a specific duty. Hot Work Procedures Purpose This procedure will provide the knowledge and equipment required to minimize the identified workplace hazards associated with Hot Work. These procedures will provide: information

More information

ASBESTOS REGULATIONS Regulation Application of Division and Regulation Application of Division

ASBESTOS REGULATIONS Regulation Application of Division and Regulation Application of Division ASBESTOS REGULATIONS Regulation 4.3.19 Application of Division and Regulation 4.3.34 Application of Division [draft regulation 225 and 240] The duty to identify asbestos and prepare an asbestos register

More information

Health and Safety Policy

Health and Safety Policy Corporate Permit to Work SOP Document Control Summary Status: Version: Author/Title: Owner/Title: Approved by: Ratified: Related Trust Strategy and/or Strategic Aims Implementation Date: Review Date: Key

More information

Making sense of risk Risk engineering. Marine hot work Permit to Work (PTW) systems

Making sense of risk Risk engineering. Marine hot work Permit to Work (PTW) systems Marine hot work Permit to Work (PTW) systems Marine hot work Permit to Work (PTW) systems Hot work is any operation involving open flames or producing heat and/or sparks, including but not limited to welding,

More information

Revised Jan 2011 SAFETY COMMITTEE BY-LAWS

Revised Jan 2011 SAFETY COMMITTEE BY-LAWS SAFETY COMMITTEE BY-LAWS Name The name of the committee is the Coos Bay Fire & Rescue Safety Committee. Purpose The purpose of the Coos Bay Fire & Rescue Safety Committee is to bring all department members

More information

HOT WORK SAFETY GUIDELINE

HOT WORK SAFETY GUIDELINE HOT WORK SAFETY GUIDELINE SAFETY GUIDELINE 2017 1 Hot work safety guideline Index 1 Hot work training... 2 2 Purpose of the safety guidelines... 2 3 Binding force of the safety guidelines... 2 4 Definitions...

More information

PRO Hot Work

PRO Hot Work MS&L Procedure PRO-4.5-0001-1-07 Hot Work Version: 3 Authorised by: Tom Angliss & Owen Quake Authorisation Date: 21/11/2017 This document has been approved for release and changed as per the associated

More information

2018 OHS Act Post Implementation Update Presentation to Alberta Association for Safety Partnerships AGM & Conference September 2018

2018 OHS Act Post Implementation Update Presentation to Alberta Association for Safety Partnerships AGM & Conference September 2018 2018 OHS Act Post Implementation Update Presentation to Alberta Association for Safety Partnerships AGM & Conference September 2018 Key Concepts in Canadian OHS Law Internal responsibility Everyone in

More information

HOT WORK PROGRAM OSHA

HOT WORK PROGRAM OSHA HOT WORK PROGRAM 1910.252 OSHA Table of Contents Purpose... 3 Definitions... 3 Responsibilities... 3 Hot Work Permitted Locations... 5 Fire Prevention Precautions... 5 Personal Protective Equipment...

More information

Work Health and Safety Act 2011 No 10

Work Health and Safety Act 2011 No 10 New South Wales Work Health and Safety Act 2011 No 10 Status information Currency of version Current version for 1 January 2014 to date (generated 17 October 2014 at 13:12). Legislation on the NSW legislation

More information

CITY OF KAMLOOPS BY-LAW NO (AS AMENDED)

CITY OF KAMLOOPS BY-LAW NO (AS AMENDED) This is a consolidated by -law prepared by the City of Kamloops for convenience only. The City does not w arrant that the information contained in this consolidation is current. It is the responsibility

More information

Occupational Health and Safety Act

Occupational Health and Safety Act Occupational Health and Safety Act CHAPTER 7 OF THE ACTS OF 1996 as amended by 2000, c. 28, ss. 86, 87; 2004, c. 6, s. 24; 2007, c. 14, s. 7; 2009, c. 24; 2010, c. 37, ss. 117-126; 2010, c. 66; 2011, c.

More information

2012 District of Columbia Code Chapter 27 Underground Facilities Protection (Section to Section ) Section Definitions Section

2012 District of Columbia Code Chapter 27 Underground Facilities Protection (Section to Section ) Section Definitions Section Chapter 27 Underground Facilities Protection (Section 34-2701 to Section 34-2709) Section 34-2701 Definitions Section 34-2702 Formation and operation of 1-call center Section 34-2703 Availability of permit

More information

Title: Safe Work Procedure. Function: Ecology & Safety No.: CTC-SAF-037 Page: 1 of 6 Reviewed: 3/1/2017 Effective: 4/1/2017 Supersedes: 3/20/16

Title: Safe Work Procedure. Function: Ecology & Safety No.: CTC-SAF-037 Page: 1 of 6 Reviewed: 3/1/2017 Effective: 4/1/2017 Supersedes: 3/20/16 Site Procedure Function: Ecology & Safety No.: CTC-SAF-037 Page: 1 of 6 Preparer: BASF Safe Work Permit Team Owner: Site Manager (Signature on File) Approver: Director (Signature on File) 1. PURPOSE To

More information

CHAPTER 4 BUILDING REGULATION

CHAPTER 4 BUILDING REGULATION CHAPTER 4 BUILDING REGULATION Article I Administration 4-101 Activities regulated 4-102 Conflict with other ordinances 4-103 Building codes enforcement officer 4-104 Board of adjustment 4-105 Building

More information

ISOLATED OPERATIONS LOCK OUT/TAG OUT (LO/TO) WORK STANDARD. Copyright 2009 All rights reserved.

ISOLATED OPERATIONS LOCK OUT/TAG OUT (LO/TO) WORK STANDARD. Copyright 2009 All rights reserved. ISOLATED OPERATIONS LOCK OUT/TAG OUT (LO/TO) WORK STANDARD Copyright 2009 All rights reserved. ISOLATED OPERATIONS LO/TO WORK STANDARD ISOLATED OPERATIONS LOCK OUT/TAG OUT (LO/TO) WORK STANDARD Copyright

More information

MANUFACTURING TECHNICAL INSTRUCTIONS - SAFETY. To provide instruction for the issue and control of permits authorizing Hot Work operations.

MANUFACTURING TECHNICAL INSTRUCTIONS - SAFETY. To provide instruction for the issue and control of permits authorizing Hot Work operations. DAIMLERCHRYSLER MANUFACTURING TECHNICAL INSTRUCTIONS - SAFETY Subject: HOT WORK PERMITS ISSUE AND CONTROL OF ISSUE DATE: 6/1/99 EFFECTIVE DATE: 6/1/99 REVIEW DATE. TBD SERIES & NO. SMI - 117 I. PURPOSE

More information

4.1 PERMIT TO WORK PROCEDURE

4.1 PERMIT TO WORK PROCEDURE TABLE OF CONTENTS 1. INTRODUCTION... 1 1.1 Purpose... 1 1.2 SCOPE... 2 2. ROLES AND RESPONSIBILITIES... 2 2.1 Permit Authoriser... 2 2.2 Permit Applicant... 3 2.3 HSEQ Manager... 3 2.4 Approvers... 3 2.5

More information

North America Business Unit (NABU) ENSCO SAFE SYSTEM OF WORK (SSOW) Permit to Work (PTW) Materials Re-Supply Catalogue

North America Business Unit (NABU) ENSCO SAFE SYSTEM OF WORK (SSOW) Permit to Work (PTW) Materials Re-Supply Catalogue North America Business Unit (NABU) ENSCO SAFE SYSTEM OF WORK (SSOW) Permit to Work (PTW) Materials Re-Supply Catalogue Contents Page Permit to Work (PTW) Hardware () Permit to Work (PTW) Location Board.3

More information

Environmental, Health and Safety. UNC Charlotte Hot Work Program (Welding, Cutting, and Brazing)

Environmental, Health and Safety. UNC Charlotte Hot Work Program (Welding, Cutting, and Brazing) Environmental, Health and Safety UNC Charlotte Hot Work Program (Welding, Cutting, and Brazing) January 2014 TABLE OF CONTENTS PURPOSE:... 2 SCOPE:... 2 HOT WORK RESPONSIBILITIES... 2 SPECIFIC DEPARTMENTAL

More information

THE CITY OF MANDALAY DEVELOPMENT LAW (1992)

THE CITY OF MANDALAY DEVELOPMENT LAW (1992) THE CITY OF MANDALAY DEVELOPMENT LAW (1992) [Repealed by the City of Mandalay Development Law (2002)] The State Law and Order Restoration Council Law No. 10/92 The 6th Waxing Day of Pyatho, 1354 M.E 29

More information

Pressure Equipment Act (869/1999; amendments up to 1160/2003 included)

Pressure Equipment Act (869/1999; amendments up to 1160/2003 included) NB: Unofficial translation Ministry of Trade and Industry, Finland Pressure Equipment Act (869/1999; amendments up to 1160/2003 included) Chapter 1 - General Provisions Section 1 This Act applies to pressure

More information

Safety & Risk Management

Safety & Risk Management Safety & Risk Management (B) Construction Safety Law http://www.mom.gov.sg/legislation/ occupational-safetyhealth/pages/default.aspx ACTS Work Injury Compensation Act (WICA) Workplace Safety and Health

More information

Coal Mining Safety and Health Act 1999

Coal Mining Safety and Health Act 1999 Queensland Coal Mining Safety and Health Act 1999 Reprinted as in force on 14 December 2007 Reprint No. 2B This reprint is prepared by the Office of the Queensland Parliamentary Counsel Warning This reprint

More information

Coles Express Work Clearance: Induction for Contractors

Coles Express Work Clearance: Induction for Contractors Coles Express Work Clearance: Induction for Contractors Part of the Coles Online Contractor Induction system, for completion by contractors who will conduct works on Coles Express sites. Prerequisites

More information

Move Safer. Work permits Work Clearance Management RWE Generation WHAT BRINGS US TO TOP SAFETY PERFORMANCE EVERYBODY, EVERYWHERE, ANYTIME.

Move Safer. Work permits Work Clearance Management RWE Generation WHAT BRINGS US TO TOP SAFETY PERFORMANCE EVERYBODY, EVERYWHERE, ANYTIME. Move Safer EVERYBODY, EVERYWHERE, ANYTIME Work permits Work Clearance Management RWE Generation WHAT BRINGS US TO TOP SAFETY PERFORMANCE Health Safety Security 1 A safe workplace overview of resources

More information

Roger Williams University Hot Work Plan

Roger Williams University Hot Work Plan Roger Williams University Hot Work Plan Roger Williams University Dept. Of Environmental Health and Safety One Old Ferry Road Bristol, RI 02809 Adopted: April 26, 2011(President s Cabinet) Roger Williams

More information

The engineer and the WHS Act. What engineers and designers need to be aware of when complying with the WHS Act

The engineer and the WHS Act. What engineers and designers need to be aware of when complying with the WHS Act The engineer and the WHS Act What engineers and designers need to be aware of when complying with the WHS Act In case you missed it A new WHS model act (2011) Harmonises WHS laws across all jurisdictions

More information

University of Delaware.

University of Delaware. HOT WORK PERMIT PROGRAM The following information describes the code required Hot Work Permit Program at the University of Delaware. PART 1 GENERAL University Contact: Department of Environmental Health

More information

IC Chapter 26. Damage to Underground Facilities

IC Chapter 26. Damage to Underground Facilities IC 8-1-26 Chapter 26. Damage to Underground Facilities IC 8-1-26-1 Application of chapter Sec. 1. (a) Except as provided by this section, this chapter does not apply to the following: (1) Excavation that

More information

The Ohio State University. Hot Work Permit Program (Welding, Cutting and Brazing)

The Ohio State University. Hot Work Permit Program (Welding, Cutting and Brazing) Environmental Health & Safety 1314 Kinnear Rd. Columbus, Ohio 43212 Phone (614) 292-1284 Fax (614) 292-6404 http://www.ehs.osu.edu/ The Ohio State University Hot Work Permit Program (Welding, Cutting and

More information

INTERPOL s Rules on the Processing of Data

INTERPOL s Rules on the Processing of Data OFFICE OF LEGAL AFFAIRS INTERPOL s Rules on the Processing of Data [III/IRPD/GA/2011] REFERENCES 51st General Assembly session, Resolution AG/51/RES/1, adopting the Rules on International Police Cooperation

More information

SAFETY. EHS Pledge Vol 3 Issue 3 March 2017 RESPONSIBILITY. is everyone s STAY ALERT! Never dismiss a NEAR MISS

SAFETY. EHS Pledge Vol 3 Issue 3 March 2017 RESPONSIBILITY. is everyone s STAY ALERT! Never dismiss a NEAR MISS EHS Pledge Vol 3 Issue 3 March 2017 Accidents occur when we don t care SAFETY is everyone s RESPONSIBILITY Never dismiss a NEAR MISS A near miss is described as an unplanned event that did not result in

More information

Electricity Supply (Safety and Network Management) Regulation 2014

Electricity Supply (Safety and Network Management) Regulation 2014 New South Wales Electricity Supply (Safety and Network Management) Regulation 2014 under the Electricity Supply Act 1995 Her Excellency the Governor, with the advice of the Executive Council, has made

More information

Safety Codes Council

Safety Codes Council Safety Codes Council 2017 Conference and AGM Presented by: Michael S. Solowan Partner 1 R v Williams Engineering Canada Inc. Alberta Provincial Court, 2014 Rocky Mountain Court Building in Calgary 2 Recap

More information

HSE - Permit to Work Procedure

HSE - Permit to Work Procedure Date Adopted: April 2016 Current Date: August 2016 Due for Review: August 2018 Division: HSE HSE - Permit to Work Procedure 1. SCOPE... 2 2. DEFINITIONS... 3 3. RESPONSIBILITIES... 5 4. PROCEDURE... 6

More information

Technology Teachers Safety & Responsibilities

Technology Teachers Safety & Responsibilities Technology Teachers Safety & Responsibilities http://teachertube.com/viewvideo.php?video_id=144518&title=shop_safety_video Luc Ouellet Technology Teacher Safety in Technology Education Programs Is an issue

More information

HOT WORK 1. PURPOSE 2. SCOPE 3. KEY TERMS

HOT WORK 1. PURPOSE 2. SCOPE 3. KEY TERMS Doc owner: Authorised by: HR Manager WHS Group Executive Human Resources HOT WORK Version PRO-05-11-01 Issue date 08/2017 1. PURPOSE The purpose of this procedure is to provide guidance to David Jones

More information

PRO Permit to Work

PRO Permit to Work MS&L Procedure PRO-4.5-0001-1-01 Permit to Work Document Owner: Bill Kruesi HSSE Manager - Asset Mgt Approved By: Bill Kruesi HSSE Manager - Asset Mgt Prepared By: Document Status: Version Number: 4 Adrian

More information

PROCEDURES FOR HOT WORK PERMITS, HOT WORK DISPENSATIONS & GAS FREE CERTIFICATES

PROCEDURES FOR HOT WORK PERMITS, HOT WORK DISPENSATIONS & GAS FREE CERTIFICATES PROCEDURES FOR HOT WORK PERMITS, HOT WORK DISPENSATIONS & GAS FREE CERTIFICATES Hot work permits, hot work dispensations and gas free certificates Version 9 - Aug 2015 Page 1 of 13 DOCUMENT CONTROL Document

More information

BYLAW NO. 3551/2015 NOW THEREFORE COUNCIL OF THE CITY OF RED DEER ENACTS AS FOLLOWS: PART I TITLE, PURPOSE AND DEFINITIONS

BYLAW NO. 3551/2015 NOW THEREFORE COUNCIL OF THE CITY OF RED DEER ENACTS AS FOLLOWS: PART I TITLE, PURPOSE AND DEFINITIONS BYLAW NO. 3551/2015 WHEREAS, pursuant to section 66 of the Safety Codes Act, RSA 2000, c S-1, an accredited municipality may pass bylaws respecting fees for anything issued or any material or service provided

More information

TOUCHSTONE EXPLORATION INC. HEALTH, SAFETY, ENVIRONMENTAL AND RESERVES COMMITTEE MANDATE

TOUCHSTONE EXPLORATION INC. HEALTH, SAFETY, ENVIRONMENTAL AND RESERVES COMMITTEE MANDATE TOUCHSTONE EXPLORATION INC. HEALTH, SAFETY, ENVIRONMENTAL AND RESERVES COMMITTEE MANDATE Role and Objective The Health, Safety, Environment and Reserves Committee (the Committee ) is a committee of the

More information

INDUSTRIAL SAFETY AND HEALTH ACT Act No. 4220, Jan. 13, 1990

INDUSTRIAL SAFETY AND HEALTH ACT Act No. 4220, Jan. 13, 1990 INDUSTRIAL SAFETY AND HEALTH ACT Act No. 4220, Jan. 13, 1990 Amended by Act No. 4622, Dec. 27, 1993 Act No. 4826, Dec. 22, 1994 Act No. 4916, Jan. 5, 1995 Act No. 5248, Dec. 31, 1996 Act No. 5453, Dec.

More information

Dangerous Goods Safety Management Act 2001

Dangerous Goods Safety Management Act 2001 Queensland Dangerous Goods Safety Management Act 2001 Reprinted as in force on 18 December 2009 Reprint No. 3 This reprint is prepared by the Office of the Queensland Parliamentary Counsel Warning This

More information

THE OCCUPATIONAL HEALTH AND SAFETY ACT: THE HIDDEN LEGAL RISKS IN ENGAGING WITH THIRD PARTIES. Kate Collier Partner Webber Wentzel

THE OCCUPATIONAL HEALTH AND SAFETY ACT: THE HIDDEN LEGAL RISKS IN ENGAGING WITH THIRD PARTIES. Kate Collier Partner Webber Wentzel THE OCCUPATIONAL HEALTH AND SAFETY ACT: THE HIDDEN LEGAL RISKS IN ENGAGING WITH THIRD PARTIES Kate Collier Partner Webber Wentzel May 2015 Webber Wentzel 2014 Legal risk exposure in terms of the ohsa Managing

More information

TAMPA ELECTRIC COMPANY ENERGY SUPPLY HOT WORK PERMITTING PROGRAM

TAMPA ELECTRIC COMPANY ENERGY SUPPLY HOT WORK PERMITTING PROGRAM TABLE OF CONTENTS TITLE PAGE # PURPOSE / INTRODUCTION 1 RESPONSIBILITY 2 EMPLOYEE TRAINING AND DOCUMENTATION 3 PROGRAM REQUIREMENTS 4 HOT WORK PERMIT PLANNING AND PRECAUTIONS 4 6 FIREWATCH 6, 7 HOT WORK

More information

PRO Permit to Work

PRO Permit to Work MS&L Procedure PRO-4.5-0001-1-01 Permit to Work Version: 3 Authorised by: Tom Angliss & Owen Quake Authorisation Date: 21 /11/2017 This document has been approved for release and changed as per the associated

More information

OHS Prosecutions under the Work Health and Safety Act

OHS Prosecutions under the Work Health and Safety Act OHS Prosecutions under the Work Health and Safety Act A better deal for NSW employers? SYDNEY LAW SCHOOL Belinda Reeve, PhD Candidate Relevant aspects of OHS law How will the model law change the use of

More information

Legal Obligations in Construction Contracts Concluded by Employers Operating in Egypt

Legal Obligations in Construction Contracts Concluded by Employers Operating in Egypt Legal Obligations in Construction Contracts Concluded by Employers Operating in Egypt Copyright 2015, L&E Global We set out below important legal information that applies to all companies and entities

More information

PROTECTION OF PERSONAL DATA AND SECURITY OF DATA IN THE SCHENGEN INFORMATION SYSTEM

PROTECTION OF PERSONAL DATA AND SECURITY OF DATA IN THE SCHENGEN INFORMATION SYSTEM The Schengen acquis - Convention implementing the Schengen Agreement of 14 June 1985 between the Governments of the States of the Benelux Economic Union, the Federal Republic of Germany and the French

More information

Hot Work Program. Purpose of Procedure:

Hot Work Program. Purpose of Procedure: BGSU Hot Work Program Page 1 Bowling Green State University Purpose of Procedure: Hot Work Program These procedures have been established to comply with Ohio s Public Employee Risk Reduction Act, the OSHA

More information

Annex I To Loughborough University Estates Services Health and Safety Policy

Annex I To Loughborough University Estates Services Health and Safety Policy Annex I Annex I To Loughborough University Estates Services Health and Safety Policy High Voltage Electricity System Safety Rules And Associated Safety Guidance 1. Introduction a. These Safety Rules are

More information

Desert Research Institute Hot Work Permit Program

Desert Research Institute Hot Work Permit Program 1.0 INTRODUCTION 1.1 PURPOSE The purpose of this policy is to prevent any fires that may result from hot work processes. 1.2 SCOPE 1.2.1 For the purposes of this policy, hot work is defined as any temporary

More information

EPR10 Management System

EPR10 Management System EPR10 Management System Contents 1. Structure of Management System 1.1 Statement of management intent 1.2 Commitment to resources 1.3 Organisational structure 1.3.1 Responsibilities of appointed persons

More information

LOCAL 1205 BYLAWS APPROVED BY THE PROVINCIAL EXECUTIVE FEBRUARY 18 19, 2015

LOCAL 1205 BYLAWS APPROVED BY THE PROVINCIAL EXECUTIVE FEBRUARY 18 19, 2015 LOCAL 1205 BYLAWS APPROVED BY THE PROVINCIAL EXECUTIVE FEBRUARY 18 19, 2015 1. NAME File No. 4480-176 The name of the local shall be Local 1205 of the B.C. Government and Service Employees' Union. 2. JURISDICTION

More information

The International Context and National Implications

The International Context and National Implications Guidance Note 1 Implementing Labour Standards in Construction The International Context and National Implications International Rights and Conventions The implementation of labour standards is about protecting

More information

For All Your Staffing Solutions

For All Your Staffing Solutions For All Your Staffing Solutions Axcess Staffing Services, Supplemental Information for Your Employment TEMPORARY EMPLOYEE FREQUENTLY ASKED QUESTIONS Following is a list of questions that Axcess employees

More information

Chapter 1. TECHNICAL STANDARDS AND SAFETY ACT (Assented to March 6, 2002)

Chapter 1. TECHNICAL STANDARDS AND SAFETY ACT (Assented to March 6, 2002) Chapter 1 TECHNICAL STANDARDS AND SAFETY ACT (Assented to March 6, 2002) Purpose 1. The purpose of this Act is to enhance public safety in Nunavut by providing for the efficient and flexible administration

More information

SUNY Geneseo ENVIRONMENTAL HEALTH & SAFETY

SUNY Geneseo ENVIRONMENTAL HEALTH & SAFETY Revision No.: 1 Page 1 of 7 I. PURPOSE The purpose of this policy is to establish minimum standards for safely conducting hot work tasks to help mitigate hazards that could occur during hot work operations.

More information

FINAL PROPOSAL OF THE ACT ON AMENDMENTS TO THE PATENT ACT

FINAL PROPOSAL OF THE ACT ON AMENDMENTS TO THE PATENT ACT FINAL PROPOSAL OF THE ACT ON AMENDMENTS TO THE PATENT ACT In the Patent Act ( Official Gazette Nos. 173/2003, 87/2005, 76/2007, 30/2009, 128/10 and 49/2011), after Article 1, Articles 1.a and 1.b are added

More information

Fair Work (Building Industry) Act 2012

Fair Work (Building Industry) Act 2012 Fair Work (Building Industry) Act 2012 No. 113, 2005 as amended Compilation start date: 12 March 2014 Includes amendments up to: Act No. 13, 2013 Prepared by the Office of Parliamentary Counsel, Canberra

More information

Workplace Surveillance Act 2005

Workplace Surveillance Act 2005 Workplace Surveillance Act 2005 As at 20 May 2014 Long Title An Act to regulate surveillance of employees at work; and for other purposes. Part 1 ñ Preliminary 1 Name of Act This Act is the Workplace Surveillance

More information

ISSUING AGENCY: New Mexico Public Regulation Commission. [ NMAC - N, ]

ISSUING AGENCY: New Mexico Public Regulation Commission. [ NMAC - N, ] TITLE 18 CHAPTER 60 PART 4 TRANSPORTATION AND HIGHWAYS PIPELINE CONSTRUCTION AND MAINTENANCE PIPELINE SAFETY ENFORCEMENT PROCEDURES 18.60.4.1 ISSUING AGENCY: New Mexico Public Regulation Commission. [18.60.4.1

More information

ARLINGTON COUNTY CODE. Chapter 55 UNDERGROUND UTILITY PROTECTION

ARLINGTON COUNTY CODE. Chapter 55 UNDERGROUND UTILITY PROTECTION Chapter 55 55-1. Short Title. 55-2. Authorization and Declaration of Policy. 55-3. Definitions. 55-4. Administration and Enforcement. 55-5. Responsibilities of the Contractor. 55-6. Responsibilities of

More information

JERSEY DOOR REGISTRATION SCHEME Application / Renewal form

JERSEY DOOR REGISTRATION SCHEME Application / Renewal form JERSEY DOOR REGISTRATION SCHEME Application / Renewal form A copy of the terms and conditions of the Jersey Door Registration scheme are attached. These are for your reference (for you to keep). Please

More information

STATE OF MASSACHUSETTS CHAPTER 82

STATE OF MASSACHUSETTS CHAPTER 82 STATE OF MASSACHUSETTS CHAPTER 82 SECTION 40. The following words, as used in this section and sections 40A to 40E, inclusive, shall have the following meanings: "Company", natural gas pipeline company,

More information

Safe Work Permits Procedure

Safe Work Permits Procedure Launceston Airport Safe Work Permits Procedure Revision: 2 March 2015 APAL-SWP-001 Safe Work Permits Procedure Page 1 of 12 Table of Contents 1. Safe Work Permits... 3 1.1 Special Authorities... 4 1.2

More information

SAFETY AND HEALTH STANDARD HOT WORK PERMIT Effective Date: 06/10/10 Standard: 16.1 Document Number: KUCSH0040 Rev: 04

SAFETY AND HEALTH STANDARD HOT WORK PERMIT Effective Date: 06/10/10 Standard: 16.1 Document Number: KUCSH0040 Rev: 04 16.1.1 INTRODUCTION 16.1.1.1 The purpose of this standard is to prevent the inadvertent ignition of combustible materials when performing hot work. 16.1.2 DEFINITIONS 16.1.2.1 Hot work - includes welding,

More information

C170 Chemicals Convention, 1990

C170 Chemicals Convention, 1990 Page 1 of 11 C170 Chemicals Convention, 1990 Convention concerning Safety in the use of Chemicals at Work (Note: Date of coming into force: 04:11:1993.) Convention:C170 Place:Geneva Session of the Conference:77

More information

Safety Codes Council Policy & Information Manual

Safety Codes Council Policy & Information Manual Background The Safety Codes Act, regulations, and codes and standards enabled under the Act are intended to administer safety to persons and property. issued under the Act are intended as a means to authorize

More information

A guide to the Offshore Installations

A guide to the Offshore Installations A guide to the Offshore Installations (Safety Representatives and Safety Committees) s 1989 on s This is a free-to-download, web-friendly version of L110, (Second edition, published 1998). This version

More information

Articles of Association of the. International Non Profit Association (AISBL) European Network of Transmission System Operators for Gas ENTSOG

Articles of Association of the. International Non Profit Association (AISBL) European Network of Transmission System Operators for Gas ENTSOG Articles of Association of the International Non Profit Association (AISBL) European Network of Transmission System Operators for Gas ENTSOG CHAPTER 1 DEFINITIONS... 4 Article 1. Definitions... 4 CHAPTER

More information

SAFEWORK PRACTICES SAFE WORK PERMITTING CAT A-1 SOP #6

SAFEWORK PRACTICES SAFE WORK PERMITTING CAT A-1 SOP #6 SUNCOR ENERGY PRODUCTS DISTRIBUTION TERMINAL OPERATING MANUAL STANDARD OPERATING PROCEDURE SAFEWORK PRACTICES Lifesaving Rules Supporting Document Work with a valid work permit when required. 1.0 PURPOSE

More information

MCW s Hot Work Permit Program

MCW s Hot Work Permit Program 2019 MCW s Hot Work Permit Program - Hot Work/Fire Watch Operations This document is the Medical College of Wisconsin s (MCW) written program for conducting hot work, and identifies roles and responsibilities

More information

BYLAWS of Old Saybrook Soccer Club, INC.

BYLAWS of Old Saybrook Soccer Club, INC. Revision 1, Approved 27-Feb-2014 BYLAWS of Old Saybrook Soccer Club, INC. (the "Corporation" or "OSSC") ARTICLE I Offices The principal office of the Corporation shall be at such place in the town of Old

More information

Part VI INVESTIGATIONS, INQUIRIES AND REPORTING OF ACCIDENTS, DANGEROUS OCCURRENCES AND OCCUPATIONAL DISEASES

Part VI INVESTIGATIONS, INQUIRIES AND REPORTING OF ACCIDENTS, DANGEROUS OCCURRENCES AND OCCUPATIONAL DISEASES 1 of 51 08/06/2012 10:09 Workplace Safety and Health Act (CHAPTER 354A) Long Title Part I PRELIMINARY 1 Short title 2 Application of Act 3 Application of Act to Government Part II INTERPRETATION 4 General

More information

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION GENERAL ASSEMBLY OF NORTH CAROLINA SESSION S SENATE BILL Health Care Committee Substitute Adopted // Third Edition Engrossed // House Committee Substitute Favorable // House Committee Substitute # Favorable

More information

Liability under the Workplace Health and Safety Act 1995: Select issues for Management

Liability under the Workplace Health and Safety Act 1995: Select issues for Management Liability under the Workplace Health and Safety Act 1995: Select issues for Management Kristy Richardson School of Commerce and Marketing, Faculty of Business and Informatics, Central Queensland University,

More information

Interim Tree Bylaw Bylaw No. 4892, 2016

Interim Tree Bylaw Bylaw No. 4892, 2016 District of West Vancouver Interim Tree Bylaw Bylaw No. 4892, 2016 Effective Date: April 20, 2016 District of West Vancouver Interim Tree Bylaw No. 4892, 2016 Table of Contents Part 1 Citation... 1 Part

More information

Guidelines for Part 17.2 of the Dutch Environmental Management Act: measures in the event of environmental damage or its imminent threat (English

Guidelines for Part 17.2 of the Dutch Environmental Management Act: measures in the event of environmental damage or its imminent threat (English Guidelines for Part 17.2 of the Dutch Environmental Management Act: measures in the event of environmental damage or its imminent threat (English translation of original version dated 8 January 2008) Introduction

More information

Safe Work Permit Practice

Safe Work Permit Practice Health & Safety Safe Work Permit Practice Content Owner Custodian H&S Discipline Program COMS Document Number Manager, Health & Safety Solutions H&S Solutions Personal Safety Safe Work Permit See COMS

More information

STANDARD PROCEDURE INSTRUCTION

STANDARD PROCEDURE INSTRUCTION STANDARD PROCEDURE INSTRUCTION Title SPI Department Hot Work Permit Supersedes SPI Dated # 34-3 Effective Date Safety, Health and Environment Dec 22, 2014 Jan 19, 2016 Hot Work Permit 1. PURPOSE 1.1 To

More information

The installation of CCTV can provide information on activities at the Water,

The installation of CCTV can provide information on activities at the Water, ST CHAD S WATER LNR CCTV CODE OF PRACTICE St Chad s Fishing Club A closed circuit television system is used at St Chad s Water LNR, Church Wilne (known in the Code as the Water) by the St Chad s Fishing

More information

THE CITY OF YANGON DEVELOPMENT LAW (1990)

THE CITY OF YANGON DEVELOPMENT LAW (1990) THE CITY OF YANGON DEVELOPMENT LAW (1990) The State Law and Order Restoration Council Law No. 11/90 The 6th Waning Day of Kason, 1352 M.E. 14 May 1990 The State Law and Order Restoration Council hereby

More information

HOT WORK GUIDELINES 3. MANDATORY AREAS REQUIRING HOT WORK PERMITS Within the Service Station Site

HOT WORK GUIDELINES 3. MANDATORY AREAS REQUIRING HOT WORK PERMITS Within the Service Station Site 1. GENERAL This procedure gives guidelines for the precautions and preparation that should be followed to ensure that work covered by a hot work permit can be carried out safely without risk to people

More information

Classification: Public Rev. 00 June 2018 Page 1 of 25

Classification: Public Rev. 00 June 2018 Page 1 of 25 Classification: Public Rev. 00 June 2018 Page 1 of 25 Rev. 00 June 2018 Page 2 of 25 Rev. 00 June 2018 Page 3 of 25 Rev. 00 June 2018 Page 4 of 25 Rev. 00 June 2018 Page 5 of 25 Rev. 00 June 2018 Page

More information

NC General Statutes - Chapter 87 Article 7A 1

NC General Statutes - Chapter 87 Article 7A 1 Article 7A. Well Contractors Certification. 87-98.1. Title. This Article may be cited as the North Carolina Well Contractors Certification Act. (1997-358, s. 2.) 87-98.2. Definitions. The definitions in

More information

Apply for Hot Works Permit

Apply for Hot Works Permit Apply for Hot Works Permit Details of revisions Level Details Date Initial 1 Creation of initial document for use 20/08/2016 J.O S 2 Review and Amendment 26/02/2018 MW Title: Apply for Hot Works Permit

More information

CODE OF PRACTICE FOR COMMUNITY- BASED CCTV SYSTEMS

CODE OF PRACTICE FOR COMMUNITY- BASED CCTV SYSTEMS CODE OF PRACTICE FOR COMMUNITY- BASED CCTV SYSTEMS 1 INTRODUCTION This Code of Practice sets out the basic conditions of use for Community-Based CCTV systems by applicants for the Department of Justice,

More information

General Part of the Economic Activities Code Act 1

General Part of the Economic Activities Code Act 1 Issuer: Riigikogu Type: act In force from: 06.07.2017 In force until: 02.01.2018 Translation published: 10.07.2017 General Part of the Economic Activities Code Act 1 Amended by the following acts Passed

More information

MINE HEALTH AND SAFETY AMENDMENT BILL

MINE HEALTH AND SAFETY AMENDMENT BILL REPUBLIC OF SOUTH AFRICA MINE HEALTH AND SAFETY AMENDMENT BILL (As amended by the Portfolio Committee on Minerals and Energy (National Assembly)) (The English text is the offıcial text of the Bill) (MINISTER

More information